CN106050234A - Construction technique for protecting underground water in coal mining process - Google Patents

Construction technique for protecting underground water in coal mining process Download PDF

Info

Publication number
CN106050234A
CN106050234A CN201610362595.4A CN201610362595A CN106050234A CN 106050234 A CN106050234 A CN 106050234A CN 201610362595 A CN201610362595 A CN 201610362595A CN 106050234 A CN106050234 A CN 106050234A
Authority
CN
China
Prior art keywords
boring
coal
water
face
horizon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610362595.4A
Other languages
Chinese (zh)
Other versions
CN106050234B (en
Inventor
张建民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shenhua Energy Co Ltd
Original Assignee
China Shenhua Energy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shenhua Energy Co Ltd filed Critical China Shenhua Energy Co Ltd
Priority to CN201610362595.4A priority Critical patent/CN106050234B/en
Publication of CN106050234A publication Critical patent/CN106050234A/en
Application granted granted Critical
Publication of CN106050234B publication Critical patent/CN106050234B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/25Methods for stimulating production
    • E21B43/26Methods for stimulating production by forming crevices or fractures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Remote Sensing (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a construction technique for protecting underground water in the coal mining process. The construction technique comprises the following steps that S001, reconnaissance is conducted on a mining area, and the positions and water distribution data of a bedding rock layer and a quaternary aquifer below a surface soil layer are determined, specifically, the bedding rock layer is located below the quaternary aquifer; S002, at least one drilled hole located below the quaternary aquifer is constructed in the surface soil layer in the mining area; S003, grouting liquid is injected into the drilled holes; and S004, after the grouting liquid is solidified, an isolation layer is formed, and the isolation layer is formed between the bedding rock layer and the quaternary aquifer or the isolation layer is formed in the bedding rock layer. By the adoption of the construction technique, dual purposes of protecting surface water and pore water in quaternary loose soils and effectively developing and utilizing crack water are achieved, the high coal recovery ratio and mining efficiency are guaranteed, and underground water losses and interference to the surface ecological environment are reduced.

Description

The construction technology in progress of coal mining, subsoil water protected
Technical field
The present invention relates to technical field of coal exploitation, particularly relate to one and in progress of coal mining, subsoil water is protected The construction technology protected.
Background technology
China is one of country of serious water shortage in the world, only the 1/4 of world's per capita share, and western Jin, Shaanxi and Inner Mongolia are the sweetest The most only account for the 6.8% of the whole nation.The current coal mining method of China causes and arranges outside a large amount of mine water, and only State owned coal mine is every The mine water the most up to 2,200,000,000 tons of year discharge, the most often one ton of coal of exploitation about discharges 2 tons of mine waters.Western China is composed and is deposited Abundant coal resources, fall within ecologically fragile areas and deficient water resources.The mine water that coal mining produces at present is mainly used in Dust removing down-hole, ground industry and the aspect such as life and ecological protection, owing to these water consumptions are limited and there is stronger seasonality With periodically, outside remaining a large amount of mine waters, row causes water resource significant wastage.Coal resources scale exploitation makes mining area and week Edge regions water imbalance between supply and demand deteriorates further, seriously governs the coordinated development of mining area coal resources and ecological environment and can hold Supervention exhibition.
Research shows, the subsoil water in the overlying rock of the main coal-bearing series of China can be divided near surface soil horizon The soil water, the pore water in Quaternary loose soils (Quaternary aquifer) and the crevice water in horizon d.Wherein, pore water is Available groundwater resources of the mankind, and the crevice water in horizon d is stored and migrates in crack, mainly by crack closeness, Opening width and connective control, if not having water producing fractures in horizon d, use conventional method to develop the crack in basement rock Water is extremely difficult.
In prior art, typically by keeping the original state of underground reservoir or after water-bearing layer is destroyed, mine water is shifted Storing, realize the protection to subsoil water, it has certain limitation to safe coal high-efficiency mining and protection of water resources in mine area Property.
Summary of the invention
It is an object of the invention to overcome defect of the prior art, it is provided that one can be effectively isolated Quaternary aquifer With horizon d, subsoil water can be carried out the construction technology of effective Sustainable use.
Technical solution of the present invention provides a kind of construction technology protected subsoil water in progress of coal mining, and it is special Levy and be, comprise the steps: S001: production zone is reconnoitred, determine horizon d and the 4th be to contain containing pore water Water layer is in the position below topsoil and water distribution data, and wherein, described horizon d is positioned under described Quaternary aquifer Side;S002: in described production zone, is positioned at the boring below Quaternary aquifer from described topsoil construction at least one; S003: inject injection slurry in described boring;S004: after described injection slurry solidifies, form one layer of sealing coat, and described isolation Layer is formed between described horizon d and described Quaternary aquifer, or described sealing coat is formed in described horizon d.
Further, described step S002 also comprises the steps S0021: by the subregion of described horizon d or Zone Full pressure break makes seam, and is formed with the pressure break crack connected with described boring in described horizon d;In described step S004 also comprising the steps, S0041: described injection slurry flows in described pressure break crack, and solidifies in described pressure break crack Form described sealing coat.
Further, when coal-face back production, due to caving zone slump, and the Zone Full in described horizon d Or in subregion, be formed with bedrock fracture, thus form water producing fractures development belt;Described sealing coat is formed at described water guide and splits Between gap development belt and described Quaternary aquifer, or described sealing coat is formed in described water producing fractures development belt.
Further, complete in described coal-face back production, periodic weighting terminates, roof is caving and water guide completely When fracture extension zone is formed, start to perform step S003.
Further, adjust the drawing speed of described coal-face, to control or to slow down described bedrock fracture to described The trend that Quaternary aquifer is grown.
Further, the top of all or part of described water producing fractures development belt is with all or part of pressure break crack even Logical.Further, the drilling direction of described boring and the direction of propulsion of coal-face are contrary.
Further, when injecting described injection slurry in described boring, apply pressure to described injection slurry simultaneously.
Further, described injection slurry horizontal direction flowing velocity in described pressure break crack is more than its vertical direction stream Dynamic speed.
Further, on the length direction of coal-face, it is disposed with the most a plurality of described boring.
Further, on the width of coal-face, it is disposed with the most a plurality of described boring.
Further, described boring includes vertical section boring, bending section boring and the horizontal segment boring sequentially formed;Described Vertical section boring extends downward the lower section of described Quaternary aquifer from topsoil, and the boring of described horizontal segment the described 4th is The lower horizontal in water-bearing layer extends, and the boring of described bending section is connected between the boring of described vertical section and the boring of described horizontal segment.
Further, it is assumed that on the length direction of described coal-face, the length direction pressure break of every described boring Command range is L1, the radius of curvature of described bending section boring is Lr;Then on the length direction of described coal-face, adjacent Two described borings original position on described topsoil between distance be L1-Lr
Further, in the direction of the width, its every side all has security control distance K to coal-face;It is assumed that described On the width of coal-face, the width fracturing control distance of every described boring is L2, the width of coal-face Degree is W;On the width of described coal-face, then arranged number n >=(the W+2K)/L of described boring2, wherein n takes Integer.
Further, it is assumed that the construction safety distance of the base plate of described Quaternary aquifer is h, the most described horizontal segment boring And distance H between described base plate >=2h.
Further, described production zone is divided into multiple stage production zone, complete one described stage mining area After construction in territory, carry out the construction of next described stage production zone according to step S001-step S004.
Further, step S005 is also included: described horizon d will be positioned at the crevice water release below described sealing coat And utilize.
Use technique scheme, have the advantages that
The construction technology that the present invention provides, changes conventional subsoil water methane drainage and utilization project, the distributed storage of subsoil water and fills Fill out and adopt the Traditional Thinking protecting water-bearing layer, by the certain layer position of production zone overlying strata is reproduced, i.e. actively this layer of position is carried out Pressure break forms it into pressure break crack through water producing fractures development belt, and slip casting forms sealing coat, on the one hand achieve surface water and Top hole water conservation, on the other hand actively discharges bottom crevice water, it is achieved the target utilizing crevice water effective exploitation, protects Demonstrate,prove higher coal mining rate and production efficiency, be particularly well-suited to super large working face mining, can be greatly lowered ground simultaneously Lower swelling enters mine and causes potential safety hazard and mine drainage difficulty, reduces the loss of subsoil water and disturbs surface environment Dynamic.
Accompanying drawing explanation
The flow chart of the construction technology that Fig. 1 provides for the present invention;
Fig. 2 is the plane graph of construction drill;
Fig. 3 is the Fig. 2 cross-sectional schematic along the length direction of coal-face;
Fig. 4 is the Fig. 2 cross-sectional schematic along the width of coal-face.
Reference synopsis:
1-topsoil;2-Quaternary aquifer;3-horizon d;
31-water producing fractures development belt;4-coal seam;5-caving zone;
6-holes;61-vertical section is holed;62-bending section is holed;
63-horizontal segment is holed;7-sealing coat;8-coal-face;
A1-4-original position;Arrow B-coal-face direction of propulsion;
L1-length direction fracturing control distance; L2-width fracturing control distance;
The width of W-coal-face;K-security control distance.
Detailed description of the invention
Further illustrate the detailed description of the invention of the present invention below in conjunction with the accompanying drawings.The most identical parts are with identical Reference represents.
As Figure 1-4, subsoil water is protected in progress of coal mining by the one that one embodiment of the invention provides Construction technology, comprise the steps:
S001: reconnoitre production zone, determines that horizon d 3 and the Quaternary aquifer 2 containing pore water are in table Position below soil layer 1 and water distribution data, wherein, horizon d 3 is positioned at the lower section of Quaternary aquifer 2.
S002: in production zone, constructs from topsoil 1 and at least one is positioned at the boring 6 below Quaternary aquifer 2.
S003: inject injection slurry in by the boring 6 of pressure break.
S004: after injection slurry solidifies, form one layer of sealing coat 7, and sealing coat 7 to be formed at horizon d 3 with the 4th be to contain Between water layer 2, or sealing coat 7 is formed in horizon d 3.
That is to say, this construction technology mainly comprises the steps:
The underground space of production zone is reconnoitred and is observed:
(1) in coal mining planning region, may suitable sealing coat be visited by the underground space of mining area for choosing Look into, it is thus achieved that the basic datas such as mining region stratum and lithology, mining overburden hierarchical relationship and property of water-bearing feature.
The means that the exploiting field underground space is reconnoitred are based on geology and hydrogeophysical prospecting, the hydrogeology disclosed in conjunction with probing reality Condition verifies.Detecting scope and density can be according to situations such as exploiting field topography and geomorphology, geological conditions and combine Practical Project need Want and set.
(2) verify further the water producing fractures development belt 31 in the horizon d 3 of production zone and Quaternary aquifer 2 point Cloth district, and the level of ground water of Quaternary aquifer 2, water quality, hydraulic pressure etc. are carried out the most dynamically observation, find out planning production zone Groundwater occurrence feature and flowing law.
Groundwater occurrence is dynamically observed and is divided into artificial and automatic two ways with acquisition means, in conjunction with actual hydrogeology bar Part, general sets weekly (manually) or every day (automatically) records 1 secondary data, by digital device importing data base, passes through data Storehouse realizes being collected by the multi-source data of different times, different-format, as original hydrology geologic basis.
The design of distance boring and formation:
(1) in coal mining area, according to length and the boring 6 optimal fracturing control distances of coal-face 8, comprehensively determine Original position A of boring 61、A2、A3、A4Deng position on topsoil 1.
(2) from topsoil 1 to the lower section construction drill 6 of Quaternary aquifer 2, and boring 6 is made to have one section to be positioned horizontally in Four is the lower section in water-bearing layer 2.
Slip casting formation sealing coat:
Injecting injection slurry in boring 6, under a certain pressure, injection slurry can flow in boring 6 or by boring 6 inflow In pressure break crack and bedrock fracture.After a certain time, injection slurry solidifies, and forms one layer of sealing coat 7 afterwards, and it is isolated in the 4th It is between water-bearing layer 2 and horizon d 3, or is positioned at horizon d 3, will be located in the Quaternary aquifer 2 above sealing coat 7 and be positioned at Horizon d 3 below sealing coat 7 is effectively closed.
By forming this sealing coat 7, cranny development in horizon d 3 can be avoided in Quaternary aquifer 2, thus protect The pore water protected in the Quaternary aquifer 2 of top may not flow in horizon d 3.
Protected effect is evaluated:
(1) use comparative approach, do not adopt the water level in the mine water yield of time and Quaternary aquifer 2 with stope Based on data, push away along with pressure (pressure break boring) adopts (coal-face back production) note (injecting injection slurry in boring) circulation Enter, persistently observe according to 1 times/day of cycle, use data base tool and GIS-Geographic Information System is managed and comparative analysis, determine The burst size of subsoil water (crevice water and pore water), determines that the water level in mine water discharge variable quantity and Quaternary aquifer 2 is steady Qualitative or downward trend, evaluates isolation effect.When the subsoil water burst size observed in different time sections closer to, illustrate every The isolation effect of absciss layer 7 is the best.
(2) use geophysical prospecting method, do not adopt the water level in the mine water yield of time and Quaternary aquifer 2 with stope Based on data, advance along with pressure adopts note circulation, persistently observe according to 1 times/day of cycle, use data base tool and geography Information system is managed and comparative analysis, determines the burst size of subsoil water, determines that mine water discharge variable quantity and the 4th is to contain Water layer stable level or downward trend, evaluate isolation effect.When the subsoil water burst size observed in different time sections more connects Closely, illustrate that the isolation effect of sealing coat 7 is the best.
It is preferred that also comprise the steps S0021 in step S002:
The subregion of horizon d 3 or Zone Full pressure break are made seam, and is formed in horizon d 3 and 6 connects with holing Pressure break crack.
S0041 is also comprised the steps in step S004:
Injection slurry flows in pressure break crack, and solidification forms sealing coat 7 in pressure break crack.
When coal-face 8 back production, the rock above working seam 4 can fall to being formed caving zone 5, in the process, Horizon d 3 subregion can deform or slump, forms bedrock fracture, thus forms water producing fractures development belt 31, and water producing fractures is sent out Educate with the bedrock fracture of 31 contains substantial amounts of crevice water.
After coal-face 8 back production completes, by fracturing unit at topsoil 1 by all or part of district of horizon d 3 Territory pressure break, is formed with pressure break crack.This process is the active pressure break to horizon d 3, in the forming process of pressure break crack, because of pressure break The formation in crack, the water that cannot be produced contained in horizon d 3 is actively converted to crevice water and flows out, such that it is able to carried out Utilize.
Whole cracks or partial fracture in fracturing fracture connect with boring 6, specifically with whole in borehole-fracture or Part connection, thus time in by injection slurry injection hole 6, injection slurry can flow in pressure break crack, and solidifying in pressure break crack Solid becomes sealing coat 7, improves isolation effect.
It is preferred that as shown in Figure 3-4, when coal-face 8 back production, due to caving zone slump, and in horizon d 3 It is formed with bedrock fracture in Zone Full or subregion, thus forms water producing fractures development belt 31.
Sealing coat 7 is formed between water producing fractures development belt 31 and Quaternary aquifer 2, or sealing coat 7 is formed at water guide In fracture extension zone 31.
As it has been described above, when coal-face 8 back production, the rock above working seam 4 can fall to being formed caving zone 5, During this, horizon d 3 subregion can deform or slump, defines bedrock fracture in horizon d 3, and bedrock fracture can be led Water, thus form water producing fractures development belt 31, containing substantial amounts of crevice water in the bedrock fracture of water producing fractures development belt 31.
Sealing coat 7 is arranged between water producing fractures development belt 31 and Quaternary aquifer 2, can be well by pore water Separate with crevice water, it is possible to achieve to the protection of top pore water and the utilization to bottom crevice water.
According to specific circumstances, it is also possible to sealing coat 7 is formed in water producing fractures development belt 31, it is ensured that the 4th is Pore water in water-bearing layer 2 may not flow in the water producing fractures development belt 31 below sealing coat 7, plays a protective role.
In such a case, only it is pointed to the crevice water below sealing coat 7 utilize.
It is preferred that complete in coal-face 8 back production, periodic weighting terminates, roof is caving and water producing fractures completely When development belt 31 is formed, start to perform step S003.
When coal-face 8 back production completes, the periodic weighting produced because of back production terminates, and roof is caving shape completely Becoming caving zone 5, the bedrock fracture in crack and rock stratum 3 is formed completely, and defines water producing fractures development belt 31, this water producing fractures Development belt 31, also into systole, now carries out slip casting to boring 6, can improve injection slurry and form the effect of sealing coat 7, no Can be because also affecting slip casting effect in formation water producing fractures development belt 31 or bedrock fracture.
It is preferred that adjust the drawing speed of coal-face 8, to control or to slow down bedrock fracture to Quaternary aquifer 2 The trend grown, it is to avoid the bedrock fracture in water producing fractures development belt 31 connects with Quaternary aquifer 2, and causes hole current Enter in water producing fractures development belt 31.
Specifically, according to the expected height of water producing fractures development belt 31, determine drawing speed V of coal-face 8, pass through Adjust the drawing speed of coal-face 8, controlled by sealing coat 7 to greatest extent or slow down to cause water guide because back production is adopted The trend that bedrock fracture in fracture extension zone 31 is grown to Quaternary aquifer 2, the water producing fractures at sealing coat 7 is grown simultaneously Uniformly grow with the crack in 31.
It is preferred that the top of all or part of water producing fractures development belt 31 connects with all or part of pressure break crack, Thus sealing coat 7 is formed on the top of water producing fractures development belt 31, isolation water producing fractures development belt 31 and the 4th well It is the contact between water-bearing layer 2, improves sealing effectiveness.
Preferably, all or part of bedrock fracture connects with all or part of pressure break crack, thus injection slurry also may be used To flow in the bedrock fracture in water producing fractures development belt 31, sealing coat 7 is formed in water producing fractures development belt 31, improves The sealing effectiveness of sealing coat 7.
It is preferred that as in figure 2 it is shown, the drilling direction of boring 6 is contrary with the direction of propulsion of coal-face 8.Coal work Face 8 advances along the direction of arrow B.
Just construct before coal-face 8 advances and has holed 6, the direction of the initial position of boring 6 to final position and The direction of propulsion of coal-face 8 is contrary.
When coal-face 8 back production, the rock above working seam 4 can fall to being formed caving zone 5, in the process, Horizon d 3 subregion can deform or slump, thus forms bedrock fracture.
So the bedrock fracture in horizon d 3 is formed when coal-face 8 back production, it is along with coal-face 8 Back production and grow.
By boring 6 drilling direction contrary with the direction of propulsion of coal-face 8, make enforcement borehole fracturing direction of propulsion and The mining direction of coal-face 8 is consistent, can connect with the bedrock fracture in water producing fractures development belt 31 with pressure break crack.
It is preferred that when injecting injection slurry in boring 6, apply pressure to injection slurry simultaneously.Specifically apply level side Upward pressure so that it is flowing rapidly in boring 6, solidification forms sealing coat.
It is preferred that the horizontal direction flowing velocity that injection slurry is in pressure break crack is more than its vertical direction flowing velocity, from And make injection slurry quickly extend formation level along horizontal direction and be isolated in water producing fractures development belt 31 and Quaternary aquifer 2 Between sealing coat.
It is preferred that as in figure 2 it is shown, on the length direction of coal-face 8, be disposed with the most a plurality of boring 6, With in the longitudinal direction, cover all coal-face 8, improve the isolation effect of sealing coat 7.
It is preferred that as in figure 2 it is shown, on the width of coal-face 8, be disposed with the most a plurality of boring 6, , on wide length direction, to cover all coal-face 8, improve the isolation effect of sealing coat 7.
It is preferred that as it is shown on figure 3, boring 6 includes vertical section boring 61, bending section boring 62 and the horizontal segment sequentially formed Boring 62.
Vertical section boring 61 extends downward the lower section of Quaternary aquifer 2 from topsoil 1, and horizontal segment boring 63 is the 4th Being the lower horizontal extension in water-bearing layer 2, bending section boring 62 is connected between vertical section boring 61 and horizontal segment boring 63.
Vertical section boring 61 is positioned at original position A of each boring 61、A2、A3、A4Place downwardly extends.Horizontal segment boring 63 In the lower section of Quaternary aquifer 2, direction of propulsion oppositely extending of its horizontally toward coal-face 8.Vertical section boring 61 It is connected by bending section boring 62 with horizontal segment boring 63.
Certainly, when construction drill 6, it is initially formed vertical section boring 61 successively, then forms bending section boring 62, eventually form Horizontal segment boring 62.
This boring 6 also can be referred to as the boring of horizontal distance.
It is preferred that as shown in Figure 1, it is assumed that on the length direction of coal-face 8, the length direction pressure of every boring 6 Splitting command range is L1, the radius of curvature of bending section boring is Lr
Then on the length direction of coal-face 8, between two adjacent boring 6 original positions on topsoil 1 Distance be L1-Lr
That is to say, horizontal segment boring 63 length direction fracturing control distances in the longitudinal direction are L1, bending section is holed Radius of curvature be Lr, the most adjacent original position A1With original position A2Between or original position A3With original position A4Between Distance is L1-Lr, to ensure that the length direction fracturing control distance of two the most adjacent borings 6 is fully connected Together, it is possible to achieve coal-face 8 is completely covered by boring 6 in the fracturing control region on length direction, does not have something lost The region of leakage.
The model that fracturing control distance involved in the present invention can control for the pressure break crack formed after borehole fracturing Enclose, it is understood that the distance can flowing to for injection slurry, specifically include the distance on the degree of depth or length direction and width side Distance upwards.
It is preferred that as it is shown in figure 1, coal-face 8 in the direction of the width, its every side all has security control distance K.
It is assumed that on the width of coal-face 8, the width fracturing control distance of every boring 6 is L2, adopt The width of coal work surface 8 is W;
On the width of coal-face 8, then arranged number n >=(the W+2K)/L of boring 62, wherein n round numbers.
Security control distance K can calculate according to the subsidence slope in coal seam, and it represents needs to control coal-face 8 Outside width distance.
Horizontal segment boring 63 width fracturing control distances in the direction of the width are L2, then need at coal-face Number n >=(the W+2K)/L of boring 6 is arranged on the width of 82, guarantee covers all coal mining in the direction of the width Work surface 8 and required security control distance thereof, have the region of omission.
It is preferred that assume that the construction safety distance of the base plate of Quaternary aquifer 2 is h, then horizontal segment boring 63 and base plate Between distance H >=2h.Horizontal segment boring 63 is arranged on below the base plate of Quaternary aquifer 2, distance H between the two >= 2h, it is ensured that when construction drill 6, will not damage base plate.
It is preferred that production zone to be divided into multiple stage production zone, the construction in completing a stage production zone After, carry out the construction of next stage production zone according to step S001-step S004, be finally completed executing of whole production zone Work.
It is preferred that this construction technology also includes step S005: enter horizon d 3 is positioned at the crevice water below sealing coat 7 Row utilizes.
The construction technology that the present invention provides, the on the one hand pore water in the Quaternary aquifer on protection upper strata, on the other hand By active pressure break horizon d so that it is forming pressure break crack, the crevice water cannot being produced in horizon d, meeting is along pressure break crack Flow out, thus play the effect of the water actively discharged in horizon d.In exploitation process, horizon d also can be formed basement rock and split Gap, the crevice water cannot being produced in horizon d, also can flow out along bedrock fracture, itself and the water one flowed out along pressure break crack With constituting the mine water that can be utilized.
To sum up, the construction technology that the present invention provides, by choosing suitable subterranean geologic formations position as adopting at production zone The sealing coat in dynamic crack, by before exploitation, formation crack in boring, by a relatively large margin when reducing back production, in horizon d The energy that upwards conducts because adopting of crack, utilize Grouting engineering measure that boring and crack thereof are carried out horizontal orientation note simultaneously Slurry, forms sealing coat, it is achieved effective protection of the pore water on sealing coat, reduces the exploitation losses of groundwater resources, borrows simultaneously Help coal scale and exploit the crevice water resource that also effective exploitation is abundant, for protection groundwater in mining area resource and exploitation crevice water Resource provides scientific and reasonable technical method.
As required, above-mentioned each technical scheme can be combined, to reach best-of-breed technology effect.
Above-described is only principle and the preferred embodiment of the present invention.It should be pointed out that, the common skill for this area For art personnel, on the basis of the principle of the invention, it is also possible to make other modification some, also should be regarded as the protection model of the present invention Enclose.

Claims (17)

1. the construction technology in progress of coal mining, subsoil water protected, it is characterised in that comprise the steps:
S001: reconnoitre production zone, determines that horizon d and the Quaternary aquifer containing pore water are under topsoil The position of side and water distribution data, wherein, described horizon d is positioned at the lower section of described Quaternary aquifer;
S002: in described production zone, is positioned at the boring below Quaternary aquifer from described topsoil construction at least one;
S003: inject injection slurry in described boring;
S004: after described injection slurry solidifies, form one layer of sealing coat, and described sealing coat is formed at described horizon d with described Between Quaternary aquifer, or described sealing coat is formed in described horizon d.
Construction technology the most according to claim 1, it is characterised in that also comprise the steps in described step S002 S0021:
Subregion or the Zone Full pressure break of described horizon d are made seam, and is formed in described horizon d and described boring The pressure break crack of connection;
S0041 is also comprised the steps in described step S004:
Described injection slurry flows in described pressure break crack, and solidification forms described sealing coat in described pressure break crack.
Construction technology the most according to claim 2, it is characterised in that when coal-face back production, owing to caving zone collapses Fall, and be formed with bedrock fracture in Zone Full in described horizon d or subregion, thus form water producing fractures and grow Band;
Described sealing coat is formed between described water producing fractures development belt and described Quaternary aquifer, or described sealing coat is formed In described water producing fractures development belt.
Construction technology the most according to claim 3, it is characterised in that complete in described coal-face back production, the cycle When pressure terminates, roof is caving completely and water producing fractures development belt is formed, start to perform step S003.
5. according to the construction technology described in Claims 2 or 3, it is characterised in that adjust the drawing speed of described coal-face, To control or to slow down the trend that described bedrock fracture is grown to described Quaternary aquifer.
Construction technology the most according to claim 3, it is characterised in that all or part of described water producing fractures development belt Top connects with all or part of pressure break crack.
7. according to the construction technology described in any claim in claim 1-4, it is characterised in that the side of creeping into of described boring Contrary to the direction of propulsion with coal-face.
Construction technology the most according to claim 1 and 2, it is characterised in that injecting described injection slurry in described boring Time, apply pressure to described injection slurry simultaneously.
Construction technology the most according to claim 2, it is characterised in that described injection slurry level in described pressure break crack Direction flowing velocity is more than its vertical direction flowing velocity.
Construction technology the most according to claim 1, it is characterised in that on the length direction of coal-face, is disposed with The most a plurality of described boring.
11. construction technologies according to claim 10, it is characterised in that on the width of coal-face, arrange There is the most a plurality of described boring.
12. according to the construction technology described in claim 10 or 11, it is characterised in that it is vertical that described boring includes sequentially forming Section boring, bending section boring and horizontal segment boring;
The boring of described vertical section extends downward the lower section of described Quaternary aquifer from topsoil, and described horizontal segment is holed in institute The lower horizontal stating Quaternary aquifer extends, and the boring of described bending section is connected to the boring of described vertical section and bores with described horizontal segment Between hole.
13. construction technologies according to claim 12, it is characterised in that it is assumed that in the length side of described coal-face Upwards, the length direction fracturing control distance of every described boring is L1, the radius of curvature of described bending section boring is Lr
Then on the length direction of described coal-face, two adjacent described borings original position on described topsoil Between distance be L1-Lr
14. according to the construction technology described in claim 1 or 13, it is characterised in that in the direction of the width, it is every for coal-face Side all has security control distance K;
It is assumed that on the width of described coal-face, the width fracturing control distance of every described boring is L2, The width of coal-face is W;
On the width of described coal-face, then arranged number n >=(the W+2K)/L of described boring2, wherein n rounds Number.
15. construction technologies according to claim 12, it is characterised in that assume the executing of base plate of described Quaternary aquifer Work safe distance is h;
Distance H >=2h between the boring of the most described horizontal segment and described base plate.
16. construction technologies according to claim 1, it is characterised in that be divided into multiple stage to exploit described production zone Region, after the construction in completing a described stage production zone, is carried out described in the next one according to step S001-step S004 The construction of stage production zone.
17. construction technologies according to claim 1, it is characterised in that also include step S005: by position in described horizon d Crevice water below described sealing coat discharges and utilizes.
CN201610362595.4A 2016-05-26 2016-05-26 The construction technology that underground water is protected in progress of coal mining Active CN106050234B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610362595.4A CN106050234B (en) 2016-05-26 2016-05-26 The construction technology that underground water is protected in progress of coal mining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610362595.4A CN106050234B (en) 2016-05-26 2016-05-26 The construction technology that underground water is protected in progress of coal mining

Publications (2)

Publication Number Publication Date
CN106050234A true CN106050234A (en) 2016-10-26
CN106050234B CN106050234B (en) 2019-01-25

Family

ID=57175385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610362595.4A Active CN106050234B (en) 2016-05-26 2016-05-26 The construction technology that underground water is protected in progress of coal mining

Country Status (1)

Country Link
CN (1) CN106050234B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956225A (en) * 2017-11-22 2018-04-24 中国煤炭地质总局水文地质局 Discarded small-size coal mine top panel area administers the processing method for reducing the increment of groundwater
CN108894727A (en) * 2018-07-05 2018-11-27 中国矿业大学 The water-retaining method of ground level directional drilling slip casting closure overlying strata water producing fractures main channel
CN110761814A (en) * 2019-10-30 2020-02-07 中煤科工集团西安研究院有限公司 Roof water control method based on presplitting and grouting modification
CN112302718A (en) * 2020-10-29 2021-02-02 中煤科工集团西安研究院有限公司 Method for protecting water resource of water-bearing stratum of coal seam roof
CN112483172A (en) * 2020-11-25 2021-03-12 中国煤炭地质总局水文地质局 Method for artificially reconstructing water blocking boundary
CN113356830A (en) * 2021-05-14 2021-09-07 华北科技学院(中国煤矿安全技术培训中心) Shallow surface layer ecological water protection method based on mining space key layer lag effect
CN114837608A (en) * 2022-05-31 2022-08-02 中国矿业大学 Method for reconstructing mining overburden rock water barrier by multi-section graded grouting
CN115354961A (en) * 2022-07-04 2022-11-18 中国矿业大学(北京) Coal seam roof water plugging and ground surface settlement reduction treatment method
CN115419384A (en) * 2022-07-04 2022-12-02 中国矿业大学(北京) Aquifer dynamic grouting, interception and water plugging method for mining overburden rock complete breakage

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1963148A (en) * 2006-11-17 2007-05-16 中国矿业大学 Water-protection coal-mining method using structural key layer as waterproof layer
CN103924975A (en) * 2014-04-16 2014-07-16 河北煤炭科学研究院 Water retaining method for coal mining process
CN102704933B (en) * 2012-05-25 2014-10-29 中国矿业大学 Isolated-section grouting filling coal-mining method for mining overburden rock
CN104989403A (en) * 2015-06-02 2015-10-21 国投新集能源股份有限公司 Method for reconstructing floor limestone aquifer into natural-artificial composite integrated aquiclude
CN105545307A (en) * 2015-12-11 2016-05-04 大同煤矿集团有限责任公司 Method for over-pit and under-pit cooperative control of roofs of far and near fields of extra-large stoping space

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1963148A (en) * 2006-11-17 2007-05-16 中国矿业大学 Water-protection coal-mining method using structural key layer as waterproof layer
CN102704933B (en) * 2012-05-25 2014-10-29 中国矿业大学 Isolated-section grouting filling coal-mining method for mining overburden rock
CN103924975A (en) * 2014-04-16 2014-07-16 河北煤炭科学研究院 Water retaining method for coal mining process
CN104989403A (en) * 2015-06-02 2015-10-21 国投新集能源股份有限公司 Method for reconstructing floor limestone aquifer into natural-artificial composite integrated aquiclude
CN105545307A (en) * 2015-12-11 2016-05-04 大同煤矿集团有限责任公司 Method for over-pit and under-pit cooperative control of roofs of far and near fields of extra-large stoping space

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956225A (en) * 2017-11-22 2018-04-24 中国煤炭地质总局水文地质局 Discarded small-size coal mine top panel area administers the processing method for reducing the increment of groundwater
CN108894727A (en) * 2018-07-05 2018-11-27 中国矿业大学 The water-retaining method of ground level directional drilling slip casting closure overlying strata water producing fractures main channel
CN108894727B (en) * 2018-07-05 2021-01-19 中国矿业大学 Water retention method for plugging main channel of overburden rock water flowing fracture by grouting in ground horizontal directional drilling
CN110761814A (en) * 2019-10-30 2020-02-07 中煤科工集团西安研究院有限公司 Roof water control method based on presplitting and grouting modification
CN112302718A (en) * 2020-10-29 2021-02-02 中煤科工集团西安研究院有限公司 Method for protecting water resource of water-bearing stratum of coal seam roof
CN112483172A (en) * 2020-11-25 2021-03-12 中国煤炭地质总局水文地质局 Method for artificially reconstructing water blocking boundary
CN113356830A (en) * 2021-05-14 2021-09-07 华北科技学院(中国煤矿安全技术培训中心) Shallow surface layer ecological water protection method based on mining space key layer lag effect
CN114837608A (en) * 2022-05-31 2022-08-02 中国矿业大学 Method for reconstructing mining overburden rock water barrier by multi-section graded grouting
CN114837608B (en) * 2022-05-31 2022-12-23 中国矿业大学 Method for reconstructing mining overburden rock water barrier by multi-section graded grouting
CN115354961A (en) * 2022-07-04 2022-11-18 中国矿业大学(北京) Coal seam roof water plugging and ground surface settlement reduction treatment method
CN115419384A (en) * 2022-07-04 2022-12-02 中国矿业大学(北京) Aquifer dynamic grouting, interception and water plugging method for mining overburden rock complete breakage
US11781429B1 (en) 2022-07-04 2023-10-10 China University Of Mining And Technology, Beijing Method for blocking mine water inrush

Also Published As

Publication number Publication date
CN106050234B (en) 2019-01-25

Similar Documents

Publication Publication Date Title
CN106050234B (en) The construction technology that underground water is protected in progress of coal mining
CN110242301B (en) Two-step grouting modification water-retention coal mining method for roof aquifer
CN102865103B (en) Distributed using method for mine underground water
CN104863629B (en) A kind of method taking out absciss layer gas and draining slip casting under overlying strata using combined drilling and counterboring
AU2013252230B2 (en) Method for distributed storage and use of underground water in mine
CN107905834A (en) A kind of hypotonic high prominent coal seam architecture gas production method
CN106351660B (en) A method of descend water resource to be regulated and controled over the ground for coal mining region
CN104633996B (en) Water source heat pump recharging technical method
CN109577980B (en) Underground longwall working face water-retaining coal mining method based on aquifer freezing
CN113175325B (en) Coal and intergrown sandstone type uranium ore coordinated mining method based on key layer protection
CN104806217A (en) Combined separated layer fracturing, grouping and layer-combining mining method for coal bed well group
CN102862775B (en) Distributed storage method of underground water of mine
CN102392677A (en) Permeability improvement technology for coal bed gas reservoir cap by using three-dimensional fracture network modification
CN107044280A (en) A kind of bored grouting detection method of mining overburden absciss layer distribution characteristics
CN112879011B (en) Method for controlling height of water guide crack zone by hard overburden rock pre-cracking weakening under aquifer
CN103161434A (en) Mining method for low permeability reservoir of shale gas and the like
CN102493831A (en) Method for extracting coal seam gas through ground fracturing and underground horizontal drill holes
CN108301866A (en) Mining of closed distance coal seam group adjacent layer gas pressure relief directional drilling stops pumping method
CN110306965A (en) A kind of method for increasing for coal bed gas low yield wellblock
CN102226412B (en) Underground dark mining drilling well gas extraction method
CN109026140B (en) A method of with band and the artificial water proof stratum of solid-filling coal-mining technique
CN117231293A (en) Mining overburden composite curtain and overburden multi-separation layer horizon accurate grouting and subsidence reducing method
CN209742871U (en) Coal-based gas multilayer co-production well type structure
CN106593444A (en) Method for reducing mining vibration energy under hard rock stratum
RU2513962C1 (en) Oil deposit development method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant