CN106003386A - Combined die - Google Patents

Combined die Download PDF

Info

Publication number
CN106003386A
CN106003386A CN201610617783.7A CN201610617783A CN106003386A CN 106003386 A CN106003386 A CN 106003386A CN 201610617783 A CN201610617783 A CN 201610617783A CN 106003386 A CN106003386 A CN 106003386A
Authority
CN
China
Prior art keywords
die
mould
horizontal support
adjusting means
going out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610617783.7A
Other languages
Chinese (zh)
Inventor
俞大有
张景明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Mingsheng Drawin Technology Investment Co Ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201610617783.7A priority Critical patent/CN106003386A/en
Publication of CN106003386A publication Critical patent/CN106003386A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0029Moulds or moulding surfaces not covered by B28B7/0058 - B28B7/36 and B28B7/40 - B28B7/465, e.g. moulds assembled from several parts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • B28B7/0011Mould seals
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • B28B7/0014Fastening means for mould parts, e.g. for attaching mould walls on mould tables; Mould clamps
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • B28B7/0014Fastening means for mould parts, e.g. for attaching mould walls on mould tables; Mould clamps
    • B28B7/002Fastening means for mould parts, e.g. for attaching mould walls on mould tables; Mould clamps using magnets

Abstract

The invention belongs to the technical field of production of building prefabricated parts, and discloses a combined die which comprises a bottom die and a blocking edge die. The blocking edge die is formed by splicing combined die plates. Each combined die plate comprises a fixing frame and a rid plate, wherein the fixing frame comprises a fixing device, a vertical adjusting device and a horizontal supporting adjusting device, the bottom of the vertical adjusting device is connected to the fixing device, one end of the horizontal supporting adjusting device is connected with the vertical adjusting device, the other end of the horizontal supporting adjusting device is connected with the rid plate, the horizontal supporting adjusting device and the vertical adjusting device are connected in a vertically and horizontally adjustable mode, and the rid plate is provided with rid holes. During die assembling, the horizontal supporting devices are adjusted to assemble the rib plates to the corresponding bottom die; after preparation of a prefabricated part is finished, during die removal, the horizontal supporting adjusting devices are adjusted to enable the rib plates to get close to the fixing devices, so that the rib plates are disengaged from the concrete face of the prefabricated part, disassembly of the die is promoted, and die removal efficiency is improved.

Description

A kind of assembling die
Technical field
The invention belongs to architectural prefab production technical field, be specifically related to a kind of assembling die.
Background technology
In assembled architecture prefabricated components production process, precast concrete cast needs to reserve to stretch out steel often Muscle, therefore need to arrange in die station to be easy to the limit mould of muscle.During production, make according to the size of prefabricated components Go out muscle limit mould or punching block, then it is placed on fixed station mould and produces.During the demoulding, by people's work point The connector of each assembly in mould, then by artificial or boom hoisting, mould is removed.In prior art, Complicated for preparing the mould often structure of muscle prefabricated component, not only assemble loaded down with trivial details, and be difficult to the demoulding, give peace Dress and production bring bigger inconvenience, increase extensive work amount.
In sum, offer a kind of simple in construction, assembling die easy to use are provided badly.
Summary of the invention
It is an object of the invention to provide a kind of simple in construction, assembling die easy to use.
Above-mentioned purpose is to be achieved through the following technical solutions: a kind of assembling die, including bed die and rib mould, Described rib mould is assembled by multiple gang forms, and described gang form includes fixed mount and goes out gusset, its In, described fixed mount includes fixing device, vertical adjustment device and horizontal support adjusting means, described vertically Connecting on the securing means bottom adjusting means, one end of described horizontal support adjusting means fills with vertical adjustment Put connection, the other end with go out link of boards, between described horizontal support adjusting means and vertical adjustment device be Vertical and the two-way adjustable connection of horizontal direction, described in go out to be provided with out on gusset muscle hole.The present invention is used for preparing Go out muscle prefabricated component, during use, go out gusset and be fixed on bed die by fixed mount, go out gusset and go out reinforced concrete Face contacts, and stretches out reinforcing bar and passes out muscle hole, by vertical adjustment device adjustable horizontal supporting and regulating device Height, indirectly regulation horizontal support adjusting means is in the fixed position gone out on gusset, horizontal support regulation dress Putting and be relatively fixed device horizontal direction and move for adjusting gusset, horizontal direction described herein refers to vertically In the direction of the place plane going out gusset, gusset can be used closer or far from fixing device, be arranged such, Time die-filling, gusset will be gone out by regulation horizontal support adjusting means and be assemblied on corresponding bed die, when prefabricated component system After completing, during the demoulding, make to show that gusset is close to fixing device by regulation horizontal support adjusting means, Gusset can be used depart from prefabricated component concrete surface, facilitate the dismounting of the present invention, improve demoulding efficiency.
Further, described fixing device is magnetic force fixed bin, and described magnetic force fixed bin is provided with magnetic force assembly.Adopt With magnetic force fixed bin as fixing device, compare traditional limit mould holder, eliminate support and rib, letter Change structure, reduced manufacturing cost, can avoid damaging rigid platfor simultaneously, extend the life-span of mould, subtract The input of few mould, therefore play an important role to reducing prefabricated components cost.
Further, described horizontal support adjusting means is connected by connection arrangement with vertical adjustment device, institute Stating horizontal support adjusting means can move horizontally by connection arrangement relatively, described vertical adjustment device can be the most double Vertically movable to connector.Horizontal direction described herein also refers to be perpendicular to out the place plane of gusset Direction.It is arranged such, by the two-way company of connection arrangement horizontal support adjusting means Yu vertical adjustment device Connect.
Further, described connection arrangement includes vertically arranged fastening ring set and horizontally disposed threaded adjusting Hole, described vertical adjustment device is montant, and described montant interts described fastening ring set, and described horizontal support is adjusted Regulating device is screw rod, threaded adjusting bore described in described screw rod cross-under.Being arranged such, fastening ring set can be the most perpendicular To adjusting means vertically movable, it is fixed on vertical adjustment device by securing member simultaneously;Level is propped up Support adjusting means is screw rod and passes described threaded adjusting bore, so, it can be made relative by rotary screw Connection arrangement moves, it is achieved the horizontal adjustment that horizontal support adjusting means is above-mentioned.
Further, described connection arrangement is provided with vertical threaded adjusting bore and horizontal threaded adjusting bore, described perpendicular It is screw rod, the two the difference vertical threaded adjusting bore of cross-under and water to adjusting means and horizontal support adjusting means Flat thread adjustment hole.So, described vertical adjustment device and horizontal support adjusting means are screw rod, pass through Rotary screw can make it move relative to connection arrangement, it is achieved vertical adjustment device and horizontal support regulation dress The regulatory function put.
Further, described horizontal support adjusting means is connected by fixture and connecting plate with going out gusset, described Fixture is arranged on out the gusset side near fixed mount, and described connecting plate is connected to horizontal support adjusting means Near going out one end of gusset, described connecting plate and fixture are fixed and are connected.It is arranged such, water can be effectively increased Flat supporting and regulating device is at the lifting surface area gone out on gusset, it is simple to horizontal support adjusting means can to go out gusset Adjust.
Further, described fixture and connecting plate are connected by T-bolt, and described fixture is provided with T-slot, Described connecting plate is provided with bar shaped notch, and the screw head of described T-bolt inserts institute after described bar shaped notch State in T-slot.It is arranged such, it is achieved being reliably connected of fixture and connecting plate.
Further, one end that described horizontal support adjusting means is connected with connecting plate is provided with bulb, described connection Plate is provided with spherical inner chamber, and described bulb is placed in described spherical inner chamber.It is arranged such, horizontal support regulation dress Putting and the flexible connection mode of connecting plate employing gimbal type, horizontal support adjusting means realizes vertically movable Time, connecting plate is without movement.
Further, described in go out muscle hole is provided with sealing strip, described sealing strip be provided with cross-under seam..It is arranged such, Stretch out reinforcing bar and pass out muscle hole, and stitch by extruding and cross cross-under, play preferable sealing effectiveness.
Further, the hole wall going out muscle hole described in is provided with cannelure, in the described sealing strip described cannelure of embedding; Being arranged such, sealing strip is reliably connected with going out the formation of muscle hole, and easy to connect, it is to avoid reinforcing bar passes sealing member Time sealing strip from going out muscle hole to come off, affect sealing effectiveness.
Further, described sealing strip is prepared by flexible material, described sealing strip with go out muscle hole interference fit.As This is arranged, and simple installation, sealing effectiveness is preferable;Described sealing strip can be rubber or silica gel.
Further, the outer wall going out the side that gusset contacts with prefabricated component described in is provided with flexible material.So Arrange, the cohesive force gusset with concrete can be reduced, both can protect mould, and be also beneficial to form removal.Institute The flexible material stated both with go out the rubber that gusset combines with spraying method, it is also possible to be by bolt even The polyurethane sheet connect, should also be as including that other can realize above-mentioned technical purpose technical scheme certainly.
Further, described assembling die also includes door opening template and/or window opening template.It is arranged such, it is simple to system Door opening and/or window opening is formed during standby prefabricated panel.
Further, described door opening template and window opening template at least include first gear cheek board and second gear cheek board, It is characterized in that, described first gear cheek board is positioned at described second gear cheek board top, described first rib mould Plate and described second gear cheek board connect into entirety by connecting fixing device, and described connection fixing device is positioned at First gear cheek board and the same side of second gear cheek board.
Further, described connection fixing device includes fixed mechanism, bindiny mechanism and locking part, described fixing Mechanism is fixing with bindiny mechanism to be connected, and first gear cheek board and second gear cheek board are fixed on by described locking part In bindiny mechanism.Described fixed mechanism is connected fixing with bed die, plays the fixing and effect of location, it is ensured that pre- There is not relative movement in component production process centre rib template processed and bed die, the connection machine being connected with fixed mechanism Structure connects the rib template being disposed adjacent by locking part so that it is forms entirety, and is fixed in fixing machine On structure.
Further, described fixed mechanism is magnetic force fixed bin, and described magnetic force fixed bin is provided with magnetic force assembly.Adopt With magnetic force fixed bin as fixed mechanism, compare traditional limit mould holder, eliminate support and rib, letter Change structure, reduced manufacturing cost, can avoid damaging rigid platfor simultaneously, extend the life-span of mould, subtract The input of few mould, therefore play an important role to reducing prefabricated components cost.
Further, described first gear cheek board and second gear cheek board set with the described side being connected fixing device Having at least one installation locating slot, described bindiny mechanism includes vertically arranged connecting plate and horizontally disposed fixing Plate, described fixed plate is connected to described magnetic force fixed bin top, and described connecting plate is provided with adjustment hole, described Adjustment hole described in locking part cross-under also stretches in described installation locating slot.
Further, described fixed plate is provided with draw-in groove, and described magnetic force fixed bin top is provided with shackle member, described Shackle member snaps in described draw-in groove.Being arranged such, fixed plate is connected with magnetic force fixed bin and dismantles all easy, Easily operated, and connect reliable.
Further, described locking part includes adjusting rod, connecting rod and locking block, and described connecting rod one end connects described Adjusting rod, the other end is connected with described locking block, and the thickness at described locking block incision position is solid less than locking block Determining the thickness at position, described connecting rod is socketed with elastomer block, described adjusting rod is close in the side of described elastomer block. Regulation or rotation adjusting rod, drive locking block to rotate, and the contact site of locking block and rib template is by switch-in part Position redirect to fixed position, owing to the thickness of locking block fixed position is more than the thickness at locking block incision position, Locking block coordinates to be fixed on rib template in elastomer block and connects in fixing device.This locking part simple in construction, Easy to operate, it is only necessary to rotate adjusting rod and the most realize the fastening of rib template, work progress can be greatly improved In the efficiency of die-filling and form removal.
Certainly, the thickness of locking block fixed position can be by cutting with the thickness relationship at locking block incision position Position is the most thickening to fixed position, is i.e. provided with certain radian near the side connecting fixing device, by turning Dynamic adjusting rod makes it be gradually increased with the thickness of the contact site of described rib template.
Further, described locking block is eccentric.It is arranged such, owing to locking block is eccentric, rotates and adjust A downward power can be applied to rib template so that rib template while the rotation of pole band movable eccentric wheel It is close to bed die or makes mutually to be close between rib template, so, concrete slurry can be prevented along the level of template Assembling seam overflows.
Further, described locking block is square block, described square block and described connecting rod eccentric setting.In like manner, Due to square block eccentric setting, it can apply a downward power to rib template while rotating so that gear Cheek board is close to bed die or makes mutually to be close between rib template, so, concrete slurry can be prevented along template Level assembling seam in overflow.Certainly, described square block can be cuboid, due to the length on its at least both sides Unequal, therefore in the case of not eccentric setting, also can reach the effect above, simply need rib mould to be fixed On T-slot eccentric setting.
Further, the corner of described assembling die is provided with corner fixing device.It is arranged such, beneficially group Fixing of the corner of mould, can prevent corner spillage simultaneously.
Accompanying drawing explanation
The accompanying drawing of the part constituting the present invention is used for providing a further understanding of the present invention, and the present invention shows Meaning property embodiment and explanation thereof are used for explaining the present invention, are not intended that inappropriate limitation of the present invention.
Fig. 1 and Fig. 2 is respectively the structural representation of a kind of assembling die involved by one embodiment of the present invention.
Fig. 3 is the structural representation of a kind of gang form involved by one embodiment of the present invention;
Fig. 4 is the front view of a kind of gang form of the present invention involved in Fig. 3;
Fig. 5 is the top view of a kind of gang form of the present invention involved in Fig. 3;
Fig. 6 is the right view of a kind of gang form of the present invention involved in Fig. 3;
Fig. 7 is the structural representation of a kind of window opening template of the present invention involved in Fig. 1;
Fig. 8 is the end view of a kind of window opening template of the present invention involved in Fig. 7;
Fig. 9 and Figure 10 is respectively in Fig. 6 the structural representation of the different visual angles of involved a kind of locking part;
Figure 11 is the front schematic view of a kind of locking block of the present invention involved in Fig. 9;
Figure 12 is the right view of a kind of locking block of the present invention involved in Fig. 9;
Figure 13 is the structural representation of a kind of gang form involved by another embodiment of the present invention.
In figure:
1 fixing device 2 vertical adjustment device 3 horizontal support adjusting means 4 goes out gusset
5 go out muscle hole 6 connection arrangement 7 fastens ring set 8 securing member
9 threaded adjusting bore 10 fixture 11 connecting plate 12T type bolts
13T type groove 14 bar shaped notch 15 bed die 16 window opening template
17 first gear cheek board 18 second gear cheek board 19 magnetic force fixed bins 20 install locating slot
21 connecting plate 22 fixed plate 23 locking part 24 shackle member
25 draw-in groove 26 adjusting rod 27 connecting rod 28 locking blocks
29 incision fixed position 31 elastomer block 32 corner, position 30 fixing devices
33 stretch out reinforcing bar
Detailed description of the invention
Describing the present invention below in conjunction with the accompanying drawings, the description of this part is only exemplary and explanatory, Protection scope of the present invention should there be is not any restriction effect.Additionally, those skilled in the art are according to herein The description of part, can carry out respective combination to the feature in embodiment in presents and in different embodiment.
The embodiment of the present invention is as follows, with reference to Fig. 1~3, and a kind of assembling die, including bed die 15 and rib mould, Described rib mould is assembled by multiple gang forms, and described gang form includes fixed mount and goes out gusset 4, Wherein, described fixed mount includes fixing device 1, vertical adjustment device 2 and horizontal support adjusting means 3, institute State and be connected to bottom vertical adjustment device 2 in fixing device 1, one end of described horizontal support adjusting means 3 Being connected with vertical adjustment device 2, the other end is connected with going out gusset 4, described horizontal support adjusting means 3 with Be vertical between vertical adjustment device 2 and the two-way adjustable connection of horizontal direction, described in go out and be provided with on gusset 4 Go out muscle hole 5.The present invention is used for preparing muscle prefabricated component, during use, goes out gusset 4 and is fixed on by fixed mount On bed die 15, go out gusset 4 and go out reinforced concrete face and contact, stretching out reinforcing bar 33 and pass out muscle hole 5, logical Cross the height of vertical adjustment device 2 adjustable horizontal supporting and regulating device 3, indirectly the regulation of regulation horizontal support Device 3 is in the fixed position gone out on gusset 4, and it is relative that horizontal support adjusting means 3 is used for adjusting gusset 4 Fixing device 1 horizontal direction moves, and horizontal direction described herein refers to that the place being perpendicular to out gusset 4 is put down The direction in face, can use gusset 4 closer or far from fixing device 1, be arranged such, time die-filling, pass through Regulation horizontal support adjusting means 3 will go out gusset 4 and be assemblied on corresponding bed die 15, when prepared by prefabricated component After, during the demoulding, make to show that gusset 4 is close to fixing device 1 by regulation horizontal support adjusting means 3, Gusset 4 can be used depart from prefabricated component concrete surface, facilitate the dismounting of the present invention, improve demoulding efficiency.
When prefabricated components are prefabricated panel, when the surrounding of prefabricated panel is both needed to out muscle, described assembling die Can be only assembled by four gang forms, i.e. it is distributed at the four edges treating prefabricated prefabricated panel;When So, described assembling die can be that the gang form more than four is assembled, and each gang form assembly is grown up It is separately positioned on after bar shaped and treats at the four edges of prefabricated prefabricated panel.Such as Fig. 1, if prefabricated component only needs one During while go out muscle, this rib mould can be assembled by one or more gang form gang forms.Need Being noted that in assembling die that the number of gang form is the most, Mosaic face is the most, and the risk of spillage is the biggest, And the number of gang form is the fewest, mould is the heaviest, the most bad management.
In another embodiment of the present invention, such as Fig. 3, described fixing device 1 is magnetic force fixed bin 19, described magnetic Power fixed bin 19 is provided with magnetic force assembly.Use magnetic force fixed bin 19 as fixing rotary device, compare traditional Limit mould holder, eliminates support and rib, simplifies structure, reduces manufacturing cost, can avoid simultaneously Damage rigid platfor, extend the life-span of mould, reduce the input of mould, therefore have reducing prefabricated components cost Important function.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 3 and Fig. 4, described level Supporting and regulating device 3 is connected by connection arrangement 6 with vertical adjustment device 2, and described horizontal support regulates Device 3 can move horizontally by connection arrangement 6 relatively, and described vertical adjustment device 2 can connection arrangement relatively 6 is vertically movable.Horizontal direction described herein also refers to be perpendicular to out the direction of the place plane of gusset 4. It is arranged such, by the two-way company of connection arrangement 6 horizontal support adjusting means 3 with vertical adjustment device 2 Connect.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 3 and Fig. 5, described two-way Connector 6 includes vertically arranged fastening ring set 7 and horizontally disposed threaded adjusting bore 9, described vertical tune Regulating device 2 is montant, and described montant interts described fastening ring set 7, and described horizontal support adjusting means 3 is Screw rod, threaded adjusting bore 9 described in described screw rod cross-under.Being arranged such, fastening ring set 7 can the most vertically be adjusted Regulating device 2, vertically movable, is fixed on vertical adjustment device 2 by securing member 8 simultaneously;Level Supporting and regulating device 3 is screw rod and passes described threaded adjusting bore 9, so, can be made by rotary screw It moves relative to connection arrangement 6, it is achieved the horizontal adjustment that horizontal support adjusting means 3 is above-mentioned.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Figure 13, described connection arrangement 6 are provided with vertical threaded adjusting bore and horizontal threaded adjusting bore, described vertical adjustment device 2 and horizontal support adjusts Regulating device 3 is screw rod, the two the difference vertical threaded adjusting bore of cross-under and horizontal threaded adjusting bore.So, Described vertical adjustment device 2 and horizontal support adjusting means 3 are screw rod, can make it by rotary screw Move relative to connection arrangement 6, it is achieved the regulation merit of vertical adjustment device 2 and horizontal support adjusting means 3 Energy.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 3 and Fig. 6, described level Supporting and regulating device 3 is connected by fixture 10 and connecting plate 11 with going out gusset 4, and described fixture 10 sets Putting and the gusset 4 side near fixed mount, described connecting plate 11 is connected to horizontal support adjusting means 3 and leans on Closely going out one end of gusset 4, described connecting plate 11 is fixing with fixture 10 to be connected.It is arranged such, can be effective Increase horizontal support adjusting means 3 at the lifting surface area gone out on gusset 4, it is simple to horizontal support adjusting means 3 To going out the adjustable of gusset 4.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 3 and Fig. 6, described fixing Part 10 and connecting plate 11 are connected by T-bolt 12, and described fixture 10 is provided with T-slot 13, described Connecting plate 11 is provided with bar shaped notch 14, and the screw head of described T-bolt 12 passes described bar shaped notch 14 In the described T-slot of rear insertion 13.It is arranged such, it is achieved being reliably connected of fixture 10 and connecting plate 11.
On the basis of above-described embodiment, in another embodiment of the present invention, described horizontal support adjusting means 3 The one end being connected with connecting plate 11 is provided with bulb, and described connecting plate 11 is provided with spherical inner chamber, and described bulb is put In described spherical inner chamber.Being arranged such, horizontal support adjusting means 3 and connecting plate 11 use universal joint shape The flexible connection mode of formula, when horizontal support adjusting means 3 realizes vertically movable, connecting plate 11 is without movement.
On the basis of above-described embodiment, in another embodiment of the present invention, described in go out in muscle hole 5 to be provided with sealing Bar, described sealing strip is provided with cross-under seam.It is arranged such, stretches out reinforcing bar 33 and pass out muscle hole 5, and by squeezing Press and cross cross-under seam, playing preferable sealing effectiveness.
On the basis of above-described embodiment, in another embodiment of the present invention, described in go out the hole wall in muscle hole 5 and be provided with Cannelure, described sealing strip embeds in described cannelure;Be arranged such, sealing strip with go out muscle hole 5 formed can By connecting and easy to connect, it is to avoid reinforcing bar, affects through sealing strip during sealing member from going out muscle hole 5 to come off Sealing effectiveness.
On the basis of above-described embodiment, in another embodiment of the present invention, described sealing strip is by flexible material system Standby, described sealing strip with go out muscle hole 5 interference fit.Being arranged such, simple installation, sealing effectiveness is preferable; Described sealing strip can be rubber or silica gel.
On the basis of above-described embodiment, in another embodiment of the present invention, described in go out gusset 4 and prefabricated component phase The outer wall of the side of contact is provided with flexible material.It is arranged such, can reduce and gusset 4 and concrete Cohesive force, both can protect mould, be also beneficial to form removal.Described flexible material both with go out gusset 4 with The rubber that spraying method combines, it is also possible to be the polyurethane sheet being bolted, should also be as including certainly Other can realize above-mentioned technical purpose technical scheme.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 1 and Fig. 2, described combination Mould also includes door opening template and/or window opening template 16.It is arranged such, it is simple to when preparing prefabricated panel, form door Hole and/or window opening.
On the basis of above-described embodiment, in another embodiment of the present invention, as shown in Figure 1, Figure 2, Fig. 7 and Fig. 8, Described door opening template and window opening template 16 at least include first gear cheek board 17 and second gear cheek board 18, its Being characterised by, described first gear cheek board 17 is positioned at described second gear cheek board 18 top, described first gear Cheek board 17 and described second gear cheek board 18 connect into entirety by connecting fixing device, and described connection is solid Determine device and be positioned at first gear cheek board 17 and the same side of second gear cheek board 18.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 7 and Fig. 8, described connection Fixing device includes fixed mechanism, bindiny mechanism and locking part 23, and described fixed mechanism is fixed with bindiny mechanism Connecting, first gear cheek board 17 and second gear cheek board 18 are fixed in bindiny mechanism by described locking part 23. Described fixed mechanism is connected fixing with bed die 15, plays the fixing and effect of location, it is ensured that prefabricated components produce During rib template and bed die 15 there is not relative movement, the bindiny mechanism being connected with fixed mechanism is by locking Firmware 23 connects the rib template being disposed adjacent so that it is forms entirety, and is fixed on fixed mechanism.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 7, described fixed mechanism is Magnetic force fixed bin 19, described magnetic force fixed bin 19 is provided with magnetic force assembly.Use magnetic force fixed bin 19 as solid Determine mechanism, compare traditional limit mould holder, eliminate support and rib, simplify structure, reduce system Cause this, can avoid damaging rigid platfor simultaneously, extend the life-span of mould, reduce the input of mould, thus right Reduce prefabricated components cost to play an important role.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 7 and Fig. 8, described first Rib template 17 and second gear cheek board 18 are provided with at least one installation with the described side being connected fixing device Locating slot 20, described bindiny mechanism includes vertically arranged connecting plate 21 and horizontally disposed fixed plate 22, institute Stating fixed plate 22 and be connected to described magnetic force fixed bin 19 top, described connecting plate 21 is provided with adjustment hole, described Adjustment hole described in locking part 23 cross-under also stretches in described installation locating slot 20.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 7 and Fig. 8, described fixing Plate 22 is provided with draw-in groove 25, and described magnetic force fixed bin 19 top is provided with shackle member 24, described shackle member 24 Snap in described draw-in groove 25.Being arranged such, fixed plate 22 is connected with magnetic force fixed bin 19 and dismantles all easy, Easily operated, and connect reliable.
On the basis of above-described embodiment, in another embodiment of the present invention, locking part 23 as described in Fig. 9~12 Including adjusting rod 26, connecting rod 27 and locking block 28, described connecting rod 27 one end connects described adjusting rod 26, The other end is connected with described locking block 28, and described locking block 28 cuts the thickness at position 29 less than locking block The thickness of 28 fixed positions 30, described connecting rod 27 is socketed with elastomer block 31, the one of described elastomer block 31 Described adjusting rod 26 is close in side.Regulation or rotation adjusting rod 26, drive locking block 28 to rotate, locking block 28 It is redirect to fixed position 30 by cutting position 29, owing to locking block 28 is fixed with the contact site of rib template The thickness at position 30 cuts the thickness at position 29 more than locking block 28, and locking block 28 coordinates in elastomer block 31 Rib template is fixed in connection fixing device.This locking part 23 simple in construction, easy to operate, it is only necessary to turn Dynamic adjusting rod 26 the most realizes the fastening of rib template, can be greatly improved die-filling in work progress and form removal Efficiency.
Certainly, the thickness of locking block 28 fixed position 30 and locking block 28 cut the thickness relationship at position 29 Can be the most thickening to fixed position 30 by incision position 29, i.e. set near the side connecting fixing device There is certain radian, make it gradually increase with the thickness of the contact site of described rib template by rotating adjusting rod 26 Greatly.
On the basis of above-described embodiment, in another embodiment of the present invention, described locking block 28 is eccentric. It is arranged such, owing to locking block 28 is eccentric, while rotating the rotation of adjusting rod 26 band movable eccentric wheel A downward power can be applied so that rib template proximate bed die 15 or make between rib template to rib template Mutually it is close to, so, can prevent concrete slurry from assembling spilling in seam along the level of template.
On the basis of above-described embodiment, in another embodiment of the present invention, described locking block 28 is square block, Described square block and described connecting rod 27 eccentric setting.In like manner, due to square block eccentric setting, it is same that it rotates Time can give rib template apply a downward power so that rib template proximate bed die 15 or make rib template it Between be mutually close to, so, can prevent concrete slurry along template level assemble seam along overflow.Certainly, institute Stating square block can be cuboid, owing to the length on its at least both sides is unequal, therefore in the situation of not eccentric setting Under also can reach the effect above, simply need the T-slot eccentric setting on rib mould to be fixed.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 1 and Fig. 2, described combination The corner of mould is provided with corner fixing device 32.It is arranged such, consolidating of the corner of advantageously combined mould Fixed, corner spillage can be prevented simultaneously.
It should be noted that such as Fig. 1 and Fig. 2, such as Fig. 1, when not four limits all go out muscle to prefabricated component, system The assembling die of standby prefabricated component is preferably and described window opening template at the rib mould used without going out the part of muscle 16 same templates.Certainly, shown in Fig. 1 without go out muscle part assembling die use gang form with Window opening template 16 locking part is different.
The above is only the preferred embodiment of the present invention, it is noted that common for the art For technical staff, under the premise without departing from the principles of the invention, it is also possible to make some improvements and modifications, These improvements and modifications also should be regarded as protection scope of the present invention.

Claims (10)

1. an assembling die, including bed die and rib mould, described rib mould is by the assembly of multiple gang forms Become, it is characterised in that described gang form includes fixed mount and goes out gusset, and wherein, described fixed mount includes Fixing device, vertical adjustment device and horizontal support adjusting means, described vertical adjustment bottom of device is connected to In fixing device, one end of described horizontal support adjusting means is connected with vertical adjustment device, the other end with go out Link of boards, is vertical between described horizontal support adjusting means and vertical adjustment device and horizontal direction is two-way Adjustable connection, described in go out to be provided with out on gusset muscle hole.
Prefabricated reinforced concrete the most according to claim 1 is with going out muscle mould, it is characterised in that described fixing Device is magnetic force fixed bin, and described magnetic force fixed bin is provided with magnetic force assembly.
Prefabricated reinforced concrete the most according to claim 2 is with going out muscle mould, it is characterised in that described level Supporting and regulating device is connected by connection arrangement with vertical adjustment device, and described horizontal support adjusting means can Relatively connection arrangement moves horizontally, described vertical adjustment device can connection arrangement relatively vertically movable.
Prefabricated reinforced concrete the most according to claim 3 is with going out muscle mould, it is characterised in that described two-way Connector includes vertically arranged fastening ring set and horizontally disposed threaded adjusting bore, described vertical adjustment device For montant, described montant interts described fastening ring set, and described horizontal support adjusting means is screw rod, described spiral shell Threaded adjusting bore described in bar cross-under.
Prefabricated reinforced concrete the most according to claim 3 is with going out muscle mould, it is characterised in that described two-way Connector is provided with vertical threaded adjusting bore and horizontal threaded adjusting bore, described vertical adjustment device and horizontal support Adjusting means is screw rod, the two the difference vertical threaded adjusting bore of cross-under and horizontal threaded adjusting bore.
6. require that the prefabricated reinforced concrete described in 4 or 5 is with going out muscle mould according to profit, it is characterised in that described water Flat supporting and regulating device is connected by fixture and connecting plate with going out gusset, and described fixture is arranged on out gusset Near the side of fixed mount, described connecting plate is connected to horizontal support adjusting means near going out one end of gusset, Described connecting plate is fixing with fixture to be connected.
Prefabricated reinforced concrete the most according to claim 6 is with going out muscle mould, it is characterised in that described fixing Part and connecting plate are connected by T-bolt, and described fixture is provided with T-slot, and described connecting plate is provided with bar Shape notch, the screw head of described T-bolt is inserted in described T-slot after described bar shaped notch.
Prefabricated reinforced concrete the most according to claim 6 is with going out muscle mould, it is characterised in that described level One end that supporting and regulating device is connected with connecting plate is provided with bulb, and described connecting plate is provided with spherical inner chamber, described Bulb is placed in described spherical inner chamber.
Prefabricated reinforced concrete the most according to claim 7 is with going out muscle mould, it is characterised in that described in go out muscle Being provided with sealing strip in hole, described sealing strip is provided with cross-under seam.
Prefabricated reinforced concrete the most according to claim 9 is with going out muscle mould, it is characterised in that described in go out The hole wall in muscle hole is provided with cannelure, and described sealing strip embeds in described cannelure;Or described sealing strip is by flexibility Prepared by material, described sealing strip with go out muscle hole interference fit;Or also include door opening template and/or window opening template; Or described door opening template and window opening template at least include first gear cheek board and second gear cheek board, its feature exists It is positioned at described second gear cheek board top, described first gear cheek board and described in, described first gear cheek board Second gear cheek board connects into entirety by connecting fixing device, and described connection fixing device is positioned at the first rib Template and the same side of second gear cheek board;Or the corner of described assembling die is provided with corner fixing device.
CN201610617783.7A 2016-07-29 2016-07-29 Combined die Pending CN106003386A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610617783.7A CN106003386A (en) 2016-07-29 2016-07-29 Combined die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610617783.7A CN106003386A (en) 2016-07-29 2016-07-29 Combined die

Publications (1)

Publication Number Publication Date
CN106003386A true CN106003386A (en) 2016-10-12

Family

ID=57115270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610617783.7A Pending CN106003386A (en) 2016-07-29 2016-07-29 Combined die

Country Status (1)

Country Link
CN (1) CN106003386A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107486927A (en) * 2017-05-16 2017-12-19 中建四局深圳实业有限公司 A kind of big die station mould for the construction of plate class prefabricated components streamline
CN107584638A (en) * 2017-11-06 2018-01-16 常德远大建筑工业有限公司 A kind of pre-buried window frame mould of prefabricated components and its installation method
CN107932696A (en) * 2017-12-12 2018-04-20 长沙远大住宅工业集团股份有限公司 For the molding mould of prefabricated components and forming method
CN108118863A (en) * 2017-12-29 2018-06-05 皇玉彬 A kind of fixing templates
CN108214838A (en) * 2018-02-07 2018-06-29 三能集成房屋股份有限公司 A kind of plugging plate and the prefabricated components mold plug-hole tooling for taking muscle out of
CN109318349A (en) * 2018-10-23 2019-02-12 中国水利水电第八工程局有限公司 A kind of general combination side form of prefabricated components, mold
CN109624037A (en) * 2018-12-27 2019-04-16 浙江大经住工科技有限公司 A kind of balcony slab prefabricated mould
CN109822726A (en) * 2019-03-20 2019-05-31 湖南三一快而居住宅工业有限公司 A kind of mold and die station
CN111979862A (en) * 2020-07-30 2020-11-24 三能集成房屋股份有限公司 Arc road base plate and forming die thereof
CN114012866A (en) * 2021-11-16 2022-02-08 上海电气风电集团股份有限公司 Adjustable polygonal mixed tower barrel template and tower barrel segment manufacturing method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200991948Y (en) * 2006-12-06 2007-12-19 于复生 Size-adjustable door-window formboard for producing sandwiched plate
CN101254615A (en) * 2004-02-27 2008-09-03 邱则有 Shaping mold of members of mould shell
CN102126246A (en) * 2010-01-19 2011-07-20 黑龙江宇辉新型建筑材料有限公司 Integral type die and method for processing building member for exposing reinforcing steel bars
CN204525721U (en) * 2015-04-15 2015-08-05 中民筑友有限公司 A kind of fixture for limit mould and prefabricated-member mould
CN204585497U (en) * 2015-05-19 2015-08-26 刘健 A kind of Cast-in-situ Beam mould
CN205276870U (en) * 2015-11-17 2016-06-01 中国三冶集团有限公司 Novel building templates and snap -action connection
CN205915480U (en) * 2016-07-29 2017-02-01 中民筑友科技投资有限公司 Combined die

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101254615A (en) * 2004-02-27 2008-09-03 邱则有 Shaping mold of members of mould shell
CN200991948Y (en) * 2006-12-06 2007-12-19 于复生 Size-adjustable door-window formboard for producing sandwiched plate
CN102126246A (en) * 2010-01-19 2011-07-20 黑龙江宇辉新型建筑材料有限公司 Integral type die and method for processing building member for exposing reinforcing steel bars
CN204525721U (en) * 2015-04-15 2015-08-05 中民筑友有限公司 A kind of fixture for limit mould and prefabricated-member mould
CN204585497U (en) * 2015-05-19 2015-08-26 刘健 A kind of Cast-in-situ Beam mould
CN205276870U (en) * 2015-11-17 2016-06-01 中国三冶集团有限公司 Novel building templates and snap -action connection
CN205915480U (en) * 2016-07-29 2017-02-01 中民筑友科技投资有限公司 Combined die

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107486927A (en) * 2017-05-16 2017-12-19 中建四局深圳实业有限公司 A kind of big die station mould for the construction of plate class prefabricated components streamline
CN107584638A (en) * 2017-11-06 2018-01-16 常德远大建筑工业有限公司 A kind of pre-buried window frame mould of prefabricated components and its installation method
CN107932696A (en) * 2017-12-12 2018-04-20 长沙远大住宅工业集团股份有限公司 For the molding mould of prefabricated components and forming method
CN108118863A (en) * 2017-12-29 2018-06-05 皇玉彬 A kind of fixing templates
CN108214838A (en) * 2018-02-07 2018-06-29 三能集成房屋股份有限公司 A kind of plugging plate and the prefabricated components mold plug-hole tooling for taking muscle out of
CN108214838B (en) * 2018-02-07 2024-03-19 三能集成房屋股份有限公司 Plugging plate and prefabricated part mold plugging tool with ribs
CN109318349B (en) * 2018-10-23 2023-08-29 中国水利水电第八工程局有限公司 Prefabricated component general combination side form, mould
CN109318349A (en) * 2018-10-23 2019-02-12 中国水利水电第八工程局有限公司 A kind of general combination side form of prefabricated components, mold
CN109624037A (en) * 2018-12-27 2019-04-16 浙江大经住工科技有限公司 A kind of balcony slab prefabricated mould
CN109822726A (en) * 2019-03-20 2019-05-31 湖南三一快而居住宅工业有限公司 A kind of mold and die station
CN111979862A (en) * 2020-07-30 2020-11-24 三能集成房屋股份有限公司 Arc road base plate and forming die thereof
CN114012866A (en) * 2021-11-16 2022-02-08 上海电气风电集团股份有限公司 Adjustable polygonal mixed tower barrel template and tower barrel segment manufacturing method
CN114012866B (en) * 2021-11-16 2023-01-31 上海电气风电集团股份有限公司 Adjustable polygonal mixed tower barrel template and tower barrel segment manufacturing method

Similar Documents

Publication Publication Date Title
CN106003386A (en) Combined die
CN205915480U (en) Combined die
CN106003388A (en) Combined die
CN108204089A (en) A kind of Side fascia connector and construction method
CN106079043A (en) A kind of gang form
CN106003387A (en) Combined die
CN205915481U (en) Built -up plate
CN205314319U (en) Metal curtain wall articulates subassembly
CN206287300U (en) A kind of assembling die
CN211974315U (en) Template system for creeping formwork variable cross-section wall construction
CN108331330A (en) A kind of building template
CN106182356A (en) A kind of assembling die
CN115162406B (en) Integral template portal suitable for box culvert structure
CN207685855U (en) A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall
CN205915484U (en) Precast reinforced concrete is with going out muscle mould
CN113833284B (en) Assembly type building structure and assembly construction method thereof
CN106079042A (en) A kind of gang form
CN107419897A (en) A kind of reinforcing mould of windowsill coping formwork
CN206186039U (en) Combined die
CN206359149U (en) Derrick crane attachment support
CN211285696U (en) Reference panel
CN215594877U (en) Building template with additional strengthening
CN204023851U (en) Curtain-wall stand-column and Curtain wall frame
CN205637587U (en) Thick liquid processing apparatus is leaked to template bottom
CN205915482U (en) Built -up plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination