CN107893659A - A kind of shaft excavation construction method for charging of being unearthed by underground - Google Patents

A kind of shaft excavation construction method for charging of being unearthed by underground Download PDF

Info

Publication number
CN107893659A
CN107893659A CN201710970399.XA CN201710970399A CN107893659A CN 107893659 A CN107893659 A CN 107893659A CN 201710970399 A CN201710970399 A CN 201710970399A CN 107893659 A CN107893659 A CN 107893659A
Authority
CN
China
Prior art keywords
shaft
underground
vertical shaft
unearthed
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710970399.XA
Other languages
Chinese (zh)
Inventor
戴兴民
董贤顺
曹德更
陈法就
贠宁
张宾
范文泽
马立敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Zhiyuan Engineering Construction Supervision Co Ltd
China Railway 16th Bureau Group Co Ltd
Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
Beijing Zhiyuan Engineering Construction Supervision Co Ltd
China Railway 16th Bureau Group Co Ltd
Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Zhiyuan Engineering Construction Supervision Co Ltd, China Railway 16th Bureau Group Co Ltd, Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical Beijing Zhiyuan Engineering Construction Supervision Co Ltd
Priority to CN201710970399.XA priority Critical patent/CN107893659A/en
Publication of CN107893659A publication Critical patent/CN107893659A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of shaft excavation construction method be unearthed and fed by underground, comprise the following steps:It is interior on construction ground to perform vertical shaft hole and construction passage, the bottom of vertical shaft hole is connected by the construction passage with the existing underground space;In the outside of vertical shaft hole from top to bottom excavating shaft, will be transported at existing vertical shaft that the soil body caused by excavating shaft has after vertical shaft hole and construction passage out of the underground space successively;During shaft excavation, first at the top of excavating shaft and fore shaft circle is performed;Then proceed to downward excavating shaft, concrete mix is transported to the bottom of vertical shaft hole after existing vertical shaft, the underground space, construction passage successively simultaneously, and the shaft wall for having excavated part being pointed to by being arranged on the spray windlass of vertical shaft hole bottom below fore shaft circle performs concrete guard wall.Greatly reduce construction site area, solve removal problem;Reduce removal, alleviate noise, dust, road occupying etc. and disturb residents.

Description

A kind of shaft excavation construction method for charging of being unearthed by underground
Technical field
The present invention relates to Excavation Technology of Shafts field, it particularly relates to which a kind of pass through the perpendicular of the unearthed charging in underground Well excavation construction method.
Background technology
With the fast development of China's metro construction, heavy difficult point engineering in planning, long and pending is removed step by step The stage of history is gone up.It is beginning that construction site therein, which is removed, stand in the breach, extremely difficult problem.Beijing Iron Art Museum station C gateways evacuation mouth Construction of Silo is exactly a typical illustration.
Evacuation mouth vertical shaft is located at Wusi Dajie and Wangfujing Dajie intersection the southeast, open cut rectangular frame structure, foreign steamer Wide 11.52 × 5.60m of size, deep 15.61m.
Traditional way is shaft excavation by charging construction method of being unearthed on well.Shaft perimeter needs to provide about 460 ㎡'s Construction site.For setting air compressor machine, mixing machine, spray windlass;Deposit the placing of material such as native, unearthed, sand material, cement, grid.But The live actual construction site for there was only 130 ㎡.If according to the conventional method, its construction site can not meet to require, it is impossible to enter Row construction.
Its main cause is:1)Bustling downtown area removal expense is high,(The Yuan/㎡ of removal expense 250,000), construction costs can not hold By;2)Narrow construction site, it is impossible to which arrangement deposits Tu Chang;Loading machine, haulage vehicle can not operate;Various machineries and material can not Arrangement, stack.
The problem of in correlation technique, effective solution is not yet proposed at present.
The content of the invention
For the above-mentioned technical problem in correlation technique, the present invention proposes a kind of shaft excavation for charging of being unearthed by underground Construction method, using resources such as the existing construction site in station, equipment, to solve the unearthed charging problem of shaft excavation.
To realize above-mentioned technical purpose, the technical proposal of the invention is realized in this way:
A kind of shaft excavation construction method for charging of being unearthed by underground, comprises the following steps:
S1 is interior on construction ground to perform vertical shaft hole and construction passage, make the bottom of the vertical shaft hole by the construction passage with The existing underground space is connected;
S2 is in the outside of the vertical shaft hole from top to bottom excavating shaft, by the soil body caused by excavating shaft successively by described Transported at the existing vertical shaft having after vertical shaft hole and construction passage out of described the underground space;
During S3 shaft excavations, first at the top of excavating shaft and fore shaft circle is performed;
S4 then proceedes to downward excavating shaft, while concrete mix is passed through into the existing vertical shaft, the underground space successively, applied Be transported to the bottom of the vertical shaft hole after work passage, and by be arranged on the spray windlass of the vertical shaft hole bottom be pointed to it is described The shaft wall for having excavated part below fore shaft circle performs concrete guard wall.
Further, after the completion of S5 shaft excavations, the construction passage is backfilled.
Further, the internal diameter 0.8m of the vertical shaft hole, the concrete guard wall thickness are 0.1m.
Further, the headroom wide 3.0m, clear height 3.5m of the construction passage.
Further, the soil body and concrete mix are transported by electro-tricycle.
Further, the spray windlass is connected with high-pressure air hose, and the high-pressure air hose is through the vertical shaft hole 1 and extends At to the shaft wall for having excavated part.
Further, by high-pressure water pipe successively after the existing vertical shaft, the underground space, construction passage through described perpendicular Wellhole hole and extending to has been excavated at the shaft wall of part.
Further, the concrete mix includes microlith, sand, cement, accelerator.
Further, borehole wall supporting is provided between the shaft wall and the concrete guard wall.
Beneficial effects of the present invention:It is unearthed and is fed by underground, so as to greatly reduce construction site area, solves removal Problem;Construction site area is reduced, reduces removal, alleviate noise, dust, road occupying etc. and disturb residents;Reduce social contradications; The utilization rate of the resources such as existing construction site, equipment, electric power is improved, the arrangement pneumatics that its Construction of Silo place need not repeat Machine, mixing machine;The arrangement that need not be repeated deposits the equipment such as Tu Chang, loading machine;Water, electric increase-volume are not needed, improves economic benefit, Removal expense is reduced, has saved construction costs.Its social and economic benefits highly significant.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to institute in embodiment The accompanying drawing needed to use is briefly described, it should be apparent that, drawings in the following description are only some implementations of the present invention Example, for those of ordinary skill in the art, on the premise of not paying creative work, can also be obtained according to these accompanying drawings Obtain other accompanying drawings.
Fig. 1 is the plane of the shaft excavation construction method fed of being unearthed by underground described according to embodiments of the present invention Figure;
Fig. 2 is that the underground of the shaft excavation construction method by the unearthed charging in underground described according to embodiments of the present invention is unearthed Schematic diagram;
Fig. 3 is that the underground of the shaft excavation construction method by the unearthed charging in underground described according to embodiments of the present invention is fed Schematic diagram;
Fig. 4 is the flow chart of the shaft excavation construction method fed of being unearthed by underground described according to embodiments of the present invention.
In figure:
1st, vertical shaft hole;2nd, construction passage;3rd, fore shaft circle;4th, borehole wall supporting;5th, construction site;6th, existing vertical shaft;7th, road is fed Line;8th, concrete mix;9th, windlass is sprayed;10th, exit and entrance;11st, the underground space;12nd, high-pressure air hose;13rd, high-pressure water pipe; 14th, electro-tricycle;15th, be unearthed route.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained, belong to what the present invention protected Scope.
As shown in Fig. 1 ~ Fig. 4, described a kind of shaft excavation fed of being unearthed by underground according to embodiments of the present invention is applied Work method, comprises the following steps:
S1 performs vertical shaft hole 1 and construction passage 2 in 5 on construction ground, the bottom of the vertical shaft hole 1 is led to by the construction Road 2 is connected with the existing underground space 11;
The soil body caused by excavating shaft is passed through institute in the outside of the vertical shaft hole 1 from top to bottom excavating shaft by S2 successively State and transported at the existing vertical shaft 6 having after vertical shaft hole 1 and construction passage 2 out of described the underground space 11;
During S3 shaft excavations, first at the top of excavating shaft and fore shaft circle is performed;
S4 then proceedes to downward excavating shaft, while concrete mix is passed through into the existing vertical shaft, the underground space successively, applied Be transported to the bottom of the vertical shaft hole after work passage, and by be arranged on the spray windlass of the vertical shaft hole bottom be pointed to it is described The shaft wall for having excavated part below fore shaft circle performs concrete guard wall.
In one particular embodiment of the present invention, after the completion of S5 shaft excavations, the construction passage 2 is backfilled.
In one particular embodiment of the present invention, the internal diameter 0.8m of the vertical shaft hole 1, the concrete guard wall thickness For 0.1m.
In one particular embodiment of the present invention, the headroom wide 3.0m, clear height 3.5m of the construction passage 2.
In one particular embodiment of the present invention, the soil body and concrete mix 8 is transported by electro-tricycle 14 It is defeated.
In one particular embodiment of the present invention, the spray windlass 9 is connected with high-pressure air hose 12, the high-pressure air hose 12 Excavated through the vertical shaft hole 1 and extending at the shaft wall of part.
In one particular embodiment of the present invention, by high-pressure water pipe 13 successively by the existing vertical shaft 6, the underground space 11st, pass through the vertical shaft hole 1 after construction passage 2 and extend to and excavated at the shaft wall of part.
In one particular embodiment of the present invention, the concrete mix 8 includes microlith, sand, cement, accelerator.
In one particular embodiment of the present invention, it is provided with the borehole wall between the shaft wall and the concrete guard wall Supporting 4.
In order to facilitate the above-mentioned technical proposal of the present invention is understood, the above-mentioned skill below by way of specifically used mode to the present invention Art scheme is described in detail.
The present invention is using resources such as the existing construction site in station, equipment, to solve the unearthed charging problem of shaft excavation.It is logical Cross and apply manually digging hole, apply the means such as construction passage to realize.The present invention is fed due to being unearthed using underground, is greatly reduced and is applied Workshop ground area, solves removal problem.Constructed using this method:The construction site 5 of vertical shaft only needs 130 ~ 180 ㎡, for setting electricity Cucurbit, grid, Steel Reinforcing Bar Material, small machine, placing of material, manual operation space etc..This mode solves 1)It is difficult to remove;2) Narrow construction site, it is impossible to which arrangement deposits Tu Chang, and loading machine, transport vehicle can not operate, and various machineries and material can not be arranged, heap The problem put.
Comprise the concrete steps that:Apply vertical shaft hole 1 → applying construction passage 2 → and apply the 3 → shaft excavation of fore shaft circle and supporting → backfill construction passage 2.
1)Apply vertical shaft hole 1.Implemented using manually digging hole.The internal diameter of vertical shaft hole 1 is preferably 0.8m, using coagulation Soil makees retaining wall, thickness 10cm.The plan-position of borehole and depth requirements connect with the top for passage 2 of constructing, and combination wind, The arrangement of water, electric line, it is unearthed and feeds the combined factors consideration such as convenient, machine drilling can also be used.0.5 ~ 0.8m of aperture, is adopted Make retaining wall, 5 ~ 10mm of wall thickness with bellows.
It should ensure that the vertical shaft that need to be excavated nearby has the available underground space 11 before excavation, and the underground space 11 connects Existing vertical shaft 6, place is provided with existing unearthed charging place, equipment on the existing well of vertical shaft 6.Certainly it is liftoff in the vertical shaft that need to be excavated Lower space 11 farther out, the underground space 11 and it is existing it is unearthed charging place equipment road be not communicated with, need excavating shaft nearby do not have In the case of the available underground space can also by by vertical shaft hole 1, the underground space 11, it is existing it is unearthed charging place equipment Realized after connection or creation other conditions.
2)Apply construction passage 2.Constructed using benching tunnelling method, the wide construction headroom of passage 2 is preferably 3.0m, and free height is preferably 3.5m;Its plan-position requires that both ends connect with vertical shaft hole 1, the existing underground space 11 respectively;Its gradient is more preferably less than 12%;Passage supporting parameter is C20 gunite concretes, thickness 0.30m, steel grating cage bar 4 Φ 22, stirrup φ 8 ,@=200;Using Benching tunnelling method is constructed, and 0.5m is excavated in often circulation, and the installation Pin of steel grating one, steel grating, reinforcing bar, C20 gunite concretes etc. erects from existing Jing6Chu is fed.
According to specific design drawing, project scale, means of transport, the feed process that is unearthed, construction passage length, geology bar The actual conditions such as part, the cross dimensions of construction passage 2 can reduce or increase;Its gradient, supporting parameter, excavation method can be made Adjustment and change.Particularly arch runs into sandy soils, or under when wearing important building, it is necessary to take grouting with small pipe, deep hole note The measures such as slurry.
Certainly also can first apply construction passage 2, after apply vertical shaft hole 1 or vertical shaft hole 1, construction 2 parallel work of passage Industry, but when vertical shaft hole 1, construction 2 parallel operations of passage, the joint of the two, the distance that to stagger is constructed respectively, prevent from caving in And cause dangerous phenomenon.
3)Shaft excavation and apply fore shaft circle 3.By shaft excavation to the bottom of fore shaft circle 3, the soil body in digging process is abandoned In vertical shaft hole 1, the bottom electro-tricycle 14 of vertical shaft hole 1 connects soil, and according to unearthed route 15 successively by constructing The underground of spoir and existing vertical shaft 6 is deposited at heatable adobe sleeping platform after passage 2, the underground space 11, then passes through the side of lifting of grabbing bucket, machinery outward transport Formula spoir.Electro-tricycle 14 can use other means of transports to substitute.
The specific of fore shaft circle 3 applies step and is:Assembling reinforcement, construct, pay attention to pre-buried downwards by design drawing, job specfication The longitudinally connected muscle of steel grating;Formwork erection, using steel form or glued board formwork erection, pay attention to firm supporting, pre-buried portal frame, steel ladder, shield The built-in fittings such as column, wind, water, electricity, casting concrete, using commerical ready-mixed concrete, directly or two-wheel car is had bad luck and shaken into mould, shock club Smash, concrete surface plastic covering film and water seasoning;Portal frame, electric hoist are installed, fore shaft circle concrete reaches 70% intensity Afterwards, installed, coordinated using small-sized machine, manual site assembles portal frame, in place, welding, then installs I-steel and leads Rail, electric hoist, the main function of electric hoist is steel grating lifting, and small machine is lifted.
4)Shaft excavation and supporting
Continue excavating shaft, the soil body in digging process, which continues through aforesaid way and is transported to along the route 15 that is unearthed, to be deposited at heatable adobe sleeping platform.Often After excavating 0.5m depths, borehole wall supporting 4 is made in installation steel grating, and steel grating is processed by processing space, is transported to by the vertical shaft that need to be excavated, warp Electric hoist on well is lifted to the scope of operation, artificial in place, is tightened connecting bolt, is welded to connect muscle, assembling reinforcement mesh sheet.Pay attention to outer Profile linear dimension is accurate, and longitudinally connected muscle reserves downwards the lap of splice, and bolt and welding quality meet the requirements everywhere, steel grating peace Gunite concrete mix 8 after the completion of dress, concrete grade, match ratio in concrete mix 8 should be by design and laboratories Charger sheet is configured, and concrete is transported near the bottom of vertical shaft hole 1 by feeding route 7, and charging route will be specifically, will be thin The buying such as stone, sand, cement, accelerator, it is stored at the existing construction site on the existing well of vertical shaft 6;Shift to an earlier date 5 ~ 10 as needed Minute carries out dispensing, mix;Concrete mix 8 times is arrived to the bottoms of existing vertical shaft 6 by existing blanking equipment;Using electronic The splicing of tricycle 14 simultaneously transports to the spray side discharging of windlass 9;Artificial loading, by high-pressure air hose 12, high-pressure water pipe 13 by vertical shaft hole 1 Gunite concrete mix 8 after to the scope of operation.Wind, water, electric line are arranged along the side of construction passage 2.Concrete mix 8 Commodity gunite concrete material can be used, and using other transports, machinery, method.
After the completion of shaft excavation and supporting, a part of exit and entrance 10 is excavated using the vertical shaft scope of operation, is then applied The secondary lining of exit and entrance 10, vertical shaft.
5)Backfill construction passage 2.When passage 2 of constructing backfills, storage nearby needs the soil body backfilled at the scene in advance, and divides Section, layering, retreat backfill, compacting.Certainly according to on-site actual situations, different materials, distinct methods can also be used;Such as Also to abolish or stay at this after fruit and use it for anything else, can not backfill temporarily.
It is of the present invention to be applied by the shaft excavation construction method and charging of being unearthed on traditional well of the unearthed charging in underground Work mode compares, except that:
It is unearthed and is fed by underground, is excavated and be unearthed and can directly abandon in vertical shaft hole 1, electro-tricycle 14 carries out connecing soil, and transports to Heatable adobe sleeping platform is deposited in the existing underground of vertical shaft 6, so as to be unearthed using existing construction site, equipment, and need not repeat to set pneumatics The equipment such as machine, mixing machine.And use charging form of construction work of being unearthed on well to need to set gantry suspension bucket, or grab bucket in well head, or rise Heavy-duty machine deposits Tu Chang, it is necessary to big machinery and operation field, it is necessary to set.And need to set sand material, cement etc. stack place with And mix and stir, air feed, the equipment such as power supply.
Construction site is reduced using underground charging of being unearthed, has saved removal expense;Water is saved, electric expense of increasing capacity is used, solution Determine the removal problem of construction site.
To sum up, by means of the above-mentioned technical proposal of the present invention, at least have the following advantages that, be advantageous to carry in technical benefits The design of high building industry, construction level;To open new approach in complex ground constructing underground building;In economic benefit
1)Save removal expense:25×(460-130)=8,250 ten thousand yuan;(Remove monovalent:Ten thousand Yuan/㎡)×(Save area)
2)Save power supply for construction expense of increasing capacity:2000000 yuan
3)Save air compressor machine one:200000 yuan
4)Save mixing machine one:50000 yuan
5)Put into borehole expense:- 0.05 × 13=- 0.65 ten thousand yuan;(Unit price:Ten thousand yuan/m)×(Stake is long:m)
6)Input construction passage and backfill expense:- 0.6 × 29=- 17.4 ten thousand yuan;(Unit price:Ten thousand yuan/m)×(Grow in hole:m)
Above expense adds up to:8250+200+20+5-0.65-17.4=8456.95 ten thousand yuan;
Reduce removal in social benefit, alleviate noise, dust, road occupying etc. and disturb residents, reduce social contradications, saved work Journey cost, its social benefit highly significant.
These are only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent substitution and improvements made etc., it should be included in the scope of the protection.

Claims (9)

1. a kind of shaft excavation construction method for charging of being unearthed by underground, it is characterised in that comprise the following steps:
S1 is on construction ground(5)Inside perform vertical shaft hole(1)With construction passage(2), make the vertical shaft hole(1)Bottom pass through The construction passage(2)With the existing underground space(11)It is connected;
S2 is in the vertical shaft hole(1)Outside from top to bottom excavating shaft, the soil body caused by excavating shaft is passed through successively The vertical shaft hole(1)With construction passage(2)Afterwards from the underground space(11)The existing vertical shaft inside having(6)Place transports;
During S3 shaft excavations, first at the top of excavating shaft and fore shaft circle is performed(3);
S4 then proceedes to downward excavating shaft, while by concrete mix(8)Pass through the existing vertical shaft successively(6), underground Space(11), construction passage(2)After be transported to the vertical shaft hole(1)Bottom, and by being arranged on the vertical shaft hole(1)Bottom The spray windlass in portion(9)It is pointed to the fore shaft circle(3)The shaft wall for having excavated part of lower section performs concrete guard wall.
2. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that S5 vertical shafts After the completion of excavation, the construction passage is backfilled(2).
3. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that described perpendicular Wellhole hole(1)Internal diameter 0.8m, the concrete guard wall thickness is 0.1m.
4. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that described to apply Work passage(2)Headroom wide 3.0m, clear height 3.5m.
5. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that the soil Body and concrete mix(8)Pass through electro-tricycle(14)Transport.
6. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that the spray Windlass(9)It is connected with high-pressure air hose(12), the high-pressure air hose(12)Through the vertical shaft hole(1)And extend to excavation portion At the shaft wall divided.
7. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that by high pressure Water pipe(13)Pass through the existing vertical shaft successively(6), the underground space(11), construction passage(2)The vertical shaft hole is passed through afterwards(1) And extend to and excavated at the shaft wall of part.
8. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that described mixed Coagulate native mix(8)Including microlith, sand, cement, accelerator.
9. the shaft excavation construction method of charging according to claim 1 of being unearthed by underground, it is characterised in that described perpendicular Borehole wall supporting is provided between the well borehole wall and the concrete guard wall(4).
CN201710970399.XA 2017-10-18 2017-10-18 A kind of shaft excavation construction method for charging of being unearthed by underground Pending CN107893659A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710970399.XA CN107893659A (en) 2017-10-18 2017-10-18 A kind of shaft excavation construction method for charging of being unearthed by underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710970399.XA CN107893659A (en) 2017-10-18 2017-10-18 A kind of shaft excavation construction method for charging of being unearthed by underground

Publications (1)

Publication Number Publication Date
CN107893659A true CN107893659A (en) 2018-04-10

Family

ID=61803568

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710970399.XA Pending CN107893659A (en) 2017-10-18 2017-10-18 A kind of shaft excavation construction method for charging of being unearthed by underground

Country Status (1)

Country Link
CN (1) CN107893659A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206550A (en) * 2019-05-27 2019-09-06 中铁十八局集团第四工程有限公司 A kind of complicated geological excavates the construction of shield received well
CN111022057A (en) * 2019-12-21 2020-04-17 西安建筑科技大学 Subway tunnel well entering construction method and construction well supporting structure in loess region

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203499692U (en) * 2013-11-25 2014-03-26 中铁十八局集团有限公司 Special-shaped shaft adopted for subway construction under pipeline conditions
CN103939105A (en) * 2014-03-24 2014-07-23 中铁工程设计咨询集团有限公司 Construction method and structure for laying construction shaft above underground engineering
CN104806274A (en) * 2015-04-20 2015-07-29 中建南方投资有限公司 Large-span long-distance underground space main body supporting integrated structure and construction method
CN105523486A (en) * 2016-01-27 2016-04-27 中国十七冶集团有限公司 Lifting, conveying, loading and unloading device for hole digging of underground pipe gallery vertical shaft
CN106049195A (en) * 2016-05-27 2016-10-26 中铁三局集团有限公司 Method for strengthening subgrade basement of existing high speed railway line
CN106150506A (en) * 2016-07-08 2016-11-23 中铁十六局集团地铁工程有限公司 A kind of gateway open excavation section inverted side-wall construction method
CN106284410A (en) * 2016-08-27 2017-01-04 廊坊师范学院 The complete rapid constructing method of covered back-digging subway transfer station

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203499692U (en) * 2013-11-25 2014-03-26 中铁十八局集团有限公司 Special-shaped shaft adopted for subway construction under pipeline conditions
CN103939105A (en) * 2014-03-24 2014-07-23 中铁工程设计咨询集团有限公司 Construction method and structure for laying construction shaft above underground engineering
CN104806274A (en) * 2015-04-20 2015-07-29 中建南方投资有限公司 Large-span long-distance underground space main body supporting integrated structure and construction method
CN105523486A (en) * 2016-01-27 2016-04-27 中国十七冶集团有限公司 Lifting, conveying, loading and unloading device for hole digging of underground pipe gallery vertical shaft
CN106049195A (en) * 2016-05-27 2016-10-26 中铁三局集团有限公司 Method for strengthening subgrade basement of existing high speed railway line
CN106150506A (en) * 2016-07-08 2016-11-23 中铁十六局集团地铁工程有限公司 A kind of gateway open excavation section inverted side-wall construction method
CN106284410A (en) * 2016-08-27 2017-01-04 廊坊师范学院 The complete rapid constructing method of covered back-digging subway transfer station

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李文俊: "夹活岩特长公路隧道竖井设计及施工方法探讨", 《铁道标准设计》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206550A (en) * 2019-05-27 2019-09-06 中铁十八局集团第四工程有限公司 A kind of complicated geological excavates the construction of shield received well
CN111022057A (en) * 2019-12-21 2020-04-17 西安建筑科技大学 Subway tunnel well entering construction method and construction well supporting structure in loess region
CN111022057B (en) * 2019-12-21 2024-05-07 西安建筑科技大学 Subway tunnel well entry construction method and construction well supporting structure in loess area

Similar Documents

Publication Publication Date Title
CN101864959B (en) Method for tunneling construction of main structure of underground station
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN108397201A (en) The safe construction method of rock tunnel(ling) machine
CN107060796A (en) One kind uses Slurry Balanced Pipe Jacking Construction technique
CN109595004B (en) Tunnel two-expansion four-expansion excavation method
CN103244128A (en) Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods
CN111287759B (en) Shallow-buried close-connection underground excavation tunnel construction method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN106437737B (en) Pipe jacking type coal mine small-section roadway tunneling method
CN106837341B (en) A kind of Metro construction construction method of shaft wall
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN113153308A (en) Construction method for double arch tunnel collapse section
CN111395322A (en) Construction method for rotary digging cast-in-place pile under karst landform
CN109706945A (en) Come down fracture belt tunnel construction method
CN103174131A (en) Underground engineering guiding-cavity-excavating small-diameter pile construction complete equipment system
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN206888990U (en) A kind of Shallow Covered Metro Station separates open type structure
CN107893659A (en) A kind of shaft excavation construction method for charging of being unearthed by underground
CN110778322A (en) Remote large-pipe-diameter multi-terrain mud-water-balance pipe jacking construction method
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN102235007A (en) Method for supporting deep foundation with upper nail-lower pile combination
CN107701192A (en) Box culvert relaying pushing tow system with pushing frame component
CN109024670B (en) Underground comprehensive pipe gallery protection and reinforcement system penetrating through buried high-voltage cable and reinforcement method
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN205618170U (en) Protective structure of no template punishment rock mass cavity in tunnel engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180410

RJ01 Rejection of invention patent application after publication