CN106014424B - A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel - Google Patents

A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel Download PDF

Info

Publication number
CN106014424B
CN106014424B CN201610477867.5A CN201610477867A CN106014424B CN 106014424 B CN106014424 B CN 106014424B CN 201610477867 A CN201610477867 A CN 201610477867A CN 106014424 B CN106014424 B CN 106014424B
Authority
CN
China
Prior art keywords
branch
arch
shallow
explosion
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610477867.5A
Other languages
Chinese (zh)
Other versions
CN106014424A (en
Inventor
李文
胡锡鹏
孙鹤明
吴洪旭
张波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority to CN201610477867.5A priority Critical patent/CN106014424B/en
Publication of CN106014424A publication Critical patent/CN106014424A/en
Application granted granted Critical
Publication of CN106014424B publication Critical patent/CN106014424B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • F42D1/08Tamping methods; Methods for loading boreholes with explosives; Apparatus therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel belongs to tunnel excavation construction field, it is higher to be applied to rock strength, but the above overburden layer of ground interface is the backfill containing a large amount of building wastes, soft or hard variation protrusion.Earth's surface road is major urban arterial highway, and with expressway exit drop-over, the magnitude of traffic flow is big, the multiple industrial products factory in periphery, therefore vehicle of passing by one's way is mostly heavy truck.This method is with small vibration compared with conventional blasting method method, sedimentation degree of control is high;Reduce backbreak backfill and the workload for owing digging repairing compared with conventional mechanical digging mode, face profile is regular, high using whole safely controllable degree.The utilization of this method is not only able to satisfy construction safety, but also improves production efficiency.This method is formed after repeatedly improving in engineering practice, is shallow buried covered excavation to condition, has the tunnel excavation construction of high, the upper overburden layer features as poor geologic condition of stringent vibration control requirement, formation strength to have universality.

Description

A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel
Technical field
The invention is related to wearing the shallow-depth-excavation tunnel Excavation Blasting of major urban arterial highway under in shallow overlying strata stratum.
Background technique
When carrying out shallow-depth-excavation tunnel construction in city, mostly underpass with arterial street, and overburden layer is more on tunnel For backfill, and soil property is poor, at the same it is tight to requirement of settlement control, concussion of blasting susceptibility is high, more than earth's surface vehicle etc. Problem to guarantee construction safety, construction quality and construction speed, and has invented and has worn the shallow overlying strata of major urban arterial highway under one kind is suitable for Bored tunnel.
Summary of the invention
A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel, it is characterised in that:
(1) conduit advance support is performed in vault before tunnel excavation, conduit is covered within the scope of 135 ° of vault, is spaced a Pin Arch performs one layer;Tunnel is divided into five parts ABCDE, A be on lead left stage portion;B leads right stage portion on being;C is led under being Left stage portion;D leads right stage portion under being;E is the remaining core soil in advance part of lower guiding center;
(2) A branch is excavated;It is first bored with water mill and partially bores a collar aperture on A contouring line, then use hydraulic breaking hammer A branch is excavated, it is lateral that the interim arch of arch, interval and bottom on the outside of A branch are installed in time after excavating 0.5 meter of drilling depth Support, then sets A branch lock foot anchoring stock and system anchor bolt, and last m esh-hanging sprayed concrete completes the supporting of A branch;
(3) B branch is excavated;After A branch drilling depth reaches 3m, drilling avris outside B branch contour line is bored using water mill, then B branch is excavated with hydraulic breaking hammer, drilling depth performs outer arc section arch after reaching 0.5m, and set lock foot anchoring stock and System anchor bolt;After the completion of anchor bolt construction, B branch cross-brace arch is performed, and connects it with A branch cross-brace arch It connects;
(4) C, D branch are excavated;After drilling depth 1.5m is excavated in the portion B, is bored using water mill and drilled along the portion C, D outline line, so The upper interim interval arch in island and cross-brace arch are removed afterwards;After interim interval arch and lateral arch, arranged in C, D branch Borehole, implements explosion, every separate explosion drilling depth 1m at filling explosive;Explosion dregs is cleared up after the completion of explosion, and is handled and owed with quartering hammer It digs, two Pin C of installation, D are distributed side arch, and set lock foot anchoring stock and system anchor bolt;
(5) E branch is excavated;After C, D branch drilling depth reach 1.5m, borehole, dress are set on the E branch that core is reserved Then medicine, explosion, one meter of every separate explosion drilling depth clear up explosion dregs, perform inverted arch;
(6) one cycle is completed after the completion of inverted arch performs, then repeats above-mentioned process, is designed until A branch reaches After mileage, other branches gradually follow up arrival.
Stand in great numbers, in the Construction of City Tunnel engineering in the busy area of road traffic in reply formation strength height, earth's surface building, has Effect ground, which reduces blasting vibration caused by digging process and construction settlement, guarantee construction quality and safely and smoothly completes construction, appoints It is engaged in most important.In contrast to conventional tunnel blasting excavation technique, have following advantage using this construction method:
(1) blasting vibration caused by digging process is small;
(2) reduce backfill of backbreaking compared with conventional mechanical digging mode with the deficient workload for digging repairing, face profile is regular;
(3) construction safety and construction speed degree of controllability are high;
(4) under the shallow overlying strata ground environment in city shallow-depth-excavation tunnel construction in application effect it is good;
(5) operation rate of machinery is improved.
Detailed description of the invention
Five excavation branch schematic diagrames of Fig. 1.
A, five excavation branches of B, C, D, E-;1-Φ, 108 advance support pipe canopy;2-Φ, 100 water mill bores bore position.
Fig. 2 excavates top view
3- tunnel excavation direction;4- measurement and positioning water mill bores;5- face;6- scaffold;7- water mill drilling machine;8- drilling is anti- Power frame;9- arch support system;10- scaffold diagonal brace.
Fig. 3 excavates direction schematic diagram
Left stage portion is led on A-;Right stage portion is led on B-;Left side base tunnel portion is led under C-;Right side base tunnel portion is led under D-;E- is pre- Stay Core Soil part.
Fig. 4 is schematic diagram during daily construction finishes
Left stage portion is led on A-;Right stage portion is led on B-;C, left and right sides base tunnel portion is led under D-;E- remaining core soil in advance portion Point.
Schematic diagram after the completion of Fig. 5 is excavated
Left stage portion is led on A-;Right stage portion is led on B-;C, left and right sides base tunnel portion is led under D-;E- remaining core soil in advance portion Point;Arch on the outside of 11- section;12- lock foot anchoring stock;13- is temporarily horizontally-supported;The bottom 14- inverted arch;The interim interval support of 15-; 16- system anchor bolt.
Specific embodiment
This technique specific embodiment is as follows:
(1) advanced tubule being performed in vault before tunnel excavation and carrying out advance support, ductule length is 3 meters, diameter 42mm, 0.3 meter of circumferential spacing, horizontal by 3~5 ° of elevations angle, ductule is covered within the scope of 135 ° of vault incident direction, One layer is performed every a Pin arch.
(2) A branch is excavated.It is first bored with water mill and partially bores a collar aperture on A contouring line, then use hydraulic breaking hammer A branch is excavated, it is lateral that the interim arch of arch, interval and bottom on the outside of A branch are installed in time after excavating 0.5 meter of drilling depth Support (supporting base end portion must clear up dross and pad tight), then sets A branch lock foot anchoring stock and system anchor bolt, last linked network injection Concrete completes the supporting of A branch.
(3) B branch is excavated.After A branch drilling depth reaches 3m, drilling avris outside B branch contour line is bored using water mill, then B branch is excavated with hydraulic breaking hammer, drilling depth performs outer arc section arch after reaching 0.5m, and set lock foot anchoring stock and System anchor bolt.After the completion of anchor bolt construction, B branch cross-brace arch is performed, and connects it with A branch cross-brace arch It connects.
(4) C, D branch are excavated.After drilling depth 1.5m is excavated in the portion B, is bored using water mill and drilled along the portion C, D outline line, so The upper interim interval arch in island and cross-brace arch are removed afterwards.After interim interval arch and lateral arch, arranged in C, D branch Borehole, implements explosion, every separate explosion drilling depth 1m at filling explosive (more to drill, lacking powder charge as principle).It is cleared up after the completion of explosion quick-fried Break soil, and handled with quartering hammer and owe to dig, two Pin C of installation, D are distributed side arch, and set lock foot anchoring stock and system anchor bolt.
(5) E branch is excavated.After C, D branch drilling depth reach 1.5m, borehole, dress are set on the E branch that core is reserved Then medicine (to use presplit blasting theory, more drillings, few powder charge as principle), explosion, one meter of every separate explosion drilling depth clear up explosion Dregs performs inverted arch.
(6) one cycle is completed after the completion of inverted arch performs, then repeats above-mentioned process, is designed until A branch reaches After mileage, other branches gradually follow up arrival.

Claims (1)

1. a kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel, it is characterised in that:
(1) conduit advance support is performed in vault before tunnel excavation, conduit is covered within the scope of 135 ° of vault, is spaced a Pin arch Perform one layer;Tunnel is divided into five parts ABCDE, A be on lead left stage portion;B leads right stage portion on being;C leads left under being Rank portion;D leads right stage portion under being;E is the remaining core soil in advance part of lower guiding center;
(2) A branch is excavated;It is first bored with water mill along A contouring line top branch borehole, then using hydraulic breaking hammer to A branch It is excavated, the interim arch of arch, interval and bottom cross-brace on the outside of A branch is installed in time after excavating 0.5 meter of drilling depth, connect Set A branch lock foot anchoring stock and system anchor bolt, last m esh-hanging sprayed concrete completes the supporting of A branch;
(3) B branch is excavated;After A branch drilling depth reaches 3m, the sidetracking hole outside B branch contour line is bored using water mill, then use liquid Pressure quartering hammer excavates B branch, and drilling depth performs outer arc section arch after reaching 0.5m, and sets lock foot anchoring stock and system Anchor pole;After the completion of anchor bolt construction, B branch cross-brace arch is performed, and connect it with A branch cross-brace arch;
(4) C, D branch are excavated;After drilling depth 1.5m is excavated in the portion B, is bored using water mill and drilled along the portion C, D outline line, then torn open Except above leading interim interval arch and cross-brace arch;After interim installation interval arch and lateral arch, arranged in C, D branch Borehole, implements explosion, every separate explosion drilling depth 1m at filling explosive;Explosion dregs is cleared up after the completion of explosion, and is handled and owed with quartering hammer It digs, two Pin C, D branch side arch is installed, and set lock foot anchoring stock and system anchor bolt;
(5) E branch is excavated;After C, D branch drilling depth reach 1.5m, core reserve E branch above set borehole, powder charge, Then explosion, one meter of every separate explosion drilling depth clear up explosion dregs, perform inverted arch;
(6) one cycle is completed after the completion of inverted arch performs, then repeats above-mentioned process, until A branch reaches design mileage Afterwards, other branches gradually follow up arrival.
CN201610477867.5A 2016-06-27 2016-06-27 A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel Expired - Fee Related CN106014424B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610477867.5A CN106014424B (en) 2016-06-27 2016-06-27 A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610477867.5A CN106014424B (en) 2016-06-27 2016-06-27 A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel

Publications (2)

Publication Number Publication Date
CN106014424A CN106014424A (en) 2016-10-12
CN106014424B true CN106014424B (en) 2019-03-05

Family

ID=57084552

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610477867.5A Expired - Fee Related CN106014424B (en) 2016-06-27 2016-06-27 A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel

Country Status (1)

Country Link
CN (1) CN106014424B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035733B (en) * 2017-11-01 2019-10-25 中铁四局集团有限公司 A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination
CN107676099A (en) * 2017-11-22 2018-02-09 北京市政建设集团有限责任公司 One kind expands foundation tunnel partial excavation construction method
CN111140237B (en) * 2020-01-08 2021-01-15 合肥市轨道交通集团有限公司 Underground excavation method for subway tunnel tunneling
CN111380428A (en) * 2020-04-24 2020-07-07 中铁五局集团有限公司 Medium pilot tunnel advanced blasting construction method based on small-spacing cavern group three-tunnel separation section
CN113338953A (en) * 2021-07-16 2021-09-03 中铁二十局集团有限公司 Construction method for extra-large section tunnel with turnout line led out from railway tunnel
CN115046444A (en) * 2022-06-30 2022-09-13 广东中人爆破工程有限公司 Lower excavation blasting construction method for double-side-wall pit guiding method of tunnel with soft top and hard bottom
CN115949411A (en) * 2023-02-24 2023-04-11 中国十七冶集团有限公司 Construction method of large-section weak surrounding rock tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102220868A (en) * 2011-05-23 2011-10-19 重庆中环建设有限公司 Urban shallow buried large-section tunnel five-step excavating method
CN102287195A (en) * 2011-05-13 2011-12-21 中铁四局集团第二工程有限公司 Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN104612714A (en) * 2014-12-31 2015-05-13 上海市机械施工集团有限公司 Mining method tunnel construction method and structure through which tunnel can penetrate through surrounding rock poor in geological condition
CN104879131A (en) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 Large-span tunnel excavation method for upper soft and lower hard compound strata
CN104564085B (en) * 2014-12-23 2016-06-01 中铁十一局集团第五工程有限公司 Large section tunnel excavation comprehensive construction method under an ultra shallow underground layering part of city

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001295579A (en) * 2000-04-18 2001-10-26 Taisei Corp Method for construction of tunnel having shallow earth covering

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287195A (en) * 2011-05-13 2011-12-21 中铁四局集团第二工程有限公司 Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN102220868A (en) * 2011-05-23 2011-10-19 重庆中环建设有限公司 Urban shallow buried large-section tunnel five-step excavating method
CN104564085B (en) * 2014-12-23 2016-06-01 中铁十一局集团第五工程有限公司 Large section tunnel excavation comprehensive construction method under an ultra shallow underground layering part of city
CN104612714A (en) * 2014-12-31 2015-05-13 上海市机械施工集团有限公司 Mining method tunnel construction method and structure through which tunnel can penetrate through surrounding rock poor in geological condition
CN104879131A (en) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 Large-span tunnel excavation method for upper soft and lower hard compound strata

Also Published As

Publication number Publication date
CN106014424A (en) 2016-10-12

Similar Documents

Publication Publication Date Title
CN106014424B (en) A kind of blasting digging method for shallow overlying strata shallow-depth-excavation tunnel
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN103321644B (en) The method of tunneling is combined in machinery and controlled blasting
CN104790978B (en) The tunnel ring-shaped base tunnel construction method of small interval crossings on different level
CN108756894B (en) Tunnel micro- three step top Core Soil construction
CN101603431B (en) Method for reinforcing outburst-prone coal seam cross-cut coal uncovering
CN106246201A (en) The excavation in tunnel and karst cave treatment method when small-sized solution cavity is positioned at tunneling surrounding
CN103206219A (en) Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method
CN105781571A (en) Construction method for soft rock deformation tunnel lining support dismantling-replacing arch
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN110409461A (en) A kind of base pit stand construction based on assembled large-diameter tubular pile
CN103244133B (en) The milling of coal measure strata tunnel is dug and is combined construction with explosion
CN107975383B (en) Underground chamber tee T intersection excavation supporting construction method
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN106121659B (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one kind
CN109113757A (en) Tunnel cross mouth rapid constructing method
CN109578007B (en) Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and drainage and construction method
CN102704480B (en) Construction method for processing ultra-thick quicksand layer of pile foundation by using front-end vibration steel casing
CN110284885A (en) Shield inspection-pit construction method
CN107605509A (en) Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN107165641B (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN104141500A (en) Hardened sand gravel stratum cavern construction method
CN108222951A (en) Pass through fine sand layer tunnel portal weak surrounding rock section constructing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190305

Termination date: 20190627

CF01 Termination of patent right due to non-payment of annual fee