CN106058927A - Peak-current-based rapid algorithm for maximum power point of photovoltaic grid-connected micro inverter - Google Patents
Peak-current-based rapid algorithm for maximum power point of photovoltaic grid-connected micro inverter Download PDFInfo
- Publication number
- CN106058927A CN106058927A CN201610502982.3A CN201610502982A CN106058927A CN 106058927 A CN106058927 A CN 106058927A CN 201610502982 A CN201610502982 A CN 201610502982A CN 106058927 A CN106058927 A CN 106058927A
- Authority
- CN
- China
- Prior art keywords
- peak
- current
- half period
- point
- maximum
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000004422 calculation algorithm Methods 0.000 title claims abstract description 31
- 238000000034 method Methods 0.000 claims abstract description 28
- 238000005070 sampling Methods 0.000 claims abstract description 26
- 230000005611 electricity Effects 0.000 claims description 7
- 230000006641 stabilisation Effects 0.000 claims 1
- 238000011105 stabilization Methods 0.000 claims 1
- 230000007547 defect Effects 0.000 abstract 1
- 238000004458 analytical method Methods 0.000 description 8
- 239000000654 additive Substances 0.000 description 7
- 230000000996 additive effect Effects 0.000 description 7
- 238000000205 computational method Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 4
- 238000001914 filtration Methods 0.000 description 2
- 230000001105 regulatory effect Effects 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 1
- 230000001276 controlling effect Effects 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000009795 derivation Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 239000004065 semiconductor Substances 0.000 description 1
Classifications
-
- H02J3/385—
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05F—SYSTEMS FOR REGULATING ELECTRIC OR MAGNETIC VARIABLES
- G05F1/00—Automatic systems in which deviations of an electric quantity from one or more predetermined values are detected at the output of the system and fed back to a device within the system to restore the detected quantity to its predetermined value or values, i.e. retroactive systems
- G05F1/66—Regulating electric power
- G05F1/67—Regulating electric power to the maximum power available from a generator, e.g. from solar cell
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
- Y02E10/56—Power conversion systems, e.g. maximum power point trackers
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Power Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- General Physics & Mathematics (AREA)
- Radar, Positioning & Navigation (AREA)
- Automation & Control Theory (AREA)
- Control Of Electrical Variables (AREA)
- Inverter Devices (AREA)
Abstract
The invention relates to a peak-current-based rapid algorithm for a maximum power point of a photovoltaic grid-connected micro inverter. According to the invention, a peak current of a main switching tube of a photovoltaic grid-connected micro inverter is sample and a sum of peak currents is obtained; and then the sampled peak current is compared with a last maximum peak current and the sum of the peak currents is compared with a last sum of peak currents, thereby realizing maximum power point tracking of a photovoltaic assembly. With the algorithm, defects of complicated algorithm, low program operation efficiency, poor maximum power point tracking precision, and high hardware cost of the existing method can be overcome. Whether maximum power point tracking of the photovoltaic assembly is realized is determined by sampling peak currents in the switching tube, so that the sampling link of photovoltaic assembly voltages is saved and obtaining of an average input current of a photovoltaic assembly by a hardware/software filter link is avoided. Therefore, the hardware cost is lowered; the execution efficiency is high; resources of a digital control chip are saved; the anti-interference capability is improved effectively; and stability of system control is enhanced.
Description
Technical field
The invention belongs to power electronics and electrical technology field, particularly to grid-connected micro-inversion based on peak point current
Device maximum power point fast algorithm.
Background technology
In grid-connected micro-inverter, control for realizing the MPPT maximum power point tracking of photovoltaic module, need to calculate photovoltaic
The power of assembly, by comparing whether calculated power reaches maximum, judges that photovoltaic module has been operated in maximum the most
Power points.
Common computational methods are the output voltage of photovoltaic module and output electric current to be done multiplying and obtain mean power.
Need output voltage and the output electric current of sampled light photovoltaic assembly for this, traditional voltage detection method has difference sampling, resistance to divide
Pressure sampling, the sampling of voltage Hall and linear optical coupling sampling;And the sampling of electric current mainly have inverter input circuit string resistance sampling,
Current transformer and current Hall sampling.Based on voltage Hall and the method for sampling of current Hall, relatively costly.For flyback
Grid-connected micro-inverter or the grid-connected micro-inverter of push-pull type High Frequency Link, owing to the input current of changer presents peak pulse shape, for
Obtain the method that its average current generally requires hardware filtering and digital filtering combines, it is known that the most relatively costly, consume
Program resource, and easily cause error, thus cause the tracking accuracy of maximum power point poor.
Before the present invention makes, the Demo plate of micro-core obtains flyback micro-inverter master by current transformer and has opened
Closing the peak point current of pipe, the output voltage of the photovoltaic module obtained with sampling by this peak point current in a program is multiplied and obtains merit
Rate, and then within some common frequency power network half periods, these performance numbers are added, and think that having obtained characterizing photovoltaic module puts down
All linear numerical of output, by the size comparing this numerical value judge photovoltaic module whether realize maximum power point with
Track controls.There is gross error in the most this computational methods, because under the conditions of fixing switching frequency, photovoltaic module is the most defeated
Going out power with the peak point current in switching tube is relationships of increase function, and unrelated with the voltage of photovoltaic module, still more photovoltaic module
Output voltage follow the tracks of during be real-time change, in general, photovoltaic module output electric current become big time, then photovoltaic group
The voltage of part is on a declining curve, therefore the computational methods using the voltage of photovoltaic module to be multiplied with peak point current in switching tube judge
The size of power, has bigger error, i.e. can not realize the accurate tracking of assembly peak power.
Thus be currently based on peak point current in switching tube be multiplied with photovoltaic module voltage the maximum power point obtaining power with
Track computational methods, not only algorithm is complicated, and program operational efficiency is low, MPPT maximum power point tracking low precision, and hardware cost is higher,
This is obviously difficult to the high-performance required by grid-connected micro-inverter, low cost.
Summary of the invention
Present invention aim to overcome that drawbacks described above, develop grid-connected micro-inverter peak power based on peak point current
Point fast algorithm.
The technical scheme is that
Grid-connected micro-inverter maximum power point fast algorithm based on peak point current, it is mainly characterized by adopts
The peak point current of the grid-connected micro-inverter main switch of sample, and the peak electricity will sampled within a common frequency power network half period
Stream carries out size and compares, and obtains the peak inrush current in this common frequency power network half period;By described peak inrush current with upper
The peak inrush current obtained in one common frequency power network half period compares size, if described peak inrush current has been maximum
Value, the peak inrush current in the follow-up common frequency power network half period is all the least than described peak inrush current, then described
Operating mode corresponding to peak inrush current is exactly the maximum power output of photovoltaic module, i.e. achieves the peak power of photovoltaic module
Point is followed the tracks of.
The present invention another solution is that
Grid-connected micro-inverter maximum power point fast algorithm based on peak point current, it is mainly characterized by institute
State the peak point current of grid-connected micro-inverter main switch of sampling, and the peak will sampled within a common frequency power network half period
Value electric current does additive operation, thus obtains peak point current sum;By described peak point current sum and a upper common frequency power network half
Peak point current sum in cycle compares size, if described peak point current sum reaches maximum, and follow-up common frequency power network half cycle
Peak point current sum in phase is all the least than described peak point current sum, then the operating mode corresponding to described peak point current sum is just
It is the maximum power output of photovoltaic module, i.e. achieves the MPPT maximum power point tracking of photovoltaic module.
The described peak inrush current in the common frequency power network half period, is the average input work of grid-connected micro-inverter
Rate is the increasing function of peak inrush current in the common frequency power network half period, therefore can be according to the peak inrush current in the power frequency half period
No reach maximum, judge that photovoltaic module has realized the tracking of maximum power point the most, if the maximum in the power frequency half period
Peak point current is not reaching to maximum, then can be by the set-point of disturbance grid-connected current, until the maximum in the power frequency half period
Peak point current is stable at maximum, thus realizes the MPPT maximum power point tracking of photovoltaic module.
The described peak inrush current in the common frequency power network half period and peak point current sum in the common frequency power network half period, also
The peak inrush current obtained in being a common frequency power network half period is peak point current sum in this common frequency power network half period
Increasing function, thus the Mean Input Power of grid-connected micro-inverter is also the increasing of peak point current sum in the common frequency power network half period
Function, therefore whether can reach maximum according to the peak point current sum in the power frequency half period, judge that photovoltaic module is the most real
The tracking of existing maximum power point.If the peak inrush current in the power frequency half period is not reaching to maximum, then can be by disturbing
The set-point of dynamic grid-connected current, until the peak point current sum in the power frequency half period is stable at maximum, thus realizes photovoltaic group
The MPPT maximum power point tracking of part.
The fast algorithm of the grid-connected micro-inverter maximum power point of the present invention, is had the advantage that and is only opened by sampling
Close the size of peak point current in pipe, judge whether photovoltaic module realizes the tracking of maximum power point, photovoltaic module electricity can be saved
The sampling element of pressure, and need not hardware or obtained the average current input of photovoltaic module by software filtering link.Thus can
To reduce the hardware cost of grid-connected Miniature inverter;Judge whether photovoltaic module is operated in maximum power point, it is only necessary to warp
Crossing logical operations and additive operation, without multiplying, therefore the execution efficiency of program is high, can save digital control chip
Resource.If additionally by the method for the peak point current sum in the common frequency power network cycle, then capacity of resisting disturbance can be effectively improved, thus
The stability that enhancing system controls.
Other advantages and the effect of the present invention will go on to say below.
The term related in the present invention: MPPT (Maximum Power Point Tracking), MPPT maximum power point tracking.
Accompanying drawing explanation
Fig. 1 principle of the invention explanation schematic diagram.
Fig. 2 application circuit of the present invention hardware constitutes schematic diagram.
Fig. 3 present invention realizes the control flow schematic diagram of MPPT by the size comparing peak value current maxima.
Fig. 4 present invention realizes the control flow schematic diagram of MPPT by the size comparing peak point current sum.
Fig. 5 present invention realizes the experimental waveform signal of MPPT maximum power point tracking based on peak point current sum algorithm
Figure.
In figure, each label represents that corresponding component names is as follows:
Grid-connected micro-inverter master switch 1, current sample sensor 2, modulate circuit 3, program processing unit 4.
Designation in Fig. 1:
Designation in Fig. 2:
Designation in Fig. 3:
Designation in Fig. 4:
Detailed description of the invention
The technology major technique thinking of the present invention is:
Realize for current grid-connected micro-inverter that the algorithm of maximum power point is complicated, tracking accuracy is the highest, program
Low and the relatively costly present situation of execution efficiency, it is proposed that grid-connected micro-inverter maximum power point based on peak point current is calculated quickly soon
Method.
The present invention is specifically described below.
As shown in Figure 1 and Figure 2, the parts of the present invention are constituted:
Grid-connected micro-inverter master switch 1, current sample sensor 2, modulate circuit 3, program processing unit 4.Electric current
Sampling sensor 2 is sampled the peak point current i in grid-connected micro-inverter master switch 1s, after delivering to modulate circuit 3, it is then sent through number
The program processing unit 4 of word control chip, within half common frequency power network cycle, electric current pressed by grid-connected micro-inverter master switch 1
During critical continuous mode work, obtain peak point current I successivelypk_i(i=1,2 ..., N).In program processing unit 4, by comparing
Ipk_iSize can obtain peak inrush current Ipk_max;By to Ipk_iSummation can obtain the peak value in half power frequency period
Electric current sum Ipk_Sum.In FIG, Ip_maxIt is peak inrush current Ipk_maxThe average current of place switch periods;Ip_i(i=1,
2 ..., N) it is peak point current Ipk_iThe average current of place switch periods;Ipk_sumIt is all peak values in half common frequency power network cycle
Electric current Ipk_iSum.
The present invention realizes the fast algorithm of grid-connected micro-inverter maximum power point, and sample grid-connected micro-inverter master
The peak point current i of switching tubesIf sampling number is n times within a common frequency power network half period, then obtains N number of peak point current and adopt
I in sample value, i.e. corresponding program processing unit 4pk_i, wherein i=1,2 ..., N.And by institute within a common frequency power network half period
The peak point current I of samplingpk_iCarry out size to compare, thus obtain the peak inrush current I in this common frequency power network half periodpk_max,
By described peak inrush current Ipk_maxSize is compared with the peak inrush current obtained in the upper common frequency power network half period,
If described peak inrush current has been maximum, the peak inrush current in the follow-up common frequency power network half period is the most all than institute
The peak inrush current I statedpk_maxLittle, then described peak inrush current Ipk_maxCorresponding operating mode is exactly photovoltaic module
Maximum power output state, i.e. achieves the MPPT maximum power point tracking of photovoltaic module.
The N number of peak point current I that will be sampled within a common frequency power network half periodpk_iDo additive operation, thus obtain peak
Value electric current sum Ipk_Sum, then by comparing this peak point current sum Ipk_SumWhether reach maximum, if maximum,
Then show to have been achieved with the MPPT maximum power point tracking of photovoltaic module, otherwise by the set-point of disturbance grid-connected current, until peak value
Electric current sum reaches maximum, finally realizes the tracking of maximum power point.The concrete derivation of this conclusion is as follows:
The N number of peak point current I that will be sampled within a common frequency power network half periodpk_iDo additive operation, thus obtain peak
Value electric current sum Ipk_Sum, by described peak point current sum Ipk_SumWith the peak point current in the upper common frequency power network half period it
Compare with carrying out size, if described peak point current sum Ipk_SumReach maximum, the peak value in the follow-up common frequency power network half period
Electric current sum is all the least than described peak point current sum, then the operating mode corresponding to described peak point current sum is exactly photovoltaic module
Maximum power output, i.e. achieve the MPPT maximum power point tracking of photovoltaic module.
Theory analysis process is given below.As shown in the program processing unit 4 in Fig. 1: inverter exports the electricity of electrical network
Stream waveform should be the sine wave Tong Bu with line voltage, it is clear that when sinusoidal wave crest and trough, output electric current reaches maximum,
The peak point current now flow through in main switch is up to maximum IPk_max, the average current within the respective switch cycle is denoted as
Ip_max.If the output voltage of photovoltaic module is Ui, the output electric current of photovoltaic module is Ii, then the average output power of photovoltaic module
Can be calculated within a common frequency power network half period, such as formula (1):
Switch periods TSIn, if the ON time of switching tube is ton, then peak point current I can be obtainedpk_maxWith
Average current I in corresponding switch periodsp_maxRelation such as formula (2):
If the inductance value of transformer primary side is L in circuitm, the voltage U of photovoltaic module can be obtainediWith peak point current Ipk_maxPass
System, sees formula (3):
Formula (3) is deformed and obtains formula (4):
Formula (1) is deformed and obtains formula (5):
Formula (4), (5) are brought in formula (2) to obtain formula (6):
Ignoring loss, the output of photovoltaic module is exactly the input power of micro-inverter.Photovoltaic is can be seen that from formula (6)
The output P of assemblyiWith I2 pk_maxIt is directly proportional, and works as Ipk_iDuring > 0, the output P of photovoltaic moduleiIt is Ipk_maxDullness
Increasing function.Analyze based on above, when maximal power tracing controls, can be by judging Ipk_maxWhether reach maximum real
The tracking of existing maximum power point.
Specifically combining Fig. 3 explanation, Fig. 3 is the method for perturbation MPPT control flow judged based on peak point current maximum.Igref
Being the set-point of grid-connected current amplitude, its initial value is given in initialization program, Δ IgDisturbance for grid-connected current amplitude walks
Long.Program calls method of perturbation MPPT subprogram with the integral multiple time of common frequency power network half period, by current grid-connected current width
Value set-point IgrefCommon frequency power network half period peak point current maximum I corresponding to (k)pk_maxK () and a upper peak point current are
It is worth greatly Ipk_max(k-1) size is compared, if present peak value current maxima Ipk_maxK () is more than Ipk_max(k-1), according to above-mentioned point
Analysis is known, now the output of photovoltaic module increases, therefore corresponding IgrefShould continue to carry out disturbance, even by same direction
IgrefK () is more than Igref(k-1), then the amplitude of current grid-connected current is given should be modified to Igref(k)=Igref(k)+ΔIg, otherwise
Should be Igref(k)=Igref(k)-ΔIg.If present peak value current maxima Ipk_maxK () is less than Ipk_max(k-1), according to above-mentioned
Analysis is known, now the output of photovoltaic module reduces, therefore corresponding IgrefDisturbance should be carried out in the opposite direction, even
IgrefK () is more than Igref(k-1), then the amplitude of current grid-connected current is given should be modified to Igref(k)=Igref(k)-ΔIg, otherwise
Should be Igref(k)=Igref(k)+ΔIg.Work as Ipk_max(k) and Ipk_max(k-1) during approximately equal, then photovoltaic module work is shown
Make at maximum power point, corresponding IgrefIt it is then grid-connected current benchmark during maximum power point.Fig. 3 gives with the grid-connected electricity of disturbance
Stream amplitude judges a kind of method of perturbation MPPT that peak power point methods combines with heretofore described peak point current maximum
Tracing control flow process.If combining with the present invention with the voltage of disturbance light photovoltaic assembly, as effect is also.
According to above-mentioned analysis, based on peak point current maximum Ipk_maxMaximum power point fast algorithm, comprise two levels
Logic size judge, be first to peak point current I within the common frequency power network half periodpk_iCarry out the ratio of n times peak current level
Relatively, the peak point current maximum I in this common frequency power network half period is obtainedpk_max, followed by by the different common frequency power network half periods
Peak point current maximum carries out the comparison of logic size, thus judges whether to realize the tracking of maximum power point.
In view of actual application, interference that the peak point current sampled is switched by HF switch unavoidably and occur
Sampling error, this may result in the mistake that maximum power point judges.For the existence of interference, commonly used flat in digital control
The method all filtered.By the N number of peak point current I in the common frequency power network half period in the present inventionpk_iTake and, i.e. transported by addition
Calculate peak point current sum I obtaining in the common frequency power network half periodpk_Sum, such as formula (7).
In formula, Ipk_iBeing switching tube peak point current in each switch periods in the common frequency power network half period, N is power frequency electric
The sampling number of peak point current in the net half period, k is constant.
By formula (7) it can be seen that work as Ipk_iDuring > 0, peak point current sum I in the common frequency power network half period of inverterpk_sum
It is peak point current maximum I in this common frequency power network half periodpk_maxMonotonic increasing function.Due to monotonic increasing function inverse function also
It is monotonic increasing function, so the I in the identical common frequency power network half periodpk_maxAlso it is Ipk_sumMonotonic increasing function.Convolution (6)
The conclusion arrived, it is recognised that work as Ipk_iDuring > 0, output power of photovoltaic module PiIt it is peak point current sum in the common frequency power network half period
Ipk_sumMonotonic increasing function.Therefore the maximum power point of photovoltaic module can use peak point current sum in the common frequency power network half period
Ipk_sumSize judge, the peak point current sum in the different common frequency power network half periods can be compared, if when certain work
Frequently there is maximum in the peak point current sum in the electrical network half period, then this photovoltaic module voltage corresponding to common frequency power network half period
Operating mode corresponding to set-point or grid-connected current set-point has realized the tracing control of maximum power point the most.The most just to photovoltaic group
The voltage set-point of part or the set-point of grid-connected current carry out disturbance, until the peak point current sum in the common frequency power network half period goes out
Existing maximum.
Propose based on peak point current sum Ipk_sumMaximum power point fast algorithm implementation MPPT tracing control, specifically
In conjunction with Fig. 4 explanation.Fig. 4 is the method for perturbation MPPT control flow judged based on peak point current sum.IgrefIt it is grid-connected current amplitude
Set-point, its initial value is given in initialization program, Δ IgDisturbance step-length for grid-connected current amplitude.With power frequency in program
The integral multiple time of electrical network half period calls method of perturbation MPPT subprogram, by current grid-connected current amplitude set-point Igref(k)
Corresponding common frequency power network half period peak point current sum Ipk_sum(k) and a upper peak point current maximum Ipk_sum(k-1) ratio
Relatively size, if present peak value electric current sum Ipk_sumK () is more than Ipk_sum(k-1), know according to above-mentioned analysis, now photovoltaic module
Output increase, therefore corresponding IgrefShould continue to carry out disturbance, even I by same directiongrefK () is more than Igref(k-
1), then the amplitude of current grid-connected current is given should be modified to Igref(k)=Igref(k)+ΔIg, otherwise should be Igref(k)=Igref
(k)-ΔIg.If present peak value electric current sum Ipk_sumK () is less than Ipk_sum(k-1), know according to above-mentioned analysis, now photovoltaic group
The output of part reduces, therefore corresponding IgrefDisturbance, even I should be carried out in the opposite directiongrefK () is more than Igref(k-1),
Then the amplitude of current grid-connected current is given should be modified to Igref(k)=Igref(k)-ΔIg, otherwise should be Igref(k)=Igref(k)+
ΔIg.Work as Ipk_max(k) and Ipk_max(k-1) during approximately equal, then show that photovoltaic module has been operated in maximum power point, accordingly
IgrefIt it is then grid-connected current benchmark during maximum power point.Fig. 4 gives with disturbance grid-connected current amplitude with heretofore described
Peak point current sum judge a kind of method of perturbation MPPT tracing control flow process that peak power point methods combines.If with disturbance light
The voltage of photovoltaic assembly combines with the present invention, as effect is also.
The present invention propose based on peak point current sum Ipk_sumMaximum power point fast algorithm, it is achieved maximum power point
Judgement mainly include two levels.First is to obtain the peak point current sum in the common frequency power network half period, followed by by difference
Peak point current sum in the common frequency power network half period carries out the logic of size and compares.This method relates to additive operation, and logic
Relatively, therefore program operation speed is fast, and execution efficiency is high.With based on peak point current maximum Ipk_maxMaximum power point calculate quickly soon
Method is compared, due to watt level judge compared decision by the size of the peak point current sum in the common frequency power network half period, it is to avoid
The impact that switch interference causes, thus can effectively improve capacity of resisting disturbance, strengthen the stability of system.
From upper analysis: according to maximum power point fast algorithm based on peak point current proposed by the invention, with
Grid-connected current amplitude disturbance method realizes maximal power tracing control, it is not necessary to the voltage U of sampled light photovoltaic assemblyi, and need not input
Voltage UiWith input current IiIt is multiplied and obtains concrete power Pi, it is possible to obtain maximum power point.Therefore the base proposed in the present invention
In peak point current maximum Ipk_maxMaximum power point fast algorithm, the speed of maximum power point algorithm can be improved and perform effect
Rate, saves the resource of program;The sampling element of input voltage can be saved simultaneously, thus reduce cost.
Knowable to above-mentioned analysis: by regulating the given I of grid-connected current amplitudegrefSize, or regulation photovoltaic module
Voltage set-point, after suitable control, if the peak point current maximum in the common frequency power network half period or peak point current sum
It is in maximum, indicates that photovoltaic module has been operated in maximum power point.
It is as follows that of the present invention is embodied as example:
Based on peak point current for the present invention grid-connected micro-inverter maximum power point fast algorithm is applied 245W's
In the grid-connected micro-inverter of flyback, as shown in Figure 2: the input voltage range of photovoltaic module: Ui=22V~50V, specified electricity
Net voltage vg=180~265V, specified mains frequency 50Hz/60Hz, mains frequency scope 47-51.5/57~60.5Hz.Flyback
Main metal-oxide-semiconductor in circuit uses Infineon 190N15NS, and the model of flyback transformer secondary fly-wheel diode is Cree company
C4D02120A, current sensor uses the B82801B305A125 of EPCOS company, and operational amplifier uses micro-core
MCP6022-I, control chip uses the single-chip microcomputer MK10DX64VLF5 of Freescale.
Flyback micro-inverter main switch Q1In electric current isBy current sensor TR2Sampling, the turn ratio is 100: 1, sensing
The secondary sampler resistance R of device1Sample rate current is become current sampling signal, delivers to current regulating circuit, the fortune in modulate circuit
Put MCP6022-I and current sampling signal is transformed into the receptible signal of single-chip microcomputer, send single-chip microcomputer Program processing unit to enter
Row processes.In the program processing unit of single-chip microcomputer, obtain the peak value in the common frequency power network half period by simple additive operation
Electric current sum Ipk_sum, then use the method for perturbation MPPT such as Fig. 4 to control, by comparing the size in the common frequency power network half period, look for
Arrive corresponding grid-connected current set-point Igref, grid-connected current ring uses PI to control, it is achieved thereby that the peak power of embodiment
Point is followed the tracks of, and Fig. 5 show the experimental waveform of maximal power tracing, and MPPT tracking accuracy reaches 0.99.The side that the visible present invention proposes
Method is effective.
Embodiment is provided without traditional power calculation and power compares the tracking and controlling method obtaining maximum power point, does not also have
There is the input voltage of sampled light photovoltaic assembly, simply have employed the additive operation of peak point current summation, and use peak current level
Logical algorithm relatively, therefore the arithmetic speed of corresponding program arithmetic element is very fast and execution efficiency is higher;Embodiment grid-connected micro-
Inverter is owing to eliminating the voltage sampling circuit of photovoltaic module, and cost is relatively low.Invention based on peak point current maximum power point
Fast algorithm is applicable not only to the grid-connected Miniature inverter of flyback, the grid-connected Miniature inverter of push-pull type High Frequency Link, and is applicable to
Micro-inverter circuit topology of all peak value comparison method.
Knowable to above description, based on peak point current grid-connected micro-inverter maximum power point of invention is calculated quickly soon
Method, has the advantage that
(1) need not voltage sampling circuit, reduce cost;
(2) fast algorithm invented has saved the resource of digital control chip, improves the speed of algorithm, improves program
Execution efficiency;
(3) fast algorithm invented is widely used, and is not limited solely to grid-connected micro-inverter, be also used in photovoltaic from
Net inverter;
(4) tracking of this fast algorithm implementation maximum power point can also be utilized in the wind-power electricity generation of middle low power.
The invention is not limited in above-described embodiment, on the basis of technical scheme disclosed by the invention, the skill of this area
Art personnel are according to disclosed technology contents, it is not necessary to some of which technical characteristic just can be made one by performing creative labour
A little replacements and deformation, these are replaced and deformation is the most within the scope of the present invention.
Claims (4)
1. grid-connected micro-inverter maximum power point fast algorithm based on peak point current, it is characterised in that sample grid-connected
The peak point current of micro-inverter main switch, and within a common frequency power network half period, the peak point current sampled is carried out size
Relatively, the peak inrush current in this common frequency power network half period is obtained;By described peak inrush current and a upper power frequency electric
The peak inrush current obtained in the net half period compares size, if described peak inrush current has been maximum, follow-up
Peak inrush current in the common frequency power network half period is all the least than described peak inrush current, then described peak-peak electricity
Operating mode corresponding to stream is exactly the maximum power output of photovoltaic module, i.e. achieves the MPPT maximum power point tracking of photovoltaic module.
2. grid-connected micro-inverter maximum power point fast algorithm based on peak point current, it is characterised in that described sampling photovoltaic
The peak point current of grid-connected micro-inverter main switch, and within a common frequency power network half period, the peak point current sampled is done and add
Method computing, thus obtain peak point current sum;By described peak point current sum and the peak in the upper common frequency power network half period
Value electric current sum compares size, if described peak point current sum reaches maximum, and the peak value in the follow-up common frequency power network half period
Electric current sum is all the least than described peak point current sum, then the operating mode corresponding to described peak point current sum is exactly photovoltaic module
Maximum power output, i.e. achieve the MPPT maximum power point tracking of photovoltaic module.
3. based on based on peak point current the grid-connected micro-inverter maximum power point fast algorithm described in claim 1, its
Being characterised by the peak inrush current in described common frequency power network half period, the Mean Input Power of grid-connected micro-inverter is
The increasing function of peak inrush current in the common frequency power network half period, therefore whether can reach according to the peak inrush current in the power frequency half period
To maximum, judge that photovoltaic module has realized the tracking of maximum power point the most;If the peak-peak in the power frequency half period
Electric current is not reaching to maximum, then can be by the set-point of disturbance grid-connected current, until the peak-peak in the power frequency half period
Current stabilization is at maximum, thus realizes the MPPT maximum power point tracking of photovoltaic module.
4. quick based on based on peak point current the grid-connected micro-inverter maximum power point described in claim 1 or 2 or 3
Algorithm, it is characterised in that the described peak inrush current in the common frequency power network half period and peak point current in the common frequency power network half period
Sum, the peak inrush current obtained in also residing in a common frequency power network half period is peak point current in this common frequency power network half period
The increasing function of sum, thus the Mean Input Power of grid-connected micro-inverter be also in the common frequency power network half period peak point current it
The increasing function of sum, therefore whether can reach maximum according to the peak point current sum in the common frequency power network half period, judge photovoltaic group
Part has realized the tracking of maximum power point the most, if the peak inrush current in the power frequency half period is not reaching to maximum, then
Can be by the set-point of disturbance grid-connected current, until the peak point current sum in the power frequency half period is stable at maximum, thus
Realize the MPPT maximum power point tracking of photovoltaic module.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610502982.3A CN106058927B (en) | 2016-06-27 | 2016-06-27 | Photovoltaic grid-connected micro-inverter maximum power point rapid algorithm based on peak current |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610502982.3A CN106058927B (en) | 2016-06-27 | 2016-06-27 | Photovoltaic grid-connected micro-inverter maximum power point rapid algorithm based on peak current |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106058927A true CN106058927A (en) | 2016-10-26 |
CN106058927B CN106058927B (en) | 2020-07-17 |
Family
ID=57200386
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610502982.3A Active CN106058927B (en) | 2016-06-27 | 2016-06-27 | Photovoltaic grid-connected micro-inverter maximum power point rapid algorithm based on peak current |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106058927B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107085449A (en) * | 2017-03-17 | 2017-08-22 | 扬州大学 | Converter Without Voltage Sensor and extracurrent sensor maximum power point implementation method |
CN112886836A (en) * | 2021-01-18 | 2021-06-01 | 浙江大学 | Flyback micro inverter analog control circuit and peak current control method |
CN113890372A (en) * | 2021-09-29 | 2022-01-04 | 苏州安步新能源科技有限公司 | Maximum power point tracking control method and system for photovoltaic power generation |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010231456A (en) * | 2009-03-26 | 2010-10-14 | Panasonic Electric Works Co Ltd | Power supply system |
CN102074968A (en) * | 2009-11-19 | 2011-05-25 | 上海岩芯电子科技有限公司 | Photovoltaic miniature grid-connected inverter control device and control method thereof |
CN102522766A (en) * | 2011-11-04 | 2012-06-27 | 浙江大学 | Flyback type miniature photovoltaic grid connected inverter with power decoupling circuit and control method thereof |
CN102931678A (en) * | 2012-07-03 | 2013-02-13 | 中南大学 | Double-staggered flyback photovoltaic grid-connected micro inverter and control method thereof |
CN103208939A (en) * | 2013-04-19 | 2013-07-17 | 江西中能电气科技有限公司 | Photovoltaic micro-inverter based on secondary-side reference current reconstruction, control system and control method |
CN103441526A (en) * | 2013-08-14 | 2013-12-11 | 华北电力大学(保定) | Grid-connected off-grid small photovoltaic power generation system and control method |
CN204539077U (en) * | 2015-04-07 | 2015-08-05 | 广东技术师范学院 | A kind of Intelligent photovoltaic Miniature inverter |
JP2015203904A (en) * | 2014-04-11 | 2015-11-16 | 株式会社三社電機製作所 | PV power conditioner |
-
2016
- 2016-06-27 CN CN201610502982.3A patent/CN106058927B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010231456A (en) * | 2009-03-26 | 2010-10-14 | Panasonic Electric Works Co Ltd | Power supply system |
CN102074968A (en) * | 2009-11-19 | 2011-05-25 | 上海岩芯电子科技有限公司 | Photovoltaic miniature grid-connected inverter control device and control method thereof |
CN102522766A (en) * | 2011-11-04 | 2012-06-27 | 浙江大学 | Flyback type miniature photovoltaic grid connected inverter with power decoupling circuit and control method thereof |
CN102931678A (en) * | 2012-07-03 | 2013-02-13 | 中南大学 | Double-staggered flyback photovoltaic grid-connected micro inverter and control method thereof |
CN103208939A (en) * | 2013-04-19 | 2013-07-17 | 江西中能电气科技有限公司 | Photovoltaic micro-inverter based on secondary-side reference current reconstruction, control system and control method |
CN103441526A (en) * | 2013-08-14 | 2013-12-11 | 华北电力大学(保定) | Grid-connected off-grid small photovoltaic power generation system and control method |
JP2015203904A (en) * | 2014-04-11 | 2015-11-16 | 株式会社三社電機製作所 | PV power conditioner |
CN204539077U (en) * | 2015-04-07 | 2015-08-05 | 广东技术师范学院 | A kind of Intelligent photovoltaic Miniature inverter |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107085449A (en) * | 2017-03-17 | 2017-08-22 | 扬州大学 | Converter Without Voltage Sensor and extracurrent sensor maximum power point implementation method |
CN112886836A (en) * | 2021-01-18 | 2021-06-01 | 浙江大学 | Flyback micro inverter analog control circuit and peak current control method |
CN112886836B (en) * | 2021-01-18 | 2022-04-12 | 浙江大学 | Flyback micro inverter analog control circuit and peak current control method |
CN113890372A (en) * | 2021-09-29 | 2022-01-04 | 苏州安步新能源科技有限公司 | Maximum power point tracking control method and system for photovoltaic power generation |
CN113890372B (en) * | 2021-09-29 | 2023-07-14 | 苏州安步新能源科技有限公司 | Maximum power point tracking control method and system for photovoltaic power generation |
Also Published As
Publication number | Publication date |
---|---|
CN106058927B (en) | 2020-07-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9899909B2 (en) | Control device and method of totem-pole bridgeless PFC soft switch | |
CN102074974B (en) | Method for eliminating grid-connected current zero-crossing distortion of unipolar control single-phase grid-connected inverter | |
CN100539381C (en) | A kind of control method of network-connecting generation inverter output current | |
CN109831094A (en) | A kind of the model-free predictive-current control system and its control method of Boost pfc converter | |
CN103414334B (en) | PF is the long-life DCM Boost pfc converter of 1 | |
CN106208684B (en) | A kind of combined control method of single-inductance double-output switch converters and its device | |
CN105116956B (en) | A kind of maximal power tracing controlling apparatus applied to photovoltaic generating system | |
CN104283413A (en) | Method for controlling bridgeless PFC circuit and device thereof | |
CN106058927A (en) | Peak-current-based rapid algorithm for maximum power point of photovoltaic grid-connected micro inverter | |
CN104360143A (en) | Load zero crossing point detection circuit and method and load voltage detection circuit and method | |
CN109687735A (en) | A kind of isolated DC power supply of high precision wide range | |
CN103166489A (en) | Control circuit for three-phase high power factor rectifier | |
CN108983864A (en) | A kind of tracking and its tracking device of maximum photovoltaic power point | |
CN105659485B (en) | Fairing | |
CN103763812B (en) | A kind of solar energy and semiconductor illuminator based on DSP and control method thereof | |
CN104992016B (en) | Modular multi-level converter loss estimation method | |
CN104503529A (en) | Thyristor single-phase voltage adjusting circuit and control method thereof | |
CN104167948A (en) | Variable-frequency soft switching control method of micro photovoltaic grid-connected inverter | |
CN106992689B (en) | A kind of single-phase direct ac/ac frequency converter and control method based on impulse-equivalent method | |
CN203233572U (en) | High power factor LED linearity constant current driving controller and LED driving device | |
CN209626955U (en) | Power supply device with overcurrent protection | |
CN103186160A (en) | Self-adjustment control method for maximum power point tracing of photovoltaic power generation | |
CN111931443A (en) | Electromagnetic transient equivalent modeling method for single-active-bridge converter | |
CN102868174B (en) | Photovoltaic grid-connected system for restraining chaos based on DSP (Digital Signal Processor) as well as working method thereof | |
CN110927565A (en) | Open-circuit fault positioning method for SVG main loop switching device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |