CN106025848A CN201610316574.9A CN201610316574A CN106025848A CN 106025848 A CN106025848 A CN 106025848A CN 201610316574 A CN201610316574 A CN 201610316574A CN 106025848 A CN106025848 A CN 106025848A
Authority
CN
China
Prior art keywords
power distribution
fire
distribution cabinet
pipe
switchgear house
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610316574.9A
Other languages
Chinese (zh)
Other versions
CN106025848B (en
Inventor
过森君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO HI-TECH S-VIEW TECHNOLOGY Co Ltd
Original Assignee
NINGBO HI-TECH S-VIEW TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO HI-TECH S-VIEW TECHNOLOGY Co Ltd filed Critical NINGBO HI-TECH S-VIEW TECHNOLOGY Co Ltd
Priority to CN201610316574.9A priority Critical patent/CN106025848B/en
Priority to CN201810148245.7A priority patent/CN108365550B/en
Publication of CN106025848A publication Critical patent/CN106025848A/en
Application granted granted Critical
Publication of CN106025848B publication Critical patent/CN106025848B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/56Cooling; Ventilation
    • H02B1/565Cooling; Ventilation for cabinets
    • AHUMAN NECESSITIES
    • A62LIFE-SAVING; FIRE-FIGHTING
    • A62CFIRE-FIGHTING
    • A62C3/00Fire prevention, containment or extinguishing specially adapted for particular objects or places
    • A62C3/16Fire prevention, containment or extinguishing specially adapted for particular objects or places in electrical installations, e.g. cableways
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B17/00Fire alarms; Alarms responsive to explosion
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B17/00Fire alarms; Alarms responsive to explosion
    • G08B17/06Electric actuation of the alarm, e.g. using a thermally-operated switch

Landscapes

  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Fire Alarms (AREA)
  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

The invention discloses a power distribution room with fire alarms. The power distribution room is internally equipped with power distribution cabinets. Each power distribution cabinet is internally equipped with a temperature probe and a temperature controller, and each power distribution cabinet has a coiler room and an air inlet room. For each power distribution cabinet, the sidewall opposite to the coiler room is equipped with a fan which works under control of the temperature controller, the coiler room is equipped with a cooling coiler inside, and the lower part of the power distribution cabinet is equipped with a main cooling water supply pipe and a cooling water return pipe. Of the cooling coiler in each power distribution cabinet, the inlet is connected with the cooling water supply pipe through a connecting pipe, and the outlet is connected with the cooling water return pipe through the connecting pipe. The ceiling in each power distribution cabinet is equipped with a fire alarm. The invention further discloses a monitoring method of the power distribution room with fire alarms. The advantages are as follows: the temperature inside the power distribution cabinets can be better reduced, the rate of temperature increase inside the power distribution cabinets can be controlled, fire is prevented, and normal work of the electrical components inside the power distribution cabinets and the safety of the power system are ensured.

Description

A kind of switchgear house with fire-alarm and monitoring method thereof
Technical field
The present invention relates to the monitoring system of a kind of switchgear house, a kind of switchgear house with fire-alarm and It monitors method.
Background technology
Switchgear house is an important ring of power system, is provided with power distribution cabinet in switchgear house, and power distribution cabinet is used for placing various electricity Electric elements needed for power distribution, electric elements the most easily generate heat, and once temperature is too high easy affects electric elements Work, thus bring loss to power system.
The immediate prior art of present patent application is: " one has and follows for the patent of Patent No. 201320095798.3 The distribution box of ring cooling water ", and the patent one geothermal constant temperature circulator of Patent No. 201320599913.0;But above-mentioned two Individual patent formula is relatively simple, and cooling-down effect is poor.
On the other hand, the switchgear house being positioned at field does not has any effective measures for fire yet.
Owing to there is above-mentioned technical problem in prior art, impact uses, it is therefore necessary to improve.
Summary of the invention
It is an object of the invention to: the switchgear house with fire-alarm of a kind of good cooling effect is provided.
The solution of the present invention is: a kind of switchgear house with fire-alarm, is provided with power distribution cabinet in described switchgear house, described Power distribution cabinet is be independently disposed in switchgear house multiple;Described power distribution cabinet has two sidewalls in left and right and one piece of base plate, described Being provided with temperature probe and temperature controller in power distribution cabinet, described temperature probe signal inputs to this temperature controller, it is characterized in that A coil pipe room being made up of vertical clapboard and one of them sidewall and one it is provided with by diaphragm plate and base plate in described power distribution cabinet The inlet air plenum constituted;That sidewall on opposite, described coil pipe room is provided with by the fan of described temperature controller control work;Institute The air inlet stating coil pipe room is positioned at described inlet air plenum;It is provided with cooling coil in coil pipe indoor;Described vertical clapboard is provided with excessive Portal or overflow groove;Described base plate is provided with blast pipe;It is provided with total cooling water in power distribution cabinet bottom and for pipe and cools down water return pipe, Supply to be provided with feed pump on pipe at cooling water;Cooling coil in each power distribution cabinet, its import is all passed through connecting tube and is connected cooling water For pipe, its outlet is all passed through connecting tube and is connected cooling water return pipe, and described connecting tube is through the blast pipe bottom corresponding power distribution cabinet;Institute State cooling water to communicate with cooling water supply side respectively for pipe and cooling water return pipe;Described distribution indoor ceiling is provided with fire Alarm.
Wherein, fire-alarm is prior art, and it utilizes detection smog to determine whether that fire occurs, and once detects Can report to the police to when having smog.
Further scheme is as follows:
It is one or more that described fire-alarm is disposed in distribution indoor ceiling;
Being additionally provided with fire extinguishing sprayer in described switchgear house, described fire extinguishing sprayer communicates for pipe with described cooling water with described water pipe, Described water pipe is provided with valve;
Described cooling water supply side is a underground water well, and described feed pump is in the immersible pump in underground water well;
The bottom, ground of described switchgear house is provided with groove;Described groove top is provided with cover plate, with each power distribution cabinet phase on cover plate To position be provided with the opening passed for blast pipe;Described cooling water is positioned at this groove for pipe and cooling water return pipe;
Described cooling coil has multiple parallel horizontal segment;Between the horizontal segment and sidewall of described cooling coil and level It is designed with coil pipe fixed block between section and vertical clapboard;The region that on described vertical clapboard, each cooling coil horizontal segment is corresponding sets The trapezoidal portion that oriented side is protruded;Described cooling coil is positioned at described trapezoidal portion, on the upper end face that described trapezoidal portion tilts It is provided with described overfolw hole or overflows groove;
The present invention have also been devised a kind of monitoring method of switchgear house with fire-alarm described above, and it uses each distribution Cabinet arranges temperature controller and controls fan for cooling, and uses water pump controller control feed pump to make cooling water circulation, it is characterized in that Described temperature controller controls process and includes:
As T >=TH, start fan, until stopping fan during T < TL;
As T < TH, start intensification monitoring mode;
Described intensification monitoring mode includes:
Measure V, as V < VS;SA resets the upper level program that simultaneously returns;
As V >=VS, starting fan, fan stops after continuing the TA time, measures V the most again, as V < VS, returns upper level Program, is otherwise labeled as 1 by SA;
Wherein: T is the real time temperature in power distribution cabinet;
TH is preset value, represents power distribution cabinet warning high temperature;
TL is preset value, represents power distribution cabinet safe temperature;
V is the programming rate in power distribution cabinet;
VS is preset value, represents the safe programming rate of power distribution cabinet;
And fire-alarm is set in distribution indoor ceiling and carries out fire hazard monitoring.
The further scheme of monitoring method of the switchgear house with fire-alarm of the present invention is:
Described water pump controller controls feed pump in periodically working;
The control process of feed pump is included by described water pump controller: when the power distribution cabinet quantity that SA is 1 accounts for a definite proportion of sum During example, start feed pump work and duration T B, SA be 1 power distribution cabinet quantity account for sum ratio the highest, the TB time is the longest;
Fire-alarm is associated with the master on off of switchgear house, when fire-alarm detects fire, and whole switchgear house power-off, Water pump is opened and is utilized the fire extinguishing sprayer fire extinguishing being arranged in switchgear house.
When feed pump works, described fan also works;
The present invention compared with prior art provides the benefit that: each power distribution cabinet is provided with coil pipe room, is provided with cold in coil pipe indoor But coil pipe, coil pipe room air can be lowered the temperature by cooling coil, can reduce the temperature in power distribution cabinet after these air spilling Degree, can slow down the programming rate of power distribution cabinet simultaneously;On the other hand, hot-air in power distribution cabinet can be extracted out by fan work, and Enter the cooling through cooling coil of the air in power distribution cabinet, be therefore easier to reduce the temperature in power distribution cabinet;Furthermore, by always Cooling water for pipe and cooling water return pipe can lower the temperature by power distribution cabinet all of to switchgear house, structure is the compactest, cost Low, such scheme good cooling effect, it can be ensured that the normal work of electric elements in power distribution cabinet, it is ensured that the work peace of power system Entirely;Furthermore, distribution indoor ceiling is provided with fire-alarm, when fire-alarm is detected with disaster hidden-trouble, permissible Reporting to the police, to point out people to carry out fire-fighting, more valuable is that cooling water supplies the cooling water of pipe can become the water source of fire extinguishing, enters One step improves safety.
Accompanying drawing explanation
Accompanying drawing is for providing a further understanding of the present invention, and constitutes a part for description, with the reality of the present invention Execute example together for explaining the present invention, be not intended that limitation of the present invention.In the accompanying drawings:
Fig. 1 is the structural representation that embodiment 1 has the switchgear house of fire-alarm;
Fig. 2 is the structural representation of the single power distribution cabinet of embodiment 1;
Fig. 3 is the enlarged drawing in Fig. 2 at A;
Fig. 4 is the structural representation of embodiment 2 coil pipe room;
Fig. 5 is the flow chart of method described in embodiment 3;
Fig. 6 is that embodiment 3 heats up the flow chart of monitoring mode;
Fig. 7 is the flow chart of method described in embodiment 5;
Fig. 8 is the structural representation that embodiment 6 has the switchgear house of fire-alarm;
Fig. 9 is the structural representation of embodiment 7;
Mark parts in figure: switchgear house 1, power distribution cabinet 2, sidewall 3, base plate 4, temperature probe 5, temperature controller 6, vertical clapboard 7, dish Pipe room 8, inlet air plenum 9, fan 10, cooling coil 11, overfolw hole 12, overflow groove 13, blast pipe 14, cooling water for pipe 15, cooling Water return pipe 16, feed pump 17, diaphragm plate 18, connecting tube 19, cooling water supply side 20, groove 21, cover plate 22, opening 23, level Section 24, coil pipe fixed block 25, trapezoidal portion 26, upper end face 27, air inlet 28, fire-alarm 29, fire extinguishing sprayer 30, water pipe 31, Valve 32, air channel 33, fan housing 34, hoisting frame 35, check valve 36.
Detailed description of the invention
The invention will be further described to combine accompanying drawing below by embodiment.
Embodiment 1:
As shown in Figure 1, 2, 3, the switchgear house with fire-alarm described by the present embodiment, it is provided with in described switchgear house 1 and joins Electricity cabinet 2, described power distribution cabinet 2 is multiple for be independently disposed in switchgear house 1;Described power distribution cabinet 2 has two sidewalls 3 and in left and right Block base plate 4, is provided with temperature probe 5 and temperature controller 6 in described power distribution cabinet 2, and described temperature probe 5 signal inputs to this temperature Degree controller 6, is provided with a coil pipe room 8 being made up of vertical clapboard 7 and one of them sidewall 3 in it is characterized in that described power distribution cabinet 2 And an inlet air plenum 9 being made up of diaphragm plate 18 and base plate 4;It should be understood that the front of coil pipe room 8 and inlet air plenum 9 can To arrange panel sealing, it is also possible to be not provided with and rely on the cabinet door of power distribution cabinet 2 to seal;That side on opposite, described coil pipe room 8 Wall 3 is provided with the fan 10 being controlled work by described temperature controller 6;The air inlet 28 of described coil pipe room 8 is positioned at described air intake In room 9;Cooling coil 11 it is provided with in coil pipe room 8;Described vertical clapboard 7 is provided with overfolw hole 12;Described base plate 4 be provided with into Airduct 14;It is provided with total cooling water in power distribution cabinet 2 bottom and for pipe 15 and cools down water return pipe 16, supply to be provided with confession on pipe 15 at cooling water Water pump 17;Cooling coil 11 in each power distribution cabinet 2, its import is all passed through connecting tube 19 and is connected cooling water confession pipe 15, its outlet All passing through connecting tube 19 and connect cooling water return pipe 16, described connecting tube 19 is through the blast pipe 14 bottom corresponding power distribution cabinet 2;Described Cooling water communicates with cooling water supply side 20 respectively for pipe 15 and cooling water return pipe 16, and wherein, cooling water supply side 20 can be Water recirculator water cooled down by coolant, but water recirculator structure is relatively complicated, due to electric power Being positioned at field in the case of switchgear house is a lot, do not possess the condition of configuration water recirculator, therefore preferred plan is described cold But water supply side 20 is a underground water well, the immersible pump that described feed pump 17 is in underground water well;Employing temperature is relatively low Well water, as cooling water, on the one hand can ensure that cooling-down effect, is on the other hand also easy to the water intaking that digs a well in the wild, it is simple to implements;Institute In the switchgear house 1 stated, ceiling is provided with fire-alarm 29, and described fire-alarm 29 is disposed on ceiling in switchgear house 1 On one (centrally located), described fire-alarm 29 can also be equally distributed multiple;Described fire-alarm 29 The preferential HZBJ101 type fire-alarm using sky, high and new technology industrial development zone, Ningbo to regard Photoelectric Co., Ltd.'s production, it is possible to purchase from the market, Such as the GSM01 type electrical fire monitor of the red Energy Science Co., Ltd in the north, Shanghai, existing patented technology also can be used, such as fire Calamity alarm (200910163698.8), fire-alarm (200910168090.4).
Wherein, can set leg bottom power distribution cabinet 2, cooling water walks ground for pipe and cooling water return pipe, it is preferred that described The bottom, ground of switchgear house 1 is provided with groove 21;Described groove 21 top is provided with cover plate 22, with each power distribution cabinet 2 on cover plate 22 Relative position is provided with the opening 23 passed for blast pipe 14;Described cooling water is positioned at this groove for pipe 15 and cooling water return pipe 16 In 21;Such structure, after cooling water circulation, the temperature of groove 21 is relatively low, and the air of groove 21 is to enter each distribution The source of cabinet 2, source temperature is low, more preferable to the cooling-down effect of power distribution cabinet 2;
This power distribution cabinet, after cooling water circulation, the temperature in coil pipe room 8 reduces, and in coil pipe room 8, Cryogenic air can be by overflowing Power distribution cabinet is lowered the temperature by 12 spillings of portalling, and on the one hand can reduce temperature, on the other hand can reduce programming rate, make distribution Being in a slower poised state of heating up in cabinet, coil pipe room 8, inlet air plenum 9, groove 21 communicate together simultaneously, temperature all than Relatively low;Making fan 10 work once distribution in-cabinet temperature is too high, the cold wind in coil pipe room 8 is outwards taken out by overfolw hole 12 Going out, inlet air plenum 9, the Cryogenic air of groove 21 are drawn into cooling in coil pipe room 8, and so extract out is hot blast, and be pumped into is cold wind, Thus it is effectively improved radiating effect.Still further aspect, this power distribution cabinet, when fire-alarm 29 is detected with disaster hidden-trouble, Can report to the police, to point out people to carry out fire-fighting.
Embodiment 2:
As shown in Figure 4, the switchgear house with fire-alarm described by the present embodiment, described cooling coil 11 has multiple flat The horizontal segment 24 of row;Between the horizontal segment 24 and sidewall 3 of described cooling coil 11 and between horizontal segment 24 and vertical clapboard 7 all It is provided with coil pipe fixed block 25;On described vertical clapboard 7, the region of each cooling coil 11 horizontal segment 24 correspondence is designed with to side The trapezoidal portion 26 protruded;Described cooling coil 11 is positioned at described trapezoidal portion 26, the upper end face 27 tilted in described trapezoidal portion 26 It is provided with described spilling groove 13.
Such structure, when fan 10 works, when the cold wind in coil pipe room 8 is outwards extracted out by overflowing groove 13, fills into Wind regime have with the horizontal segment of the horizontal segment 24 of cooling coil 11 and sufficiently contact, so that it is guaranteed that heat transfer effect;Because air must Three passages formed by cambered surface and plane that must pass through cooling coil 11 left and right sides and obliquely downward could be from overflowing groove 13 Go out.
In the present embodiment, preferably more arriving top, to overflow groove 13 width the biggest, and more arriving bottom, to overflow groove 13 width the least, this Sample, when fan 10 works, can ensure that all spilling grooves 13 can uniformly extract cold wind out, it is to avoid the only spilling groove 13 of bottom exists Air-out, and make the cooling coil 11 on top lose efficacy.
Embodiment 3
The present embodiment describes the monitoring method of the switchgear house described in a kind of example 1 above with fire-alarm, and it uses often Individual power distribution cabinet 2 arranges temperature controller 6 and controls fan 10 and lower the temperature, and uses water pump controller to control feed pump 17 to make cooling water follow Ring, is characterized in that described temperature controller 6 controls process and includes:
As T >=TH, start fan 10, until stopping fan 10 during T < TL;
As T < TH, start intensification monitoring mode;
Described intensification monitoring mode includes:
Measure V, as V < VS;SA resets the upper level program that simultaneously returns;
As V >=VS, starting fan 10, fan 10 stops after continuing the TA time, measures V the most again, as V < VS, in return One-level program, is otherwise labeled as 1 by SA;
Wherein: T is the real time temperature in power distribution cabinet 2;
TH is preset value, represents power distribution cabinet 2 and reports to the police high temperature;
TL is preset value, represents power distribution cabinet 2 safe temperature;
V is the programming rate in power distribution cabinet 2;
VS is preset value, represents the safe programming rate of power distribution cabinet 2;
Measuring V and refer to the programming rate of units of measurement time, intensification total amount, divided by the time, can be to wait for 1-2 minute then entering Row survey calculation;
And fire-alarm 29 is set on ceiling in switchgear house 1 and carries out fire hazard monitoring;
Described water pump controller controls feed pump 17 in periodically working;As started once per hour, continue 5 minutes every time;
The principle of this temperature monitoring method is:
Feed pump 17 is in periodically working, and cooling coil 11 is periodically lowered the temperature and (can is to work per hour once, hold every time Continuous five minutes), coil pipe room 8 temperature is relatively low, relies on the spilling of cold air to carry out the temperature in power distribution cabinet and programming rate Control;
When fortuitous event T is higher as T >=TH, fan 10 works until temperature in power distribution cabinet 2 being lowered, and drops to safety Value TL;And when T < TH, start intensification monitoring mode, when the programming rate in power distribution cabinet 2 more than it is considered that the most suitable Safe programming rate VS time, also start fan 10 and work and lower the temperature, because there being the cold air of coil pipe room 8 normally a little while Spilling, the programming rate in power distribution cabinet should not exceed safety range, beyond explanation coil pipe room 8 cooling efficiency low, Or certain element heating is bigger, for preventing too fast intensification, startup fan 10, with cooling, so makes whole power distribution cabinet all be unlikely to Temperature is too high.Feed pump 17 is the most frequent in periodically working, and the cooling efficiency of coil pipe room 8 just can be guaranteed, but energy consumption meeting Strengthen.
Temperature controller 6 control method can refer to Fig. 5, Fig. 6 and performs, but is not limited to the pattern of Fig. 5, Fig. 6.
In this method, the value of SA can associate the warning lamp outside power distribution cabinet, when quick heating is not got off by fan control Can warn with bright light.
Embodiment 4
The present embodiment describes the monitoring method of the switchgear house described in a kind of example 1 above with fire-alarm, with embodiment 3 Except for the difference that water pump controller is the most intelligent, and it is not merely to control feed pump 17 in periodically working, but described water The control process of feed pump 17 is included by pump controller:
When power distribution cabinet 2 quantity that SA is 1 accounts for the certain proportion of sum (such as 1/3rd), start feed pump 17 and work and hold Continuous time TB, SA be 1 power distribution cabinet 2 quantity to account for the ratio of sum the highest, the TB time is the longest;
When the power distribution cabinet 2 quantity accounting that SA is 1 is higher, illustrate that the cooling coil 11 in these power distribution cabinets 2 faces inefficacy, therefore Needing to start feed pump 17, when power distribution cabinet 2 quantity that SA is 1, to account for the ratio of sum the highest, and illustrate in the most power distribution cabinets 2 is cold But coil pipe 11 faces inefficacy, the working time of feed pump 17 to be lengthened, to guarantee the cooling coil 11 in all power distribution cabinets 2 Cooling-down effect;
May is that when accounting reach three/for the moment, TB is 5 minutes;When accounting reach two/for the moment, TB is 7 minutes;When accounting for Than when reaching 3/4ths, TB is 10 minutes;When accounting reaches for the moment, and TB is 15 minutes.
Embodiment 5
The present embodiment describes the monitoring method of the switchgear house described in a kind of example 1 above with fire-alarm, with embodiment 3 Except for the difference that, when feed pump 17 works, described fan 10 also works;
In embodiment 3, during feed pump 17, fan 10 realizes work or stopping according to original control method;The present embodiment Be different from is when feed pump 17 works, the also and then work of described fan 10, during because feed pump 17 works, and cooling coil The good cooling effect of 11, wind regime is colder, and fan 10 is regardless of the temperature in oneself power distribution cabinet and programming rate also and then work, permissible In making power distribution cabinet, state of temperature is safer.
The improvement of the present embodiment method is also suitably for embodiment 4, and control flow can refer to Fig. 7.
Method described in embodiment 3-5 is equally applicable to the structure of embodiment 2.
Embodiment 6
As shown in Figure 8, the switchgear house with fire-alarm described by the present embodiment, as different from Example 1: fire report Alert device 29 is associated with the master on off of switchgear house 1, is additionally provided with fire extinguishing sprayer 30 in described switchgear house 1, and described fire extinguishing sprayer 30 leads to Cross described water pipe 31 to communicate for pipe 15 with described cooling water, described water pipe 31 is provided with valve 32;
The technology that fire-alarm 29 is associated with the master on off of switchgear house 1 belongs to prior art, can be master on off be one By the catalyst of total brake controller control work, can be by the way of wired or wireless when fire-alarm 29 detects the condition of a fire It is sent to total brake controller, total brake controller control contactor power-off;Can also be that fire-alarm 29 is logical when the condition of a fire being detected Cross and be wirelessly sent to remote control center, remote control center control contactor work;Concrete mode belongs to existing, And can be multiple, do not describe in detail.
The monitoring method of this switchgear house with fire-alarm, when fire-alarm 29 detects fire, whole Switchgear house 1 power-off, water pump 17 is opened and is utilized the fire extinguishing sprayer 30 being arranged in switchgear house 1 to put out a fire.The improvement of this monitoring method It is equally applicable in embodiment 3-5.
In the wild, when fire-alarm is detected with disaster hidden-trouble, underground water well provides the water source of fire extinguishing, makes fire extinguishing Becoming possibility, if if not having the underground water well that this scheme is had by oneself, water intaking, the most very because of difficulty, more cannot be put out a fire, therefore originally Embodiment safety is more preferable.
Embodiment 7
As it is shown in figure 9, the switchgear house with fire-alarm described by the present embodiment, as different from Example 1: described in join Electricity is provided with, in room 1, the air channel 33 that an end is positioned at outside switchgear house 1, and bottom, air channel 33 is provided with multiple fan housing 34 communicated therewith, Fan housing 34 is provided with the check valve 36 that can only dry from bottom to top, and the effect of check valve 36 is to make wind can only blow to outdoor, described The air inlet of fan housing 34 is relative with the fan 10 of each power distribution cabinet 2.Wherein, air channel 33 can be by sheet iron or corrosion resistant plate system Become, it addition, air channel 33 can be fixed on ceiling by hoisting frame 35.Hoisting frame 35 is generally used for ceiling-mounted cable testing bridge On.
Advantage of this embodiment is that: switchgear house 1 can be exhausted directly to through fan housing 34, air channel 33 from the hot blast of fan 10 blowout Outward, such heat is discharged to outside, and in can preventing switchgear house 1, temperature rises.
Finally it is noted that the foregoing is only the preferred embodiments of the present invention, it is not limited to the present invention, Although being described in detail the present invention with reference to previous embodiment, for a person skilled in the art, it still may be used So that the technical scheme described in foregoing embodiments to be modified, or wherein portion of techniques feature is carried out equivalent. All within the spirit and principles in the present invention, any modification, equivalent substitution and improvement etc. made, should be included in the present invention's Within protection domain.

Claims (10)

1. having a switchgear house for fire-alarm, be provided with power distribution cabinet (2) in described switchgear house (1), described power distribution cabinet (2) is Be independently disposed in switchgear house (1) is multiple;Described power distribution cabinet (2) has two sidewalls (3) in left and right and one piece of base plate (4), Being provided with temperature probe (5) and temperature controller (6) in described power distribution cabinet (2), described temperature probe (5) signal inputs to this temperature Controller (6), is provided with a dish being made up of vertical clapboard (7) and one of them sidewall (3) in it is characterized in that described power distribution cabinet (2) Pipe room (8) and an inlet air plenum (9) being made up of diaphragm plate (18) and base plate (4);That side on described coil pipe room (8) opposite Wall (3) is provided with the fan (10) being controlled work by described temperature controller (6);Air inlet (28) position of described coil pipe room (8) In described inlet air plenum (9);Cooling coil (11) it is provided with in coil pipe room (8);Described vertical clapboard (7) is provided with overfolw hole (12) or overflow groove (13);Described base plate (4) is provided with blast pipe (14);It is provided with total cooling water to supply in power distribution cabinet (2) bottom Pipe (15) and cooling water return pipe (16), at cooling water for being provided with feed pump (17) on pipe (15);Cooling in each power distribution cabinet (2) Coil pipe (11), its import all pass through connecting tube (19) connect cooling water for pipe (15), its outlet all pass through connecting tube (19) connection Cooling water return pipe (16), described connecting tube (19) is through the blast pipe (14) of corresponding power distribution cabinet (2) bottom;Described cooling water is for pipe (15) communicate with cooling water supply side (20) respectively with cooling water return pipe (16);Described switchgear house (1) interior ceiling is provided with Fire-alarm (29).
The switchgear house with fire-alarm the most according to claim 1, is characterized in that described fire-alarm (29) is Be arranged on switchgear house (1) interior ceiling is one or more.
The switchgear house with fire-alarm the most according to claim 1, is additionally provided with in it is characterized in that described switchgear house (1) Fire extinguishing sprayer (30), described fire extinguishing sprayer (30) communicates, at described water for pipe (15) with described cooling water with described water pipe (31) Pipe (31) is provided with valve (32).
The switchgear house with fire-alarm the most according to claim 1, is characterized in that described cooling water supply side (20) it is a underground water well, the immersible pump that described feed pump (17) is in underground water well.
The switchgear house with fire-alarm the most according to claim 1, is characterized in that the subsurface of described switchgear house (1) Portion is provided with groove (21);Described groove (21) top is provided with cover plate (22), and cover plate (22) is upper relative with each power distribution cabinet (2) Position is provided with the opening (23) passed for blast pipe (14);Described cooling water is positioned at this groove for pipe (15) and cooling water return pipe (16) In ditch (21).
The switchgear house with fire-alarm the most as claimed in any of claims 1 to 5, is characterized in that described cooling Coil pipe (11) has multiple parallel horizontal segment (24);Between the horizontal segment (24) and sidewall (3) of described cooling coil (11) And between horizontal segment (24) and vertical clapboard (7), it is designed with coil pipe fixed block (25);Described vertical clapboard (7) each cooler pan upper The region that pipe (11) horizontal segment (24) is corresponding is designed with the trapezoidal portion (26) protruded to side;Described cooling coil (11) is positioned at institute State in trapezoidal portion (26), the upper end face (27) that described trapezoidal portion (26) tilts is provided with described overfolw hole (12) or overflows groove (13).
7. having a monitoring method for the switchgear house of fire-alarm as claimed in claim 1, it uses each power distribution cabinet (2) Temperature controller (6) is set and controls fan (10) cooling, and use water pump controller control feed pump (17) to make cooling water circulation, It is characterized in that described temperature controller (6) control process includes:
As T >=TH, start fan (10), until stopping fan (10) during T < TL;
As T < TH, start intensification monitoring mode;
Described intensification monitoring mode includes:
Measure V, as V < VS;SA resets the upper level program that simultaneously returns;
As V >=VS, starting fan (10), fan (10) stops after continuing the TA time, measures V the most again, as V < VS, returns Return upper level program, otherwise SA is labeled as 1;
Wherein: T is the real time temperature in power distribution cabinet (2);
TH is preset value, represents power distribution cabinet (2) warning high temperature;
TL is preset value, represents power distribution cabinet (2) safe temperature;
V is the programming rate in power distribution cabinet (2);
VS is preset value, represents power distribution cabinet (2) safe programming rate;
And fire-alarm (29) is set on ceiling in switchgear house (1) and carries out fire hazard monitoring.
The monitoring method of the switchgear house with fire-alarm the most according to claim 7, is characterized in that described water pump control Device processed controls feed pump (17) in periodically working.
The monitoring method of the switchgear house with fire-alarm the most according to claim 7, is characterized in that described water pump control The control process of feed pump (17) is included by device processed: when power distribution cabinet (2) quantity that SA is 1 accounts for the certain proportion of sum, open Dynamic feed pump (17) work duration T B, SA be 1 power distribution cabinet (2) quantity to account for the ratio of sum the highest, the TB time is the longest.
The monitoring method of the switchgear house with fire-alarm the most according to claim 7, is characterized in that fire-alarm (29) master on off with switchgear house (1) is associated, when fire-alarm (29) detects fire, and whole switchgear house (1) power-off, Fire extinguishing sprayer (30) fire extinguishing that utilization is arranged in switchgear house (1) opened by water pump (17).
CN201610316574.9A 2016-05-13 2016-05-13 A kind of switchgear house and its monitoring method with fire-alarm Expired - Fee Related CN106025848B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610316574.9A CN106025848B (en) 2016-05-13 2016-05-13 A kind of switchgear house and its monitoring method with fire-alarm
CN201810148245.7A CN108365550B (en) 2016-05-13 2016-05-13 Power distribution room with fire alarm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610316574.9A CN106025848B (en) 2016-05-13 2016-05-13 A kind of switchgear house and its monitoring method with fire-alarm

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201810148245.7A Division CN108365550B (en) 2016-05-13 2016-05-13 Power distribution room with fire alarm

Publications (2)

Publication Number Publication Date
CN106025848A true CN106025848A (en) 2016-10-12
CN106025848B CN106025848B (en) 2018-04-06

Family

ID=57099400

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610316574.9A Expired - Fee Related CN106025848B (en) 2016-05-13 2016-05-13 A kind of switchgear house and its monitoring method with fire-alarm
CN201810148245.7A Active CN108365550B (en) 2016-05-13 2016-05-13 Power distribution room with fire alarm

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201810148245.7A Active CN108365550B (en) 2016-05-13 2016-05-13 Power distribution room with fire alarm

Country Status (1)

Country Link
CN (2) CN106025848B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106530565A (en) * 2017-01-10 2017-03-22 杭州超视科技有限公司 Security protection alarm system and method
CN108491013A (en) * 2018-05-21 2018-09-04 江西省计算技术研究所 A kind of henhouse monitor control system and method
CN108491014A (en) * 2018-05-21 2018-09-04 江西省计算技术研究所 A kind of pig house monitor control system and method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112821227B (en) * 2021-04-01 2022-11-01 中海油能源发展装备技术有限公司 Safe waterproof switch board
CN117039685B (en) * 2023-08-10 2024-02-20 申恒电力设备有限公司 Energy-saving box-type transformer substation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204598553U (en) * 2015-04-30 2015-08-26 唐佳 A kind of water-cooled cabinet and the water-cooling system containing this rack
CN204720834U (en) * 2015-04-30 2015-10-21 国家电网公司 A kind of box type transformer station shell
CN105188306A (en) * 2015-07-28 2015-12-23 皖西学院 Electrical cabinet cooling and drying device
CN205005412U (en) * 2015-08-12 2016-01-27 哈尔滨商业大学 Computer room server rack cooling system
CN205232621U (en) * 2015-11-26 2016-05-11 丹阳蓝思信息技术有限公司 Novel communication heat dissipation cabinet

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200443588Y1 (en) * 2008-08-18 2009-02-26 강은진 Electric appliance container system with the functions of waterproof and heat radiation for being laid underground
JP2010102418A (en) * 2008-10-22 2010-05-06 Nohmi Bosai Ltd Fire alarm
JP4828591B2 (en) * 2008-10-22 2011-11-30 能美防災株式会社 Fire alarm
CN203119351U (en) * 2013-03-04 2013-08-07 宁波恒升电气有限公司 Distribution box with circulating cooling water
CN103488211B (en) * 2013-08-06 2015-09-23 奇瑞汽车股份有限公司 A kind of intelligent machine box temperature control system and method
CN203722094U (en) * 2013-09-27 2014-07-16 国家电网公司 Ground temperature constant temperature circulator
CN203536761U (en) * 2014-01-06 2014-04-09 重庆众恒电器有限公司 Switch cabinet
CN204992343U (en) * 2015-07-30 2016-01-20 山东航天正和电子有限公司 Prepackage type transformer station
CN205051209U (en) * 2015-11-01 2016-02-24 塔里木大学 Portable outdoor switch board

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204598553U (en) * 2015-04-30 2015-08-26 唐佳 A kind of water-cooled cabinet and the water-cooling system containing this rack
CN204720834U (en) * 2015-04-30 2015-10-21 国家电网公司 A kind of box type transformer station shell
CN105188306A (en) * 2015-07-28 2015-12-23 皖西学院 Electrical cabinet cooling and drying device
CN205005412U (en) * 2015-08-12 2016-01-27 哈尔滨商业大学 Computer room server rack cooling system
CN205232621U (en) * 2015-11-26 2016-05-11 丹阳蓝思信息技术有限公司 Novel communication heat dissipation cabinet

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106530565A (en) * 2017-01-10 2017-03-22 杭州超视科技有限公司 Security protection alarm system and method
CN108491013A (en) * 2018-05-21 2018-09-04 江西省计算技术研究所 A kind of henhouse monitor control system and method
CN108491014A (en) * 2018-05-21 2018-09-04 江西省计算技术研究所 A kind of pig house monitor control system and method

Also Published As

Publication number Publication date
CN108365550B (en) 2020-08-14
CN108365550A (en) 2018-08-03
CN106025848B (en) 2018-04-06

Similar Documents

Publication Publication Date Title
CN106025848A (en) Power distribution room with fire alarms and monitoring method thereof
CN105914615A (en) Switching room monitoring alarm system
CN206075473U (en) A kind of intelligent building fire protection device
CN110575641B (en) Fire control and safety control system integrated with indoor intelligent fire-fighting product
CN209198973U (en) Switchgear house intelligent monitor system and switchgear house remote monitoring system
CN109164857A (en) Switchgear house intelligent monitor system and switchgear house remote monitoring system
CN208387156U (en) A kind of radiator of communication base station
CN110891403A (en) Electrical cabinet heat dissipation control system and method based on Internet of things
CN103153032A (en) Integrated temperature control balanced cabinet
CN109173130A (en) A kind of pipe gallery fire management system
CN108744362A (en) A kind of fire fighting device engineering wireless real-time monitoring intelligent alarm and fire extinguishing system
CN111999050A (en) Fire-fighting equipment safety detection system and use method
CN205942319U (en) Building monitoring system
CN205942828U (en) Control system of entrance guard
CN203219676U (en) Integrated temperature control balance cabinet
CN205804737U (en) Indoor intelligent Integral ceiling
CN205942829U (en) Energy -conserving access control system
CN204067945U (en) Outdoor energy-saving power distribution cabinet
CN106200727A (en) A kind of electric power IT-room environment monitoring system
CN205881619U (en) Radiator for transformer
CN206619261U (en) A kind of alarm controller for combustible gas base
CN207069330U (en) A kind of outdoor power distribution cabinet with detection device
CN201753984U (en) Heater for aging chamber
CN206058836U (en) A kind of electronic anti-theft doorplate
CN205860274U (en) A kind of central air-conditioning runs safety convenience instrument

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180406

CF01 Termination of patent right due to non-payment of annual fee