CN106049524A - Composite cylinder type foundation with auxiliary piles added in later period - Google Patents
Composite cylinder type foundation with auxiliary piles added in later period Download PDFInfo
- Publication number
- CN106049524A CN106049524A CN201610618677.0A CN201610618677A CN106049524A CN 106049524 A CN106049524 A CN 106049524A CN 201610618677 A CN201610618677 A CN 201610618677A CN 106049524 A CN106049524 A CN 106049524A
- Authority
- CN
- China
- Prior art keywords
- auxiliary
- auxiliary pile
- cylindrical foundation
- foundation
- top cover
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
- E02D27/425—Foundations for poles, masts or chimneys specially adapted for wind motors masts
Abstract
A composite cylinder type foundation with auxiliary piles added in the later period is composed of a cylindrical foundation body, a transition section, reinforcing ribs, auxiliary pile fixing ring sleeves and the auxiliary piles. The center of a cylindrical foundation body top cover is fixedly connected with the transition section. The transition section is connected with a fan tower cylinder through a flange. The reinforcing ribs are evenly distributed on the transition section and the cylindrical foundation body top cover annularly and radially. The reinforcing ribs, the transition section and the cylindrical foundation body top cover are prefabricated into a whole. The auxiliary pile ring sleeves are arranged at the bottom ends of the outer sides of the reinforcing ribs. After a cylindrical foundation structure is sunk, the auxiliary piles are driven into the cylindrical foundation structure, and the auxiliary piles are driven into a seabed through the auxiliary pile ring sleeves; and the auxiliary piles are fixedly connected with the auxiliary pile ring sleeves. The composite cylinder type foundation has the beneficial effects that due to the fact that auxiliary pile structures radially distributed on the edge of the composite cylinder type foundation have large pulling-resistant bearing capacity, the composite cylinder type foundation can resist the higher transverse load and the bending moment load; and by means of the cylinder type foundation, the standardized production and one-step type installation of the structure can be achieved, production and installation efficiency is improved greatly, and the production cost is lowered.
Description
Technical field
The present invention relates to offshore wind power foundation structure, a kind of later stage adds the compound bucket foundation of auxiliary pile.
Background technology
In recent years, offshore wind farm quickly grows as a kind of green clean reproducible energy, and its market is almost with every year
The speed of more than 40% increases swift and violent.Offshore wind farm has that wind field quality is good, turbulivity is little, be not take up ploughing, utilize in year little
The significant advantages such as Shi Gao.But maritime environment is complicated, stormy waves stream is complicated to the coupling of basis and pylon structure, and sea water is to basis
Wash away obvious with corrosion function.Simultaneously as maritime environment is complicated, the difficulty of construction of base structure is relatively big, relatively costly, and
Later stage monitoring and maintenance is costly.Therefore, how to improve the bearing capacity of base structure, and to reduce cost be offshore wind farm
The key issue of technology development.
In numerous offshore wind power foundation structures, compound cylindrical foundation is shown as a kind of emerging base structure
It is at the superiority of wind power foundation technical field.Compound tubular base structure has good bearing capacity and transportation by driving ability.
But, due to the difference of the geological conditions of different wind fields, the geological conditions difference of the most identical wind field different regions so that tubular
The size on basis differs greatly with the design of structure.This significantly limit the mass of cylindrical foundation structure, standardized life
Producing, its design is of a relatively high with the cost manufactured.Simultaneously as the design of cylindrical foundation structure is decided by the geology of addressing substantially
Condition, relative transportation by driving condition considers less with sinking condition, thus adds being constructed into of cylindrical foundation to a certain extent
This.Most importantly, due to compound cylindrical foundation is that single structure carries, once bearing capacity deficiency, entirety can be caused
Structural damage, risk is bigger.Proposing a kind of later stage for this application and add the compound bucket foundation of auxiliary pile, this basis is by cylinder
Jointly carry with auxiliary pile, reduce the risk that entirety is destroyed, improve bearing capacity so that the design of cylindrical foundation structure is cleverer
Live, thus the standardized production that can realize cylindrical foundation is installed with single step, reduces cost, improves efficiency.
Summary of the invention
It is an object of the invention to for above-mentioned existing problems, it is provided that a kind of later stage adds the compound bucket foundation of auxiliary pile, should
Compound bucket foundation can realize the compound cylinder-shaped foundation structure that standardized production is installed with single step, and ensures that cylindrical foundation is not
With the bearing capacity under foundation condition.
Technical scheme:
A kind of later stage adds the compound bucket foundation of auxiliary pile, by cylindrical foundation, changeover portion, ribs, auxiliary pile retainer ring
Set and auxiliary pile are constituted, and cylindrical foundation top cover is reinforced concrete structure, and sidewall is steel construction;Cylindrical foundation top cap central and mistake
The section of crossing is fixing to be connected;Changeover portion is steel construction, and diameter and blower fan tower barrel lower end diameter quite and pass through flange and blower fan tower barrel phase
Even;Changeover portion and cylindrical foundation top cover arrange 4-8 the radial equally distributed ribs of hoop;Ribs is steel construction, with
Changeover portion and cylindrical foundation top cover are made as unified entirety in advance;Ribs outer lower end arranges 4-8 auxiliary pile ring set;Auxiliary anchor ear
Set is steel construction, is welded and fixed with ribs;Squeezing into auxiliary pile after cylindrical foundation structure is sunk, auxiliary pile number is with auxiliary
Help anchor ear set number identical;Auxiliary pile squeezes into sea bed by auxiliary pile ring set respectively;Auxiliary pile is steel construction, with auxiliary pile ring set
Fixing connection.
The invention has the beneficial effects as follows:
This compound bucket foundation has bigger resistance to plucking bearing capacity because of the auxiliary pile structure of the radial distribution in its edge, makes
Obtain this base structure and can resist higher, more complicated lateral load and moment load;Simultaneously because structure bending resistance, shear resistance
Raising so that the design of tubular construction can be wholly constrained to the factor of geological conditions, and more consideration structure is made
Cost, the optimum transportation by driving degree of depth and optimum sinking condition;This cylindrical foundation can realize the standardized production of structure and install with single step,
Greatly improve the efficiency producing with installing, reduce production cost.
Accompanying drawing explanation
Fig. 1 is this compound bucket foundation facade structures schematic diagram.
Fig. 2 is this compound bucket foundation plan structure schematic diagram.
In figure 1, standardization cylindrical foundation;2, changeover portion;3, ribs;4, auxiliary pile Fixing shrink ring;5, auxiliary pile.
Detailed description of the invention
Embodiment:
A kind of later stage adds the compound bucket foundation of auxiliary pile, as shown in Figure 1-2, by cylindrical foundation 1, changeover portion 2, ribs
3, auxiliary pile Fixing shrink ring 4 and auxiliary pile 5 are constituted, and cylindrical foundation 1 top cover is reinforced concrete structure, and sidewall is steel construction;Cylinder
Shape basis 1 top cap central is fixing with changeover portion 2 to be connected;Changeover portion 2 is steel construction, and diameter is with blower fan tower barrel lower end diameter the most also
It is connected with blower fan tower barrel by flange;Changeover portion 2 and cylindrical foundation 1 top cover arrange six radial equally distributed reinforcements of hoop
Rib 3;Ribs 3 is steel construction, is made as unified entirety in advance with changeover portion 2 and cylindrical foundation 1 top cover;Ribs 3 outer lower end sets
Put six auxiliary pile ring sets 4;Auxiliary pile ring set 4 is steel construction, with being welded and fixed of ribs 3;When cylindrical foundation structure is sunk
After squeeze into auxiliary pile 5, six auxiliary piles 5 squeeze into sea bed by six auxiliary pile ring sets 4 respectively;Auxiliary pile 5 is steel construction,
Fix with auxiliary pile ring set 4 and be connected.
In this embodiment: cylindrical foundation 1 external diameter 20m, top cover thickness 0.7m, wall thickness 0.05m, wall height 6m;Changeover portion 2 external diameter
6m, wall thickness 0.05m;Ribs 3 height 6m, thickness 0.1m;Auxiliary pile ring set 4 internal diameter 1m, thickness 0.03m;Auxiliary pile 6 external diameter
1m, wall thickness 0.03m.
The work progress of this compound bucket foundation, step is as follows:
1) complete cylindrical foundation 1, changeover portion 2, ribs 3 and the standardization of auxiliary pile Fixing shrink ring 4, integration produces;
2) by prefabricated profiled structure towage to sinking place, sinking work is carried out subsequently;
3), after sinking completes, the construction of auxiliary pile 5 is carried out according to the geological conditions being obtained ahead of time and wind direction condition;
4) auxiliary pile 5 and auxiliary pile ring set 4 are fixedly connected the globality of guarantee composite construction.
Claims (1)
1. later stage adds the compound bucket foundation of auxiliary pile, it is characterised in that: by cylindrical foundation, changeover portion, ribs, auxiliary
Stake Fixing shrink ring and auxiliary pile are constituted, and cylindrical foundation top cover is reinforced concrete structure, and sidewall is steel construction;Cylindrical foundation top cover
Center is fixing with changeover portion to be connected;Changeover portion is steel construction, and diameter and blower fan tower barrel lower end diameter quite and pass through flange and wind
Machine tower is connected;Changeover portion and cylindrical foundation top cover arrange 4-8 the radial equally distributed ribs of hoop;Ribs is steel
Structure, is made as unified entirety in advance with changeover portion and cylindrical foundation top cover;Ribs outer lower end arranges 4-8 auxiliary pile ring set;
Auxiliary pile ring set is steel construction, is welded and fixed with ribs;Auxiliary pile, auxiliary pile is squeezed into after cylindrical foundation structure is sunk
Number is identical with auxiliary pile ring set number;Auxiliary pile squeezes into sea bed by auxiliary pile ring set respectively;Auxiliary pile is steel construction, with auxiliary
Help the fixing connection of anchor ear set.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610618677.0A CN106049524A (en) | 2016-07-27 | 2016-07-27 | Composite cylinder type foundation with auxiliary piles added in later period |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610618677.0A CN106049524A (en) | 2016-07-27 | 2016-07-27 | Composite cylinder type foundation with auxiliary piles added in later period |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106049524A true CN106049524A (en) | 2016-10-26 |
Family
ID=57196094
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610618677.0A Pending CN106049524A (en) | 2016-07-27 | 2016-07-27 | Composite cylinder type foundation with auxiliary piles added in later period |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106049524A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108104151A (en) * | 2017-12-20 | 2018-06-01 | 中国能源建设集团广东省电力设计研究院有限公司 | Jacket changeover portion |
CN109403368A (en) * | 2018-09-06 | 2019-03-01 | 李敬 | A kind of load basis and its design method |
CN110397071A (en) * | 2019-07-01 | 2019-11-01 | 天津大学 | A kind of conduit stake and barrel combined offshore wind power foundation |
CN110593298A (en) * | 2019-09-30 | 2019-12-20 | 天津大学 | Composite foundation for improving bearing performance of cylindrical foundation by using auxiliary piles and construction method thereof |
CN110847215A (en) * | 2019-12-18 | 2020-02-28 | 长江勘测规划设计研究有限责任公司 | Full-paved long and short pile composite foundation-barrel offshore wind power foundation and construction method |
CN114482114A (en) * | 2022-01-28 | 2022-05-13 | 天津大学 | Spiral pile-cylinder composite foundation structure based on fixed support and construction method thereof |
CN114517489A (en) * | 2022-01-18 | 2022-05-20 | 天津大学 | Offshore wind power barrel type foundation structure with pile pier |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20120074047A (en) * | 2010-12-27 | 2012-07-05 | 재단법인 포항산업과학연구원 | Suction pile for rapid construction |
CN104234069A (en) * | 2013-06-07 | 2014-12-24 | 刘红静 | Offshore wind turbine foundation with plug-in honeycomb structure chassis |
CN204370469U (en) * | 2014-12-24 | 2015-06-03 | 广州华申建设工程管理有限公司 | A kind of drilled pile long leg jacket offshore wind turbine foundation |
CN205857228U (en) * | 2016-07-27 | 2017-01-04 | 天津大学前沿技术研究院有限公司 | A kind of later stage adds the compound bucket foundation of auxiliary pile |
-
2016
- 2016-07-27 CN CN201610618677.0A patent/CN106049524A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20120074047A (en) * | 2010-12-27 | 2012-07-05 | 재단법인 포항산업과학연구원 | Suction pile for rapid construction |
CN104234069A (en) * | 2013-06-07 | 2014-12-24 | 刘红静 | Offshore wind turbine foundation with plug-in honeycomb structure chassis |
CN204370469U (en) * | 2014-12-24 | 2015-06-03 | 广州华申建设工程管理有限公司 | A kind of drilled pile long leg jacket offshore wind turbine foundation |
CN205857228U (en) * | 2016-07-27 | 2017-01-04 | 天津大学前沿技术研究院有限公司 | A kind of later stage adds the compound bucket foundation of auxiliary pile |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108104151A (en) * | 2017-12-20 | 2018-06-01 | 中国能源建设集团广东省电力设计研究院有限公司 | Jacket changeover portion |
CN108104151B (en) * | 2017-12-20 | 2020-12-15 | 中国能源建设集团广东省电力设计研究院有限公司 | Jacket transition section |
CN109403368A (en) * | 2018-09-06 | 2019-03-01 | 李敬 | A kind of load basis and its design method |
CN110397071A (en) * | 2019-07-01 | 2019-11-01 | 天津大学 | A kind of conduit stake and barrel combined offshore wind power foundation |
CN110593298A (en) * | 2019-09-30 | 2019-12-20 | 天津大学 | Composite foundation for improving bearing performance of cylindrical foundation by using auxiliary piles and construction method thereof |
CN110847215A (en) * | 2019-12-18 | 2020-02-28 | 长江勘测规划设计研究有限责任公司 | Full-paved long and short pile composite foundation-barrel offshore wind power foundation and construction method |
CN114517489A (en) * | 2022-01-18 | 2022-05-20 | 天津大学 | Offshore wind power barrel type foundation structure with pile pier |
CN114482114A (en) * | 2022-01-28 | 2022-05-13 | 天津大学 | Spiral pile-cylinder composite foundation structure based on fixed support and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106049524A (en) | Composite cylinder type foundation with auxiliary piles added in later period | |
CN205857228U (en) | A kind of later stage adds the compound bucket foundation of auxiliary pile | |
EP2837554A1 (en) | Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method | |
CN103225315A (en) | Offshore wind power foundation consisting of single pile, cylindrical foundations and anchor cable | |
KR101318111B1 (en) | Substructure of hybrid offshore wind turbine with multi-pile for reducing wave forces, and constructing method for the same | |
CN109339092A (en) | A kind of more sleeve joint reinforcement formula cylinder-shaped foundation structures of offshore wind turbine and its construction method | |
CN202689022U (en) | Offshore wind power truss single pile base structure with negative pressure tube | |
CN110055995A (en) | A kind of offshore power generator foundation structure and its construction method | |
CN103362113B (en) | Offshore wind farm, bridge and marine works local buoyancy ocean platform and construction method | |
CN110453714B (en) | Offshore wind power jacket gravity type cylindrical foundation structure and construction method thereof | |
CN102995655A (en) | Cylindrical structure and pile group combined type offshore wind turbine foundation | |
CN102400469A (en) | Secant pile drum type foundation and construction method thereof | |
CN103255752B (en) | Support the buoyant support fixed platform of offshore wind turbine, marine works | |
CN103590415A (en) | Prefabricated bearing platform suitable for large-diameter tubular column foundation of sea bridge and construction method thereof | |
CN110155264B (en) | Marine fan composite cylinder foundation towing structure and towing method | |
KR101665979B1 (en) | Concrete base of offshore wind substructure and the construction method therefor | |
CN110453715A (en) | Can gas-liquid displacement combined type cartridge type jacket frame foundation structure and its construction method | |
CN210766855U (en) | Multi-barrel combined foundation system connected with offshore wind power box-shaped beams | |
CN116161175A (en) | Anchoring system for shared foundation | |
CN202247927U (en) | Barrel-shaped foundation with occlusive piles | |
CN102606408B (en) | Wind generation set at sea | |
CN204491567U (en) | Pre-manufactured steel pile tube wind power generation platform | |
CN105155573A (en) | Offshore wind turbine barrel-in-barrel foundation | |
CN110670618A (en) | Prefabricated gravity type suction caisson foundation with wing plates | |
CN212561601U (en) | Wind power foundation newly built and expanded on soft foundation shallow covering layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20161026 |