CN106049543A - Tunnel inspection well with draining and floating resisting functions - Google Patents
Tunnel inspection well with draining and floating resisting functions Download PDFInfo
- Publication number
- CN106049543A CN106049543A CN201610627500.7A CN201610627500A CN106049543A CN 106049543 A CN106049543 A CN 106049543A CN 201610627500 A CN201610627500 A CN 201610627500A CN 106049543 A CN106049543 A CN 106049543A
- Authority
- CN
- China
- Prior art keywords
- inspection shaft
- tunnel
- inverted arch
- inspection well
- sluicing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000007689 inspection Methods 0.000 title claims abstract description 63
- 238000007667 floating Methods 0.000 title claims abstract description 15
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 28
- 241000282326 Felis catus Species 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 239000004746 geotextile Substances 0.000 claims description 3
- 238000001914 filtration Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 9
- 230000009286 beneficial effect Effects 0.000 abstract 1
- 239000012634 fragment Substances 0.000 description 5
- 238000003325 tomography Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 241000521257 Hydrops Species 0.000 description 1
- 206010030113 Oedema Diseases 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 239000003245 coal Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 239000008187 granular material Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F16/00—Drainage
- E21F16/02—Drainage of tunnels
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a tunnel inspection well with draining and floating resisting functions. The tunnel inspection well comprises an inverted arch filling layer, a tunnel inverted arch and a center draining pipe arranged in the inverted arch filling layer. An inspection well body is formed in the inverted arch filling layer. The inspection well body passes through the tunnel inverted arch in depth. Draining holes are reserved in an inspection well bottom plate of the inspection well body. Overflow pipes are inserted into the draining holes. The side wall of the inspection well body communicates with the center draining pipe. The tunnel inspection well is applicable to railway tunnel engineering in water-rich sections such as faults and karst development sections, the situation that due to the fact that base water pressure in a tunnel is too high, a ballastless track arches up can be effectively prevented, and safe operation of a railway is guaranteed. The tunnel inspection well has the beneficial effects of simple construction, small investment and the like, the application prospect is wide, construction operation is very simple, and the construction cost is extremely low.
Description
Technical field
The invention belongs to a kind of tunnel inspection shaft, be specifically related to a kind of tunnel inspection shaft with sluicing anti-floating function.
Background technology
At present, China be that Tunnel Engineering is largest in the world, quantity at most, geological conditions and version the most multiple
Country miscellaneous, that technology of building is with the fastest developing speed.For railway tunnel, mostly use and center is set in inverted arch packed layer
Water pipe, as the drainage pattern of main drainage channel, keeps at a certain distance away simultaneously and arranges center inspection shaft at, in order to desilting, white-out
Central water tube, meets the requirement that tunnel drainage system " can be safeguarded ".It addition, along with the development of high-speed railway, for satisfied row
Overall height speed service requirement, generally starts in high ferro tunnel to lay non-fragment orbit.Compared with traditional Ballast track, although without tiny fragments of stone, coal, etc. rail
Road can reduce maintenance, reduction dust, beautify the environment, but the stability requirement to tunnel bottom structure is the highest.
But, in the last few years, the railway tunnel of operation, at the water abundant ground such as tomography, karsts developing area, owing to hydraulic pressure is high, causes
The phenomenon of non-fragment orbit arch occurs repeatedly;Further, since problems such as constructing tunnel technique, construction qualities, cause tunnel inverted arch
It is more universal that the situations such as layering performs and inverted arch construction joint waterproof effect is undesirable filled by bottom leakiness, inverted arch, if tunnel
Road periphery subsoil water is grown, the water yield is enriched, and the weak location of these guarded drainage will produce hydrops, under hydraulic pressure effect, causes
The protuberance of track plates, causes extreme influence to safety of railway operation.
Summary of the invention
The present invention solves that problem that prior art exists proposes, its objective is to provide one to have sluicing anti-floating function
Tunnel inspection shaft.
The technical scheme is that a kind of tunnel inspection shaft with sluicing anti-floating function, including inverted arch packed layer, tunnel
Road inverted arch and be arranged on the central drainage pipe in inverted arch packed layer, forms inspection shaft, described inspection in described inverted arch packed layer
Well depth crossing-river tunnel inverted arch, in the inspection shaft base plate of inspection shaft, reserved spilled water hole, is inserted with overflow pipe in described spilled water hole, described
Inspection shaft sidewall connects with central drainage pipe.
Granular cushion it is provided with, between described inspection shaft base plate, granular cushion below described inspection shaft base plate
It is provided with loaded filter.
Described loaded filter is geotextiles.
Described overflow pipe outer wall is provided with, with the contact site of spilled water hole inwall, the rubber ring sealed.
Described overflow pipe fixes with inspection shaft sidewall.
Described overflow pipe pipe is risen in drain pipe.
Described inspection shaft sidewall is formed foot nest, and is provided with reinforcing bar cat ladder.
Described inspection shaft opening is provided with cover plate.
The present invention is be applicable to the water abundant ground railway tunnel work such as tomography, karsts developing area, in effectively preventing tunnel
Causing greatly non-fragment orbit to arch up because sole presses through, ensured the safe operation of railway, the present invention has that construction is simple, it is little to invest
Etc. feature, having a extensive future, constructing operation is very simple, and construction costs is extremely low.
Accompanying drawing explanation
Fig. 1 is the top view of the present invention;
Fig. 2 is the sectional view of I-I line along Fig. 1;
Fig. 3 is the sectional view of II-II line along Fig. 1;
Fig. 4 is the sectional view of 1-1 line along Fig. 2;
Fig. 5 is the structure enlarged diagram in A portion in Fig. 2;
Wherein:
1 spilled water hole 2 inspection shaft base plate
3 loaded filter 4 granular cushions
5 inspection shaft 6 inverted arch packed layers
7 tunnel inverted arch 8 central drainage pipes
9 reinforcing bar cat ladder 10 foot nests
11 cover plate 12 overflow pipes
13 rubber rings.
Detailed description of the invention
Hereinafter, referring to the drawings and embodiment the present invention is described in detail:
As shown in Fig. 1 ~ 5, a kind of tunnel inspection shaft with sluicing anti-floating function, including inverted arch packed layer 6, tunnel inverted arch 7 with
And the central drainage pipe 8 being arranged in inverted arch packed layer 6, described inverted arch packed layer 6 is formed inspection shaft 5, described inspection shaft 5 is deep
Degree crossing-river tunnel inverted arch 7, i.e. inspection shaft base plate 2 are arranged at below tunnel inverted arch 7 bottom surface, pre-in the inspection shaft base plate 2 of inspection shaft 5
Staying spilled water hole 1, be inserted with overflow pipe 12 in described spilled water hole 1, described inspection shaft 5 sidewall connects with central drainage pipe 8.
Spilled water hole 1 in inspection shaft base plate 2 and overflow pipe 12 enough make subsoil water collect rapidly to return to, in inspection shaft, reach
To quick pressure release, it is to avoid the purpose that track structure floats.
Granular cushion 4, described inspection shaft base plate 2, granular cushion 4 it is provided with below described inspection shaft base plate 2
Between be provided with loaded filter 3.
Described loaded filter 3 is geotextiles.
Described loaded filter 3 is prevented from tunnel subsoil stone granule blocking spilled water hole 1, to reach to be effectively isolated, draining smoothly
Purpose.
Described overflow pipe 12 outer wall is provided with, with the contact site of spilled water hole 1 inwall, the rubber ring 13 sealed.
In described rubber ring 13 is prevented from inspection shaft 5, water enters at the bottom of tunnel, makes certain pressure subsoil water to converge simultaneously
Return in inspection shaft 5 on collection, it is to avoid because of tunnel perimeter water level increase, hydraulic pressure increase, and cause track structure float deformation.
Described overflow pipe 12 fixes with inspection shaft 5 sidewall.
Described overflow pipe 12 pipe is risen in drain pipe.Making charge for remittance one-way flow, in being prevented effectively from gutter, charge for remittance is by inspection
Look into well 5 to Tunnel Base seepage.
Described inspection shaft 5 sidewall is formed foot nest 10, and is provided with reinforcing bar cat ladder 9.The personnel of maintaining easily go into the well and manage
Road is safeguarded.
Spilled water hole 1 in the present invention is five.
Described inspection shaft 5 opening is provided with cover plate 11.
The present invention is be applicable to the water abundant ground railway tunnel work such as tomography, karsts developing area, in effectively preventing tunnel
Causing greatly non-fragment orbit to arch up because sole presses through, ensured the safe operation of railway, the present invention has that construction is simple, it is little to invest
Etc. feature, having a extensive future, constructing operation is very simple, and construction costs is extremely low.
Claims (8)
1. there is a tunnel inspection shaft for sluicing anti-floating function, including inverted arch packed layer (6), tunnel inverted arch (7) and setting
Central drainage pipe (8) in inverted arch packed layer (6), it is characterised in that: described inverted arch packed layer (6) is formed inspection shaft (5),
Described inspection shaft (5) degree of depth crossing-river tunnel inverted arch (7), in the inspection shaft base plate (2) of inspection shaft (5), reserved spilled water hole (1), described
Being inserted with overflow pipe (12) in spilled water hole (1), described inspection shaft (5) sidewall connects with central drainage pipe (8).
The tunnel inspection shaft with sluicing anti-floating function the most according to claim 1, it is characterised in that: at the bottom of described inspection shaft
Plate (2) lower section is provided with granular cushion (4), is provided with anti-between described inspection shaft base plate (2), granular cushion (4)
Filtering layer (3).
The tunnel inspection shaft with sluicing anti-floating function the most according to claim 2, it is characterised in that: described loaded filter
(3) it is geotextiles.
The tunnel inspection shaft with sluicing anti-floating function the most according to claim 1, it is characterised in that: described overflow pipe
(12) outer wall is provided with, with the contact site of spilled water hole (1) inwall, the rubber ring (13) sealed.
5. according to the tunnel inspection shaft with sluicing anti-floating function described in claim 1 or 4, it is characterised in that: described spilling water
Pipe (12) fixes with inspection shaft (5) sidewall.
6. according to the tunnel inspection shaft with sluicing anti-floating function described in claim 1 or 4, it is characterised in that: described spilling water
Pipe (12) pipe is risen in drain pipe.
The tunnel inspection shaft with sluicing anti-floating function the most according to claim 1, it is characterised in that: described inspection shaft
(5) sidewall forms foot nest (10), and be provided with reinforcing bar cat ladder (9).
The tunnel inspection shaft with sluicing anti-floating function the most according to claim 1, it is characterised in that: described inspection shaft
(5) opening is provided with cover plate (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610627500.7A CN106049543B (en) | 2016-08-03 | 2016-08-03 | Tunnel inspection shaft with sluicing anti-floating function |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610627500.7A CN106049543B (en) | 2016-08-03 | 2016-08-03 | Tunnel inspection shaft with sluicing anti-floating function |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106049543A true CN106049543A (en) | 2016-10-26 |
CN106049543B CN106049543B (en) | 2019-07-30 |
Family
ID=57197334
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610627500.7A Expired - Fee Related CN106049543B (en) | 2016-08-03 | 2016-08-03 | Tunnel inspection shaft with sluicing anti-floating function |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106049543B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111074944A (en) * | 2020-01-10 | 2020-04-28 | 重庆市云鹏水泥制品有限公司 | Prefabricated assembled concrete anti-floating inspection well and processing method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4313239A1 (en) * | 1993-04-22 | 1994-10-27 | Preussag Anlagenbau | Procedure for performing civil engineering work |
JP2002327600A (en) * | 2001-04-27 | 2002-11-15 | Daiwa-Cres Co Ltd | Retaining wall structure of tunnel watchman's passage and member for forming retaining wall |
CN102661171A (en) * | 2012-05-02 | 2012-09-12 | 中铁十一局集团第五工程有限公司 | Frost damage prevention drainage system for tunnel |
CN105673074A (en) * | 2016-01-19 | 2016-06-15 | 铁道第三勘察设计院集团有限公司 | Tunnel base local deep-buried drainage ditch structure |
CN205934974U (en) * | 2016-08-03 | 2017-02-08 | 铁道第三勘察设计院集团有限公司 | Tunnel inspection shaft with anti function of floating sluices |
-
2016
- 2016-08-03 CN CN201610627500.7A patent/CN106049543B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4313239A1 (en) * | 1993-04-22 | 1994-10-27 | Preussag Anlagenbau | Procedure for performing civil engineering work |
JP2002327600A (en) * | 2001-04-27 | 2002-11-15 | Daiwa-Cres Co Ltd | Retaining wall structure of tunnel watchman's passage and member for forming retaining wall |
CN102661171A (en) * | 2012-05-02 | 2012-09-12 | 中铁十一局集团第五工程有限公司 | Frost damage prevention drainage system for tunnel |
CN105673074A (en) * | 2016-01-19 | 2016-06-15 | 铁道第三勘察设计院集团有限公司 | Tunnel base local deep-buried drainage ditch structure |
CN205934974U (en) * | 2016-08-03 | 2017-02-08 | 铁道第三勘察设计院集团有限公司 | Tunnel inspection shaft with anti function of floating sluices |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111074944A (en) * | 2020-01-10 | 2020-04-28 | 重庆市云鹏水泥制品有限公司 | Prefabricated assembled concrete anti-floating inspection well and processing method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN106049543B (en) | 2019-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209212297U (en) | A kind of guarded drainage and decompression system for rich water section tunnel | |
CN103147614B (en) | Pool with multi-layer structure and building method thereof | |
CN103510528A (en) | Blind trench water discharging structure used for underground structure up-floating prevention | |
CN105735055A (en) | Imbibition drainage method | |
CN108533316A (en) | A kind of full packet pressure release waterproof/drainage structure in tunnel | |
CN102383408B (en) | Greening method for high water level impermeable saline and alkaline lands and greening system | |
CN102172198A (en) | Water-saving irrigation device for road greenbelt and forming method thereof | |
CN202730785U (en) | Anti-floating blind ditch water drainage structure for underground structure | |
CN105201024B (en) | Refuse landfill HDPE film rain dirt separation panel water channel | |
CN207568626U (en) | A kind of tunnel structure for expansive stratum | |
CN106049543A (en) | Tunnel inspection well with draining and floating resisting functions | |
CN108361065A (en) | A kind of tunnel inverted arch filling discharge structure | |
CN108533317A (en) | A kind of tunnel bottom discharge structure | |
CN205934974U (en) | Tunnel inspection shaft with anti function of floating sluices | |
CN208168937U (en) | A kind of tunnel bottom discharge structure | |
CN203113863U (en) | Multi-layer structure water pool | |
CN209636585U (en) | A kind of pavement grass planting ditch | |
CN108951557B (en) | Irrigation and flood control dam for hydraulic engineering | |
CN107905809B (en) | Double-hole hollow rectangular section beam bearing cutting type arched tunnel lining structure | |
CN208266612U (en) | A kind of town road structure | |
CN102536318A (en) | Level linear highway tunnel with drainage system | |
CN113464174B (en) | Construction method of tunnel row waterproof comprehensive treatment system | |
CN214938891U (en) | Stable roadbed structure | |
CN212803334U (en) | Tunnel inverted arch lower one-way drain pipe convenient for drainage and pressure relief | |
CN212742576U (en) | Internal drainage structure of loess high fill side slope |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 300142 No. 10, Hebei District, Tianjin, Zhongshan Road Applicant after: China Railway Design Group Limited Address before: 300142 No. 10, Hebei District, Tianjin, Zhongshan Road Applicant before: China Railway Third Survey and Design Institute Group Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190730 Termination date: 20200803 |