CN106121652A - Closed pit open-pit mine ore recovery method - Google Patents

Closed pit open-pit mine ore recovery method Download PDF

Info

Publication number
CN106121652A
CN106121652A CN201610593578.1A CN201610593578A CN106121652A CN 106121652 A CN106121652 A CN 106121652A CN 201610593578 A CN201610593578 A CN 201610593578A CN 106121652 A CN106121652 A CN 106121652A
Authority
CN
China
Prior art keywords
ore
hole
back production
pit
stoping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610593578.1A
Other languages
Chinese (zh)
Other versions
CN106121652B (en
Inventor
薛世忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuoliwei Beijing Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610593578.1A priority Critical patent/CN106121652B/en
Publication of CN106121652A publication Critical patent/CN106121652A/en
Application granted granted Critical
Publication of CN106121652B publication Critical patent/CN106121652B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/26Methods of surface mining; Layouts therefor
    • E21C41/30Methods of surface mining; Layouts therefor for ores, e.g. mining placers

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Remote Sensing (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The invention discloses a closed pit open-pit mine ore stoping method, relates to the technical field of open-pit mine ore mining, and aims to shorten the stoping period and improve the production efficiency. A closed pit open pit mine ore recovery method comprises the following steps: determining a corresponding stoping method according to occurrence conditions of stopable ores; carrying out stoping construction according to the stoping method; carrying out regional or one-time inter-hole differential interval initiation on the whole recoverable ore of the closed-pit surface mine according to a preset initiation sequence; ore removal is carried out on ore which is disintegrated by regional or disposable differential detonation between holes. The invention is suitable for the stoping of the closed pit open-pit mine ores.

Description

One closes hole surface mine Ore stoping method
Technical field
The present invention relates to surface mine technical field of ore extraction, particularly relate to one and close surface mine Ore back production side, hole Method.
Background technology
Closed or the neighbouring Metal Open mountain closed, its length of service all more than 15 years or longer time, At the beginning of its exploitation, owing to domestic mining, ore dressing overall technology level fall behind, equipment is equipped with low SI, and institutional factor etc. is in many ways The restriction of the factor in face, the design of mine overall plan, layout and progressively implement congenital defect the most, the just sizing of its result is at it It is more or less in before closedown in mining process and has discarded a part of Ore.The development of technology, resource in short supply, price soaring, The exploitation once again of this part Ore, with regard to urgent pendulum in face of enterprise, enterprise is limited by the impact of various factors, such as, Mining right boundary of a piece of land scope, comprehensive economic index etc., cannot expand side on the basis of former mining by original method and give birth to Produce, but ignoring of this part Ore can not being abandoned, if these resources do not develop and utilize, by along with the closedown of stope, Backfill, is forever embedded in underground, makes enterprise and country sustain a loss simultaneously, and it shows four aspects, the waste of national resources with Running off, enterprise shortens the length of service, and country and enterprise have been subject to huge economic loss, and social benefit sustains damage.
Outdoor metal mine closes remaining ore deposit, corner often during hole, or conventional poor value, and possessing now can Adopt value, but the border in pit has been formed, horizontal direction has arrived at border, to deep mining in vertical direction Multiple steps, residue ore deposit depends on side slope, and residue ore deposit carried out back production is a great problem.
Immediate scheme is by remaining the back production in ore deposit needs Expanding decompression boundary, increases rock-peeling quantity, needs increase to open Opening up engineering, cycle length, efficiency are low.Or carrying out the back production of many subzones, the same cycle is long, and efficiency is low.
Summary of the invention
The present invention provides that a kind of mining period is short, production efficiency is high closes hole surface mine Ore stoping method.
For reaching above-mentioned purpose, embodiments of the invention adopt the following technical scheme that
One closes hole surface mine Ore stoping method, including:
According to the occurrence condition of production ore determining corresponding stoping method;
According to described stoping method, carry out back production construction;
According to predetermined firing order, the described hole surface mine that closes the Ore entirety of back production can be carried out regionality or disposable hole Between millisecond time detonate;
The Ore being spaced institute's avalanche of detonating through disposable Delay between holes is carried out ore removal.
Wherein, according to described stoping method, carry out back production construction and include:
Utilize existing security platform and/or cleaning platform can offer big gun hole on production ore.
Alternatively, according to described stoping method, carry out back production construction and include:
When Ore horizontal depth only has within 10 to 20 meters, according to the payable grade boundary of geologic report delineation, put down in safety Platform and clean directly rock drilling on platform, blast hole depth to Ore can adopt border, big gun orifice angle be on to inclination, level, level Tilt or lower to vertical direction;Use digital electric detonator, explosive can carry out regionality or once in the range of the Ore of back production Property filling, preferably on-site mixed explosive.
Alternatively, according to described stoping method, carry out back production construction and include:
When the slanting angle of ore body is more than 40 degree, in ore body, form the Yan Mai tunnel of multiple level, at bottommost step, form bucket River, beats fan shaped medium length hole in Yan Mai tunnel, use electric detonator, explosive can carry out in the range of the Ore of back production regionality or Disposable filling, preferably on-site mixed explosive.
Alternatively, according to described stoping method, carry out back production construction and include:
When ore body horizontal depth is more than more than 15 meters, when inclination angle is less than 52 degree of Natural care in angle, in different ore removal levels, in ore deposit The Yan Mai tunnel of the multiple level of internal formation and multiple bucket river, beat fan shaped medium length hole in Yan Mai tunnel, uses digital electric thunder Pipe, explosive can carry out regionality in the range of the Ore of back production or disposably load, preferably on-site mixed explosive.
The present invention closes hole surface mine Ore stoping method, use to close hole surface mine can all Ores of back production overall Carry out regionality or detonate in disposable Delay between holes interval, and the Ore being spaced institute's avalanche of detonating through Delay between holes is gone out Ore deposit, which reduces number of times and the ore removal cycle of explosion, and mining period is short, production efficiency is high, and is effectively protected side slope Stable.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing In having technology to describe, the required accompanying drawing used is briefly described, it should be apparent that, the accompanying drawing in describing below is only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to Other accompanying drawing is obtained according to these accompanying drawings.
Fig. 1 is the schematic flow sheet that the present invention closes hole surface mine Ore stoping method;
Fig. 2 be the present invention close hole surface mine Ore stoping method one embodiment close hole surface mine top view;
Fig. 3 be along close shown in Fig. 2 hole surface mine top view A A to sectional view;
Fig. 4 be the present invention close hole surface mine Ore another embodiment of stoping method close hole surface mine top view;
Fig. 5 be along close shown in Fig. 4 hole surface mine top view A A to sectional view;
Fig. 6 be along close shown in Fig. 4 hole surface mine top view B B to sectional view;
Fig. 7 be the present invention close hole the surface mine another embodiment of Ore stoping method close hole surface mine top view;
Fig. 8 be along close shown in Fig. 7 hole surface mine top view A A to sectional view;
Fig. 9 be along close shown in Fig. 7 hole surface mine top view B B to sectional view.
Detailed description of the invention
The detailed description of the invention of closing hole surface mine Ore stoping method a kind of to the present invention is carried out in detail below in conjunction with the accompanying drawings Thin description.
It will be appreciated that described embodiment be only the present invention a part of embodiment rather than whole embodiments.Base Embodiment in the present invention, those of ordinary skill in the art obtained under not making creative work premise all its Its embodiment, broadly falls into the scope of protection of the invention.
Referring to shown in Fig. 1, embodiment of the present invention one closes hole surface mine Ore stoping method, including step:
S1, according to the occurrence condition of production ore determining corresponding stoping method.
The generally occurrence condition in metal mine residue ore deposit generally has certain angle in side slope, and low-angle dip to high-dipping is not Deng, variable thickness, generally broadly fall into progressively pinching state, also have the occurrence condition of fresh kidney beans shape;Thickness is several meters to tens meters, water The flat degree of depth is several meters to tens meters, and depth direction is even up to hundreds of rice.
According to the occurrence condition of residue ore body, determine cutoff grade, as Kuang Yan demarcation line, mineral deposit is obvious, directly as production ore Demarcation line;Or high low-grade boundary unconspicuous Ore inconspicuous for the boundary of ore deposit rock needs professional technique to demarcate payable grade Demarcation line;Drawn a circle to approve prospective ore amount by geomatics engineer, to ore removal spirogram, determine according to occurrence condition, determine the space model of three-dimensional Enclose;According to prospective ore amount and three-dimensional spatial dimension, determine feasible Ore stoping method and the stability control techniques of side slope.
S2, according to described stoping method, carry out back production construction.
According to the feasible Ore stoping method determined, ore body is implemented the working measures such as perforation, powder charge, backfill.Wear Hole can be 7655 small-bores, can be the suitable fanhole(s) such as 80mm, 100mm.
S3, according to predetermined firing order, the described hole surface mine that closes can the Ore entirety of back production be carried out between disposable hole Millisecond time detonates.
Use digital electric detonator, according to compensation space, according to predetermined firing order, such as according to from bottom to top, by Outer to interior order, the described hole surface mine that closes all Ore entirety of back production can be carried out disposable Delay between holes is spaced Quick-fried.The reliability of digital electric detonator is high, can On line inspection, and there is broken string detonate function;Disposably detonate and improve back production Efficiency, and the mode detonated of Delay between holes interval is conducive to farthest reducing the concussion of blasting harm to side slope.
S4, carry out ore removal to through the detonate Ore of institute's avalanche of disposable Delay between holes interval.
In ore removal level, the Ore being spaced institute's avalanche of detonating through disposable Delay between holes is carried out ore removal.
The present invention closes hole surface mine Ore stoping method, use to close hole surface mine can all Ores of back production overall Carry out disposable Delay between holes interval to detonate, and the Ore being spaced institute's avalanche of detonating through disposable Delay between holes carried out ore removal, Which reducing number of times and the ore removal cycle of explosion, mining period is short, production efficiency is high.Further, hole dew is closed in the present invention In it mine Ore stoping method, described step S2, according to described stoping method, carries out back production construction and includes: utilize existing peace Full platform and/or cleaning platform can offer big gun hole on production ore.
The present invention need not increase development engineering, utilizes existing security platform and cleans platform, as operating personnel's Passage and the transport channel of middle-size and small-size rock drill, it is not necessary to increase development engineering, need not to increase rock-peeling quantity, return period short, Efficiency is high, and loss and dilution is few.
Fig. 2 be the present invention close hole surface mine Ore stoping method one embodiment close hole surface mine top view;Fig. 3 is Along close shown in Fig. 2 hole surface mine top view A A to sectional view;Wherein labelling 1 is for cleaning platform, and 2 is security platform, and 3 are Fan shaped medium length hole, big gun orifice angle can be each angle, on to inclination, level, horizontal tilt or lower to vertical direction.
Referring to shown in Fig. 2 and Fig. 3, in the present invention closes hole surface mine Ore stoping method, described step S2 is according to institute State stoping method, carry out back production construction and include: when Ore horizontal depth only has within 10 to 20 meters, draw a circle to approve according to geologic report Payable grade boundary, at security platform 2 with clean on platform 1 directly rock drilling and form fan shaped medium length hole 3, blast hole depth is to ore deposit Stone can adopt border, big gun orifice angle be on to inclination, level, horizontal tilt or lower to vertical direction;Employing digital electric detonator, Explosive disposably can load in the range of the Ore of back production, preferably on-site mixed explosive.
When Ore horizontal depth only has within 10 to 20 meters, it is not necessary to beat Yan Mai tunnel, according to geologic report delineation Payable grade boundary, directly rock drilling on security platform and cleaning platform, blast hole depth to Ore can adopt border, big gun orifice angle To inclination, level, horizontal tilt or lower angle each of in vertical direction on can being, it is also possible to be these angles Combination;Select one-time pad bulk explosive as far as possible and use digital electric detonator once detonation.Because need not reserved studding, Ore Naturally the bottom in pit, direct ore removal it are slipped to.
Fig. 4 be the present invention close hole surface mine Ore another embodiment of stoping method close hole surface mine top view;Fig. 5 For along close shown in Fig. 4 hole surface mine top view A A to sectional view;Fig. 6 is for along closing hole surface mine top view shown in Fig. 4 B B to sectional view;Wherein labelling 1 is discharging tunnel, and 2 wear arteries and veins for ore removal, and 3 is funnel, and 4 is drilling drift, and 5 is in sector Deep hole.
Referring to shown in Fig. 4 to Fig. 6, in the present invention closes hole surface mine Ore stoping method, described step S2 is according to institute State stoping method, carry out back production construction and include: when the slanting angle of ore body is more than 40 degree, in ore body, form the rock drilling lane of multiple level Road 4, is also called Yan Mai tunnel, forms funnel 3 at bottommost step, is also called bucket river, deep in shape of fanning in Yan Mai tunnel Hole, uses digital electric detonator, explosive disposably can load in the range of the Ore of back production, preferably on-site mixed explosive.
When horizontal depth is more than more than 15 meters, when inclination angle is more than 40 degree, it is simple to Ore nature landing, fetch water in ore body Flat Yan Mai tunnel, every 15-30 rice or the Yan Mai tunnel of one level of two shoulder heights, the prolonging of level of bottommost step In arteries and veins tunnel, reserved certain barrier pillar, beats the bucket river of corresponding interval, in the Yan Mai tunnel of remaining level in barrier pillar According to use YG80 rig (or rig of other form) lay to, on to, the scallop hole of level, use digital electric thunder Pipe, explosive disposably can load in the range of the Ore of back production, preferably on-site mixed explosive.
The construction in the Yan Mai tunnel of level can use the general blasting of hand-held airleg rock drill rock drilling.Selection can With the level of ore removal, making a call to a Yan Mai tunnel along mineral ore edge, how deep ore body is beats the most deeply, completes in tunnel on former intrinsic step Yan Mai tunnel.
The Yan Mai tunnel of one level of each two shoulder height, it is possible to two steps of back production while protection adjoining rock stability Ore.
When the stage level prolong arteries and veins tunnelling after, enter into mining link, with four walls in Yan Mai tunnel for just The beginning scope of freedom, is advanced inwards carry out blasting mining by prolonging arteries and veins access adit, be the initial scope of freedom to prolong arteries and veins back, carry out rock drilling Round, the fanhole(s) that angle of spot hole is ascending, is that the optimal scope of freedom carries out blasting mining with the side slope of opencut, uses digital electricity Sub-detonator once detonation.
In one embodiment, the blasthole diameter of scallop hole is 57mm, and largest hole spacing is that 1.00-1.20 rice, array pitch are 1.20-1.5 rice, every meter of hole charge 2.0-2.5kg/m, unit consumption 0.7-0.9kg/t.
In another embodiment, the blasthole diameter of scallop hole is 100mm, and largest hole spacing is that 1.5-2.0 rice, array pitch are 2.0-2.5 rice, every meter of hole charge 6.5-7.0kg/m, unit consumption 0.5-0.7kg/t.
Using digital electric detonator once detonation, an Ore part for each stage avalanche naturally flows to pit along bench face Bottommost step, major part falls outdoor pit bottom stage level naturally along the bucket river of each bottommost step.
In order to when ore removal, it is to avoid the risk of Rolling Stone landing, a discharging tunnel 1 is made a call in bottom level side in ore deposit in the open, In discharging tunnel 1, get some ore removals towards ore body wear arteries and veins 2.Certainly, when thinking without Rolling Stone landing risk through assessment, Also bottom stage Yan Mai tunnel ore removal can be directly utilized.
Fig. 7 be the present invention close hole the surface mine another embodiment of Ore stoping method close hole surface mine top view;Fig. 8 For along close shown in Fig. 7 hole surface mine top view A A to sectional view;Fig. 9 is for along closing hole surface mine top view shown in Fig. 7 B B to sectional view;Wherein labelling 1 is discharging tunnel, and 2 wear arteries and veins for ore removal, and 3 is funnel, and 4 is drilling drift, and 5 is in sector Deep hole.
Referring to shown in Fig. 7 to Fig. 9, in the present invention closes hole surface mine Ore stoping method, according to described stoping method, Carry out back production construction to include: when ore body horizontal depth is more than more than 15 meters, when inclination angle is less than 52 degree of Natural care in angle, different Ore removal level, forms drilling drift 4 and multiple funnel 3 of multiple level in ore body, and wherein drilling drift is also called Yan Mai lane Road, funnel is also called bucket river, beats fan shaped medium length hole 5 in Yan Mai tunnel, and employing digital electric detonator, explosive are can the ore deposit of back production Disposably load in the range of stone, preferably on-site mixed explosive.
When the slanting angle of ore body is less than 52 degree of Natural care in angle, prolonging of multiple level to be formed if desired by bucket river ore removal Arteries and veins tunnel and multiple bucket river.Preferably, one Yan Mai tunnel of each two step design, the most each one have bucket river level every Layer, the boring of upper and lower two steps can be implemented in a Yan Mai tunnel, but must be reserved with the interlayer in bucket river up and down, and each hangs down Straight and the ore deposit, corner of horizontal continuity, first implements Yan Mai tunnel, forms struggle against river and scallop hole in Yan Mai tunnel, and Yan Mai tunnel is whole After formation, once perforated, a powder charge, once implement Delay between holes and detonate, concentrate step bottommost step concentrating mining, for protecting The safety of card bottom stage ore removal, a discharging tunnel 1 is made a call to, in discharging tunnel 1 in the position being located away from bottommost bucket river Get some ore removals towards ore body and wear arteries and veins 2, to ensure ore removal safety.
Semi-steep ore body ore deposit in the open is compared the most rare, when the angle of gently inclined orebody is less than 30 degree, can be in ore deposit Dispatch workers to do on-site repairs the haulage drift of level in stone border, the most different ore removal platform ore removals;When the slanting angle of ore body is between 30 degree to 52 degree, need Increase some road engineerings, create the platform of transport.
According to the occurrence condition in mineral deposit, gently inclined orebody leaves vertical studding, tilts above ore body and leaves horizontal studding, with Ensure temporary support country rock.
In the present invention closes hole surface mine Ore stoping method, in described step S3, use digital electric detonator, according to Predetermined firing order, all Ore entirety of back production can be carried out disposable Delay between holes and is spaced the described hole surface mine that closes In a quick-fried embodiment, blasting parameter includes:
In the every artillery salvo of fan shaped medium length hole, single big gun hole selects the extension time of 1-5ms/m according to bottom hole pitch;To many Hole placing blast Time, selecting 8-50ms/m between row, time delay design between preferably 15-30ms/m arranges, above-mentioned time delays takes when ore body is hard Little value, time delay takes large values when ore body is soft, takes large values time for the purpose of shock dropping, is broken for during purpose getting the small value, and scallop hole row is few Time get the small value, take large values when row is many, near the scope of freedom time get the small value, take large values during away from the scope of freedom.
Bottom hole pitch selects 1.0-3.2 rice, and ore caving interval 1.5-3.5 rice, hole depth 6-45 rice, aperture 60-100mm, powder column is big Select to use double digital electric detonators, 1, bottom, the centre position one of 2nd/to three/3rd of powder column in 10 meters time Send out, detonate simultaneously, prevent explosive from falling disconnected medicine after rise.
Single big gun hole selects the extension time according to bottom hole pitch, if be less than 1ms/m, and the blasting impact produced between adjacent shot hole Ripple superimposed anomaly is obvious, bigger to the Blasting Vibration Hazards of side slope;If during more than 5ms/m, the explosion punching produced between adjacent shot hole The synergistic effect hitting ripple is less so that the lumpiness of Ore is relatively big, adds the follow-up cost crushing Ore.
Similarly, during to many Hole placing blast, if the delay time between row is less than 8ms/m, the explosion that between row, big gun hole produces Shock wave superposition is also abnormal obvious, bigger to the Blasting Vibration Hazards of side slope;If during more than 50ms/m, produce big gun hole between row and detonate The synergistic effect of the Blasting shock wave of rear generation is greatly reduced so that the lumpiness of Ore is relatively big, had both been unfavorable for ore removal, and had too increased The follow-up cost that Ore is crushed.
Above-described embodiment mainly all Ore entirety of back production can carry out disposable Delay between holes to closing hole surface mine The explanation that interval is carried out as a example by detonating.But the invention is not restricted to this, it is possible to close hole surface mine can all Ores of back production whole Body carries out subregion, implements the explosion of detonating of subregion one by one, uses Delay between holes interval to detonate in the explosion of each subregion.This At least two subregion that all Ores are overall can also be implemented disposably detonate explosion by bright embodiment, in this case, often The explosion of individual subregion still uses Delay between holes interval detonate, interval millisecond time is implemented in different by stages and detonates.
State the explosion of detonating of subregion one by one on the implementation, or at least two subregion that all Ores are overall is implemented disposable Detonate explosion time, other method step and corresponding parameter with aforementioned to close hole surface mine can all Ores of back production overall Carry out disposable Delay between holes interval detonate identical, do not repeat them here.
Heretofore described can all Ore entirety of back production carry out between disposable Delay between holes closing hole surface mine Refer to every detonating: to close hole surface mine can all Ores of back production overall, explosion of implementing disposably to detonate, disposably rise at this Explosion use Delay between holes interval detonate.
Heretofore described can all Ore entirety of back production carry out between regional Delay between holes closing hole surface mine Refer to every detonating: all Ore entirety of back production can carry out subregion to closing hole surface mine, implement the explosion of detonating of subregion one by one, Delay between holes interval is used to detonate in the explosion of each subregion;Also include following situation: to all Ores overall at least two Individual subregion is implemented disposably to detonate explosion, still uses Delay between holes interval to detonate, to different subregions in the explosion of each subregion Between implement interval millisecond time detonate.
The above, the only detailed description of the invention of the present invention, but protection scope of the present invention is not limited thereto, and any Those familiar with the art in the technical scope that the invention discloses, the change that can readily occur in or replacement, all answer Contain within protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with scope of the claims.

Claims (2)

1. one kind is closed hole surface mine Ore stoping method, it is characterised in that including:
According to the occurrence condition of production ore determining corresponding stoping method;
According to described stoping method, carry out back production construction;
According to predetermined firing order, the described hole surface mine that closes the Ore entirety of back production can be carried out regionality or disposable hole Between millisecond time detonate;
The Ore being spaced institute's avalanche of detonating through regional or disposable Delay between holes is carried out ore removal, wherein according to described back production Method, carries out back production construction and includes:
When Ore horizontal depth only has within 10 to 20 meters, according to the payable grade boundary of geologic report delineation, put down in safety Platform and clean directly rock drilling on platform, blast hole depth to Ore can adopt border, big gun orifice angle be on to inclination, level, level Tilt or lower to vertical direction;
Use digital electric detonator, explosive can carry out regionality in the range of the Ore of back production or disposably load.
The most according to claim 1 closing cheats surface mine Ore stoping method, it is characterised in that according to described back production side Method, carries out back production construction and includes:
Utilize existing security platform and/or cleaning platform can offer big gun hole on production ore.
CN201610593578.1A 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method Active CN106121652B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610593578.1A CN106121652B (en) 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201210234382.5A CN102733808B (en) 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method
CN201610593578.1A CN106121652B (en) 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201210234382.5A Division CN102733808B (en) 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method

Publications (2)

Publication Number Publication Date
CN106121652A true CN106121652A (en) 2016-11-16
CN106121652B CN106121652B (en) 2019-02-01

Family

ID=46990027

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201610593578.1A Active CN106121652B (en) 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method
CN201210234382.5A Active CN102733808B (en) 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method
CN201610593579.6A Active CN106121653B (en) 2012-07-09 2012-07-09 One kind closing hole surface mine ore stoping method

Family Applications After (2)

Application Number Title Priority Date Filing Date
CN201210234382.5A Active CN102733808B (en) 2012-07-09 2012-07-09 Closed pit open-pit mine ore recovery method
CN201610593579.6A Active CN106121653B (en) 2012-07-09 2012-07-09 One kind closing hole surface mine ore stoping method

Country Status (1)

Country Link
CN (3) CN106121652B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112901172A (en) * 2021-01-14 2021-06-04 尹怀镇 Method for elutriating placer gold in sandy soil with frozen soil layer

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612689B (en) * 2015-01-20 2016-08-24 辽宁工程技术大学 A kind of optimization method of opencut underlying seam open-pit limit
CN108412495A (en) * 2018-01-30 2018-08-17 西安科技大学 A kind of excavating plant bench blasting method
CN108952713B (en) * 2018-05-31 2019-12-27 西北矿冶研究院 Recovery method of scattered minerals in closed-section stope
CN108979280B (en) * 2018-08-30 2019-10-11 中国矿业大学 Close hole Mine Roadway storage tank farm, oil storage method and construction method
CN111578802A (en) * 2020-05-28 2020-08-25 广州市顺兴石场有限公司 High-acquisition-degree mine smooth blasting mining method
CN111691888B (en) * 2020-06-12 2021-10-22 鞍钢集团矿业有限公司 Accurate shovel loading system and method for surface mine
CN115391897B (en) * 2022-09-02 2023-11-17 辽宁工程技术大学 Parallel development step distance determining method for dumping sites in adjacent strip mines

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4103972A (en) * 1973-12-03 1978-08-01 Kochanowsky Boris J Open pit mine
CN1178284A (en) * 1997-10-23 1998-04-08 北京矿冶研究总院 Open-air high-step mining method
CN1601054A (en) * 2004-10-10 2005-03-30 北京科技大学 Method for intensified mining deep-dished strip mine
CN1888391A (en) * 2006-07-25 2007-01-03 武汉理工大学 Fast spoil disposal slope protection and ecological recovery open-pit mining technology
CN101424503A (en) * 2007-11-01 2009-05-06 鞍钢集团矿业公司 Rim angle excavation method by blasting for natural side hill
WO2009087604A1 (en) * 2008-01-11 2009-07-16 Brink Jacobus Pieter Daniel Method for mining
CN101899976A (en) * 2010-07-15 2010-12-01 煤炭科学研究总院太原研究院 Continuous coal mining process method of open-pit coal mine
CN102140916A (en) * 2010-12-15 2011-08-03 河北天择重型机械有限公司 Process and apparatus for mining open pit
CN102331212A (en) * 2011-09-07 2012-01-25 薛世忠 Loss and dilution controlled blasting method for open metal mine

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4103972A (en) * 1973-12-03 1978-08-01 Kochanowsky Boris J Open pit mine
CN1178284A (en) * 1997-10-23 1998-04-08 北京矿冶研究总院 Open-air high-step mining method
CN1601054A (en) * 2004-10-10 2005-03-30 北京科技大学 Method for intensified mining deep-dished strip mine
CN1888391A (en) * 2006-07-25 2007-01-03 武汉理工大学 Fast spoil disposal slope protection and ecological recovery open-pit mining technology
CN101424503A (en) * 2007-11-01 2009-05-06 鞍钢集团矿业公司 Rim angle excavation method by blasting for natural side hill
WO2009087604A1 (en) * 2008-01-11 2009-07-16 Brink Jacobus Pieter Daniel Method for mining
CN101899976A (en) * 2010-07-15 2010-12-01 煤炭科学研究总院太原研究院 Continuous coal mining process method of open-pit coal mine
CN102140916A (en) * 2010-12-15 2011-08-03 河北天择重型机械有限公司 Process and apparatus for mining open pit
CN102331212A (en) * 2011-09-07 2012-01-25 薛世忠 Loss and dilution controlled blasting method for open metal mine

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
匡忠祥等: "《地下金属矿山灾害防治技术》", 30 November 2008, 冶金工业出版社 *
陈国山: "《露天采矿技术》", 31 March 2008, 冶金工业出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112901172A (en) * 2021-01-14 2021-06-04 尹怀镇 Method for elutriating placer gold in sandy soil with frozen soil layer
CN112901172B (en) * 2021-01-14 2023-02-24 尹怀镇 Method for elutriating placer gold in sandy soil with frozen soil layer

Also Published As

Publication number Publication date
CN102733808B (en) 2016-10-19
CN106121652B (en) 2019-02-01
CN102733808A (en) 2012-10-17
CN106121653B (en) 2019-04-26
CN106121653A (en) 2016-11-16

Similar Documents

Publication Publication Date Title
CN102733808B (en) Closed pit open-pit mine ore recovery method
CN101328809B (en) Non-bottom pillar deep hole falling-back type mining method
CN104989404B (en) It is pseudo- in Steeply dipping narrow deposits arteries and veins to tilt ore deposit Medium-long hole mining method
CN102182461A (en) Efficient mining method for thick metal ore body in slanting
CN102808622B (en) Method for recovering ore pillar by medium-length hole and deep hole combined blasting technology
CN102607341B (en) A kind of Stability of Open-pit Mine Slope controlled blasting method
CN100535387C (en) Improved sublevel caving method without bottom column
CN109029168B (en) Blasting treatment method for underground suspended roof
CN104154830B (en) Medium-length hole blasting method for underground mining
CN107165636B (en) A kind of method of strip pit exploitation
CN104847352A (en) Chamber and overhand cut combined cut-and-filling stoping method in pre-roof-protecting stage
CN102927866B (en) Open-bench blasting method capable of controlling forward stroke of blasting muck pile
CN107339920B (en) The method of superdeep holes presplit blasting
CN105735996A (en) Presplitting type wall cutting and filling stoping method for thin ore vein
CN110595308B (en) Method for treating goaf by ultra-deep hole blasting of strip mine
CN102967191A (en) Blasting method for treatment of gob
CN107762511B (en) A kind of class strip-type coal-mining method cut top filling and close on goaf
CN118327584A (en) Natural caving mining method in combination stage of deep hole pre-fracturing and hydraulic fracturing of steep thin ore body
CN101893415A (en) Blasting method by arch roof control and smooth-surface pillar control
CN102620614B (en) Cave depot is slagged tap the construction method of funnel
CN109974545A (en) A kind of medium-length hole blasting outstanding top processing method in sublevel caving method
CN108362181B (en) A kind of driving recovery method of extra narrow vein ore body
CN104089548A (en) Fan-shaped arrangement blast mining method
CN104790950A (en) Optimized mining middle-deep blasthole millisecond blasting slot cutting method
CN103410513B (en) Uneasily mining orebody mechanization process for stoping

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220519

Address after: Room 4713, 47F, building 1, No. 6, Xinyuan South Road, Chaoyang District, Beijing 100027

Patentee after: ZHUOLIWEI (BEIJING) TECHNOLOGY Co.,Ltd.

Address before: Room 705, 12 Shengshi garden, torch hi tech Industrial Development Zone, Weihai City, Shandong Province, 264209

Patentee before: Xue Shizhong

TR01 Transfer of patent right