CN106219116B - Mobile piler and its clamp method - Google Patents

Mobile piler and its clamp method Download PDF

Info

Publication number
CN106219116B
CN106219116B CN201610607559.XA CN201610607559A CN106219116B CN 106219116 B CN106219116 B CN 106219116B CN 201610607559 A CN201610607559 A CN 201610607559A CN 106219116 B CN106219116 B CN 106219116B
Authority
CN
China
Prior art keywords
piler
mobile
loading platform
organism frame
fixedly installed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610607559.XA
Other languages
Chinese (zh)
Other versions
CN106219116A (en
Inventor
朱红蔚
张松刚
职山杰
崔少中
王世鑫
唐勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guoxin Robot Wuxi Ltd By Share Ltd
Original Assignee
Guoxin Robot Wuxi Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guoxin Robot Wuxi Ltd By Share Ltd filed Critical Guoxin Robot Wuxi Ltd By Share Ltd
Priority to CN201610607559.XA priority Critical patent/CN106219116B/en
Publication of CN106219116A publication Critical patent/CN106219116A/en
Application granted granted Critical
Publication of CN106219116B publication Critical patent/CN106219116B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G1/00Storing articles, individually or in orderly arrangement, in warehouses or magazines
    • B65G1/02Storage devices
    • B65G1/04Storage devices mechanical
    • B65G1/0407Storage devices mechanical using stacker cranes
    • B65G1/0428Transfer means for the stacker crane between the alleys

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Forklifts And Lifting Vehicles (AREA)
  • Warehouses Or Storage Devices (AREA)

Abstract

The present invention relates to a kind of mobile pilers, including organism frame and the loading platform for being movably disposed in the organism frame, being carried up and down for completing cargo, the loading platform its up and down motion is realized by the lifting mechanism being installed on the organism frame;Further include being fixedly installed on the organism frame bottom, for realizing the whole free-moving mobile mechanism of piler, and it is fixedly installed on the organism frame side, is integrally oriented to and maintains stable guiding mechanism, the mobile mechanism to match the self-movement for completing piler entirety with guiding mechanism for realizing piler.The mobile piler of the present invention can be moved freely directly in warehouse, fully realized piler high efficiency, run to facilitation.Meanwhile mobile piler of the invention, the complicated architectures in traditional stereoscopic warehousing system are simplified, the track for eliminating day rail is laid with, and improves the practicability of system.

Description

Mobile piler and its clamp method
Technical field
The present invention relates to a kind of piler more particularly to a kind of mobile piler suitable for using in bulk storage plant, Belong to logistics and transportation technical field.
Background technology
Now, logistlcs technology increasingly attracts people's attention, and warehouse plays critical effect in logistics system.Heap Stack machine plays the carrying work of storage cargo in the entire system, is an essential link of automatic stereowarehouse, can To say, piler technology is the core place of entire Automatic Warehouse technology.
Currently, the operation of piler is typically necessary by day rail and track, and under the mating reaction of the two, stacking function It is enough to complete front and back operation, and the hoistable platform on piler can then be run up and down.This knockdown operation enables to heap Any goods yard in stack machine trouble-free operation to warehouse carries out stock and picking work.
In the prior art, the piler in large-sized automated warehouse just needs to preset rail in present warehouse when in use Road.Specifically, storage enterprise needs the pre-buried track in warehouse floor before using piler.In addition to this, piler is such as Fruit only relies on track operation, it is difficult to ensure that the stabilization of its operation, therefore in order to realize the reliable and stable operation of piler, storage enterprise Industry also needs to again to being reinforced at the top of warehouse, then re-laying a day rail.Without doubt, track and the laying of day rail are undoubtedly big The big difficulty for increasing warehouse foundation of civil work construction and period, construction cost is increased, whole project progress is extended, one Determine to also result in the wasting of resources of enterprise in degree.
Chinese patent CN105366372A is related to a kind of piler, including rack, the orientating and conveying mechanisms of device in rack And disc mechanism is unfolded, and unfold the top that disc mechanism is placed in the orientating and conveying mechanisms, it is described to unfold disc mechanism and pass through horizontal slider Carriage drives on the horizontal slide rail of frame top and by the mobile motor of frame top side;It is described to unfold disc mechanism Disk device is unfolded including one, disk device is unfolded and turnover box can be pressed from both sides in being slided up and down on slider bracket by slide block structure It holds and discharges.The structure of piler is improved in above-mentioned technical proposal, traditional day rail and track are integrated Improvement, is reduced to rack, keeps the overall operation process of piler more independent, convenient.But such structure setting is again Bring some new problems, precisely due to the limitation of rack construction, cause in use piler can run covering Region it is smaller.Simultaneously because the overall structure of piler becomes increasingly complex, thus its movement, use and follow-up maintenance all compared with For difficulty.
Therefore, how under the premise of ensureing efficient piler, convenient operation, simplify and exempt the paving of day rail and track If reducing machinery and the crossed construction of civil engineering, the construction cost of storage enterprise is reduced, shortens construction period, expands stacking The scope of application of machine just becomes those skilled in that art's technical problem urgently to be resolved hurrily.
Invention content
In view of the prior art there are drawbacks described above, the purpose of the present invention is to propose to a kind of suitable for using in bulk storage plant Mobile piler.
The purpose of the present invention will be achieved by the following technical programs:
A kind of movable type piler, including organism frame and be movably disposed in the organism frame, be used for At the loading platform that cargo is carried up and down, the loading platform is real by the lifting mechanism being fixedly installed on the organism frame Its existing up and down motion;Further include be fixedly installed on the organism frame bottom, for realizing the mobile piler it is whole from By mobile mobile mechanism, and it is fixedly installed on the organism frame side, for realizing the mobile piler entirety It is oriented to and maintains stable guiding mechanism, it is whole that the mobile mechanism matches the completion mobile piler with guiding mechanism Self-movement.
Preferably, the loading platform includes top-support and bottom bracket, between the top-support and bottom bracket It is fixedly connected by the completion of at least two root posts, the dimensions of the top-support and the bottom bracket is consistent.
Preferably, the loading platform and the bottom bracket of the organism frame match, and are arranged in the loading platform There are multiple load stations to match with cargo to be handled, the both ends of the loading platform are both provided with sliding bearing, the load Goods platform is slided up and down by the sliding bearing along column extending direction completion.
Preferably, the lifting mechanism includes hoist engine and the pulley assembly that is drivingly connected with the hoist engine, the volume The machine of raising is fixedly installed on the center position of the bottom bracket lower face, and the pulley assembly includes at least four fixed settings In pulley and at least two steel wire ropes being fixedly connected with the hoist engine on the organism frame, the pulley fixation is set The end positions of the organism frame are placed in, one end of the steel wire rope is fixedly connected with the loading platform, the other end bypasses It is intertwined and connected with the hoist engine after the pulley.
Preferably, the mobile mechanism is fixedly installed on the organism frame bottom, for realizing institute including at least four It states the free-moving movable pulley of mobile piler and is fixedly installed on the organism frame bottom, for driving the movement Take turns the driving motor of rotation.
Preferably, the center position of the movable pulley is provided through the mounting hole for being fixedly connected, the movement Wheel is connect by the mounting hole with axle drive, and the rotation axis for assisting it to complete rotation is also embedded on the movable pulley It holds, the axle is connect with the bearing hole of the rolling bearing, and the axle is fixedly installed on the two of the organism frame bottom End position, at least one transmission gear for transmission is further fixedly arranged on the axle, and the driving motor is drivingly connected There is a decelerating motor, a driving gear, the driving gear and driving cog are fixedly installed on the output shaft of the decelerating motor The driving of the mobile mechanism is completed in wheel engagement, the two cooperation.
Preferably, the guiding mechanism includes at least eight sets of guide wheel groups for playing guiding and stabilization, described Guide wheel group is uniformly arranged the end Angle Position in the top-support and bottom bracket.
Guide wheel group described in every group includes directive wheel, guide bearing, shaft and fixed seat, is offered on the directive wheel Endoporus, the guide bearing, which is inlayed, to be fixedly installed in the endoporus, and the shaft runs through connection with the guide bearing, described Fixed seat is fixedly connected with the both ends of the shaft, and the shaft is fixedly connected by the fixed seat with the organism frame.
Preferably, further include being fixedly installed on the organism frame, for driving the mobile piler integrally to transport The electric mechanism of work, the electric mechanism are electrically connected with each electric component inside the mobile piler and drive each electric appliance Part runs, the electric mechanism include being fixedly installed on the power control cabinet of the organism frame bottom and electrical with the power control cabinet The harness of connection, the power control cabinet is electrically connected by the harness and hoist engine, driving motor and decelerating motor, described Harness fixes the bottom for being accommodated in the organism frame.
Present invention further teaches a kind of clamp methods using above-mentioned mobile piler, include the following steps:
(1)Code goods step,
After S1, cargo reach warehouse by lorry or mobile platform, it is transported to yard freight house storage area domain of waiting in warehouse, is moved Dynamic formula piler is moved to corresponding station, and the guiding mechanism on the mobile piler by mobile mechanism thereon immediately With in storage area wall or container be bonded and complete the support of the mobile piler and position;
S2, the mobile piler positioning after the completion of, operator is put down cargo block pattern row pattern to loading using fork truck On platform, then the electric mechanism on the mobile piler starts to drive lifting mechanism running, in the drive of the lifting mechanism Under dynamic, the loading platform rises, and by goods handling to eminence, when the loading platform rises to preset storage height When, the lifting mechanism stops operating, and the loading platform stops rising immediately;
S3, the loading platform stop after rising, and the operator in eminence storage region recycles fork truck described The cargo of block pattern row pattern unloads in loading platform, and piles up to the storage region of eminence, until it is flat to complete the entire loading Removing for cargo is unloaded on platform, and the lifting mechanism drives the loading platform to reset, and then the mobile piler is moved to down One storage region, completes the operation of subsequent code goods;
(2)Unloading operation,
S1, mobile piler, which are moved to by mobile mechanism thereon in warehouse, waits for unloading storage region, and described Guiding mechanism on mobile piler in storage area wall or container be bonded and complete the branch of the mobile piler Support positioning;
S2, the mobile piler positioning after the completion of, the electric mechanism on the movable type piler starts to drive Lifting mechanism operates, and under the driving of the lifting mechanism, the loading platform rises, when the loading platform rise to it is default Storage height when, the lifting mechanism stops operating, and the loading platform stops rising immediately, then in eminence warehouse district Operator in domain will be on cargo block pattern row pattern to loading platform using fork truck;
After the completion of S3, cargo are piled up, the lifting mechanism operates again, and drives the loading platform with dropping to warehouse Cargo in the loading platform is unloaded and is carried on lorry or mobile platform using fork truck again by face, subsequent operator, It is unloaded until completing removing for cargo in the entire loading platform, then the mobile piler is moved to next storage region, Complete follow-up unloading operation.
The present invention protrusion effect be:The mobile piler of the present invention can be moved freely directly in warehouse, completely Ground covers the space of entire store interior, fully realizes piler high efficiency, runs to facilitation.Meanwhile the present invention Mobile piler the positioning of its own is completed using guide wheel system, simplify answering in traditional stereoscopic warehousing system Miscellaneous framework, the track for eliminating day rail are laid with, reduce machinery and the crossed construction of civil engineering to the maximum extent, reduce storehouse The construction cost for storing up enterprise, shortens whole construction period, improves the practicability of system.In addition, the movable type of the present invention Stacker structure is simple, and each storage enterprise can be obtained by repacking, assembling to existing equipment, not only equipment cost it is low, But also various working is coped with, there is very high use value and the wide scope of application.
In conclusion wide coverage of the present invention, operational efficiency are high, cope with and work long hours and various working, and And its is simple in structure, is easily obtained, and has very high use and promotional value.
Just attached drawing in conjunction with the embodiments below, the embodiment of the present invention is described in further detail, so that of the invention Technical solution is more readily understood, grasps.
Description of the drawings
Fig. 1 is the front view of the present invention;
Fig. 2 is the side view of the present invention;
Fig. 3 is the vertical view of the present invention;
Wherein:1, organism frame;2, loading platform;3, lifting mechanism;4, mobile mechanism;5, guiding mechanism;6, electrical machine Structure.
Specific implementation mode
Present invention is disclosed a kind of mobile pilers suitable for being used in bulk storage plant.
As shown in Fig. 1 ~ Fig. 3, a kind of movable type piler, including organism frame 1 and it is movably disposed in the machine The loading platform 2 carried up and down in body frame 1, for completing cargo, the loading platform 2 is by being fixedly installed in the body Lifting mechanism 3 on frame 1 realizes its up and down motion;Further include being fixedly installed on 1 bottom of the organism frame, for realizing institute Mobile piler integrally free-moving mobile mechanism 4 is stated, and is fixedly installed on 1 side of the organism frame, for real The existing mobile piler is integrally oriented to and maintains stable guiding mechanism 5, the mobile mechanism 4 to match with guiding mechanism 5 Close the self-movement for completing the mobile piler entirety.Self-movement described herein refers to the mobile piler Autonomous can be completed under the premise of not by day rail, track.
The loading platform 2 includes top-support and bottom bracket, by extremely between the top-support and bottom bracket Few two root posts completion is fixedly connected, and the dimensions of the top-support and the bottom bracket is consistent.In this reality It applies in example, the column is provided with two, and two columns are symmetrically disposed on the two of the top-support and bottom bracket End position.
The loading platform 2 and the bottom bracket of the organism frame 1 match, and are provided in the loading platform 2 more The both ends of a load station to match with cargo to be handled, the loading platform 2 are both provided with sliding bearing, and the loading is flat Platform 2 is slided up and down by the sliding bearing along column extending direction completion.
In the present embodiment, two end side surfaces of the loading platform 2 are provided with the short axle of stretching, consolidate respectively in the short axle Equipped with sliding bearing is nested, the sliding bearing can slide up and down on the inside of the column for Dingan County, play guiding and make With to enable the loading platform 2 smoothly to complete oscilaltion.Corresponding, the upper and lower ends of the column are also solid Surely the limited block for limiting the sliding bearing movement travel, area of the sliding bearing between the limited block are provided with It is movable in domain.
The lifting mechanism 3 includes that hoist engine and the pulley assembly with hoist engine drive connection, the hoist engine are solid Surely it is set to the center position of the bottom bracket lower face, the pulley assembly is fixedly installed on described including at least four Pulley on organism frame 1 and at least two steel wire ropes being fixedly connected with the hoist engine, the pulley are fixedly installed on The end positions of the organism frame 1, one end of the steel wire rope is fixedly connected with the loading platform 2, the other end bypasses institute It is intertwined and connected with the hoist engine after stating pulley.
Specifically, in the present embodiment, the hoist engine, which is bolted, to be installed on the organism frame 1, institute The output shaft for stating hoist engine has been directly connected to lifting speed reducing, and the lifting speed reducing is fixed with the reel in the hoist engine to be connected It connects, the reel uses double-rope structure, stretches out two steel wire ropes, the loading at synchronized links both ends respectively to both direction Platform 2.
The pulley assembly includes at least eight pulleys and two steel wire ropes, and the pulley is uniformly arranged in the top branch Every one end of the end positions of frame and bottom bracket, the top-support and bottom bracket is both provided at least two pulleys.This The setting of the multiple pulleys of sample is that movable pulley labour-saving principle is utilized, and by increasing the quantity of pulley, makes lifting mechanism part structure At running block structure, to play the role of reducing the hoist engine live load.
One end of the steel wire rope is fixedly connected on the side of the loading platform 2, and the other end sequentially bypasses setting successively It is wound to again on the reel of the hoist engine after the pulley at the top-support and bottom bracket both ends.So, work as institute When stating hoist engine and starting operation, the spool turns, to drive the loading platform 2 to complete lifting.
The mobile mechanism 4 is fixedly installed on 1 bottom of the organism frame, for realizing the movement including at least four The free-moving movable pulley of formula piler and it is fixedly installed on 1 bottom of the organism frame, for driving the mobile rotation Dynamic driving motor.
The center position of the movable pulley is provided through the mounting hole for being fixedly connected, and the movable pulley is by institute It states mounting hole to connect with axle drive, the rolling bearing for assisting it to complete rotation is also embedded on the movable pulley, it is described Axle is connect with the bearing hole of the rolling bearing, and the axle is fixedly installed on the end positions of 1 bottom of the organism frame, In the present embodiment, the axle is fixedly installed at the end positions of the bottom bracket lower face.It is also solid on the axle Surely it is provided at least one transmission gear for transmission, the driving motor drive connection has a decelerating motor, the deceleration Motor is fixedly installed on the lower face of the bottom bracket by decelerating motor flange, is fixed on the output shaft of the decelerating motor It is provided with a driving gear, the driving gear is engaged with transmission gear, the two coordinates the driving for completing the mobile mechanism.
In the present embodiment, the driving gear is fixedly connected with the movable pulley, and the driving gear is fixedly installed on The center position of the movable pulley is completed to fix between the driving gear and the movable pulley by connecting key, and by Bolt realizes that the compression between the two connects.Likewise, the driving gear also completes itself and the decelerating motor by connecting key Output shaft be fixedly connected.
The guiding mechanism 5 includes at least eight sets of guide wheel groups for playing guiding and stabilization, the directive wheel Group is uniformly arranged the end Angle Position in the top-support and bottom bracket.Guide wheel group described in every group includes directive wheel, leads To bearing, shaft and fixed seat, endoporus is offered on the directive wheel, the guide bearing, which is inlayed, is fixedly installed on the endoporus In, the shaft is with the guide bearing through connection, and the fixed seat is fixedly connected with the both ends of the shaft, the shaft It is fixedly connected with the organism frame 1 by the fixed seat.
It, can also be according to actual herein it should be noted that in addition to the structure setting of above-mentioned directive wheel and guide bearing It is arranged and covers using needing to omit the structure of the guide bearing, instead in the wheel week outer rim of the directive wheel One layer of rubber ring of lid, such structure setting equally disclosure satisfy that the use needs of the guide wheel group.
Further include be fixedly installed on the organism frame 1, the electricity for driving the mobile piler overall operation Mechanism of qi structure 6, the electric mechanism 6 are electrically connected with each electric component inside the mobile piler and drive each electric component Running, the electric mechanism includes being fixedly installed on the power control cabinet of 1 bottom of the organism frame and electrically connecting with the power control cabinet The harness connect, the power control cabinet are electrically connected by the harness and hoist engine, driving motor and decelerating motor, the line Beam fixes the bottom for being accommodated in the organism frame 1.
In addition it is also necessary to illustrate, the mobile mechanism 4 in mobile piler of the invention not only may be used Rubber-tyred structure as mentioned in above-described embodiment, additionally it is possible to using such as conveyer belt, crawler belt structure come realizing piler It moves freely.More specifically structure setting operator can be further true according to its specific needs in actual use It is fixed.
Present invention further teaches a kind of clamp methods using above-mentioned mobile piler, include the following steps:
(1)Code goods step,
After S1, cargo reach warehouse by lorry or mobile platform, it is transported to yard freight house storage area domain of waiting in warehouse, is moved Dynamic formula piler is moved to corresponding station, and the guiding mechanism on the mobile piler by mobile mechanism thereon immediately With in storage area wall or container be bonded and complete the support of the mobile piler and position;
S2, the mobile piler positioning after the completion of, operator is put down cargo block pattern row pattern to loading using fork truck On platform 2, then the electric mechanism 6 on the mobile piler starts that lifting mechanism 3 is driven to operate, in the lifting mechanism 3 Driving under, the loading platform 2 rises, and by goods handling to eminence, when the loading platform 2 rises to preset storage When height, the lifting mechanism 3 stops operating, and the loading platform 2 stops rising immediately;
S3, the loading platform 2 stop after rising, and the operator in eminence storage region recycles fork truck described The cargo of block pattern row pattern unloads in loading platform 2, and piles up to the storage region of eminence, until it is flat to complete the entire loading Removing for cargo is unloaded on platform 2, and the lifting mechanism 3 drives the loading platform 2 to reset, and then the mobile piler is moved to The operation of subsequent code goods is completed in next storage region;
(2)Unloading operation,
S1, mobile piler, which are moved to by mobile mechanism thereon in warehouse, waits for unloading storage region, and described Guiding mechanism on mobile piler in storage area wall or container be bonded and complete the branch of the mobile piler Support positioning;
S2, the mobile piler positioning after the completion of, the electric mechanism 6 on the movable type piler starts to drive Lifting mechanism 3 operates, and under the driving of the lifting mechanism 3, the loading platform 2 rises, when the loading platform 2 rises to When preset storage height, the lifting mechanism 3 stops operating, and the loading platform 2 stops rising immediately, then in eminence The operator to store in a warehouse in region will be on cargo block pattern row pattern to loading platform 2 using fork truck;
After the completion of S3, cargo are piled up, the lifting mechanism 3 operates again, and the loading platform 2 is driven to drop to warehouse Cargo in the loading platform 2 is unloaded and is carried to lorry or mobile platform by ground, subsequent operator using fork truck again On, it is unloaded until completing removing for cargo in the entire loading platform 2, then the mobile piler is moved to next warehouse district Follow-up unloading operation is completed in domain.
The mobile piler of the present invention can be moved freely directly in warehouse, completely cover entire store interior Space, fully realize that piler is efficient, runs to facilitation.Meanwhile mobile piler of the invention is used and is led The positioning that its own is completed to wheel system simplifies the complicated architectures in traditional stereoscopic warehousing system, eliminates day rail Track is laid with, and is reduced machinery and the crossed construction of civil engineering to the maximum extent, is reduced the construction cost of storage enterprise, is contracted Short whole construction period, improves the practicability of system.In addition, the mobile stacker structure of the present invention is simple, each storehouse Storage enterprise can be obtained by repacking, assembling to existing equipment, and not only equipment cost is low but also copes with a variety of works Condition has very high use value and the wide scope of application.
In conclusion wide coverage of the present invention, operational efficiency are high, cope with and work long hours and various working, and And its is simple in structure, is easily obtained, and has very high use and promotional value.
Still there are many embodiment, all technical sides formed using equivalents or equivalent transformation by the present invention Case is within the scope of the present invention.

Claims (2)

1. a kind of movable type piler, it is characterised in that:Including organism frame (1) and it is movably disposed in the body frame The loading platform (2) carried up and down in frame (1), for completing cargo, the loading platform (2) is by being fixedly installed in the machine Lifting mechanism (3) on body frame (1) realizes its up and down motion;Further include being fixedly installed on the organism frame (1) bottom, use In realizing the mobile piler integrally free-moving mobile mechanism (4), and it is fixedly installed on the organism frame (1) Side is integrally oriented to and maintains stable guiding mechanism (5), the mobile mechanism (4) for realizing the mobile piler The self-movement for completing the mobile piler entirety is matched with guiding mechanism (5);The loading platform (2) includes top Holder and bottom bracket are fixedly connected between the top-support and bottom bracket by the completion of at least two root posts, the top Portion's holder and the dimensions of the bottom bracket are consistent;The bottom of the loading platform (2) and the organism frame (1) Portion's holder matches, and multiple load stations to match with cargo to be handled, the loading are provided on the loading platform (2) The both ends of platform (2) are both provided with sliding bearing, and the loading platform (2) is by the sliding bearing along the column extension side It is slided up and down to completion;The lifting mechanism (3) includes hoist engine and the pulley assembly that is drivingly connected with the hoist engine, described Hoist engine is fixedly installed on the center position of the bottom bracket lower face, and the pulley assembly includes that at least four fixations are set The pulley and at least two steel wire ropes being fixedly connected with the hoist engine being placed on the organism frame (1), the pulley It is fixedly installed on the end positions of the organism frame (1), one end of the steel wire rope and the fixed company of the loading platform (2) It connects, the other end is intertwined and connected after bypassing the pulley with the hoist engine;The mobile mechanism (4) includes that at least four fixations are set It is placed in the organism frame (1) bottom, for realizing the free-moving movable pulley of the movable type piler and fixed setting In the organism frame (1) bottom, the driving motor for driving the movable pulley rotation;The center position of the movable pulley It is provided through the mounting hole for being fixedly connected, the movable pulley is connect by the mounting hole with axle drive, the shifting The rolling bearing for assisting it to complete rotation is also embedded on driving wheel, the bearing hole of the axle and the rolling bearing connects It connects, the axle is fixedly installed on the end positions of the organism frame (1) bottom, is further fixedly arranged at least on the axle One transmission gear for transmission, the driving motor drive connection have a decelerating motor, the output shaft of the decelerating motor On be fixedly installed a driving gear, the driving gear engage with transmission gear, both coordinate the completion mobile mechanism Driving;The guiding mechanism (5) includes at least eight sets of guide wheel groups for playing guiding and stabilization, the guide wheel group It is uniformly arranged the end Angle Position in the top-support and bottom bracket;Guide wheel group described in every group includes directive wheel, is oriented to Bearing, shaft and fixed seat offer endoporus on the directive wheel, and the guide bearing, which is inlayed, is fixedly installed on the endoporus In, the shaft is with the guide bearing through connection, and the fixed seat is fixedly connected with the both ends of the shaft, the shaft It is fixedly connected with the organism frame (1) by the fixed seat;Further include being fixedly installed on the organism frame (1), using In the electric mechanism (6) for driving the mobile piler overall operation, the electric mechanism (6) and the mobile piler Internal each electric component is electrically connected and each electric component is driven to operate, and the electric mechanism includes being fixedly installed on the body The power control cabinet of frame (1) bottom and with the power control cabinet be electrically connected harness, the power control cabinet by the harness with it is described Hoist engine, driving motor and decelerating motor are electrically connected, and the harness fixes the bottom for being accommodated in the organism frame (1).
2. a kind of clamp method of application mobile piler as described in claim 1, which is characterized in that including walking as follows Suddenly:(1) code goods step after S1, cargo reach warehouse by lorry or mobile platform, is transported in warehouse and waits for a yard freight house storage Region, mobile piler are moved to corresponding station by mobile mechanism thereon immediately, and on the mobile piler Guiding mechanism in storage area wall or container be bonded and complete the support of the mobile piler and position;S2, the shifting After the completion of the positioning of dynamic formula piler, operator using fork truck by cargo block pattern row pattern to loading platform (2), the subsequent shifting Electric mechanism (6) on dynamic formula piler starts that lifting mechanism (3) is driven to operate, under the driving of the lifting mechanism (3), institute Loading platform (2) rising is stated, and by goods handling to eminence, when the loading platform (2) rises to preset storage height, The lifting mechanism (3) stops operating, and the loading platform (2) stops rising immediately;On S3, the loading platform (2) stopping After rising, the operator in eminence storage region recycles fork truck to unload the cargo of block pattern row pattern in the loading platform (2) Under, and pile up to the storage region of eminence, it is unloaded until completing removing for cargo on the entire loading platform (2), the raising Mechanism (3) drives the loading platform (2) to reset, and then the mobile piler is moved to next storage region, after the completion Continued code goods operates;(2) unloading operation, S1, mobile piler are moved in warehouse by mobile mechanism thereon and wait unloading Store in a warehouse region, and the guiding mechanism on the mobile piler in storage area wall or container be bonded the completion shifting The support of dynamic formula piler positions;S2, the mobile piler positioning after the completion of, it is electrical on the movable type piler Mechanism (6) starts that lifting mechanism (3) is driven to operate, and under the driving of the lifting mechanism (3), the loading platform (2) rises, When the loading platform (2) rises to preset storage height, the lifting mechanism (3) stops operating, the loading platform (2) stop rising immediately, put down cargo block pattern row pattern to loading using fork truck then in the operator in eminence storage region On platform (2);After the completion of S3, cargo are piled up, the lifting mechanism (3) operates again, and the loading platform (2) is driven to drop to Cargo in the loading platform (2) is unloaded and is carried to lorry or shifting by warehouse floor, subsequent operator using fork truck again On moving platform, unloaded until completing removing for cargo on the entire loading platform (2), then the mobile piler is moved to down One storage region, completes follow-up unloading operation.
CN201610607559.XA 2016-07-29 2016-07-29 Mobile piler and its clamp method Active CN106219116B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610607559.XA CN106219116B (en) 2016-07-29 2016-07-29 Mobile piler and its clamp method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610607559.XA CN106219116B (en) 2016-07-29 2016-07-29 Mobile piler and its clamp method

Publications (2)

Publication Number Publication Date
CN106219116A CN106219116A (en) 2016-12-14
CN106219116B true CN106219116B (en) 2018-09-11

Family

ID=57533940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610607559.XA Active CN106219116B (en) 2016-07-29 2016-07-29 Mobile piler and its clamp method

Country Status (1)

Country Link
CN (1) CN106219116B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106956441B (en) * 2017-05-10 2022-12-20 浙江钲浩建筑科技有限公司 Conveying device of energy-saving inner wall welding mechanism

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07187321A (en) * 1993-12-28 1995-07-25 Komatsu Forklift Co Ltd Brake device for stacker crane
JP2008222424A (en) * 2007-03-15 2008-09-25 Hitachi Plant Technologies Ltd Travel control device of stacker crane
CN105730954A (en) * 2016-03-29 2016-07-06 浙江厚达智能科技股份有限公司 Stacking RGV
CN105775544A (en) * 2016-05-11 2016-07-20 深圳普智联科机器人技术有限公司 Warehousing system with simple and convenient positioning function and cargo delivery method
CN205906541U (en) * 2016-07-29 2017-01-25 国信机器人无锡股份有限公司 Portable stacker

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07187321A (en) * 1993-12-28 1995-07-25 Komatsu Forklift Co Ltd Brake device for stacker crane
JP2008222424A (en) * 2007-03-15 2008-09-25 Hitachi Plant Technologies Ltd Travel control device of stacker crane
CN105730954A (en) * 2016-03-29 2016-07-06 浙江厚达智能科技股份有限公司 Stacking RGV
CN105775544A (en) * 2016-05-11 2016-07-20 深圳普智联科机器人技术有限公司 Warehousing system with simple and convenient positioning function and cargo delivery method
CN205906541U (en) * 2016-07-29 2017-01-25 国信机器人无锡股份有限公司 Portable stacker

Also Published As

Publication number Publication date
CN106219116A (en) 2016-12-14

Similar Documents

Publication Publication Date Title
CN206244337U (en) A kind of sheet material chooses piler
CN104973540B (en) A kind of stacking machine for tunnel with track
CN104773337B (en) Snatch formula tray automatic distribution device
EP1636120B1 (en) Arrangement and method in circumferential storage and a transferring device in the circumferential store
CN102718074A (en) Automatic stacking device for wooden trays
US20140236343A1 (en) Apparatus and method for the defined intermediate storage and picking of produced articles of the same type but different size
CN206307949U (en) Single column piler vertical-lift structure
CN108557494A (en) Fully-automatic intelligent stacking entrucking unloading system
CN106809587A (en) A kind of intensive intelligent tri-dimensional storage system for storing steel
CN102910559B (en) Stacking equipment for storage logistics system
CN108820675A (en) Built-in conveying wire type combination bracket shelf and electric energy meter intelligent memory system
CN107021314A (en) It is a kind of can across shelf picking tiered warehouse facility
CN110053989A (en) The Full automatic loading system and loading method of batch cabinet class cargo
CN106219116B (en) Mobile piler and its clamp method
CN112208995A (en) Telescopic fork for quickly carrying work bin for stacker and work bin storing and taking method
CN205906541U (en) Portable stacker
CN202193591U (en) Stacking equipment for warehousing and logistic system
CN107973221B (en) Intelligent crane based on infrared measurement
CN201972434U (en) Multi-row parking space roadway stacking mechanical garage
CN107082217A (en) A kind of twin columns dual stage piler stereo garage system
US20130343843A1 (en) Automated storage and handling systems
CN207468123U (en) Intelligent single upright column and double stretches a lifting mechanism
CN206827445U (en) A kind of twin columns dual stage piler stereo garage system
CN208585658U (en) A kind of storage automatic material fetching machine
CN108455296A (en) It is a kind of for lithium battery raw material access without day rail piler

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: Room 509, No. 152, shangmadun Road, Liangxi District, Wuxi City, Jiangsu Province

Patentee after: GUOXIN ROBOT WUXI STOCK Co.,Ltd.

Address before: No. 101, Meixi Road, Meicun, New District, Wuxi City, Jiangsu Province, 214000

Patentee before: GUOXIN ROBOT WUXI STOCK Co.,Ltd.