CN106088662A - 混凝土框架结构框架梁、叠合板支撑施工方法 - Google Patents
混凝土框架结构框架梁、叠合板支撑施工方法 Download PDFInfo
- Publication number
- CN106088662A CN106088662A CN201610440946.9A CN201610440946A CN106088662A CN 106088662 A CN106088662 A CN 106088662A CN 201610440946 A CN201610440946 A CN 201610440946A CN 106088662 A CN106088662 A CN 106088662A
- Authority
- CN
- China
- Prior art keywords
- superimposed sheet
- support
- frame
- vierendeel girder
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/04—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
- E04G2025/003—Supports therefor, e.g. tripods
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610440946.9A CN106088662B (zh) | 2016-06-20 | 2016-06-20 | 混凝土框架结构框架梁、叠合板支撑施工方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610440946.9A CN106088662B (zh) | 2016-06-20 | 2016-06-20 | 混凝土框架结构框架梁、叠合板支撑施工方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106088662A true CN106088662A (zh) | 2016-11-09 |
| CN106088662B CN106088662B (zh) | 2018-03-27 |
Family
ID=57236194
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610440946.9A Active CN106088662B (zh) | 2016-06-20 | 2016-06-20 | 混凝土框架结构框架梁、叠合板支撑施工方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106088662B (zh) |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108035537A (zh) * | 2018-01-16 | 2018-05-15 | 广州市快易模板工程有限公司 | 一种用于楼板的条状早拆支撑体系 |
| CN108265748A (zh) * | 2017-12-31 | 2018-07-10 | 中冶天工集团有限公司 | 一种板柱结构模板支设体系及模块化施工方法 |
| CN109184193A (zh) * | 2018-10-26 | 2019-01-11 | 严雄 | 一种早拆模板体系及其施工方法 |
| CN109610817A (zh) * | 2018-11-29 | 2019-04-12 | 山东金城建设有限公司 | 井字梁模板支架及其设计与施工方法 |
| CN110593559A (zh) * | 2019-09-02 | 2019-12-20 | 中冶天工集团天津有限公司 | 一种混凝土梁模板支撑装置及其施工工艺 |
| CN111677272A (zh) * | 2020-07-07 | 2020-09-18 | 湖南五新建筑科技有限公司 | 现浇梁板盖体施工方法 |
| CN112431421A (zh) * | 2020-10-29 | 2021-03-02 | 上海宝冶冶金工程有限公司 | 高层钢筋混凝土结构建筑梁、板安装方法 |
| CN113137075A (zh) * | 2021-04-27 | 2021-07-20 | 荣华(青岛)建设科技有限公司 | 一种用于控制叠合板反拱值的可拆卸工装及其使用方法 |
| CN114352007A (zh) * | 2022-01-18 | 2022-04-15 | 无锡信泰模架科技有限公司 | 一种单元式支撑与早拆模板体系施工工法 |
| CN116044212A (zh) * | 2023-02-16 | 2023-05-02 | 中国十七冶集团有限公司 | 一种叠合板安装架体及其使用方法 |
| CN117027262A (zh) * | 2023-04-23 | 2023-11-10 | 北京城建五建设集团有限公司 | 一种框架结构密拼式叠合板建筑结构的施工方法 |
| CN117846288A (zh) * | 2023-12-15 | 2024-04-09 | 中国五冶集团有限公司 | 一种适用于装配式混凝土框架结构施工的支撑单元及体系 |
| CN118187447A (zh) * | 2024-03-27 | 2024-06-14 | 中建八局第三建设有限公司 | 一种钢管桁架预应力叠合板分段式支撑体系施工方法 |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104234428A (zh) * | 2014-09-25 | 2014-12-24 | 管金平 | 一种建筑装配整体式结构柱、梁、板施工工艺 |
| CN105089270A (zh) * | 2015-08-20 | 2015-11-25 | 中建三局第二建设工程有限责任公司 | 一种混凝土梁板快拆木模装置支模体系的施工方法 |
-
2016
- 2016-06-20 CN CN201610440946.9A patent/CN106088662B/zh active Active
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104234428A (zh) * | 2014-09-25 | 2014-12-24 | 管金平 | 一种建筑装配整体式结构柱、梁、板施工工艺 |
| CN105089270A (zh) * | 2015-08-20 | 2015-11-25 | 中建三局第二建设工程有限责任公司 | 一种混凝土梁板快拆木模装置支模体系的施工方法 |
Non-Patent Citations (3)
| Title |
|---|
| 张思云等: ""高效预应力叠合楼盖结构施工技术"", 《建筑施工》 * |
| 陈宽诚: ""高效预应力叠合梁_板在金源大厦的应用"", 《施工技术》 * |
| 龙炳煌等: ""叠合式楼盖结构的设计与施工"", 《施工技术》 * |
Cited By (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108265748A (zh) * | 2017-12-31 | 2018-07-10 | 中冶天工集团有限公司 | 一种板柱结构模板支设体系及模块化施工方法 |
| CN108035537A (zh) * | 2018-01-16 | 2018-05-15 | 广州市快易模板工程有限公司 | 一种用于楼板的条状早拆支撑体系 |
| CN109184193A (zh) * | 2018-10-26 | 2019-01-11 | 严雄 | 一种早拆模板体系及其施工方法 |
| CN109610817A (zh) * | 2018-11-29 | 2019-04-12 | 山东金城建设有限公司 | 井字梁模板支架及其设计与施工方法 |
| CN110593559A (zh) * | 2019-09-02 | 2019-12-20 | 中冶天工集团天津有限公司 | 一种混凝土梁模板支撑装置及其施工工艺 |
| CN111677272A (zh) * | 2020-07-07 | 2020-09-18 | 湖南五新建筑科技有限公司 | 现浇梁板盖体施工方法 |
| CN112431421A (zh) * | 2020-10-29 | 2021-03-02 | 上海宝冶冶金工程有限公司 | 高层钢筋混凝土结构建筑梁、板安装方法 |
| CN113137075A (zh) * | 2021-04-27 | 2021-07-20 | 荣华(青岛)建设科技有限公司 | 一种用于控制叠合板反拱值的可拆卸工装及其使用方法 |
| CN114352007A (zh) * | 2022-01-18 | 2022-04-15 | 无锡信泰模架科技有限公司 | 一种单元式支撑与早拆模板体系施工工法 |
| CN116044212A (zh) * | 2023-02-16 | 2023-05-02 | 中国十七冶集团有限公司 | 一种叠合板安装架体及其使用方法 |
| CN117027262A (zh) * | 2023-04-23 | 2023-11-10 | 北京城建五建设集团有限公司 | 一种框架结构密拼式叠合板建筑结构的施工方法 |
| CN117846288A (zh) * | 2023-12-15 | 2024-04-09 | 中国五冶集团有限公司 | 一种适用于装配式混凝土框架结构施工的支撑单元及体系 |
| WO2025123648A1 (zh) * | 2023-12-15 | 2025-06-19 | 中国五冶集团有限公司 | 一种适用于装配式混凝土框架结构施工的支撑单元及体系 |
| CN117846288B (zh) * | 2023-12-15 | 2025-07-25 | 中国五冶集团有限公司 | 一种适用于装配式混凝土框架结构施工的支撑单元及体系 |
| CN118187447A (zh) * | 2024-03-27 | 2024-06-14 | 中建八局第三建设有限公司 | 一种钢管桁架预应力叠合板分段式支撑体系施工方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106088662B (zh) | 2018-03-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106088662B (zh) | 混凝土框架结构框架梁、叠合板支撑施工方法 | |
| CN103352563B (zh) | 自承板式钢筋网架组合模板及其施工方法 | |
| CN105863275B (zh) | 装配式环筋扣合混凝土剪力墙体系施工方法 | |
| CN103352564B (zh) | 水平结构模板体系及施工方法 | |
| CN102392536B (zh) | 大跨度悬空通廊式模板支撑体系施工方法 | |
| CN209369328U (zh) | 一种单侧墙模的可移动模架结构 | |
| CN105696789A (zh) | 一种竖向铝模建造系统及其施工方法 | |
| CN106193589B (zh) | 混凝土超高重型梁及叠合板组合结构支撑方法 | |
| CN105544873A (zh) | 一种波浪形空心屋面及其施工方法 | |
| CN106193402B (zh) | 桁架梁集成式楼面模块及其安装方法 | |
| CN102518148A (zh) | 一种有关地铁明挖车站三角支撑结构的建筑物及施工方法 | |
| CN110409624A (zh) | 一种大型设备安装与主体结构逆作计算与施工方法 | |
| CN103603494B (zh) | 一种超薄钢桁架斜墙施工方法及模板结构 | |
| CN203834926U (zh) | 清水混凝土地下室外墙模板支模结构 | |
| CN116411694A (zh) | 一种可调型模块化盘扣式支撑系统及其支撑方法 | |
| CN103147573B (zh) | 游泳馆顶梁板高支模施工方法 | |
| CN102787717B (zh) | 自承式组合钢模板施工方法 | |
| CN114000708A (zh) | 一种桁架叠合板的安装方法及安装支撑架 | |
| CN105133770B (zh) | 地下通道入口的屋面结构 | |
| CN116657875B (zh) | 一种带支模体系的悬挑钢结构施工平台及施工方法 | |
| CN207905389U (zh) | 装配式全螺栓连接钢筋加工棚 | |
| CN116591462A (zh) | 一种狭窄空间结构板逆作法免拆模结构及施工方法 | |
| CN218668507U (zh) | 钢筋桁架楼承板支撑结构 | |
| CN104405069B (zh) | 一种曲面中空顶板及其施工方法 | |
| CN108678424A (zh) | 一种超重构件的钢格构支撑装置及支撑方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20250620 Address after: 064200 Hebei Province, Zunhua City, Jinshan Industrial Park, east side of Tangzun Railway Patentee after: 22MCC Group (Tangshan) Green Assembly Intelligent Manufacturing Co.,Ltd. Country or region after: China Patentee after: China MCC22 Group Corp.,Ltd. Address before: 064000 Hebei province Fengrun District No. 16 Tangshan City road of happiness Patentee before: China MCC22 Group Corp.,Ltd. Country or region before: China |
|
| TR01 | Transfer of patent right |