CN106194204A - A kind of drift cobble tunnel advanced support structure and method for protecting support - Google Patents

A kind of drift cobble tunnel advanced support structure and method for protecting support Download PDF

Info

Publication number
CN106194204A
CN106194204A CN201610808664.XA CN201610808664A CN106194204A CN 106194204 A CN106194204 A CN 106194204A CN 201610808664 A CN201610808664 A CN 201610808664A CN 106194204 A CN106194204 A CN 106194204A
Authority
CN
China
Prior art keywords
tunnel
self
type hollow
advancing type
hollow grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610808664.XA
Other languages
Chinese (zh)
Inventor
赖金星
昝文博
谢永利
曹校勇
杨绍战
张玉伟
邱军领
冯志华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201610808664.XA priority Critical patent/CN106194204A/en
Publication of CN106194204A publication Critical patent/CN106194204A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • E21D21/0046Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts formed by a plurality of elements arranged longitudinally

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention belongs to tunnel advanced support technical field, be specifically related to a kind of drift cobble tunnel advanced support structure and method for protecting support, including the concrete jacket arch being arranged at tunnel portal, tunnel vault is vertically arranged with self-advancing type hollow Grouting Pipe canopy along tunnel;It is embedded with, between adjacent self-advancing type hollow Grouting Pipe canopy, the double-deck self-advancing type hollow grouting anchor being longitudinally arranged along tunnel, including: upper strata self-advancing type hollow grouting anchor and lower floor's self-advancing type hollow grouting anchor;It is provided with shaped steel arch, described upper strata self-advancing type hollow grouting anchor and lower floor's self-advancing type hollow grouting anchor afterbody in tunnel to be welded and fixed with shaped steel arch;The present invention can effectively solve the problem that the advance support pore-forming bit freezing difficult, easy generally existed in current drift cobble constructing tunnel and to problems such as country rock disturbance are big;The method pipe canopy reinforcing scope of the present invention accurately, reliably, gives full play to self to country rock disturbance relatively I, and arch, tunnel forms thick shell frame and ensures safety for tunnel engineering.

Description

A kind of drift cobble tunnel advanced support structure and method for protecting support
Technical field
The invention belongs to tunnel advanced support technical field, be specifically related to a kind of drift cobble tunnel advanced support structure and prop up Maintaining method.
Background technology
In recent years, along with highway to river valley, overbank, the foot of a mountain, seashore, terrace etc. constantly extend, tunnel construction is increasingly Many is faced with the problem that geological condition is complicated and changeable, particularly builds tunnel in the gravel-boulder bed that valley terrace generally exists Time, not only constructional difficulties, progress is slow, engineering safety risk big, and the generation of geological disaster the most universal and disastrous by force Strong.Drift cobble tunnel excavation one touches and i.e. collapses, it is necessary to take suitable advanced pre-reinforcement measure improve country rock and reinforce country rock.So And, there is pore-forming bit freezing difficult, easy on this stratum and ask country rock disturbance is big etc. in traditional super-front large pipe shed, advanced tubule Topic;Surface drilling slip casting, equally exists pore-forming difficulty, and owing to drift cobble country rock is loose, porosity big, serosity flow range Be difficult to control to, consolidation effect the most uncertain.Therefore, be badly in need of combining the drift special Study on engineering properties of cobble necessary novel in advance Method for protecting support and supporting construction ensure this special formation safety for tunnel engineering.
Summary of the invention
The defect existed for prior art and deficiency, it is an object of the invention to provide a kind of drift cobble tunnel and prop up in advance Protection structure and method for protecting support, it is possible to effective solution advance support pore-forming difficulty that currently this formation tunnel generally exists in constructing, Easily bit freezing and to problems such as country rock disturbance are big, reduces the disturbance that country rock is caused by construction, is effectively improved tunnel surrounding, gives full play to Self, so that it is guaranteed that safety for tunnel engineering.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of gravel-boulder bed tunnel advanced support structure, including the concrete jacket arch being arranged at tunnel portal, tunnel encircles Top is vertically arranged with self-advancing type hollow Grouting Pipe canopy along tunnel;It is embedded with between adjacent self-advancing type hollow Grouting Pipe canopy along tunnel longitudinally The double-deck self-advancing type hollow grouting anchor arranged, including: upper strata self-advancing type hollow grouting anchor and lower floor's self-advancing type hollow slip casting Anchor pole;Shaped steel arch, described upper strata self-advancing type hollow grouting anchor and lower floor's self-advancing type hollow grouting anchor it is provided with in tunnel Afterbody is welded and fixed with shaped steel arch.
Further, described self-advancing type hollow Grouting Pipe canopy is arranged in outside tunnel excavation contour line, and at tunnel vault Arrange in the range of 120 °.
Further, described upper strata self-advancing type hollow grouting anchor a length of 3~3.5m, squeeze into 40~45 ° of outer limbs Country rock, anchor pole circumferential distance is 35~40cm, and longitudinal array pitch is 100~110cm;Described lower floor self-advancing type hollow grouting anchor is long Degree is 2.5~3.0m, squeezes into country rock with 10~15 ° of outer limbs, and anchor pole circumferential distance is 35~40cm, longitudinal array pitch be 100~ 110cm。
Further, described concrete jacket arch is preset with the guide pipe for applying self-advancing type hollow Grouting Pipe canopy, institute Stating guide pipe circumferential distance is 35~40cm, the elevation angle 1~3 °.
Further, described self-advancing type hollow Grouting Pipe canopy includes that impacter, described impacter front end are provided with alloy and bore Head, rear end is connected with the drilling rod of injected hole by adapter sleeve, and described drilling rod is that hollow-core construction being provided with at afterbody is only starched Section.
Further, described upper strata self-advancing type hollow grouting anchor and lower floor's self-advancing type hollow grouting anchor all include arranging Having the body of rod of injected hole, lever front end is provided with anchor pole alloy bit, and described body of rod rear end is provided with stop grouting plug, and by with Spherical nut and arch backing plate are fixed;The adapter sleeve for extension rod body length it is provided with on the described body of rod.
Further, described injected hole is quincunx injected hole, and pitch of holes is 30~35cm.
A kind of gravel-boulder bed tunnel advanced support method, comprises the following steps:
1) reinforced concrete soil suite arch is applied before excavation in penumbra, tunnel, along tunnel in described reinforced concrete soil suite arch Hoop is evenly distributed with some guide pipes;
2) apply self-advancing type hollow Grouting Pipe canopy by guide pipe, expanded by set arch end slip casting in pipe canopy after applying Dissipate and reinforce peripheral rock, fill pipe canopy body;
3) set up shaped steel arch after tunnel excavation immediately, apply upper strata self-advancing type hollow grouting anchor and lower floor from entering every Pin Formula hollow grouting anchor, and anchor pole afterbody is welded and fixed with steel arch-shelf;
4) until excavation to self-advancing type hollow Grouting Pipe canopy reinforce end time, repeat step 2), 3) persistently excavate.
Further, the order of described slip casting uses every hole slip casting;Grouting serous fluid uses the cement mortar being mixed with waterglass Liquid, waterglass content is the 5% of cement grout volume.
Compared with prior art, the present invention has following useful technique effect: by using self-advancing type hollow Grouting Pipe Canopy, it is ensured that pipe canopy length meets requirement, solves gravel-boulder bed pipe roof construction pore-forming bit freezing difficult, easy, problem that efficiency of construction is low; By arranging that double-deck advance anchor bolt slip casting make front of tunnel heading country rock form the arcuately frame that thickness is bigger, it is ensured that on top The excavation in tunnel, bottom is carried out under the protection of thick shell frame;It is right to be reduced by the hollow Grouting Pipe canopy and anchor pole using pipe with small pipe diameter The disturbance of country rock, gives full play to self;Self-advancing type hollow Grouting Pipe canopy and double-deck advance anchor bolt composite reinforcement guarantee Portal Section start tunneling safety, can conveniently be adjusted to monolayer or extended length according to country rock situation in hole, bilayer anchor pole after entering hole. The present invention is on the premise of being effectively improved gravel-boulder bed tunnel advanced support efficiency of construction, it is ensured that Tunnel Engineering is safe and reliable.
Further, by arranging guide pipe on encircleing at concrete jacket, it is ensured that self-advancing type hollow Grouting Pipe canopy position and hole Mouth direction is the most in place, makes pipe canopy reinforcing scope accurately, reliably.
Further, by arranging quincunx injected hole on drilling rod and the body of rod, slip casting makes serosity diffusion consolidation, improves country rock Cohesive strength.
The method that the present invention provides, by utilizing guide pipe to apply self-advancing type hollow Grouting Pipe canopy, it can be ensured that pipe canopy position Putting the most in place with direction, aperture, make pipe canopy reinforcing scope clearly, reliably, double-deck self-advancing type advance anchor bolt slip casting make face Front country rock forms the arcuately frame that thickness is bigger, it is ensured that carry out the excavation in tunnel, bottom under the protection of top thickness shell frame; Reduce the disturbance to country rock by the hollow Grouting Pipe canopy and anchor pole using pipe with small pipe diameter, give full play to self;From entering Formula hollow Grouting Pipe canopy and double-deck advance anchor bolt composite reinforcement guarantee Portal Section start tunneling safety.
Accompanying drawing explanation
Fig. 1 is the tunnel advanced support schematic cross-sectional view of the present invention.
Fig. 2 is the tunnel advanced support schematic longitudinal section of the present invention.
Fig. 3 is the self-advancing type hollow Grouting Pipe canopy organigram of the present invention.
Fig. 4 is the self-advancing type hollow grouting anchor organigram of the present invention.
Wherein: 1-reinforced concrete soil suite encircles, 2-self-advancing type hollow Grouting Pipe canopy, 201-alloy bit, 202-impacter, 203-adapter sleeve, 204-drilling rod, 205-injected hole, the 206-only section of slurry;3-lower floor self-advancing type hollow grouting anchor, 301-anchor pole closes Gold drill bit, the 302-body of rod, 303-anchor pole adapter sleeve, 304-stop grouting plug, 305-arch backing plate, 306-spherical nut;4-upper strata is certainly Enter formula hollow grouting anchor, 5-guide pipe, 6-shaped steel arch.
Detailed description of the invention
Below in conjunction with the accompanying drawings the present invention is described in further detail.
Seeing Fig. 1, Fig. 2, the drift cobble tunnel advanced support structure that the present invention provides, including being arranged at tunnel portal Concrete jacket arch 1, concrete jacket arch 1 is preset with the guide pipe 5 for applying self-advancing type hollow Grouting Pipe canopy 2, tunnel vault Be vertically arranged with self-advancing type hollow Grouting Pipe canopy 2 along tunnel, self-advancing type hollow Grouting Pipe canopy 2 is arranged in outside tunnel excavation contour line Side, and arrange in the range of tunnel vault 120 °.It is embedded with between adjacent self-advancing type hollow Grouting Pipe canopy 2 and to be longitudinally arranged along tunnel Double-deck self-advancing type hollow grouting anchor, including: upper strata self-advancing type hollow grouting anchor 3 and lower floor's self-advancing type hollow grouting anchor 4; Being provided with shaped steel arch 6 in tunnel, shaped steel arch 6 longitudinal pitch is 50cm.Described upper strata self-advancing type hollow grouting anchor 3 and under Layer self-advancing type hollow grouting anchor 4 afterbody is welded and fixed with shaped steel arch 6.
Concrete jacket arch 1 employing C35 armored concrete apply, and be directed to pipe 5 be fixed on concrete jacket arch 1 in, guide Should strictly control steel pipe circumferential distance 40cm when pipe 5 is installed, the elevation angle is at 1~3 °, it is ensured that orifice position and direction are accurate.
Seeing Fig. 3, self-advancing type hollow Grouting Pipe canopy 2 includes that impacter 202, described impacter front end are provided with alloy bit 201, rear end is connected with the drilling rod 204 of injected hole 205 by adapter sleeve 203, and described drilling rod 204 is hollow-core construction at tail Portion is provided with only slurry section 206.Adapter sleeve 203 spreading is used between follow-up drilling rod 204.
The a length of 3m of upper strata self-advancing type hollow grouting anchor 4, squeezes into country rock, anchor pole circumferential distance with 40~45 ° of outer limbs Being 35~40cm, longitudinal array pitch is 100cm;The described lower floor a length of 2.5m of self-advancing type hollow grouting anchor 3, with 10~15 ° outside Limb squeezes into country rock, and anchor pole circumferential distance is 35~40cm, and longitudinal array pitch is 100cm.See Fig. 4, in the self-advancing type of described upper strata Empty grouted anchor bar 3 and lower floor's self-advancing type hollow grouting anchor 4 all include the body of rod 302 being provided with injected hole, and the body of rod 302 front end sets Being equipped with anchor pole alloy bit 301, the described body of rod 302 rear end is provided with stop grouting plug 304, and by with spherical nut 306 and arch Shape backing plate 305 is fixed;The adapter sleeve 303 for extending the body of rod 302 length it is provided with on the described body of rod 302.
Injected hole is quincunx injected hole, and pitch of holes is 30~35cm.
The advanced support method in the gravel-boulder bed tunnel that the present invention provides, comprises the following steps:
1) reinforced concrete soil suite arch 1 is applied before excavation in penumbra, tunnel, vertical along tunnel in reinforced concrete soil suite arch 1 To being evenly distributed with some guide pipes 5;
2) apply self-advancing type hollow Grouting Pipe canopy 2 by guide pipe 5, use down-the-hole drill by set encircle on guide pipe execute Making the first segment drilling rod of pipe canopy, first segment drilling rod front end, with alloy bit and impacter, uses adapter sleeve between follow-up drilling rod Spreading.The construction method of many self-advancing type hollow Grouting Pipe canopies is the most identical, by set arch end slip casting in pipe canopy after applying Peripheral rock is reinforced in diffusion, fills pipe canopy body;The order of described slip casting uses every hole slip casting;Grouting serous fluid uses and is mixed with water glass The cement grout of glass, waterglass content is the 5% of cement grout volume.
3) setting up shaped steel arch 6 after tunnel excavation immediately, shaped steel arch is installed along the cross section circumference of tunnel surrounding;Every Pin Apply upper strata self-advancing type hollow grouting anchor 3 and lower floor's self-advancing type hollow grouting anchor 4, and anchor pole afterbody is welded with steel arch-shelf Fixing;Can be according to country rock situation in hole after entering hole, double-deck anchor pole can conveniently be adjusted to monolayer or extended length, and construction is flexible, side Just adjust.
4) until excavation reinforce end to self-advancing type hollow Grouting Pipe canopy 2 time, repetition step 2), 3) persistently excavate.
During construction, before tunnel excavation, first apply reinforced concrete soil suite arch 1, reinforced concrete soil suite arch 1 is preset with and leads To pipe 5, apply self-advancing type hollow Grouting Pipe canopy 2 by guide pipe 5, after all self-advancing type hollow Grouting Pipe canopies 2 have applied Excavate into hole;Excavate behind hole, in hole, set up shaped steel arch 6 immediately, and apply double-deck advance anchor bolt, by advance anchor bolt 3 and 4 Afterbody be welded and fixed with shaped steel arch together with;Persistently opening of tunnel is carried out under the protection of pipe canopy 2 and double-deck advance anchor bolt Dig.
By the gravel-boulder bed tunnel portal section advance support structure of foregoing invention, it can be ensured that Guan Peng position and aperture side To the most in place, making pipe canopy reinforcing scope clearly, reliably, by using alloy bit and impacter to ensure, pipe canopy length meets wants Asking, and can increase substantially pipe roof construction efficiency, double-deck self-advancing type advance anchor bolt slip casting make front of tunnel heading country rock be formed The arcuately frame that thickness is bigger, it is ensured that carry out the excavation in tunnel, bottom under the protection of top thickness shell frame;By using tubule The hollow Grouting Pipe canopy in footpath and anchor pole reduce the disturbance to country rock, give full play to self;Self-advancing type hollow Grouting Pipe Canopy and double-deck advance anchor bolt composite reinforcement guarantee Portal Section start tunneling safety;Enter according to country rock situation in hole behind hole, double-deck anchor Bar can conveniently be adjusted to monolayer or extended length, and construction is flexible, convenient to be adjusted.

Claims (9)

1. a gravel-boulder bed tunnel advanced support structure, it is characterised in that include the concrete jacket being arranged at tunnel portal Arch (1), tunnel vault is vertically arranged with self-advancing type hollow Grouting Pipe canopy (2) along tunnel;Adjacent self-advancing type hollow Grouting Pipe canopy (2) Between be embedded with the double-deck self-advancing type hollow grouting anchor being longitudinally arranged along tunnel, including upper strata self-advancing type hollow grouting anchor (3) With lower floor's self-advancing type hollow grouting anchor (4);Shaped steel arch (6), described upper strata self-advancing type hollow slip casting anchor it is provided with in tunnel Bar (3) and lower floor's self-advancing type hollow grouting anchor (4) afterbody are welded and fixed with shaped steel arch (6).
A kind of gravel-boulder bed tunnel advanced support structure the most according to claim 1, it is characterised in that in described self-advancing type Empty Grouting Pipe canopy (2) is arranged in outside tunnel excavation contour line, and arranges in the range of tunnel vault 120 °.
A kind of gravel-boulder bed tunnel advanced support structure the most according to claim 1, it is characterised in that described upper strata is from entering Formula hollow grouting anchor (4) a length of 3~3.5m, squeezes into country rock with 40~45 ° of outer limbs, anchor pole circumferential distance be 35~ 40cm, longitudinal array pitch is 100~110cm;Described lower floor's self-advancing type hollow grouting anchor (3) a length of 2.5~3.0m, with 10~ 15 ° of outer limbs squeeze into country rock, and anchor pole circumferential distance is 35~40cm, and longitudinal array pitch is 100~110cm.
A kind of gravel-boulder bed tunnel advanced support structure the most according to claim 1, it is characterised in that described concrete jacket Being preset with the guide pipe (5) for applying self-advancing type hollow Grouting Pipe canopy (2) on arch (1), described guide pipe (5) circumferential distance is 35~40cm, the elevation angle 1~3 °.
A kind of gravel-boulder bed tunnel advanced support structure the most according to claim 1, it is characterised in that in described self-advancing type Empty Grouting Pipe canopy (2) includes that impacter (202), described impacter front end are provided with alloy bit (201), and adapter sleeve is passed through in rear end (203) being connected with the drilling rod (204) of injected hole (205), described drilling rod (204) is hollow-core construction and is only provided with at afterbody Slurry section (206).
A kind of gravel-boulder bed tunnel advanced support structure the most according to claim 1, it is characterised in that described upper strata is from entering Formula hollow grouting anchor (3) and lower floor's self-advancing type hollow grouting anchor (4) all include the body of rod (302) being provided with injected hole, bar Body (302) front end is provided with anchor pole alloy bit (301), and the described body of rod (302) rear end is provided with stop grouting plug (304), and passes through Fix with spherical nut (306) and arch backing plate (305);It is provided with for extending the body of rod (302) long on the described body of rod (302) The adapter sleeve (303) of degree.
7. according to a kind of gravel-boulder bed tunnel advanced support structure described in claim 5 or 6, it is characterised in that described slip casting Hole is quincunx injected hole, and pitch of holes is 30~35cm.
8. according to the advanced support method in gravel-boulder bed tunnel described in any one of claim 1-7, it is characterised in that include following Step:
1) reinforced concrete soil suite arch (1) is applied before excavation in penumbra, tunnel, along tunnel in described reinforced concrete soil suite arch (1) Road hoop is evenly distributed with some guide pipes (5);
2) self-advancing type hollow Grouting Pipe canopy (2) is applied by guide pipe (5), by set arch end slip casting in pipe canopy after applying Peripheral rock is reinforced in diffusion, fills pipe canopy body;
3) set up shaped steel arch (6) after tunnel excavation immediately, every Pin apply upper strata self-advancing type hollow grouting anchor (3) and lower floor from Enter formula hollow grouting anchor (4), and anchor pole afterbody is welded and fixed with steel arch-shelf;
4) until excavation to self-advancing type hollow Grouting Pipe canopy (2) reinforce end time, repeat step 2), 3) persistently excavate.
A kind of drift cobble tunnel advanced support method the most according to claim 8, it is characterised in that the order of described slip casting Use every hole slip casting;Grouting serous fluid uses the cement grout being mixed with waterglass, and waterglass content is cement grout volume 5%.
CN201610808664.XA 2016-09-08 2016-09-08 A kind of drift cobble tunnel advanced support structure and method for protecting support Pending CN106194204A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610808664.XA CN106194204A (en) 2016-09-08 2016-09-08 A kind of drift cobble tunnel advanced support structure and method for protecting support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610808664.XA CN106194204A (en) 2016-09-08 2016-09-08 A kind of drift cobble tunnel advanced support structure and method for protecting support

Publications (1)

Publication Number Publication Date
CN106194204A true CN106194204A (en) 2016-12-07

Family

ID=58067486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610808664.XA Pending CN106194204A (en) 2016-09-08 2016-09-08 A kind of drift cobble tunnel advanced support structure and method for protecting support

Country Status (1)

Country Link
CN (1) CN106194204A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107013220A (en) * 2017-05-16 2017-08-04 深圳市瑞利源工程技术有限公司 A kind of tunnel deep hole grouting method, pipe canopy and retrusive Grouting Pipe
CN107605509A (en) * 2017-11-08 2018-01-19 中铁十局集团有限公司 Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN108756893A (en) * 2018-04-19 2018-11-06 济南城建集团有限公司 A kind of city shallow tunnel vault soil stabilization method
CN108798718A (en) * 2018-07-09 2018-11-13 中铁十七局集团第四工程有限公司 Subsequent grouting method is held before tunnel
CN109854281A (en) * 2019-02-01 2019-06-07 安徽建筑大学 The method for protecting support of the lower rock compound cross-section stratum jacking construction of upper soil
CN113174928A (en) * 2021-04-30 2021-07-27 福建永宏建设工程有限公司 Fine casting and grouting process for pebble layer with large permeability coefficient
CN113236263A (en) * 2021-06-25 2021-08-10 中铁十八局集团有限公司 Construction method of open type TBM front-mounted type advanced pipe shed
CN113982646A (en) * 2021-10-25 2022-01-28 中铁隧道局集团有限公司 Advanced support construction method for tunnel water-rich soil-rock mixed stratum slump accumulation body
CN115030165A (en) * 2022-05-13 2022-09-09 中交一公局第四工程有限公司 Ultra-shallow buried tunnel underpass highway structure and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2480501A (en) * 2010-05-21 2011-11-23 Tube Lines Ltd A tunnel support apparatus
CN203756182U (en) * 2014-04-04 2014-08-06 湖南省高速公路建设开发总公司 Support structure applied to shallow road tunnel in weak rock area
CN203835406U (en) * 2014-05-07 2014-09-17 中铁第一勘察设计院集团有限公司 Double-layer forepoling structure for underneath pass valley tunnel
CN204511478U (en) * 2014-12-24 2015-07-29 浙江大学城市学院 A kind of self-feeding anchor pile structure
CN204511479U (en) * 2015-01-15 2015-07-29 山东科技大学 The impervious frictional resistance anchor pole of a kind of novel self-advancing type
CN204920977U (en) * 2015-08-13 2015-12-30 青岛业高建设工程有限公司 Spray tube canopy construction equipment is revolved in advance to percussion drilling formula
CN105715287A (en) * 2016-03-23 2016-06-29 徐州立方机电设备制造有限公司 Combined self feeding type grouting anchor rod
CN206144570U (en) * 2016-09-08 2017-05-03 长安大学 Float cobble tunnel advance support structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2480501A (en) * 2010-05-21 2011-11-23 Tube Lines Ltd A tunnel support apparatus
CN203756182U (en) * 2014-04-04 2014-08-06 湖南省高速公路建设开发总公司 Support structure applied to shallow road tunnel in weak rock area
CN203835406U (en) * 2014-05-07 2014-09-17 中铁第一勘察设计院集团有限公司 Double-layer forepoling structure for underneath pass valley tunnel
CN204511478U (en) * 2014-12-24 2015-07-29 浙江大学城市学院 A kind of self-feeding anchor pile structure
CN204511479U (en) * 2015-01-15 2015-07-29 山东科技大学 The impervious frictional resistance anchor pole of a kind of novel self-advancing type
CN204920977U (en) * 2015-08-13 2015-12-30 青岛业高建设工程有限公司 Spray tube canopy construction equipment is revolved in advance to percussion drilling formula
CN105715287A (en) * 2016-03-23 2016-06-29 徐州立方机电设备制造有限公司 Combined self feeding type grouting anchor rod
CN206144570U (en) * 2016-09-08 2017-05-03 长安大学 Float cobble tunnel advance support structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
乔广红: "雁门关隧道后腰铺斜井正洞大变形段处理方案", 《铁道建筑技术》 *
赵朋涛等: "中条山隧道涌砂处理施工技术", 《铁道建筑技术》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107013220A (en) * 2017-05-16 2017-08-04 深圳市瑞利源工程技术有限公司 A kind of tunnel deep hole grouting method, pipe canopy and retrusive Grouting Pipe
CN107605509A (en) * 2017-11-08 2018-01-19 中铁十局集团有限公司 Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN108756893A (en) * 2018-04-19 2018-11-06 济南城建集团有限公司 A kind of city shallow tunnel vault soil stabilization method
CN108798718A (en) * 2018-07-09 2018-11-13 中铁十七局集团第四工程有限公司 Subsequent grouting method is held before tunnel
CN109854281A (en) * 2019-02-01 2019-06-07 安徽建筑大学 The method for protecting support of the lower rock compound cross-section stratum jacking construction of upper soil
CN113174928A (en) * 2021-04-30 2021-07-27 福建永宏建设工程有限公司 Fine casting and grouting process for pebble layer with large permeability coefficient
CN113174928B (en) * 2021-04-30 2022-06-10 福建永宏建设工程有限公司 Fine casting and grouting process for pebble layer with large permeability coefficient
CN113236263A (en) * 2021-06-25 2021-08-10 中铁十八局集团有限公司 Construction method of open type TBM front-mounted type advanced pipe shed
CN113982646A (en) * 2021-10-25 2022-01-28 中铁隧道局集团有限公司 Advanced support construction method for tunnel water-rich soil-rock mixed stratum slump accumulation body
CN115030165A (en) * 2022-05-13 2022-09-09 中交一公局第四工程有限公司 Ultra-shallow buried tunnel underpass highway structure and construction method
CN115030165B (en) * 2022-05-13 2024-01-19 中交一公局第四工程有限公司 Under-penetration highway structure for ultra-shallow buried tunnel and construction method

Similar Documents

Publication Publication Date Title
CN106194204A (en) A kind of drift cobble tunnel advanced support structure and method for protecting support
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN103306687B (en) Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method
CN107060834A (en) Grout injection control technique is oozed in drainage slowly under back rich water broken condition
CN109372555A (en) A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN109098733B (en) Rapid grouting reinforcement method for large-section tunnel in fracture zone rock stratum
CN202866826U (en) Shield tunnel working well outer end socket stratum reinforced structure
CN108252719B (en) Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN104818991A (en) Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure
CN204703160U (en) Two anchoring section prestressed anchor Cable Structure
CN106917627B (en) The advanced support method of pilot tunnel under a kind of water rich strata boring construction
CN104612696B (en) Construction method for large-section underground excavation subway station to pass through viaduct in fine sand layer by using column hole method
CN107605498A (en) Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method
CN107060774A (en) A kind of anti-tunnel portal wall damage device and construction method
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN109538216A (en) Pass through mined out and subsidence area constructing tunnel technique
CN107165661A (en) A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method
CN102518451B (en) Construction method of shotcrete support for water contained loess geological tunnel
CN108678781A (en) One kind closing on river shield launching end stratum consolidation method
CN109736850A (en) A kind of tunnel shell arch combination strength bearing structure and its construction method
CN111140248A (en) Bias tunnel structure applying prestress to pilot tunnel and construction method thereof
CN108180018A (en) A kind of shallow embedding collapsible loess tunnel Core Soil and glass bolt anchorage construction method
CN206144570U (en) Float cobble tunnel advance support structure
CN102606173B (en) Construction method for treating tunnel deformation segment and accelerating tunneling
CN104612714B (en) Tunneling by mining method construction method and structure under the conditions of the poor geology of country rock is passed through

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161207