CN106169746A - A kind of grid power blackout early warning system and method - Google Patents

A kind of grid power blackout early warning system and method Download PDF

Info

Publication number
CN106169746A
CN106169746A CN201610559073.3A CN201610559073A CN106169746A CN 106169746 A CN106169746 A CN 106169746A CN 201610559073 A CN201610559073 A CN 201610559073A CN 106169746 A CN106169746 A CN 106169746A
Authority
CN
China
Prior art keywords
information
power
event
early warning
grid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610559073.3A
Other languages
Chinese (zh)
Inventor
杜宁
马泽杰
王柯成
黄朝凯
张泽锐
潘沪明
吴丽贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201610559073.3A priority Critical patent/CN106169746A/en
Publication of CN106169746A publication Critical patent/CN106169746A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/001Methods to deal with contingencies, e.g. abnormalities, faults or failures

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

This application discloses a kind of grid power blackout early warning system and method, this system includes: information integrated platform is joined by battalion, for when electrical network occurs power-off event, transferring the Electricity customers information of Power Marketing Management System, the power equipment information of power production management system and the topological structure of electric of power grid GIS the most respectively;Data analysis module, for utilizing battalion to join the data that information integrated platform is transferred out, carries out unified accident analysis to electrical network, obtains corresponding electric network fault information;Data simultaneous module, is used for electric network fault synchronizing information to each operation system.Visible, the present invention is electrical network generation power-off event when, each autocorrelative data can be transferred respectively from each operation system and electrical network is carried out unified accident analysis, the most again by the corresponding electric network fault synchronizing information that obtains to each operation system, thus ensure that and can launch effective collaborative work based on consistent electric network fault information for current power-off event between different business systems.

Description

A kind of grid power blackout early warning system and method
Technical field
The present invention relates to electric network information management technical field, particularly to a kind of grid power blackout early warning system and method.
Background technology
Due to the aspect such as idea, mechanism for a long time, in the internal control of power grid enterprises, Electric Power Marketing Management The construction of each operation systems such as system, power production management system and power grid GIS is separate, this A little operation systems also adhere to different specialized departments in daily management separately, consequently leads to the data letter in above-mentioned each operation system The state mutually isolated it is between breath.The phenomenon that this information is mutually isolated makes, when there is power-off event in electrical network, logical Cross and often there is inconsistent place between the electric network fault information that the analysis of different business systems obtains, so cause difference It is difficult between operation system launch effective collaborative work for power-off event, the most also constrains the customer service of electric power enterprise The lifting of ability.
In sum it can be seen that how to guarantee to launch effective association for power-off event between different business systems It is current problem demanding prompt solution with work.
Summary of the invention
In view of this, it is an object of the invention to provide a kind of grid power blackout early warning system and method, it is ensured that the most of the same trade or business Effective collaborative work can be launched for power-off event between business system.Its concrete scheme is as follows:
A kind of grid power blackout early warning system, including:
Information integrated platform is joined by battalion, for when there is power-off event in electrical network, transferring Power Marketing Management System the most respectively Electricity customers information, the power equipment information of power production management system and power grid GIS power network topology knot Structure;
Data analysis module, for utilizing described battalion to join the data that information integrated platform is transferred out, unifies electrical network Accident analysis, obtain corresponding electric network fault information;
Data simultaneous module, for by described electric network fault synchronizing information to described Power Marketing Management System, described electricity Power production management system and described power grid GIS.
Preferably, information integrated platform is joined by described battalion is the platform built based on SOA framework.
Preferably, described electric network fault information includes power supply interrupted district information, the customer information affected by power-off event, fault Line information and faulty equipment information.
Preferably, described grid power blackout early warning system, also include:
First send platform, be used for utilizing mobile communication technology, to the described customer information pair affected by power-off event The client's communicating terminal answered sends power failure information.
Preferably, described grid power blackout early warning system, also include:
Information transfers module, is used for utilizing described power supply interrupted district information, transfers the maintainer letter on corresponding power supply interrupted district Breath;
Second sends platform, for described faulty line information and described faulty equipment information being sent to and described maintenance On the maintainer communicating terminal that personal information is corresponding.
The invention also discloses a kind of grid power blackout method for early warning, including:
When electrical network occurs power-off event, transfer the Electricity customers information of Power Marketing Management System, electric power life the most respectively Produce power equipment information and the topological structure of electric of power grid GIS of management system;
Utilize the data transferred out, electrical network is carried out unified accident analysis, obtains corresponding electric network fault information;
By described electric network fault synchronizing information to described Power Marketing Management System, described power production management system and institute State power grid GIS.
Preferably, the data that described utilization is transferred out, electrical network is carried out unified accident analysis, obtains the event of corresponding electrical network The process of barrier information, including:
Utilize described Electricity customers information, described power equipment information and described topological structure of electric, electrical network is carried out event Barrier is analyzed, and obtains power supply interrupted district information, the customer information, faulty line information and the faulty equipment information that are affected by power-off event.
Preferably, described grid power blackout method for early warning, also include:
Utilize mobile communication technology, send out to client's communicating terminal corresponding with the described customer information affected by power-off event Send power failure information.
Preferably, described grid power blackout method for early warning, also include:
Utilize described electric network fault information, analyze and estimate electrical network Maintenance Demand Time, and this time is sent to described visitor Family communicating terminal.
Preferably, described grid power blackout method for early warning, also include:
Utilize described power supply interrupted district information, transfer the maintainer information on corresponding power supply interrupted district;
Described faulty line information is sent to the dimension corresponding with described maintainer information with described faulty equipment information Repair on personnel's communicating terminal.
In the present invention, grid power blackout early warning system, including: information integrated platform is joined by battalion, for when having a power failure in electrical network Event, transfers the power equipment information of the Electricity customers information of Power Marketing Management System, power production management system the most respectively Topological structure of electric with power grid GIS;Data analysis module, is used for utilizing battalion to join information integrated platform and transfers out Data, electrical network is carried out unified accident analysis, obtains corresponding electric network fault information;Data simultaneous module, for by electricity Net fault message is synchronized to Power Marketing Management System, power production management system and power grid GIS.Visible, this Bright electrical network generation power-off event when, can be respectively from Power Marketing Management System, power production management system and electrical network ground Reason information system is transferred each autocorrelative data electrical network is carried out unified accident analysis, the corresponding electricity that will obtain the most again Net fault message is synchronized to each operation system, thus avoids the electricity obtained between different business systems present in prior art The phenomenon that net fault message is inconsistent, thus ensure that between different business systems can based on consistent electric network fault information, Effective collaborative work is launched for current power-off event.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing In having technology to describe, the required accompanying drawing used is briefly described, it should be apparent that, the accompanying drawing in describing below is only this Inventive embodiment, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to according to The accompanying drawing provided obtains other accompanying drawing.
Fig. 1 is a kind of grid power blackout early warning system structural representation disclosed in the embodiment of the present invention;
Fig. 2 is a kind of grid power blackout method for early warning flow chart disclosed in the embodiment of the present invention.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise Embodiment, broadly falls into the scope of protection of the invention.
The embodiment of the invention discloses a kind of grid power blackout early warning system, shown in Figure 1, this system includes:
Information integrated platform 11 is joined by battalion, for when there is power-off event in electrical network, transferring Electric Power Marketing Management system the most respectively The power network topology knot of Electricity customers information, the power equipment information of power production management system and the power grid GIS of system Structure;
Data analysis module 12, for utilizing battalion to join the data that information integrated platform 11 is transferred out, unifies electrical network Accident analysis, obtain corresponding electric network fault information;
Data simultaneous module 13, for by electric network fault synchronizing information to Power Marketing Management System, power production management System and power grid GIS.
Wherein, in embodiments of the present invention, preferentially based on SOA framework (SOA, i.e. Service-Oriented Architecture, service-oriented architectural framework) build above-mentioned battalion and join information integrated platform 11.The core concept of SOA framework Be break traditions towards each business scope, rigid vertical applications system constructing pattern, application system is decomposed into loose coupling Reusable service.
It is further to note that above-mentioned data simultaneous module 13 is when carrying out data synchronization processing, can be first by above-mentioned Electric network fault information sends joins information integrated platform 11 to battalion, then joins information integrated platform 11 by battalion, by the event of above-mentioned electrical network Barrier information is respectively sent to Power Marketing Management System, power production management system and power grid GIS, comes real with this Now by the purpose of electric network fault synchronizing information to different business systems.
In the embodiment of the present invention, grid power blackout early warning system, including: information integrated platform is joined by battalion, for when sending out in electrical network Raw power-off event, transfers the Electricity customers information of Power Marketing Management System, the electric power of power production management system sets the most respectively Standby information and the topological structure of electric of power grid GIS;Data analysis module, is used for utilizing battalion to join information integrated platform The data transferred out, carry out unified accident analysis to electrical network, obtain corresponding electric network fault information;Data simultaneous module, uses In by electric network fault synchronizing information to Power Marketing Management System, power production management system and power grid GIS.Can Seeing, the embodiment of the present invention, can be respectively from Power Marketing Management System, power production management electrical network generation power-off event when System and power grid GIS are transferred each autocorrelative data electrical network is carried out unified accident analysis, the most again will The corresponding electric network fault synchronizing information obtained is to each operation system, thus avoids different business systems present in prior art Between the inconsistent phenomenon of the electric network fault information that obtains, thus ensure that can be based on consistent electricity between different business systems Net fault message, launches effective collaborative work for current power-off event.
The embodiment of the invention discloses a kind of concrete grid power blackout early warning system, relative to a upper embodiment, this enforcement Technical scheme has been made further instruction and optimization by example.Concrete:
In the present embodiment, data analysis module specifically may be used for utilizing Electricity customers information, power equipment information and Topological structure of electric, carries out accident analysis to electrical network, obtains power supply interrupted district information, the customer information affected by power-off event, event Barrier line information and faulty equipment information.That is, the electric network fault information in the present embodiment specifically includes power supply interrupted district information, is subject to Customer information, faulty line information and the faulty equipment information of power-off event impact.
In order to send power failure information to affected Electricity customers in time after electrical network generation power-off event, this Grid power blackout early warning system in bright embodiment, it is also possible to farther include: first send platform, for by power-off event Client's communicating terminal that the customer information of impact is corresponding sends power failure information.Concrete, above-mentioned first transmission platform is permissible Utilize mobile communication technology, such as 2G, 3G or 4G mobile communication technology, to the visitor corresponding with the customer information affected by power-off event Family communicating terminal sends power failure information.It is of course also possible to by internet communication technology, to relevant client's communicating terminal Send power failure information.
It addition, in order to notify that after electrical network generation power-off event corresponding power equipment maintaining personnel launch maintenance work in time, Grid power blackout early warning system in the embodiment of the present invention, the information of still further comprising transfer module and second send platform, wherein,
Information transfers module, is used for utilizing power supply interrupted district information, transfers the maintainer information on corresponding power supply interrupted district;
Second sends platform, for being sent to corresponding with maintainer information with faulty equipment information by faulty line information Maintainer communicating terminal on.
Further, the embodiment of the present invention can also include that maintenance time estimates module, is used for utilizing electric network fault information, Electrical network Maintenance Demand Time is estimated in analysis, and sends this time to the client corresponding with the customer information affected by power-off event Communicating terminal.Concrete, estimate above-mentioned maintenance time module specifically can utilize the faulty line information in current power-off event, Faulty equipment information and the professional standards of associate power maintainer, be analyzed pre-to current electric grid Maintenance Demand Time Estimate.It is understood that faulty line is the most complicated, faulty line quantity is the most, the corresponding maintenance estimated time is the longest, with Reason, faulty equipment structure is the most complicated, faulty equipment quantity is the most, and the corresponding maintenance estimated time is the longest, it addition, associate power The professional standards of maintainer are the highest, and the corresponding maintenance estimated time is the shortest.
Accordingly, the embodiment of the present invention further discloses a kind of grid power blackout method for early warning, shown in Figure 2, should Method includes:
Step S21: when there is power-off event in electrical network, transfers the Electricity customers letter of Power Marketing Management System the most respectively Breath, the power equipment information of power production management system and the topological structure of electric of power grid GIS.
It should be noted that the embodiment of the present invention preferentially joins information integrated platform by the battalion built based on SOA framework, come Transfer the Electricity customers information of above-mentioned Power Marketing Management System, the power equipment information of power production management system and electrical network ground The topological structure of electric of reason information system.
Step S22: utilize the data transferred out, electrical network is carried out unified accident analysis, obtains corresponding electric network fault Information.
That is, specifically utilize Electricity customers information, power equipment information and topological structure of electric, electrical network is unified Accident analysis, obtains corresponding electric network fault information.
Step S23: by electric network fault synchronizing information to Power Marketing Management System, power production management system and electrical network ground Reason information system.
Wherein, above-mentioned electric network fault information first can be sent and build based on SOA framework to the most above-mentioned by the embodiment of the present invention Information integrated platform is joined by battalion, then joins information integrated platform by this battalion, above-mentioned electric network fault information is respectively sent to electric power Marketing management system, power production management system and power grid GIS, realize electric network fault synchronizing information with this Purpose to different business systems.
Visible, the embodiment of the present invention, can be respectively from Power Marketing Management System, electricity electrical network generation power-off event when Power production management system and power grid GIS are transferred each autocorrelative data electrical network is carried out unified fault divide Analysis, the most again by the corresponding electric network fault synchronizing information that obtains to each operation system, thus avoids present in prior art The phenomenon that the electric network fault information that obtains between different business systems is inconsistent, thus ensure that can between different business systems Based on consistent electric network fault information, launch effective collaborative work for current power-off event.
The embodiment of the present invention further discloses a kind of concrete grid power blackout method for early warning, relative to a upper embodiment, Technical scheme has been made further instruction and optimization by the present embodiment.Concrete:
In upper embodiment step S22, utilize the data transferred out, electrical network is carried out unified accident analysis, obtains phase The process of the electric network fault information answered, specifically may include that and utilizes Electricity customers information, power equipment information and power network topology knot Structure, carries out accident analysis to electrical network, obtains power supply interrupted district information, the customer information affected by power-off event, faulty line information With faulty equipment information.That is, the electric network fault information in the present embodiment specifically includes power supply interrupted district information, by power-off event shadow Customer information, faulty line information and the faulty equipment information rung.
In order to send power failure information to affected Electricity customers in time after electrical network generation power-off event, this Grid power blackout method for early warning in bright embodiment, it is also possible to farther include: utilize mobile communication technology, to by power-off event Client's communicating terminal that the customer information of impact is corresponding sends power failure information.Such as, 2G, 3G or 4G mobile communication skill is utilized Art, sends power failure information to client's communicating terminal corresponding with the customer information affected by power-off event.It is of course also possible to By internet communication technology, send power failure information to relevant client's communicating terminal.
Further, the grid power blackout method for early warning in the present embodiment, it is also possible to farther include:
Utilize electric network fault information, analyze and estimate electrical network Maintenance Demand Time, and this time is sent to client's communication eventually End.Concrete can be to utilize the faulty line information in current power-off event, faulty equipment information and associate power maintenance The professional standards of personnel, are analyzed estimating to current electric grid Maintenance Demand Time.It is understood that faulty line is the most multiple Miscellaneous, faulty line quantity is the most, the corresponding maintenance estimated time is the longest, and in like manner, faulty equipment structure is the most complicated, fault sets Standby quantity is the most, and the corresponding maintenance estimated time is the longest, it addition, the professional standards of associate power maintainer are the highest, accordingly The maintenance estimated time the shortest.
It addition, in order to notify that after electrical network generation power-off event corresponding power equipment maintaining personnel launch maintenance work in time, Grid power blackout method for early warning in the embodiment of the present invention, it is also possible to farther include:
Utilize power supply interrupted district information, transfer the maintainer information on corresponding power supply interrupted district;
Faulty line information is sent to the maintainer communication corresponding with maintainer information eventually with faulty equipment information On end.
Finally, in addition it is also necessary to explanation, in this article, the relational terms of such as first and second or the like be used merely to by One entity or operation separate with another entity or operating space, and not necessarily require or imply these entities or operation Between exist any this reality relation or order.And, term " includes ", " comprising " or its any other variant meaning Containing comprising of nonexcludability, so that include that the process of a series of key element, method, article or equipment not only include that A little key elements, but also include other key elements being not expressly set out, or also include for this process, method, article or The key element that equipment is intrinsic.In the case of there is no more restriction, statement " including ... " key element limited, do not arrange Except there is also other identical element in including the process of described key element, method, article or equipment.
Above a kind of grid power blackout early warning system provided by the present invention and method are described in detail, herein should Being set forth principle and the embodiment of the present invention by specific case, the explanation of above example is only intended to help reason Solve method and the core concept thereof of the present invention;Simultaneously for one of ordinary skill in the art, according to the thought of the present invention, All will change in detailed description of the invention and range of application, in sum, this specification content should not be construed as this Bright restriction.

Claims (10)

1. a grid power blackout early warning system, it is characterised in that including:
Information integrated platform is joined by battalion, for when there is power-off event in electrical network, transferring the use of Power Marketing Management System the most respectively Electricity customer information, the power equipment information of power production management system and the topological structure of electric of power grid GIS;
Data analysis module, for utilizing described battalion to join the data that information integrated platform is transferred out, carries out unified event to electrical network Barrier is analyzed, and obtains corresponding electric network fault information;
Data simultaneous module, for by described electric network fault synchronizing information to described Power Marketing Management System, the life of described electric power Produce management system and described power grid GIS.
Grid power blackout early warning system the most according to claim 1, it is characterised in that it is base that information integrated platform is joined by described battalion In the platform that SOA framework is built.
Grid power blackout early warning system the most according to claim 1, it is characterised in that described electric network fault information includes having a power failure Area information, the customer information, faulty line information and the faulty equipment information that are affected by power-off event.
Grid power blackout early warning system the most according to claim 3, it is characterised in that also include:
First sends platform, is used for utilizing mobile communication technology, to corresponding with the described customer information affected by power-off event Client's communicating terminal sends power failure information.
5. according to the grid power blackout early warning system described in claim 3 or 4, it is characterised in that also include:
Information transfers module, is used for utilizing described power supply interrupted district information, transfers the maintainer information on corresponding power supply interrupted district;
Second sends platform, for described faulty line information and described faulty equipment information being sent to and described maintainer On the maintainer communicating terminal that information is corresponding.
6. a grid power blackout method for early warning, it is characterised in that including:
When electrical network occurs power-off event, transfer the Electricity customers information of Power Marketing Management System, power generation pipe the most respectively The power equipment information of reason system and the topological structure of electric of power grid GIS;
Utilize the data transferred out, electrical network is carried out unified accident analysis, obtains corresponding electric network fault information;
By described electric network fault synchronizing information to described Power Marketing Management System, described power production management system and described electricity Network Geographical Information System.
Grid power blackout method for early warning the most according to claim 6, it is characterised in that the data that described utilization is transferred out, right Electrical network carries out unified accident analysis, obtains the process of corresponding electric network fault information, including:
Utilize described Electricity customers information, described power equipment information and described topological structure of electric, electrical network is carried out fault and divides Analysis, obtains power supply interrupted district information, the customer information, faulty line information and the faulty equipment information that are affected by power-off event.
Grid power blackout method for early warning the most according to claim 7, it is characterised in that also include:
Utilize mobile communication technology, send to client's communicating terminal corresponding with the described customer information affected by power-off event and stop Electricity information.
Grid power blackout method for early warning the most according to claim 8, it is characterised in that also include:
Utilize described electric network fault information, analyze and estimate electrical network Maintenance Demand Time, and the transmission of this time is led to described client News terminal.
10. according to the grid power blackout method for early warning described in any one of claim 7 to 9, it is characterised in that also include:
Utilize described power supply interrupted district information, transfer the maintainer information on corresponding power supply interrupted district;
Described faulty line information is sent to the maintenance people corresponding with described maintainer information with described faulty equipment information On member's communicating terminal.
CN201610559073.3A 2016-07-13 2016-07-13 A kind of grid power blackout early warning system and method Pending CN106169746A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610559073.3A CN106169746A (en) 2016-07-13 2016-07-13 A kind of grid power blackout early warning system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610559073.3A CN106169746A (en) 2016-07-13 2016-07-13 A kind of grid power blackout early warning system and method

Publications (1)

Publication Number Publication Date
CN106169746A true CN106169746A (en) 2016-11-30

Family

ID=58065465

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610559073.3A Pending CN106169746A (en) 2016-07-13 2016-07-13 A kind of grid power blackout early warning system and method

Country Status (1)

Country Link
CN (1) CN106169746A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108320126A (en) * 2016-12-16 2018-07-24 山东电力调度控制中心 A kind of grid company province ground county's Integrated management system
CN112101707A (en) * 2020-07-31 2020-12-18 广东卓维网络有限公司 Power utilization emergency management system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204156610U (en) * 2014-11-15 2015-02-11 国网河南省电力公司开封供电公司 A kind of intelligent distribution network fault processing module

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204156610U (en) * 2014-11-15 2015-02-11 国网河南省电力公司开封供电公司 A kind of intelligent distribution network fault processing module

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
ZWE-LEE GAING等: "Optimal Grey Topological Predicting Approach to Short-term Load Forecasting in Power System", 《POWER ENGINEERING SOCIETY SUMMER MEETING》 *
钟秀超: "惠州电网营配一体化构建", 《中国优秀硕士学位论文全文数据库》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108320126A (en) * 2016-12-16 2018-07-24 山东电力调度控制中心 A kind of grid company province ground county's Integrated management system
CN112101707A (en) * 2020-07-31 2020-12-18 广东卓维网络有限公司 Power utilization emergency management system

Similar Documents

Publication Publication Date Title
CN102646230B (en) A kind of infosystem realizing the management of distribution network failure fast power restoration
CN103986227A (en) Electric power distribution network operation monitoring method and system based on GIS platform
CN102565572A (en) Platform and method for judging fault of match power grid
CN110557758A (en) Power system communication network deployment processing method and device
CN103632312A (en) Power grid resource module building method based on GIS (geographic information system)
CN102800033A (en) Distribution production and marketing business integration system
CN109473970A (en) Protect power supply trouble monitoring removal system and method
CN105678651A (en) Power grid big data quality standardization-based power grid information management system and method
CN107832854A (en) A kind of method and system of distribution network failure repairing progress msg management
CN105447127A (en) Failure outage range visualization system and method based on power distribution automation and marketing GIS
CN103955865A (en) Scheduled and faulted power outage range visualization method based on information interaction
CN103023147A (en) Remote vision linkage method for electric power master station and substation based on computer integrated manufacturing (CIM) data model
WO2022166562A1 (en) Modeling analysis method for device management network, and network model updating method
CN205407414U (en) Mistake system is prevented to intelligent power distribution net based on electric power GIS
CN103606055A (en) Intelligent interaction platform for power fault rush repair
CN106169746A (en) A kind of grid power blackout early warning system and method
CN202353815U (en) GIS short message power grid service system
Johnson Smart City Development in China.
CN111291950A (en) Economic park distribution network active service and operation management and control unified platform
CN202306271U (en) Remote wireless monitoring system of mine
CN111476547A (en) Method for analyzing assets of distribution network line ring-out point arrangement in user
CN206908606U (en) Mine-used I. S communication, positioning and broadcast integral system
CN103607050A (en) Electric informatization intelligent monitoring and management system
CN104573986B (en) One realizes GCRMS and electrical network multi-source operation system interoperability integrated approach
CN103500384A (en) Comprehensive management system for power distribution and consumption side communication basic resources

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161130

RJ01 Rejection of invention patent application after publication