CN106150055B - The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting - Google Patents

The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting Download PDF

Info

Publication number
CN106150055B
CN106150055B CN201610708483.XA CN201610708483A CN106150055B CN 106150055 B CN106150055 B CN 106150055B CN 201610708483 A CN201610708483 A CN 201610708483A CN 106150055 B CN106150055 B CN 106150055B
Authority
CN
China
Prior art keywords
steel pipe
hanger bolt
bracket
built
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610708483.XA
Other languages
Chinese (zh)
Other versions
CN106150055A (en
Inventor
穆瑞刚
刘会铁
王志
魏彤
沈华勇
邢光杰
王斌
马亮
冉隆林
路树峰
白月海
崔凯
侯文洪
钱伟龙
王家欢
胡月增
戴罡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin No2 Construction Engineering Co Ltd
Original Assignee
Tianjin No2 Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin No2 Construction Engineering Co Ltd filed Critical Tianjin No2 Construction Engineering Co Ltd
Priority to CN201610708483.XA priority Critical patent/CN106150055B/en
Publication of CN106150055A publication Critical patent/CN106150055A/en
Application granted granted Critical
Publication of CN106150055B publication Critical patent/CN106150055B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/36Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements
    • E04G21/185Means for positioning building parts or elements for anchoring elements or elements to be incorporated in the structure

Abstract

The present invention relates to architectural furniture technical fields, more particularly to a kind of flat hanging installment work rack of concrete embedded part essence, including bracket, locking regulating part, lateral steel pipe, longitudinal steel pipe, hanger bolt, the both ends of the transverse direction steel pipe are separately fixed on the bracket, the upper and lower ends of the hanger bolt are respectively provided with screw thread, the longitudinal direction steel pipe is connect by the locking regulating part with the hanger bolt, and the longitudinal direction steel tube lapping is on the top of the lateral steel pipe.The invention has the following advantages that 1, protect positive built-in fitting absolute altitude error within 1mm, flatness zero deflection;2, it ensure that built-in fitting in the construction process, not because concrete casting, template or reinforcing bar vibration are subjected to displacement;3, the sizing hard frame of steel is firm, indeformable, can set up precision instrument.

Description

The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting
Technical field
The present invention relates to architectural furniture technical field more particularly to a kind of flat hanging erectors of concrete embedded part essence Make the installation method of rack and built-in fitting.
Background technique
Currently, traditional form of construction work not can guarantee the flatness of built-in fitting in concreting built-in fitting, constructing In the process, usually cause built-in fitting error larger, Wu Fahou since the vibration of concrete casting, template or reinforcing bar is subjected to displacement Continuous installation.
Summary of the invention
It is an object of the invention to overcome the shortcomings of above-mentioned technology, and provide a kind of flat hanging installation of concrete embedded part essence Working gantry protects positive built-in fitting absolute altitude error within 1mm, flatness zero deflection.
The present invention to achieve the above object, using following technical scheme:
A kind of flat hanging installment work rack of concrete embedded part essence, it is characterised in that: including bracket, locking regulating part, The both ends of lateral steel pipe, longitudinal steel pipe, hanger bolt, the transverse direction steel pipe are separately fixed on the bracket, the hanging spiral shell The upper and lower ends of bolt are respectively provided with screw thread, and the longitudinal direction steel pipe is connect by the locking regulating part with the hanger bolt, institute Longitudinal steel tube lapping is stated on the top of the lateral steel pipe.
Preferably, the locking regulating part is made of top nut and lower nut, and upper and lower nut clamps longitudinal steel pipe, hanging The upper end of bolt is connect with the upper and lower nut thread respectively.
Preferably, the bracket is equipped with the wooden scaffold board.
A kind of installation method of built-in fitting, it is characterised in that: the following steps are included:
Step 1: steel plate cutting is processed, steel plate is processed into required specification shape;
Step 2: drilling, processes circular hole on the steel plate;
Step 3: welding dowel, welds dowel in the bottom of the steel plate;
Step 4: welded nut, in the position welded nut of the circular hole;
Step 5: fixed hanger bolt, the nut thread in the lower end and step 4 of bolt is fixed;
Step 6: setting up bracket, bracket is ridden upon to the two sides of walling body to be poured;
Step 7: steel plate handling is in place, steel plate handling is to be installed in the top of bracket etc.;
Step 8: installation upper lateral, vertical steel pipe, by horizontal, vertical penstock installation on bracket;
Step 9: locking hanger bolt, the top of hanger bolt is mounted on longitudinal lever by locking regulating part;
Step 10: control absolute altitude, fine tuning hanger bolt transfers steel plate to designed elevation;
Step 11: casting concrete;
Step 12: embedded part absolute altitude is calibrated before initial set again;
Step 13: conserving to demoulding.
Preferably, further include the steps that setting up interim reinforcing bar shoulder pole before step 7.
Preferably, further include the steps that removing interim reinforcing bar shoulder pole before step 10.
Preferably, in the step 2, the quantity of circular hole is four, and the circle center line connecting of four circular holes is square, rectangular Central point is located at the center of steel plate.
The beneficial effects of the present invention are: compared with the existing technology, the present invention is suitable for having built-in fitting embedding precision high It is required that concrete wall upper rail pipeline installation construction.It has the advantage that 1, protect positive built-in fitting absolute altitude error within 1mm, it is smooth Spend zero deflection;2, it ensure that built-in fitting in the construction process, not because concrete casting, template or reinforcing bar vibration are subjected to displacement;3, The hard frame of steel of being formed is firm, indeformable, can set up precision instrument.
Detailed description of the invention
Fig. 1 is the structural schematic diagram in the present invention;
Fig. 2 is partial enlarged view in the present invention.
Specific embodiment
With reference to the accompanying drawing and the preferred embodiment specific embodiment that the present invention will be described in detail.As depicted in figs. 1 and 2, A kind of flat hanging installment work rack of concrete embedded part essence, including bracket 1, locking regulating part, lateral steel pipe 3, longitudinal steel pipe 4, the both ends of hanger bolt 5, the transverse direction steel pipe are separately fixed on the bracket, the upper and lower ends difference of the hanger bolt With screw thread, the longitudinal direction steel pipe is connect by the locking regulating part with the hanger bolt, and the longitudinal direction steel tube lapping exists The top of the transverse direction steel pipe.
In the present invention, the locking regulating part is made of top nut 6 and lower nut 7, and upper and lower nut clamps longitudinal steel Pipe, the upper end of hanger bolt is connect with the upper and lower nut thread respectively.
For the ease of worker operation, the bracket is equipped with the wooden scaffold board 8.
The present invention also provides a kind of installation methods of built-in fitting, comprising the following steps: Step 1: 9 blanking of steel plate is processed, Steel plate is processed into required specification shape;Step 2: drilling, processes circular hole 10 on the steel plate;Step 3: weld anchor Muscle 11 welds dowel in the bottom of the steel plate;Step 4: welded nut 12, in the position welded nut of the circular hole;Step Five, fixed hanger bolt, the nut thread in the lower end and step 4 of bolt is fixed;Step 6: setting up bracket, bracket is taken It is located at the two sides of walling body to be poured;Step 7: steel plate handling is in place, steel plate handling is to be installed in the top of bracket etc.;Step Eight, upper lateral, vertical steel pipe are installed, by horizontal, vertical penstock installation on bracket;Step 9: locking hanger bolt, by hanger bolt Top is mounted on longitudinal lever by locking regulating part;Step 10: control absolute altitude, fine tuning hanger bolt decentralization steel plate to design Absolute altitude;Step 11: casting concrete 13;Step 12: embedded part absolute altitude is calibrated before initial set again;Step 13: maintenance is to tearing open Mould.
Further include the steps that setting up interim reinforcing bar shoulder pole before step 7.It further include removing temporary steel before step 10 The step of muscle shoulder pole.A preliminary support first can be carried out to steel plate by setting reinforcing bar shoulder pole, when horizontal, vertical steel pipe has been set up Cheng Houzai is removed.
In order to make steel plate keep balancing, in the step 2, the quantity of circular hole is four, and the center of circle of four circular holes connects Line is square, and rectangular central point is located at the center of steel plate.By adjust four hanger bolts can levelness to steel plate into Row is adjusted.
The concrete wall upper rail pipeline installation construction that the present invention is suitable for having built-in fitting embedding precision high requirement.With with Lower advantage: 1, positive built-in fitting absolute altitude error is protected within 1mm, flatness zero deflection;2, it ensure that built-in fitting in the construction process, Not because concrete casting, template or reinforcing bar vibration are subjected to displacement;3, the sizing hard frame of steel is firm, indeformable, can set up precision instrument.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (7)

1. a kind of flat hanging installment work rack of concrete embedded part essence, it is characterised in that: including bracket, locking regulating part, cross To steel pipe, longitudinal steel pipe, hanger bolt, the both ends of the transverse direction steel pipe are separately fixed on the bracket, the hanger bolt Upper and lower ends be respectively provided with screw thread, the longitudinal direction steel pipe is connect by the locking regulating part with the hanger bolt, described Longitudinal steel tube lapping is on the top of the lateral steel pipe.
2. the flat hanging installment work rack of concrete embedded part essence according to claim 1, it is characterised in that: the locking Regulating part is made of top nut and lower nut, and upper and lower nut clamps longitudinal steel pipe, the upper end of hanger bolt respectively with it is described it is upper, Lower nut is threadedly coupled.
3. the flat hanging installment work rack of concrete embedded part essence according to claim 1, it is characterised in that: the bracket It is equipped with the wooden scaffold board.
4. a kind of installation method of built-in fitting, it is characterised in that: the following steps are included: Step 1: steel plate cutting is processed, by steel plate It is processed into required specification shape;
Step 2: drilling, processes circular hole on the steel plate;
Step 3: welding dowel, welds dowel in the bottom of the steel plate;
Step 4: welded nut, in the position welded nut of the circular hole;
Step 5: fixed hanger bolt, the nut thread in the lower end and step 4 of bolt is fixed;
Step 6: setting up bracket, bracket is ridden upon to the two sides of walling body to be poured;
Step 7: steel plate handling is in place, steel plate handling is to be installed in the top of bracket etc.;
Step 8: installation upper lateral, vertical steel pipe, by horizontal, vertical penstock installation on bracket;
Step 9: locking hanger bolt, the top of hanger bolt is mounted on longitudinal lever by locking regulating part;
Step 10: control absolute altitude, fine tuning hanger bolt transfers steel plate to designed elevation;
Step 11: casting concrete;
Step 12: embedded part absolute altitude is calibrated before initial set again;
Step 13: conserving to demoulding.
5. the installation method of built-in fitting according to claim 4, it is characterised in that: further include setting up to face before step 7 When reinforcing bar shoulder pole the step of.
6. the installation method of built-in fitting according to claim 5, it is characterised in that: further include removing to face before step 10 When reinforcing bar shoulder pole the step of.
7. the installation method of built-in fitting according to claim 4, it is characterised in that: in the step 2, the quantity of circular hole It is four, the circle center line connecting of four circular holes is square, and rectangular central point is located at the center of steel plate.
CN201610708483.XA 2016-08-23 2016-08-23 The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting Active CN106150055B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610708483.XA CN106150055B (en) 2016-08-23 2016-08-23 The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610708483.XA CN106150055B (en) 2016-08-23 2016-08-23 The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting

Publications (2)

Publication Number Publication Date
CN106150055A CN106150055A (en) 2016-11-23
CN106150055B true CN106150055B (en) 2019-02-05

Family

ID=57342478

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610708483.XA Active CN106150055B (en) 2016-08-23 2016-08-23 The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting

Country Status (1)

Country Link
CN (1) CN106150055B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059913A (en) * 2017-05-22 2017-08-18 中国五冶集团有限公司 A kind of reactor built-in fitting supporting construction and method for embedding
CN108035440A (en) * 2017-10-27 2018-05-15 西安建筑科技大学 A kind of assembled Self-resetting Column Joint with Wedge device
CN109914820A (en) * 2019-03-25 2019-06-21 中国核工业华兴建设有限公司 Portable high-accuracy absolute altitude installation of embedded parts tool
CN110206166B (en) * 2019-06-06 2020-09-29 广东建星建造集团有限公司 Section steel column base and installation and construction method thereof
WO2021103895A1 (en) * 2019-11-29 2021-06-03 中建三局第二建设工程有限责任公司 Pre-embedded assembly type expansion joint ultra-long installation suspension leveling positioning system and construction method
CN111218991A (en) * 2020-01-19 2020-06-02 中国化学工程第十一建设有限公司 Installation method of large embedded part

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268659A (en) * 1996-04-02 1997-10-14 Hitachi Metals Ltd Fixing structure of anchor bolt
JP3752310B2 (en) * 1996-05-20 2006-03-08 住友林業株式会社 Anchor bolt positioning tool and method
CN202031179U (en) * 2011-04-20 2011-11-09 中国十七冶集团有限公司 Centre line aligning and elevation adjusting device of basic embedded bolts
CN202611261U (en) * 2012-04-17 2012-12-19 中国建筑第五工程局有限公司 Preset embedded bolt support of concrete foundation
CN204252284U (en) * 2014-11-21 2015-04-08 中冶天工集团有限公司 Built-in fitting bracing means
CN205976407U (en) * 2016-08-23 2017-02-22 天津二建建筑工程有限公司 Smart flat installation work rack of hanging of concrete built -in fitting

Also Published As

Publication number Publication date
CN106150055A (en) 2016-11-23

Similar Documents

Publication Publication Date Title
CN106150055B (en) The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting
CN106320715B (en) A kind of construction method of installation of the I-shaped inclined-plane built-in fitting of large size
CN109208790B (en) Single-side formwork erecting construction method for arc shear wall
CN107386455B (en) Shock insulation support and installation and construction method thereof
CN206971769U (en) A kind of rubber support installation positioning special purpose device
CN104481167A (en) High-formwork construction method for miscellaneous fill ground
CN106351450A (en) Suspension type pouring-leveling device in building operations and pouring method
CN204626966U (en) A kind of deformation joint formwork erection device
CN204875558U (en) Shaped steel runs through inside and outside compound support formula bracket system of encorbelmenting
CN206071044U (en) A kind of constructional column plate device
CN106760014A (en) A kind of board-like adjustable damper embedded part of full assembled and installation method
JP6529009B2 (en) Construction method of foundation for building
CN107859058A (en) A kind of cast-in-place concrete retaining wall anti-incline anti-floating large steel moulding plate device and installation method
CN201901941U (en) Building system combining precast concrete member and cast-in-place concrete template
CN104831832A (en) Assembly type shearing wall structure and mounting method thereof
CN205976407U (en) Smart flat installation work rack of hanging of concrete built -in fitting
CN205188812U (en) Rail guard template
CN207685855U (en) A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall
CN116623939A (en) Tool type suspension steel template construction method
CN206539026U (en) A kind of one side formwork formwork system
CN206205455U (en) A kind of construction centre mounted type pours leveling unit
CN206189607U (en) Rag bolt location structure
CN205654082U (en) Half tunnel formwork
CN205242684U (en) Wall body erection joint spare
CN104481163B (en) A kind of L beam construction equipment for building structure reinforcing and method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant