CN106149989B - The installation method of space roof boarding in non-finished product skylight - Google Patents

The installation method of space roof boarding in non-finished product skylight Download PDF

Info

Publication number
CN106149989B
CN106149989B CN201510146714.8A CN201510146714A CN106149989B CN 106149989 B CN106149989 B CN 106149989B CN 201510146714 A CN201510146714 A CN 201510146714A CN 106149989 B CN106149989 B CN 106149989B
Authority
CN
China
Prior art keywords
skylight
space
installation
track
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510146714.8A
Other languages
Chinese (zh)
Other versions
CN106149989A (en
Inventor
林锡森
王争
张志坤
凌香宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201510146714.8A priority Critical patent/CN106149989B/en
Publication of CN106149989A publication Critical patent/CN106149989A/en
Application granted granted Critical
Publication of CN106149989B publication Critical patent/CN106149989B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to the installation methods of roof boarding in roof boarding installation more particularly to skylight.The installation method of space roof boarding in the non-finished product skylight of the present invention;According to bulk in femerell, dedicated space plate horizontal transport trolley is made, special transport trolley includes four parts: steel pipe support, idler wheel, track, jack.Using between space plate and skylight arc frame gap, simultaneously utilize the boundless rib of space plate short, short panel gap below, to install interim Cantilever Beams, with the Cantilever Beams come the walking track of supporting trolley.After track and trolley are in place, the installation of horizontal transport space plate is carried out by walking dolly.The installation problem of space plate can be successfully solved using the technology, shortens the construction period, reduce mounting cost.Present invention efficiently solves the lifting problems of space roof boarding in the overlength of restricted clearance, superelevation skylight frame, shorten the construction period, reduce mounting cost.

Description

The installation method of space roof boarding in non-finished product skylight
Technical field
The present invention relates to the installation methods of roof boarding in roof boarding installation more particularly to skylight.
Background technique
In recent years construction market is become increasingly prosperous, higher and higher to the requirement in terms of building products energy-saving and environmental protection.Space plate can expire Material requirements in terms of the sufficient increasing energy-saving and environmental protection of construction market, is widely used in industrial premises and residential houses etc. and builds In the wallboard and roof boarding built.Using the large area industrial premises of roof steel bracket skylight (non-finished product skylight), the peace of skylight Harness has overlength, superelevation and the difficult points such as is limited by space and space plank house face can not be widely used, such as due to being limited by the difficult point It is a great problem in space plate installing engineering that, which solves the mounting technique,.
Non- finished product skylight is located on the roof truss of industrial premises longitudinal direction, and the skylight length of general workshop is between 50m ~ 200m. Skylight skeleton is made of main frame and arc frame, and space plate is arranged on the main frame beam of skylight, is surrounded in it by arc frame, peace Fill narrow space.It (is lifted using tower crane or large-scale crane) when using traditional installation method, is such as all pacified to skylight The roof boarding installation can not be carried out after installing.Therefore, it is necessary to adjust erection sequence: i.e. after 1 ~ 2 Pin skylight frame of every installation immediately into The installation of the row Pin space roof boarding.Skylight frame and roof boarding construction team need alternately operating, and co-ordination amount is big, the construction period It is long, and the large-scale crane machine-team waste of installing louver frame is serious, mounting cost is big.
Summary of the invention
Present invention seek to address that drawbacks described above, a kind of installation method of space roof boarding in non-finished product skylight is provided.This hair The lifting problem of space roof boarding in the bright overlength for efficiently solving restricted clearance, superelevation skylight frame shortens the construction period, drop Low mounting cost.
The present invention is implemented as follows: in a kind of non-finished product skylight space roof boarding installation method, it includes: A, level Travelling bogie production: trolley steel pipe support is welded using the scaffold tubes at scene, including four steel pipe posts, upper layer and lower layer water Flat pipe and its support;Steel pipe support length and width dimensions ensure gauge of walking mainly depending on the space board size of pre-installation Control is between space plate two sides and arc frame column gap;
B, the idler wheel installation of travelling bogie: below angle steel and outer in the column root weld angle steel of each steel pipe support Side is respectively welded thick steel plate and round steel and is used to fix vertical idler wheel and horizontal roller, it is ensured that idler wheel accessible row in orbit It walks;
C, lifting jack installation: a jack is hung, respectively in steel pipe support four corners for hanging space plate;
D, system peace Cantilever Beams: J-shaped hook is fabricated to using channel steel, hooks the elongated main frame beam upper limb of femerell Edge, long to arranged for interval along skylight, overhanging channel steel is flat to be buckled on Vierendeel girder, and height palpus control is in space plate face plate side rib below In gap, the wherein boundless rib of roof boarding short;
E, installation carriage track: the track of travelling bogie is using [20# channel steel is connected using L50x5 angle steel between track It connects, track is fixed on Cantilever Beams.
F, travelling bogie is in place: using truck crane, travelling bogie is filled in skylight from skylight end, and is once located in On groove steel rail;
G, it lifts space plate: then use in space plate vertical transport to the main frame of skylight end using truck crane Horizontal transport trolley and its jack handling are successively installed to the skylight other end by manually push carriage walking.
The present invention makes dedicated space plate horizontal transport trolley according to bulk in femerell, and special transport is small Vehicle includes four parts: steel pipe support, idler wheel, track, jack.(about using the gap between space plate and skylight arc frame 500mm), the boundless rib of space plate short is utilized simultaneously, and short panel gap below (140mm) is used to install interim Cantilever Beams The Cantilever Beams carry out the walking track of supporting trolley.After track and trolley are in place, horizontal transport space plate is carried out by walking dolly Installation.The installation problem of space plate can be successfully solved using the technology, shortens the construction period, reduce mounting cost.
Specific embodiment
The installation method of space roof boarding in the non-finished product skylight of the present invention, including the production of 1. dedicated leveling travelling bogies:
(1) trolley steel pipe support using scene Φ 48x3.5 scaffold tubes be welded, including 4 steel pipe posts, up and down Two layers of horizontal tube and its support.Steel pipe support length and width dimensions are mainly depending on the space board size of pre-installation, than pre-installation The wide 500mm out of space board size, while ensuring to walk gauge control between space plate two sides and arc frame column gap.
(2) the idler wheel installation of travelling bogie: in the column root weld L50X5 angle steel of each steel pipe support, length is 300mm;Below angle steel and 10mm thick steel plate is respectively welded for lateral surface and 20 round steel of φ is used to fix vertical idler wheel and horizontal rolling Wheel, it is ensured that idler wheel accessible walking in orbit.
(3) lifting jack installation: 1 2t jack is hung, respectively in steel pipe support four corners for hanging space plate.
2. system peace Cantilever Beams: being fabricated to J-shaped hook using 12# channel steel, hook on the elongated main frame beam of femerell The edge of a wing, it is long to arranged for interval, spacing 2000mm along skylight.Overhanging channel steel is flat to be buckled on Vierendeel girder, and height must be controlled in 140mm Within (should having a size of space plate face plate side rib below gap, wherein the boundless rib of roof boarding short).
3. installation carriage track: the track of travelling bogie is using [20# channel steel is connected using L50x5 angle steel between track It connects, track is fixed on Cantilever Beams.
4. travelling bogie is in place: using 25t truck crane, travelling bogie is filled in skylight from skylight end, and once On groove steel rail.
5. lifting space plate: being carried out in space plate vertical transport to the main frame of skylight end using 25t truck crane, then It is successively installed to the skylight other end with horizontal transport trolley and its jack handling by manually push carriage walking.

Claims (1)

1. the installation method of space roof boarding in a kind of non-finished product skylight, which is characterized in that it includes: A, horizontal transport trolley system Make: trolley steel pipe support is welded using the scaffold tubes at scene, including four steel pipe posts, upper layer and lower layer horizontal tube and its branch Support;Steel pipe support length and width dimensions are mainly depending on the space board size of pre-installation, while the gauge control that ensures to walk is in space Between plate two sides and arc frame column gap;
B, the idler wheel installation of travelling bogie: in the column root weld angle steel of each steel pipe support, below angle steel and lateral surface Thick steel plate is respectively welded and round steel is used to fix vertical idler wheel and horizontal roller, it is ensured that idler wheel accessible walking in orbit;
C, lifting jack installation: a jack is hung, respectively in steel pipe support four corners for hanging space plate;
D, system peace Cantilever Beams: J-shaped hook is fabricated to using channel steel, hooks the elongated main frame beam top flange of femerell, edge Skylight is long to arranged for interval, and overhanging channel steel is flat to be buckled on Vierendeel girder, and height palpus control is in space plate face plate side rib below gap It is interior, the wherein boundless rib of roof boarding short;
E, installation carriage track: the track of travelling bogie using [20# channel steel is attached between track using L50x5 angle steel, Track is fixed on Cantilever Beams;
F, travelling bogie is in place: using truck crane, travelling bogie is filled in skylight from skylight end, and be once located in channel steel On track;
G, it lifts space plate: being carried out in space plate vertical transport to the main frame of skylight end using truck crane, then with level Travelling bogie and its jack handling are successively installed to the skylight other end by manually push carriage walking.
CN201510146714.8A 2015-03-31 2015-03-31 The installation method of space roof boarding in non-finished product skylight Active CN106149989B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510146714.8A CN106149989B (en) 2015-03-31 2015-03-31 The installation method of space roof boarding in non-finished product skylight

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510146714.8A CN106149989B (en) 2015-03-31 2015-03-31 The installation method of space roof boarding in non-finished product skylight

Publications (2)

Publication Number Publication Date
CN106149989A CN106149989A (en) 2016-11-23
CN106149989B true CN106149989B (en) 2019-04-23

Family

ID=57337192

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510146714.8A Active CN106149989B (en) 2015-03-31 2015-03-31 The installation method of space roof boarding in non-finished product skylight

Country Status (1)

Country Link
CN (1) CN106149989B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4864837A (en) * 1988-09-29 1989-09-12 Fielden Jr Swan R Apparatus for producing panel roofing
CN201080674Y (en) * 2007-08-11 2008-07-02 山东中通钢构建筑股份有限公司 Steel structure architecture roof board elevated automatic conveying vehicle
CN201560539U (en) * 2009-09-30 2010-08-25 中太建设集团股份有限公司 Tool car for long-span net rack roof space plate
CN203452285U (en) * 2013-08-13 2014-02-26 广东中辰钢结构有限公司 Horizontal handling pulley for roof panels

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4864837A (en) * 1988-09-29 1989-09-12 Fielden Jr Swan R Apparatus for producing panel roofing
CN201080674Y (en) * 2007-08-11 2008-07-02 山东中通钢构建筑股份有限公司 Steel structure architecture roof board elevated automatic conveying vehicle
CN201560539U (en) * 2009-09-30 2010-08-25 中太建设集团股份有限公司 Tool car for long-span net rack roof space plate
CN203452285U (en) * 2013-08-13 2014-02-26 广东中辰钢结构有限公司 Horizontal handling pulley for roof panels

Also Published As

Publication number Publication date
CN106149989A (en) 2016-11-23

Similar Documents

Publication Publication Date Title
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN103669215B (en) Vertical-horizontal overall-sliding type side mold of fulcrum-few support
CN107447973B (en) Unilateral suspension type air mobile steel platform
CN202751338U (en) Rail type suspension basket
CN106677542A (en) Construction method of roof base truss structure
CN107288352B (en) The transport of the closed shed dormer roof boarding of overlarge area and installation method
CN207553606U (en) A kind of mobile holder device of overhead station construction
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN102190249A (en) Method for hoisting equipment positioned at bottom of multilayer frame platform
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN103821084B (en) Operational method at the bottom of implement at the bottom of beam and beam
CN105442773A (en) Technology and construction platform for installing and constructing inner plates of metal roof
CN103654610A (en) Rail type hanging basket
CN101284618A (en) Construction elevator device for reverse construction of underground structure
CN208455637U (en) The installation system of bracing members in a kind of foundation pit
CN203795315U (en) High pier cable-stayed bridge No.0 block non-bracket construction structure
CN203034777U (en) Rail-mounted mobile tall operation platform
CN102926330B (en) Installation method of hanging basket suitable for bridge construction
CN106149989B (en) The installation method of space roof boarding in non-finished product skylight
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN106223203A (en) Steel girder erection support and using method thereof
CN203257106U (en) Multifunctional power-driven walking type walking system
CN202899639U (en) Concrete column structure
CN207228604U (en) A kind of unilateral suspension type aerial movement steel platform
CN201647844U (en) Beam lifting station without abutments

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant