CN108252519A - A kind of construction method of the house construction engineering template construction technique model based on BIM - Google Patents

A kind of construction method of the house construction engineering template construction technique model based on BIM Download PDF

Info

Publication number
CN108252519A
CN108252519A CN201810210663.4A CN201810210663A CN108252519A CN 108252519 A CN108252519 A CN 108252519A CN 201810210663 A CN201810210663 A CN 201810210663A CN 108252519 A CN108252519 A CN 108252519A
Authority
CN
China
Prior art keywords
construction
bim
technique model
model based
house
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810210663.4A
Other languages
Chinese (zh)
Inventor
许涛
邓利平
冉华
杨华超
杨波
陈胜兵
袁大鹏
张骏程
蒋健
刘凌龙
郭伟
王昭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority to CN201810210663.4A priority Critical patent/CN108252519A/en
Publication of CN108252519A publication Critical patent/CN108252519A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Architecture (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Theoretical Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a kind of construction methods of the house construction engineering template construction technique model based on BIM, include the following steps:S1:The preliminary arrangement and method for construction of agent structure technique model is determined according to structural working drawing and standard;S2:Agent structure technique model model is established using BIM softwares according to preliminary arrangement and method for construction, assigns information to component later;S3:The visual design is carried out to agent structure formwork erection scheme in BIM models;S4:Collision detection is carried out to wall, column negative and positive angular position reinforcement measure, carries out preceding preparation of constructing, accurate guiding construction;S5:Form work engineering model is constructed.The present invention is using BIM technology to project templet engineering process pattern modeling, determine formwork erection designing scheme and connection detail, engineering technology is improved to tell somebody what one's real intentions are efficiency and accuracy, worker need to only design and construct according to threedimensional model, construction requirement is clear and definite, it reduces mistake to do over again, improves template construction efficiency, be more advantageous to unified technique model technical standard.

Description

A kind of construction method of the house construction engineering template construction technique model based on BIM
Technical field
The present invention relates to building BIM technology fields, and in particular to a kind of building construction process template based under BIM technology Construction technology model construction method.
Background technology
BIM, that is, Building Information Modeling refer to create and using digital model to construction project Process, the method and technique that design, construction and the O&M Life cycle of project are managed and optimize.In simple terms, BIM skills Art is to move into the life cycle management of building in computer, the condition for providing science preferably to implement management.It is built in engineering If field, BIM illustrates its distinctive potentiality, becomes the lifeblood of new century engineering construction industry development.With BIM technology In the popularization of construction industry, more and more units start with technique, it has become one of direction of construction industry development.
Technique model demonstration area has been one of standardization action of many construction units, unit in charge of construction.Form work engineering is Ensure an important ring for main body construction quality, however in traditional building template engineering process model construction, it is applied using plane Work figure carries out formwork erection, Design of Reinforcement and material planning, but due to plane drawing can not by the data information of whole set process, patrol It collects association to show, is particularly required to set the progress nonstandardized technique of its working measure in the complex nodes such as wall column corner position Meter.At present, template construction relies primarily on carpenter master worker and empirically carries out live arrangement, adjustment, since individual skill difference is deposited It can not unify in standard, Construction defect is difficult control, and can not often play the role of technique model should play.
Invention content
Current formwork is solved it is an object of the invention to overcome the deficiencies of the prior art and provide a kind of Complexity, low construction efficiency, the factor for influencing construction quality is more, and technique model standard disunity, the poor problem of construction directiveness.
The purpose of the present invention is achieved through the following technical solutions:A kind of house construction engineering template construction based on BIM The construction method of technique model, includes the following steps:
S1:The preliminary arrangement and method for construction of agent structure technique model is determined according to structural working drawing and standard;
S2:Agent structure technique model model is established using BIM softwares according to preliminary arrangement and method for construction, component is assigned later Information;
S3:The visual design is carried out to agent structure formwork erection scheme in BIM models;
S4:Collision detection is carried out to wall, column negative and positive angular position reinforcement measure, carries out preceding preparation of constructing, accurate guiding construction;
S5:Form work engineering model is constructed.
It is preferred that before the model construction of S5 is carried out, if no respective material needs to carry out material purchases, and Material is processed.Material requested includes the materials such as steel pipe, flitch, quarter bend, template, U supports, split bolt.
It is preferred that the preparation of construction of S4 determines to reinforce position, spacing before including construction.
It is preferred that agent structure technique model floor height 2900mm, frame column dimension 600*600mm, shear wall are wide 200mm, plate thickness 120mm, beam section size 200*600mm, 200*400mm.
It is preferred that component includes beam, plate, column, wall.
It is preferred that the agent structure template in S3 is 18mm thickness overlay film gluing plank sheathings;Flitch is 50*100mm Straight hard flitch;Quarter bend is 50*100, wall thickness 2.5mm;Steel pipe is direct 48mm, wall thickness 3.5mm.
It is preferred that in S4, needed with reference to live practice of construction, to the complex regions formwork reinforcement measure such as negative and positive angle It is checked, corrects the preliminary project in the BIM models, according to the arrangement of revised formwork reinforcement and detail drawing, carried Detail parameters is taken to carry out construction manager and teams and groups operator visualization to tell somebody what one's real intentions are.
It is preferred that damage is reduced to the accurate blanking of form work engineering material requested using the visualization function of BIM technology Consumption.
It is preferred that template construction includes the following steps in the step S5:
(g1) it is levelling with C10 concreting 4200mm*6000mm bed courses before constructing, major axis is released, and bullet is good each The position line of component, and construction area eliminating impurities are clean;
(g2) according to the visual design of the BIM models and reinforcing detail drawing, steel pipe support frame body, template are accurately positioned Installation, reinforcement measure;
(g3) full hall scaffold is set, and the rod piece spacing of formwork bracing system should be computed determining with the visual design, walk Away from no more than 1.5 meters, upright bar spacing is not more than 1.2 meters;
(g4) 200*200*50mm cushion blocks should be set under upright bar, and jacking outer Rose mouthful length in top is not greater than 200mm, indulges Bar of laterally sweeping the floor must be closed, and height off the ground is between 200-300mm;
(g5) beam forms is reinforced using flitch, and thin space is not greater than 300mm step by step;When being more than 550mm using deck-molding Split bolt should be set, and split bolt spacing is not greater than 600mm;
(g6) plate bottom back of the body side uses steel quarter bend, and spacing is not greater than 200mm, and jacking support uses double steel pipe without exception;
(g7) wall column formwork is reinforced using steel quarter bend+split bolt, is reinforced spacing and is not greater than 600mm, the first step is reinforced It is liftoff to be not greater than 250mm.
The beneficial effects of the invention are as follows:Using BIM technology to project templet engineering process pattern modeling, formwork erection is determined Designing scheme and connection detail improve engineering technology and tell somebody what one's real intentions are efficiency and accuracy, and worker need to only design and construct according to threedimensional model, Construction requirement is clear and definite, reduces mistake and does over again, improves template construction efficiency, is more advantageous to unified technique model technical standard, enhancing To construction can directiveness.
Description of the drawings
Fig. 1 is that a kind of shear wall formwork of form work engineering technique model in the present invention installs BIM schematic three dimensional views;
Fig. 2 is that a kind of height of form work engineering technique model in the present invention is more than the main view reinforcing schematic diagram of 550mm beams;
Fig. 3 is that adjustable supports and beam bottom step fastener set node under a kind of plate of form work engineering technique model in the present invention BIM schematic three dimensional views;
Fig. 4 is that formwork frame system and frame column reinforcing BIM three-dimensionals are shown under a kind of plate of form work engineering technique model in the present invention It is intended to;
In figure, 1. cushion blocks, 2. sweep the floor bar, 3. cross bars, 4. beam sill sides, 5. upright bars, 6. split bolts, and 7. beams reinforce steel Pipe, 8. beam side rail sides, 9. step fasteners, 10. fasteners, 11. steel quarter bends, 12. plank sheathings, 13. bed courses, 14. adjustable supports.
Specific embodiment
Technical scheme of the present invention is described in further detail below in conjunction with the accompanying drawings, but protection scope of the present invention is not limited to It is as described below.
As shown in Figure 1, Figure 2, Figure 3 and Figure 4, it is involved based on the form work engineering technique model construction method under BIM technology To material have steel pipe, steel quarter bend 11, flitch, plank sheathing 12, split bolt 6, fastener 10, step fastener 9 etc., form bracing system 5 lower section of upright bar is respectively provided with the flitch 1 of 200*200;Shear wall, frame column template are reinforced using steel quarter bend 11+ steel pipes+split bolt 6 Form, highly more than 550mm beam setting split bolt 66 reinforce, 6 spacing of split bolt be not more than 600mm;Beam sill side 4 It is reinforced with step fastener 99, spacing 300mm, first of upright bar 55 is 300mm apart from beam back gauge;Frame column external corner, shear wall turn The reinforcing of all directions split bolt 6 of angular position should mutually stagger, and distance is not greater than technical standard requirement;Outside exterior wall, frame column Side steel quarter bend 11 answers overall height to set;Formwork frame system upright bar 5 spacing in plate bottom is not more than 1.2m, and step pitch is not more than 1.5m, adjustable supporting 14 exposed screws are supportted no more than 200mm.
A kind of building engineering template construction technique model construction method based under BIM technology, includes the following steps:
(a) the item body knot is determined according to the D CAD structural working drawing of designing unit and company's technique model standard The preliminary arrangement and method for construction of structure technique model;
(b) agent structure technique model model is established, and to beam, plate, column, wall etc. using BIM softwares according to said program Component assigns information;
(c) the visual design is carried out to agent structure formwork erection scheme in the BIM models, by calculating repeatedly Ensure safety, and input the information of material therefor in a model;
(d) collision detection is carried out to wall, column negative and positive angular position reinforcement measure, determines to reinforce the side such as position, spacing before construction Case, accurate guiding construction;
(e) steel pipe (steel pipe be mainly used as beam reinforce steel pipe 7) is purchased, (flitch includes beam sill side 4 and beam side rail side to flitch 8), the materials such as quarter bend, template, U supports, split bolt 6, adjustable supports 14, fastener 10;
(f) material is processed;
(g) form work engineering model is constructed.
In a preferred embodiment, in the step (b), with reference to the item types and BIM technology three-dimensional relationship Optimization, determines the agent structure technique model floor height 2900mm, frame column dimension 600*600mm, the wide 200mm of shear wall, plate thickness 120mm, beam section size 200*600mm, 200*400mm.
In a preferred embodiment, the template in the step (c) is 18mm thickness overlay film gluings plank sheathing 12;Flitch is The straight hard flitches of 50*100mm;Quarter bend is 50*100, wall thickness 2.5mm;Steel pipe is direct 48mm, wall thickness 3.5mm.By above-mentioned material Material establishes standardization race in BIM modeling softwares, and inputs information.
In a preferred embodiment, it in the step (d), is needed with reference to live practice of construction, to complexity such as negative and positive angles Position template reinforcement measure is checked, is corrected the preliminary project in the BIM models, is added according to revised template Gu arrangement and detail drawing, extraction detail parameters carry out construction manager and teams and groups operator visualization and tell somebody what one's real intentions are.
In a preferred embodiment, in the step (f), using the visualization function of BIM technology to form work engineering institute The accurate blanking of material is needed, reduces loss.
In a preferred embodiment, template construction includes the following steps in the step (g):
(g1) it is levelling with C10 concreting 4200mm*6000mm bed courses 13 before constructing, major axis is released, and bullet is good The position line of each component, and construction area eliminating impurities are clean;
(g2) according to the visual design of the BIM models and reinforcing detail drawing, steel pipe support frame body, template are accurately positioned Installation, reinforcement measure;
(g3) full hall scaffold is set, and the rod piece spacing of formwork bracing system should be computed determining with the visual design, walk Away from no more than 1.5 meters, 5 spacing of upright bar is not more than 1.2 meters;
(g4) 200*200*50mm cushion blocks 1 should be set under upright bar 5, jacking outer Rose mouthful length in top is not greater than 200mm, Bar 2 of vertically and horizontally sweeping the floor must be closed, and height off the ground is between 200-300mm;Upright bar 5 respectively with sweeping the floor bar 2 and cross bar 3 is connect, Cross bar 3 includes horizontal and vertical cross bar 3;
(g5) beam forms is reinforced using flitch, and 9 spacing of step fastener is not greater than 300mm;When being more than 550mm using deck-molding Split bolt 6 should be set, and 6 spacing of split bolt is not greater than 600mm;
(g6) plate bottom back of the body side uses steel quarter bend 11, and spacing is not greater than 200mm, and jacking support uses double steel pipe without exception;
(g7) wall column formwork is reinforced using steel quarter bend 11+ split bolts 6, is reinforced spacing and is not greater than 600mm, the first step adds Gu liftoff be not greater than 250mm.
(h) according under BIM models form work engineering technique model design and connection detail, to form work engineering technique model into Row completion acceptance, and model is filed and is preserved, reference is provided for later similar engineering technique model planning, further improves enterprise Industry technique model standardization.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, it is noted that all All any modification, equivalent and improvement made within the spirit and principles in the present invention etc. should be included in the guarantor of the present invention Within the scope of shield.

Claims (9)

1. a kind of construction method of the house construction engineering template construction technique model based on BIM, which is characterized in that including walking as follows Suddenly:
S1:The preliminary arrangement and method for construction of agent structure technique model is determined according to structural working drawing and standard;
S2:Agent structure technique model model is established using BIM softwares according to preliminary arrangement and method for construction, component is assigned believing later Breath;
S3:The visual design is carried out to agent structure formwork erection scheme in BIM models;
S4:Collision detection is carried out to wall, column negative and positive angular position reinforcement measure, carries out preceding preparation of constructing, accurate guiding construction;
S5:Form work engineering model is constructed.
2. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1, special Sign is:Before the model construction of S5 is carried out, if no respective material needs to carry out material purchases, and add material Work.
3. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1, special Sign is:The preparation of construction of S4 determines to reinforce position, spacing before including construction.
4. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1, special Sign is:Agent structure technique model floor height 2900mm, frame column dimension 600*600mm, the wide 200mm of shear wall, plate thickness 120mm, beam section size 200*600mm, 200*400mm.
5. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1, special Sign is:Component includes beam, plate, column, wall.
6. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1, special Sign is:Agent structure template in S3 is 18mm thickness overlay film gluing plank sheathings.
7. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1, special Sign is:It in S4, is needed with reference to live practice of construction, the complex regions formwork reinforcement measure such as negative and positive angle is checked, corrected Preliminary project in the BIM models, according to the arrangement of revised formwork reinforcement and detail drawing, extraction detail parameters are to applying Work administrative staff and teams and groups operator carry out visualization and tell somebody what one's real intentions are.
8. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1 or 2, It is characterized in that:Using the visualization function of BIM technology to the accurate blanking of form work engineering material requested, loss is reduced.
9. a kind of construction method of house construction engineering template construction technique model based on BIM according to claim 1, special Sign is that template construction includes the following steps in the step S5:
(g1) it is levelling with C10 concreting 4200mm*6000mm bed courses before constructing, release major axis, and the good each component of bullet The position line, it is and construction area eliminating impurities are clean;
(g2) according to the visual design of the BIM models and reinforcing detail drawing, steel pipe support frame body, template peace are accurately positioned Dress, reinforcement measure;
(g3) full hall scaffold is set, and the rod piece spacing of formwork bracing system should be computed determining with the visual design, and step pitch is not More than 1.5 meters, upright bar spacing is not more than 1.2 meters;
(g4) 200*200*50mm cushion blocks should be set under upright bar, and jacking outer Rose mouthful length in top is not greater than 200mm, vertically and horizontally Bar of sweeping the floor must be closed, and height off the ground is between 200-300mm;
(g5) beam forms is reinforced using flitch, and thin space is not greater than 300mm step by step;It should be set when being more than 550mm when using deck-molding Split bolt is put, split bolt spacing is not greater than 600mm;
(g6) plate bottom back of the body side uses steel quarter bend, and spacing is not greater than 200mm, and jacking support uses double steel pipe without exception;
(g7) wall column formwork is reinforced using steel quarter bend+split bolt, is reinforced spacing and is not greater than 600mm, the first step is reinforced liftoff It is not greater than 250mm.
CN201810210663.4A 2018-03-14 2018-03-14 A kind of construction method of the house construction engineering template construction technique model based on BIM Pending CN108252519A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810210663.4A CN108252519A (en) 2018-03-14 2018-03-14 A kind of construction method of the house construction engineering template construction technique model based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810210663.4A CN108252519A (en) 2018-03-14 2018-03-14 A kind of construction method of the house construction engineering template construction technique model based on BIM

Publications (1)

Publication Number Publication Date
CN108252519A true CN108252519A (en) 2018-07-06

Family

ID=62745869

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810210663.4A Pending CN108252519A (en) 2018-03-14 2018-03-14 A kind of construction method of the house construction engineering template construction technique model based on BIM

Country Status (1)

Country Link
CN (1) CN108252519A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109614666A (en) * 2018-11-22 2019-04-12 中铁二局第四工程有限公司 A method of based on the arrangement and method for construction of BIM technology than choosing
CN110206293A (en) * 2019-06-04 2019-09-06 中国十七冶集团有限公司 A kind of construction method of the form bracing system based on BIM technology
CN110321615A (en) * 2019-06-25 2019-10-11 河南博维建筑规划设计有限公司 A kind of interior decoration engineering template construction method
CN110409799A (en) * 2019-08-01 2019-11-05 中国建筑第八工程局有限公司 A kind of wind-tunnel Construction technology of fair-faced concrete
CN112329105A (en) * 2020-11-05 2021-02-05 甘肃省长城建设集团有限责任公司 Optimized construction method of aluminum mould and modular attached scaffold based on BIM technology
CN114444176A (en) * 2021-12-31 2022-05-06 天津鑫裕房屋智能制造股份有限公司 Layout algorithm of wood formwork in main structure construction based on BIM

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279329A (en) * 2015-10-13 2016-01-27 中国十七冶集团有限公司 BIM (Building Information Modeling)-based sample plate guide quality management method
CN105696467A (en) * 2016-02-04 2016-06-22 广厦建设集团有限责任公司 Formwork support construction method based on P-BIM technology
CN105956257A (en) * 2016-04-28 2016-09-21 上海宝冶集团有限公司 BIM-based aluminum alloy template deep design method
CN106284976A (en) * 2016-09-27 2017-01-04 中国建筑局(集团)有限公司 A kind of aluminum alloy mould plate based on Revit joins mould method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279329A (en) * 2015-10-13 2016-01-27 中国十七冶集团有限公司 BIM (Building Information Modeling)-based sample plate guide quality management method
CN105696467A (en) * 2016-02-04 2016-06-22 广厦建设集团有限责任公司 Formwork support construction method based on P-BIM technology
CN105956257A (en) * 2016-04-28 2016-09-21 上海宝冶集团有限公司 BIM-based aluminum alloy template deep design method
CN106284976A (en) * 2016-09-27 2017-01-04 中国建筑局(集团)有限公司 A kind of aluminum alloy mould plate based on Revit joins mould method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李智慧: "基于P_BIM技术的高大模板与支撑架施工工艺应用分析", 《建筑施工》 *
黄凯: "钢木组合模板设计与施工", 《天津建设科技》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109614666A (en) * 2018-11-22 2019-04-12 中铁二局第四工程有限公司 A method of based on the arrangement and method for construction of BIM technology than choosing
CN110206293A (en) * 2019-06-04 2019-09-06 中国十七冶集团有限公司 A kind of construction method of the form bracing system based on BIM technology
CN110321615A (en) * 2019-06-25 2019-10-11 河南博维建筑规划设计有限公司 A kind of interior decoration engineering template construction method
CN110409799A (en) * 2019-08-01 2019-11-05 中国建筑第八工程局有限公司 A kind of wind-tunnel Construction technology of fair-faced concrete
CN110409799B (en) * 2019-08-01 2021-07-13 中国建筑第八工程局有限公司 Wind tunnel fair-faced concrete construction process
CN112329105A (en) * 2020-11-05 2021-02-05 甘肃省长城建设集团有限责任公司 Optimized construction method of aluminum mould and modular attached scaffold based on BIM technology
CN114444176A (en) * 2021-12-31 2022-05-06 天津鑫裕房屋智能制造股份有限公司 Layout algorithm of wood formwork in main structure construction based on BIM

Similar Documents

Publication Publication Date Title
CN108252519A (en) A kind of construction method of the house construction engineering template construction technique model based on BIM
CN108595891B (en) Two-dimensional BIM design method for temporary support structure for concrete bridge girder construction
CN110689607B (en) System, method, computer readable storage medium and apparatus for drawing recognition and three-dimensional modeling
CN110287513A (en) A kind of built-in fitting construction method based on BIM technology
CN110847593A (en) Construction process of gradient curved surface bare concrete wall based on BIM technology
CN103526930A (en) Multi-directional intersection reinforced bare concrete inclined column construction method
CN113605716A (en) Construction method of multi-curved-surface concrete structure of colorful rose-shaped theater
CN115977401A (en) High-altitude installation method for steel structure
CN114781047A (en) Dynamo-based concrete beam and slab template system internal force calculation method
CN108589959A (en) A kind of building non-load bearing wall cast-in-place method
CN112482779B (en) Integral hoisting construction method for cornice bucket arch of antique building
Lim et al. An experimental study for quality assurance of free-form concrete panels produced by CNC machine
CN116446293A (en) Construction method of concrete beam cable guide pipe of cable-stayed bridge
CN116910854A (en) Large-span arch concrete structure construction method based on digital construction
CN110469348B (en) BIM technology-based underground tunnel large curve turning steel grid arrangement method
CN115584816B (en) High-precision steel inclined curved curtain wall system installation method based on intelligent lofting technology
CN116816103A (en) External expansion type construction method for large-span aluminum alloy single-layer reticulated shell dome structure
CN116498061A (en) High formwork construction method for arc-shaped structure
Tian et al. Nonlinear time-varying analysis algorithms for modeling the behavior of complex rigid long-span steel structures during construction processes
CN113807609B (en) Automatic generation and digital optimization method for climbing scheme of tower crane and steel platform
JP3165339B2 (en) Automatic formwork control system for short line match casting
CN116628795A (en) Multi-curved-surface combined high and large template installation method based on BIM modeling technology
CN114266087A (en) Thin-shell structure formwork system construction method and management system based on BIM technology
CN104196153A (en) Thick L-shaped steel plate shear wall column and manufacturing method thereof
Bagautdinov et al. Feasibility study tool for semi-rigid joints design of high-rise buildings steel structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180706