CN106193570A - Hanging basket anti-fall anti-shake hooking device and using method thereof - Google Patents

Hanging basket anti-fall anti-shake hooking device and using method thereof Download PDF

Info

Publication number
CN106193570A
CN106193570A CN201610650597.3A CN201610650597A CN106193570A CN 106193570 A CN106193570 A CN 106193570A CN 201610650597 A CN201610650597 A CN 201610650597A CN 106193570 A CN106193570 A CN 106193570A
Authority
CN
China
Prior art keywords
hanging basket
hook
wall
retainer ring
shake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610650597.3A
Other languages
Chinese (zh)
Inventor
焦文俊
宋功业
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Institute of Architectural Technology
Jiangsu Jianzhu Institute
Original Assignee
Jiangsu Institute of Architectural Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Institute of Architectural Technology filed Critical Jiangsu Institute of Architectural Technology
Priority to CN201610650597.3A priority Critical patent/CN106193570A/en
Publication of CN106193570A publication Critical patent/CN106193570A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • E04G3/325Safety devices for stabilising the mobile platform, e.g. to avoid it swinging in the wind

Abstract

Hanging basket anti-fall anti-shake hooking device is to use safe construction during cradling to design for construction, belongs to the realm of building construction;Hanging basket anti-fall anti-shake hooking device is made up of with wall pipe retainer ring, hook, cross-arm;Hook is made up of front hook and back side hook;Retainer ring is fixedly arranged at inside hanging basket suitable for reading;Wall pipe is imbedded and through body of wall;Link up with retainer ring and cross-arm clasp joint through wall pipe;The invention has the beneficial effects as follows and prevent hanging basket from rocking in work progress, when hoist cable fracture or roof equipment break down, hanging basket will not fall.

Description

Hanging basket anti-fall anti-shake hooking device and using method thereof
Technical field
The present invention is hanging basket anti-fall anti-shake hooking device and using method thereof, when using cradling for construction Safe construction and design, belong to the realm of building construction.
Background technology
Hanging basket is a kind of instrument conventional in construction, typically arranges pulley on the parapet on roof, on roofing Hoist engine is set, with hoist cable through pulley one ends wound on hoist engine, one end is connected to the suitable for reading of hanging basket;Operating personnel is hanging Skin surface is fitted up by basket, by the hoist engine contraction to hoist cable, makes hanging basket to move up and down;Above-mentioned can Knowing, the personnel worked in hanging basket are constantly present following risk factor: 1, hoist engine is fixed in roofing, due to roofing Waterproof requirement, not in roofing pre-embedded anchoring bolts, does not the most allow to be fixed hoist engine by expansion bolt, hoist engine Under conditions of not having foundation bolt fixing, risk mobile, that slip is to exist, and once hoist engine moves or slips, hanging basket The possibility of bust will occur, and operating personnel, in hanging basket, just has the danger of " being dished out ";Even if 2 hoist engines do not slip Or mobile, but elevator locking device is malfunctioning, it is also possible to makes hoist cable out of control, causes hanging basket to drop rapidly;3, pulley is installed in On parapet, carry the heavy duty that hanging basket transmits, once pulley or pulley yoke unstability, also result in hanging basket and drop rapidly;4, i.e. Making the said equipment the most intact, the most normally, but hanging basket is to be suspended skyborne, and stability is bad, and personnel's operation, transverse shifting are all Hanging basket can be caused to shake from side to side, the impact of the strong wind swept the most suddenly, may result in hanging-basket from drop or personnel's height pendant.
Above-mentioned analysis understands, and hanging basket is construction, the instrument that particularly decoration construction is indispensable, but uses hanging basket Time, it is necessary to evade above-mentioned risk.
The hanging basket anti-fall anti-shake hook control method that the present invention provides can solve these problems.
Summary of the invention
The specific practice of this programme is:
Use hanging basket anti-fall anti-shake hooking device as shown in Figures 1 to 4 by hanging basket 1, retainer ring 2, hoist cable 3, hook 4, cross-arm 5, wall pipe 6 and body of wall 7 composition;Hook 4 is made up of front hook 41 and back side hook 42;Hanging basket 1 is suspended in midair by hoist cable 3 On roofing equipment;Retainer ring 2 is fixedly arranged at inside hanging basket 1 suitable for reading;Wall pipe 6 is imbedded and through body of wall 7;Hook 4 is through through walls Retainer ring 2 is tangled by pipe 6 with cross-arm 5;Front hook 41 links up with 42 grafting in wall pipe 6 with the back side.
Retainer ring 2 is fixed in the hanging basket 1 endless member suitable for reading by body of wall 7 side, and preferential recommendation uses 20-30 milli The reinforcement fabrication of rice becomes the annulus of diameter 30-40 millimeter, according to the distance every 1-1.5 rice, retainer ring 2 is weldingly fixed on and hangs Basket is suitable for reading near body of wall 7 side;Before hanging basket preparation is arranged on a certain position operation of body of wall 7, by the shifting of hoist cable 3 Dynamic, make hanging basket 1 in place, with hook 4, retainer ring 2 is connected with cross-arm 5.
The front hook 41 of hook 4 is made up of with arc shaped hook sleeve pipe, and sleeve pipe is consolidated into entirety with one end of arc shaped hook, And at grade;The length of sleeve pipe is equal to the thickness of body of wall 7;During work, arc shaped hook is through in the circular hole of retainer ring 2;Hang The back side hook 42 of hook 4 is made up of with crotch inserted link, and the length of the inserted link of back side hook 42, equal to the thickness of body of wall 7, is inserted The diameter of bar is equal to the internal diameter of the sleeve pipe of front hook 41, and during work, cross-arm 5 is inserted in the crotch of back side hook 42, and the back side hangs The inserted link of hook 42 passes body of wall 7, is inserted in the sleeve pipe of front hook 41.
Cross-arm 5 is rod-like members, and preferential recommendation uses No. 6 channel-section steels to make;Cross-arm 5 is by the hook 4 through wall pipe 6 even Connect retainer ring 2, make hanging basket 1 be relatively fixed at the Seeding location of body of wall 7.
Wall pipe 6 is to pass perpendicularly through and be embedded in the tubular part in body of wall 7, and preferential recommendation uses the hard of diameter 25 millimeters Matter plastic tube makes;Wall pipe 6 is just embedded in body of wall 7 when wall construction, makes body of wall 7 both sides be able to through.
Hanging basket anti-fall anti-shake hook control method is, when carrying out body of wall 7 and constructing it is necessary to wanted according to design by wall pipe 6 Ask and be embedded in body of wall 7 inside;
Use hanging basket 1 when the outer surface operation of body of wall 7, the Hoist Control Unit of hanging basket 1 is first installed and at parapet on roof On install pulley bracket and fixed pulley;
The one end of the hoist cable 3 being wrapped on Hoist Control Unit is consolidated with hanging basket 1, hanging basket 1 when parapet top, operation people Member enters hanging basket 1, by rotating Hoist Control Unit, hanging basket 1 is placed in job position;By the operating personnel in hanging basket 1 with Indoor occupant coordinates, and will be located in the retainer ring 2 of body of wall 7 both sides with hook 4 by wall pipe 6 and cross-arm 5 connects into entirety, so Just make not rock during hanging basket 1 operation;Even if at this moment Hoist Control Unit or pulley gear or hoist cable 3 go wrong, hanging basket 1 also will not Suddenly fall;
After having constructed in this position of body of wall 7, after unclamping hook 4, hanging basket 1 can lift again freely;
When hanging basket 1 often stops at operation at, just with hook 4, retainer ring 2 and cross-arm 5 are wound in entirety, so can ensure that and hang Basket 1 safe construction.
The invention has the beneficial effects as follows and prevent hanging basket from rocking in work progress, when event occur in hoist cable fracture or roof equipment During barrier, hanging basket will not fall.
Accompanying drawing explanation
Fig. 1 hanging basket anti-fall anti-shake hooking device schematic diagram;
Fig. 2 hanging basket anti-fall anti-shake hooking device outdoor section schematic diagram;
Fig. 3 hanging basket anti-fall anti-shake hooking device indoor section schematic diagram;
The hook schematic diagram of Fig. 4 hanging basket anti-fall anti-shake hooking device.
In figure: 1-hanging basket;2-retainer ring;3-hoist cable;4-links up with;41-front is linked up with;The 42-back side is linked up with;5-cross-arm; 6- Wall pipe;7-body of wall.
Detailed description of the invention
Embodiment
Certain engineering use hanging basket anti-fall anti-shake hooking device as shown in Figures 1 to 4 by hanging basket 1, retainer ring 2, hoist cable 3, Hook 4, cross-arm 5, wall pipe 6 and body of wall 7 composition;Hook 4 is made up of front hook 41 and back side hook 42;Hanging basket 1 leads to Cross hoist cable 3 to be suspended on roofing equipment;Retainer ring 2 is fixedly arranged at inside hanging basket 1 suitable for reading;Wall pipe 6 is imbedded and through body of wall 7;Hang Retainer ring 2 is tangled with cross-arm 5 by hook 4 through wall pipe 6;Front hook 41 and back side hook 42 grafting in wall pipe 6;Front Hook 41 links up with 42 grafting in wall pipe 6 with the back side.
Hanging basket 1 is the suitable for reading unlimited basket parts of elongate body surrounded with steel construction 5 face;Hanging basket 1 is suspended on by hoist cable 3 Being arranged on the equipment of roof structure, operating personnel stands in hanging basket 1 and carries out the operation of body of wall 7, by the control of roofing equipment, Can ramp up, it is possible to decline;Hanging basket 1 is suitable for reading by body of wall 7 side, consolidates retainer ring 2.
Retainer ring 2 is fixed in the hanging basket 1 endless member suitable for reading by body of wall 7 side, uses the reinforcing bar system of 20 millimeters It is made the annulus of diameter 30 millimeters, according to every the distance of 1 meter, retainer ring 2 is weldingly fixed on hanging basket near body of wall 7 side Suitable for reading;Before hanging basket preparation is arranged on a certain position operation of body of wall 7, by the movement of hoist cable 3, make hanging basket 1 in place, with extension Retainer ring 2 is connected by hook 4 with cross-arm 5.
Hoist cable 3 is to hang and the strand parts of moving hanging basket 1;Employing steel wire rope makes;Hoist cable 3 upper end is fixed and is wrapped in On the cylinder of hoist engine, through the fixed pulley being arranged on parapet, lower end is fixedly arranged at the suitable for reading of hanging basket 1;Rotate hoist engine, can To move hoist cable 3, hanging basket 1 is also driven to move up and down.
The front hook 41 of hook 4 is made up of with arc shaped hook sleeve pipe, and sleeve pipe is consolidated into entirety with one end of arc shaped hook, And at grade;The length of sleeve pipe is equal to the thickness of body of wall 7;During work, arc shaped hook is through in the circular hole of retainer ring 2;Hang The back side hook 42 of hook 4 is made up of with crotch inserted link, and the length of the inserted link of back side hook 42, equal to the thickness of body of wall 7, is inserted The diameter of bar is equal to the internal diameter of the sleeve pipe of front hook 41, and during work, cross-arm 5 is inserted in the crotch of back side hook 42, and the back side hangs The inserted link of hook 42 passes body of wall 7, is inserted in the sleeve pipe of front hook 41.
Cross-arm 5 is rod-like members, uses No. 6 channel-section steels to make;Cross-arm 5 connects retainer ring by the hook 4 through wall pipe 6 2, make hanging basket 1 be relatively fixed at the Seeding location of body of wall 7.
Wall pipe 6 is to pass perpendicularly through and be embedded in the tubular part in body of wall 7, uses the plastic conduit of diameter 25 millimeters Make;Wall pipe 6 is just embedded in body of wall 7 when wall construction, makes body of wall 7 both sides be able to through.
Body of wall 7 is the building enclosure of building, and when carrying out body of wall 7 face finish, hanging basket 1 passes through the movement of hoist cable 3 at wall The outer surface of body 7 moves up and down.
The using method of hanging basket anti-fall anti-shake hooking device is, when carrying out body of wall 7 and constructing it is necessary to by wall pipe 6 according to It is internal that design requirement is embedded in body of wall 7;
Use hanging basket 1 when the outer surface operation of body of wall 7, the Hoist Control Unit of hanging basket 1 is first installed and at parapet on roof On install pulley bracket and fixed pulley;
The one end of the hoist cable 3 being wrapped on Hoist Control Unit is consolidated with hanging basket 1, hanging basket 1 when parapet top, operation people Member enters hanging basket 1, by rotating Hoist Control Unit, hanging basket 1 is placed in job position;By the operating personnel in hanging basket 1 with Indoor occupant coordinates, and will be located in the retainer ring 2 of body of wall 7 both sides with hook 4 by wall pipe 6 and cross-arm 5 connects into entirety, so Just make not rock during hanging basket 1 operation;Even if at this moment Hoist Control Unit or pulley gear or hoist cable 3 go wrong, hanging basket 1 also will not Suddenly fall;
After having constructed in this position of body of wall 7, after unclamping hook 4, hanging basket 1 can lift again freely;
When hanging basket 1 often stops at operation at, just with hook 4, retainer ring 2 and cross-arm 5 are wound in entirety, so can ensure that and hang Basket 1 safe construction.

Claims (6)

1. hanging basket anti-fall anti-shake hooking device, is characterized in that, by retainer ring (2), hook (4), cross-arm (5), wall pipe (6) and group Become;Hook (4) is made up of front hook (41) and back side hook (42);It is suitable for reading that retainer ring (2) is fixedly arranged at hanging basket (1) inner side; Wall pipe (6) is imbedded and through body of wall (7);Retainer ring (2) is tangled with cross-arm (5) by hook (4) through wall pipe (6);Front Hook (41) links up with (42) grafting in wall pipe (6) with the back side.
Hanging basket the most according to claim 1 anti-fall anti-shake hooking device, is characterized in that, retainer ring (2) is fixed in hanging Basket (1) is by the endless member suitable for reading of body of wall (7) side, before hanging basket preparation is arranged on a certain position operation of body of wall (7), By the movement of hoist cable (3), make hanging basket (1) in place, with hook (4), retainer ring (2) is connected with cross-arm (5).
Hanging basket the most according to claim 1 anti-fall anti-shake hooking device, is characterized in that, front hook (41) of hook (4) Being made up of with arc shaped hook sleeve pipe, one end of sleeve pipe and arc shaped hook is consolidated into entirety, and at grade;The length of sleeve pipe Thickness equal to body of wall (7);During work, arc shaped hook is through in the circular hole of retainer ring (2);Back side hook (42) of hook (4) is Being made up of inserted link and crotch, the length of the inserted link at back side hook (42) is equal to the thickness of body of wall (7), and the diameter of inserted link is equal to just The internal diameter of the sleeve pipe in face hook (41), during work, cross-arm (5) is inserted in the crotch at back side hook (42), back side hook (42) Inserted link passes body of wall (7), is inserted in the sleeve pipe in front hook (41).
Hanging basket the most according to claim 1 anti-fall anti-shake hooking device, is characterized in that, cross-arm (5) is by through through walls The hook (4) of pipe (6) connects retainer ring (2) makes hanging basket (1) in body of wall (7) relatively-stationary rod-like members.
Hanging basket the most according to claim 1 anti-fall anti-shake hooking device, is characterized in that, wall pipe (6) is to pass perpendicularly through also It is embedded in the tubular part in body of wall (7), makes body of wall (7) both sides be able to through.
6. the using method of hanging basket anti-fall anti-shake hooking device, is characterized in that, when carrying out body of wall (7) construction it is necessary to by through walls It is internal that pipe (6) is embedded in body of wall (7) according to design requirement;
Use hanging basket (1) when the outer surface operation of body of wall (7), first install on roof hanging basket (1) Hoist Control Unit and Pulley bracket and fixed pulley is installed on parapet;
The one end of hoist cable (3) being wrapped on Hoist Control Unit is consolidated with hanging basket (1), hanging basket (1) when parapet top, Operating personnel enters hanging basket (1), by rotating Hoist Control Unit, hanging basket (1) is placed in job position;By in hanging basket (1) Operating personnel coordinate with indoor occupant, with hook (4) by wall pipe (6) will be located in body of wall (7) both sides retainer ring (2) and Cross-arm (5) connects into entirety;
After having constructed in this position of body of wall (7), after unclamping hook (4), hanging basket (1) can lift again freely;
When hanging basket (1) often stops at operation at, just with hook (4), retainer ring (2) and cross-arm (5) are wound in entirety, so Can ensure that hanging basket (1) safe construction.
CN201610650597.3A 2016-08-10 2016-08-10 Hanging basket anti-fall anti-shake hooking device and using method thereof Pending CN106193570A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610650597.3A CN106193570A (en) 2016-08-10 2016-08-10 Hanging basket anti-fall anti-shake hooking device and using method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610650597.3A CN106193570A (en) 2016-08-10 2016-08-10 Hanging basket anti-fall anti-shake hooking device and using method thereof

Publications (1)

Publication Number Publication Date
CN106193570A true CN106193570A (en) 2016-12-07

Family

ID=57514752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610650597.3A Pending CN106193570A (en) 2016-08-10 2016-08-10 Hanging basket anti-fall anti-shake hooking device and using method thereof

Country Status (1)

Country Link
CN (1) CN106193570A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112814359A (en) * 2020-12-31 2021-05-18 象山中宇模具有限公司 Fixable safety hanging basket for high-rise building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2204832Y (en) * 1994-05-04 1995-08-09 中国建筑第七工程局科研所 Automatic lifting scaffold
CN2853977Y (en) * 2005-12-13 2007-01-03 北京市建筑工程研究院 Wall sleeve type attaching device of reused lifting scaffold
CN201040922Y (en) * 2007-06-11 2008-03-26 江苏省建工集团有限公司 Anti-slip hook for fixing and suspending scaffold
US20080217104A1 (en) * 2007-03-05 2008-09-11 Bergeron William P Wildlife observation blind
CN204728682U (en) * 2015-05-27 2015-10-28 中国建筑第六工程局有限公司 A kind of fastening devices preventing hanging basket from swinging
CN205955166U (en) * 2016-08-10 2017-02-15 江苏建筑职业技术学院 Hanging flower basket couple formula prevents weighing down anti -shaking device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2204832Y (en) * 1994-05-04 1995-08-09 中国建筑第七工程局科研所 Automatic lifting scaffold
CN2853977Y (en) * 2005-12-13 2007-01-03 北京市建筑工程研究院 Wall sleeve type attaching device of reused lifting scaffold
US20080217104A1 (en) * 2007-03-05 2008-09-11 Bergeron William P Wildlife observation blind
CN201040922Y (en) * 2007-06-11 2008-03-26 江苏省建工集团有限公司 Anti-slip hook for fixing and suspending scaffold
CN204728682U (en) * 2015-05-27 2015-10-28 中国建筑第六工程局有限公司 A kind of fastening devices preventing hanging basket from swinging
CN205955166U (en) * 2016-08-10 2017-02-15 江苏建筑职业技术学院 Hanging flower basket couple formula prevents weighing down anti -shaking device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112814359A (en) * 2020-12-31 2021-05-18 象山中宇模具有限公司 Fixable safety hanging basket for high-rise building

Similar Documents

Publication Publication Date Title
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN103603504B (en) The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction
CN201221193Y (en) High altitude packway ceiling construction operating platform
CN202324571U (en) Overhanging type double-row scaffold
CN103993735A (en) Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN201962932U (en) Building construction segmented overhung outer scaffold
CN106437153A (en) Telescopic and transferrable crane climbing passageway for tower crane driver
CN110158937B (en) Cradle hanging structure without support and counterweight and construction method thereof
CN111764629A (en) Method for mounting and dismounting inclined roof hanging basket without counterweight
CN102733608B (en) Construction method for spray head layer of granulation tower
CN106150057B (en) A kind of split blade type hydraulic pressure lift climbing frame
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN102296829A (en) Method for constructing three-dimensional cable net curtain wall and node connection member used in same
CN201288415Y (en) Subsection gradual change overhanging type external scaffold for tall building
CN107575032A (en) A kind of bolt-ball net frame roofing installation method
CN110469102A (en) A kind of high-altitude combined steel beam installs the operating platform and its construction method
CN205955166U (en) Hanging flower basket couple formula prevents weighing down anti -shaking device
CN106193570A (en) Hanging basket anti-fall anti-shake hooking device and using method thereof
CN206503349U (en) A kind of vertical hoistway trackless is from the safe cage of lifting self-lock formula
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN105888269A (en) Suspended cable type safety protection device for building construction overhead operation, and construction method of suspended cable type safety protection device
CN205875672U (en) Hanging flower basket wound form is prevented weighing down and is prevented shaking device
CN106185618A (en) A kind of for Generator Stator hoisting structure and hanging method thereof
CN106193569A (en) Hanging basket anti-fall anti-shake wind and using method thereof
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161207