CN106246187B - Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility - Google Patents

Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility Download PDF

Info

Publication number
CN106246187B
CN106246187B CN201610716117.9A CN201610716117A CN106246187B CN 106246187 B CN106246187 B CN 106246187B CN 201610716117 A CN201610716117 A CN 201610716117A CN 106246187 B CN106246187 B CN 106246187B
Authority
CN
China
Prior art keywords
shaft
chamber
well
facility
sinking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610716117.9A
Other languages
Chinese (zh)
Other versions
CN106246187A (en
Inventor
李文光
张小刚
刘焕鑫
李阳
吕英磊
汪姣妍
叶立生
李文波
石明超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SANSHANDAO GOLD MINE SHANDONG GOLD MINING (LAIZHOU) CO Ltd
Original Assignee
SANSHANDAO GOLD MINE SHANDONG GOLD MINING (LAIZHOU) CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SANSHANDAO GOLD MINE SHANDONG GOLD MINING (LAIZHOU) CO Ltd filed Critical SANSHANDAO GOLD MINE SHANDONG GOLD MINING (LAIZHOU) CO Ltd
Priority to CN201610716117.9A priority Critical patent/CN106246187B/en
Publication of CN106246187A publication Critical patent/CN106246187A/en
Application granted granted Critical
Publication of CN106246187B publication Critical patent/CN106246187B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft
    • E21D7/02Arrangement of guides for cages in shafts; Connection of guides for cages to shaft walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to a kind of self well digging construction method of multiple spot arrangement interior shaft sinking shaft facility, change the horizontally disposed pattern of conventional sinking shaft measures engineering list, make full use of existing engineering, realize the new approaches of the multiple spot arrangement interior shaft sinking shaft facility in the range of vertical space, also achieve pit shaft hanging scaffold signal, 600m hole top signals, 575m and turn over gangue dumping platform, 555m mixing plants, the progress of 537m hoist engine operational outfit signals uniform synchronization, be feasible on theoretical and lifting safety requirements.

Description

Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility
Technical field
The present invention relates to the construction method of self well digging.
Background technology
As in the interior shaft engineering construction of the prior art, interior shaft sinking shaft facility generally uses single horizontally disposed form, Its major defect is:Firstth, singly horizontally disposed sinking shaft narrow space, security risk are big for underground;Secondth, the single horizontally disposed need in underground More interim sinking shaft chamber is wanted, this stability to permanent system engineering generates more serious damaging influence;The 3rd, the driving amount of measures engineering is big, and long construction period, adds construction cost.
The content of the invention
The technical problem to be solved by the invention is to provide a kind of a kind of pit shaft pick of multiple spot arrangement interior shaft sinking shaft facility Construction method is built, existing measures engineering and the permanent works constructed are made full use of, to reduce the driving of measures engineering Amount, and improve working security.
Technical scheme is as follows:
Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility, it is characterised in that comprises the following steps:
The first step:Constructed interior shaft well cap engineering using parallel construction mode, step is as follows:
1), at interior shaft -537m, -555m and -600m respectively working measure tunnel to the position of pit shaft, then blind Construction hoisting machine chamber and in -555m working measures engineering tunnel, mixing plant chamber, yellow sand cement chamber above vertical shaft -537m And stone chamber, and-the 600m that constructs respectively since the -600m is to -575m ore storage bins and -600m to the light section of -555m pit shafts;
2), in step 1)After engineering construction, implement pit shaft at -600m to -555m sections and expand brush, and construct in -575m Distribute trolley chamber;
3), in step 2)After engineering construction, closing -555m well heads;Then in -537m to -555m construction guide wheel caves Room, and p- 600m is poured to -575m ore storage bins, then mouth installs ore drawing facility under -600m to -575m ore storage bins.
Bis- Walk:Carry out arrangement, the installment work of the top sinking shaft facility of interior shaft wellbore section -600m to -1240m, step It is rapid as follows:
1), carry out in -537m elevators chamber and guide wheel chamber the interim lifting erection of equipment of sinking shaft respectively:In guide wheel Chamber installs sinking headframe;And utilization -537m elevators chamber, guide wheel chamber, -537m return aircourses and -537m cross hairs caves The space of room is installed by some stable cars;And separately dig big section and the setting winch in the big section;
2), in -555m utilize working measure tunnel, be stirred station chamber, yellow sand cement chamber and stone cave respectively The arrangement of room;
3), in -575m using distributing trolley chamber, in the pit shaft of well cap, reinforcing -575m turns over gangue dumping platform and turns over cash groove, The barren rock of shaft excavation is directly entered by well-bucket into gangue dumping platform is turned in -575m the ore storage bins, be then transported to new vertical Main shaft is simultaneously promoted to earth's surface;
4), in -600m hole top signal system and distribution system are installed.
The step 4 of bis- Walk)In, the decentralization of personnel, material are each provided at -600m well heads;The discarded chamber of original becomes as interim Electric institute and compressor house, install pressure fan, transformer and corresponding low-tension switch cabinet for pressure fan, temporary drainage, suspending pump respectively And inferior power electricity consumption on well head.
The step 3 of the first step)Material for closing -555m well heads is prepared in accordance with the following methods:With 40# I-steel 120m, I-steel two are fixed with diameter 32mm twisted steel anchor rods, 38kg rail 200m, and thick 60 ㎡ of 8mm steel plates is completed, welded Afterwards, the concrete of 0.5m thickness is poured above, and the buffering slag of 2m thickness is padded after solidification.
The positive effect of the present invention is:In the method for the present invention, interior shaft faces facility arrangement fully in the big of shaft excavation Existing measures engineering and the permanent works constructed are make use of, arranges dig in -537m, -555m, -575m and -600m respectively Well installations and facilities, realize cost efficiency and improve working security.It is in particular in the following aspects:
1st, the horizontally disposed pattern of conventional sinking shaft measures engineering list is changed, has reached the multiple spot cloth in the range of vertical space Put the purpose of interior shaft sinking shaft facility, at the same reached pit shaft hanging scaffold signal, -600m hole top signals, -575m turn over gangue dumping platform, - The purpose that 555m mixing plants and -537m hoist engine operational outfit signals uniform synchronization carry out.
2nd, change as unloading ore storage bin using the permanent ore storage bin of -575m to -600m and be directly transported to earth's surface with truck originally Means of transportation, newly vertical main shaft hooist is directly transported to by electric locomotive by main haulage roadway after unloading and, to earth's surface, greatlys save fortune Defeated cost.It is actual to save 9.11 yuan/t through adjusting.
3rd, erection of equipment is faced greatly in -537m elevators chamber and guide wheel chamber progress sinking shaft, interim lifting, in directive wheel base A set of sinking headframe is installed in processing on plinth hole, takes full advantage of construction work, while it also avoid digging too much in -537m Destruction of the chamber to the stability of whole elevator chamber.
4th, hole top signal and distribution system are installed in -600m, the well head head of the horse for take full advantage of former discarded chamber, having constructed Door and cage assembling chamber.Solve the problems, such as upper and lower and material the stacking of personnel and equipment, be pit shaft it is safe efficient, Quickly driving creates condition.
Embodiment
The method that the present invention is further illustrated with reference to specific embodiment.
The first step:Using parallel construction mode(Parallel construction:Construct or construct respectively at the same time)Construction interior shaft well cap Engineering, effect one:Arrangement for interior shaft pit shaft sinking shaft facility provides condition;Effect two:In the construction of interior shaft well cap, realize Multilevel parallel, cross-operation speedy drivage.Comprise the following steps that:
1), at interior shaft -537m, -555m and -600m respectively working measure tunnel to the position of pit shaft, then blind Construction hoisting machine chamber above vertical shaft -537m(Long 18.7m, wide 14.1m, high 15.65m)And in -555m working measure engineerings lane Road, mixing plant chamber, yellow sand cement chamber and stone chamber, and-the 600m that constructs respectively since the -600m is to -575m ore storage bins With the light section of -600m to -555m pit shafts.
2), in step 1)After engineering construction, implement pit shaft at -600m to -555m sections and expand brush, and construct in -575m Distribute trolley chamber.
3), in step 2)After engineering construction, closing -555m well heads;Then in -537m to -555m construction guide wheel caves Room(Long 12m, wide 10.5m, high 9m), and p- 600m extremely -575m ore storage bins are poured, then under -600m to -575m ore storage bins Mouth installation ore drawing facility.
Closing -555m well heads:With 40# I-steel 120m, I-steel two is fixed with diameter 32mm twisted steel anchor rods, 38kg Rail 200m, thick 60 ㎡ of 8mm steel plates complete, weld after, pour the concrete of 0.5m thickness above, the buffering of 2m thickness padded after solidification Slag, for closing -555m well heads.
Bis- Walk:Carry out arrangement, the installment work of the top sinking shaft facility of interior shaft wellbore section -600m to -1240m.
1), carry out in -537m elevators chamber and guide wheel chamber the large-scale interim lifting erection of equipment of sinking shaft respectively: Guide wheel chamber installs a set of sinking headframe;And utilization -537m elevators chamber, guide wheel chamber, -537m return aircourses and -537m 9 stable cars are installed in the space of cross hairs chamber, and wherein 10 tons of stable cars of hanging scaffold 3,10 tons of stable cars of synovial membrane 3,10 tons of pipeline 1 is steady Car, 1, suspending pump double 16 tons of stable cars, the special 5 tons of stable cars of emergency staircase 1.And separately dig big section and in the big section One 2.5m winch is installed.
Take full advantage of the engineerings such as elevator chamber, guide wheel chamber, -537 meters of return aircourses, -537m cross hairs chambers;Profit Temporary transformer station is done with -537m switchgear houses, corresponding high-tension switch cabinet is installed, to winch and transformer-supplied, winch high pressure is 600KW/6000V, while a 400KVA transformer and corresponding low-tension switch cabinet are installed, supplied to stable vehicles and electric controll winch Electricity.
2), in -555m utilize working measure tunnel, be stirred station chamber, yellow sand cement chamber and stone cave respectively The arrangement of room.
3), in -575m using distributing trolley chamber, in the pit shaft of well cap, reinforcing -575m turns over gangue dumping platform and turns over cash groove, The barren rock of shaft excavation is directly entered by well-bucket into gangue dumping platform is turned in -575m the ore storage bins, be then transported to new vertical Main shaft is simultaneously promoted to earth's surface.
4), in -600m hole top signal system and distribution system are installed.The decentralization of personnel, material are each provided at -600m well heads. The discarded chamber of original installs the pressure fan of two 20m3, installs a 800KVA transformer as temporary transformer station and compressor house And corresponding low-tension switch cabinet, for power electricity consumption inferior on pressure fan, temporary drainage, suspending pump and well head.

Claims (3)

1. multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility, it is characterised in that comprises the following steps:
The first step:Constructed interior shaft well cap engineering using parallel construction mode, step is as follows:
1), at interior shaft -537m, -555m and -600m respectively working measure tunnel to the position of pit shaft, then interior shaft - Above 537m construction hoisting machine chamber and -555m working measures engineering tunnel, mixing plant chamber, yellow sand cement chamber and Stone chamber, and-the 600m that constructs respectively since the -600m is to -575m ore storage bins and -600m to the light section of -555m pit shafts;
2), in step 1)After engineering construction, implement pit shaft at -600m to -555m sections and expand brush, and construct and distribute in -575m Trolley chamber;
3), in step 2)After engineering construction, closing -555m well heads;Then in -537m to -555m construction guide wheel chambers, and P- 600m is poured to -575m ore storage bins, and then mouth installs ore drawing facility under -600m to -575m ore storage bins;
Bis- Walk:Arrangement, the installment work of the top sinking shaft facility of interior shaft wellbore section -600m to -1240m are carried out, step is such as Under:
1), carry out in -537m elevators chamber and guide wheel chamber the interim lifting erection of equipment of sinking shaft respectively:In guide wheel chamber Sinking headframe is installed;And utilization -537m elevators chamber, guide wheel chamber, -537m return aircourses and -537m cross hairs chambers Space is installed by some stable cars;And separately dig big section and the setting winch in the big section;
2), in -555m utilize working measure tunnel, be stirred station chamber, yellow sand cement chamber and stone chamber respectively Arrangement;
3), in -575m using distributing trolley chamber, in the pit shaft of well cap, reinforcing -575m turns over gangue dumping platform and turns over cash groove, makes well The barren rock of cylinder driving is directly entered in -575m the ore storage bins by well-bucket into gangue dumping platform is turned over, and is then transported to newly vertical main shaft And it is promoted to earth's surface;
4), in -600m hole top signal system and distribution system are installed.
2. a kind of self well digging construction method of multiple spot arrangement interior shaft sinking shaft facility as claimed in claim 1, its feature exist In:The step 4 of bis- Walk)In, the decentralization of personnel, material are each provided at -600m well heads;The discarded chamber of original as temporary transformer station and Compressor house, installs pressure fan, transformer and corresponding low-tension switch cabinet and supplies pressure fan, temporary drainage, suspending pump and well head respectively Upper and lower power electricity consumption.
3. a kind of self well digging construction method of multiple spot arrangement interior shaft sinking shaft facility as claimed in claim 1 or 2, its feature It is the step 3 of the first step)Material for closing -555m well heads is prepared in accordance with the following methods:With 40# I-steel 120m, I-steel two are fixed with diameter 32mm twisted steel anchor rods, 38kg rail 200m, and thick 60 ㎡ of 8mm steel plates is completed, welded Afterwards, the concrete of 0.5m thickness is poured above, and the buffering slag of 2m thickness is padded after solidification.
CN201610716117.9A 2016-08-25 2016-08-25 Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility Active CN106246187B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610716117.9A CN106246187B (en) 2016-08-25 2016-08-25 Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610716117.9A CN106246187B (en) 2016-08-25 2016-08-25 Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility

Publications (2)

Publication Number Publication Date
CN106246187A CN106246187A (en) 2016-12-21
CN106246187B true CN106246187B (en) 2018-04-27

Family

ID=57596126

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610716117.9A Active CN106246187B (en) 2016-08-25 2016-08-25 Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility

Country Status (1)

Country Link
CN (1) CN106246187B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577988B (en) * 2018-11-16 2021-07-02 北京中煤矿山工程有限公司 Parallel construction method for blind inclined shaft of metal mine
CN109630179B (en) * 2018-12-18 2020-04-14 中煤第一建设有限公司 Combined construction method for permanent locking notch of return air vertical shaft and pile wall of wind tunnel
CN113356859B (en) * 2021-06-10 2024-02-20 山东黄金矿业(莱州)有限公司三山岛金矿 Interlayer pouring and installing construction method for permanent engineering of blind vertical shaft cap

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3608822A1 (en) * 1986-03-17 1987-09-24 Deilmann Haniel Gmbh Guide arrangement for blind shafts
CN203199861U (en) * 2013-01-11 2013-09-18 玉溪大红山矿业有限公司 Bearing device for operations at mouth of blind shaft
CN203374282U (en) * 2013-06-13 2014-01-01 中国瑞林工程技术有限公司 Head sheave chamber arrangement structure of mine underground grounded multi-rope lifting system
CN103953368A (en) * 2014-05-14 2014-07-30 山东黄金矿业(莱州)有限公司三山岛金矿 Three-layer combined tunneling construction method for chamber of extra-large elevator
CN103967503A (en) * 2014-05-07 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Production-stop-free transformation method for tower type interior shaft elevating system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3608822A1 (en) * 1986-03-17 1987-09-24 Deilmann Haniel Gmbh Guide arrangement for blind shafts
CN203199861U (en) * 2013-01-11 2013-09-18 玉溪大红山矿业有限公司 Bearing device for operations at mouth of blind shaft
CN203374282U (en) * 2013-06-13 2014-01-01 中国瑞林工程技术有限公司 Head sheave chamber arrangement structure of mine underground grounded multi-rope lifting system
CN103967503A (en) * 2014-05-07 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Production-stop-free transformation method for tower type interior shaft elevating system
CN103953368A (en) * 2014-05-14 2014-07-30 山东黄金矿业(莱州)有限公司三山岛金矿 Three-layer combined tunneling construction method for chamber of extra-large elevator

Also Published As

Publication number Publication date
CN106246187A (en) 2016-12-21

Similar Documents

Publication Publication Date Title
CN103032073B (en) Urban subway mudstone stratum connected aisle and shield tunneling parallel construction method
CN103899335B (en) Synchronize tunneling operation system and the method for inverted arch synchronization lining
CN111852521B (en) Mouth-shaped piece assembling trolley for construction of internal structure of large-section shield tunnel and synchronous construction method
CN106246187B (en) Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility
CN106437737B (en) Pipe jacking type coal mine small-section roadway tunneling method
CN111810180B (en) Construction method for ultra-large-diameter earth pressure balance jacking pipe to penetrate through expressway
CN113530558A (en) Double-chute-inclined roadway combined layered construction method for big and high chamber
CN111550259A (en) Construction method of small-section long-distance soft rock tunnel
CN109706918B (en) Reinforcing cage orifice forming device for hoisting limited space and construction method thereof
CN202703579U (en) Large slope inclined shaft rail transport construction apparatus
CN112727470B (en) Construction reinforcing method for shield tunnel at overlapped section
Brannon et al. Development of and production update for the Grasberg Block Cave mine–PT Freeport Indonesia
CN103967052B (en) A kind of method of protecting the new and old frame core-tube system substrate discrepancy in elevation soil body
CN112922610A (en) Construction method for special railway line for downward passing freight by using shield tunneling machine
CN106337687A (en) Convenient segmented support method for mine slant chute
CN110284886B (en) Safety prevention and control method for deep vertical shaft wall fracture
CN109024670B (en) Underground comprehensive pipe gallery protection and reinforcement system penetrating through buried high-voltage cable and reinforcement method
CN110565634A (en) Method for repeatedly constructing and utilizing ultra-long steel casing
CN109930610A (en) Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete
CN207293981U (en) The hanging apparatus of two lining trolleys in a kind of sand gravel tunnel
CN1046784C (en) Reverse sinking construction method for mine vertical shaft
CN209873743U (en) Water and electricity engineering semi-underground shaft barrel type factory building
CN213063662U (en) Mechanized supporting construction equipment of heavy grade inclined shaft
CN107893659A (en) A kind of shaft excavation construction method for charging of being unearthed by underground
JP7188861B2 (en) Installation method of track for truck running

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Li Wenguang

Inventor after: Zhang Xiaogang

Inventor after: Liu Huanxin

Inventor after: Li Yang

Inventor after: Lv Yinglei

Inventor after: Wang Jiaoyan

Inventor after: Ye Lisheng

Inventor after: Li Wenbo

Inventor after: Shi Mingchao

Inventor before: Li Wenguang

Inventor before: Zhang Xiaogang

Inventor before: Liu Huanxin

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Li Wenguang

Inventor after: Zhang Xiaogang

Inventor after: Liu Huanxin

Inventor after: Li Yang

Inventor after: Lv Yinglei

Inventor after: Wang Jiaoyan

Inventor after: Ye Lisheng

Inventor after: Li Wenbo

Inventor after: Shi Mingchao

Inventor before: Li Wenguang

Inventor before: Zhang Xiaogang

Inventor before: Liu Huanxin

Inventor before: Li Yang

Inventor before: Lv Yinglei

Inventor before: Wang Jiaoyan

Inventor before: Ye Lisheng

Inventor before: Li Wenbo

Inventor before: Shi Mingchao