Novel prefabricated building connecting joint Download PDFInfo
- Publication number
- CN105937270A CN105937270A CN201610385641.2A CN201610385641A CN105937270A CN 105937270 A CN105937270 A CN 105937270A CN 201610385641 A CN201610385641 A CN 201610385641A CN 105937270 A CN105937270 A CN 105937270A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- layer
- top board
- sandwich
- situ
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005452 bending Methods 0.000 claims abstract description 19
- 238000011065 in-situ storage Methods 0.000 claims abstract description 17
- 230000002787 reinforcement Effects 0.000 claims description 24
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 229910000831 Steel Inorganic materials 0.000 abstract 4
- 239000010959 steel Substances 0.000 abstract 4
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B2001/4192—Connecting devices specially adapted for embedding in concrete or masonry attached to concrete reinforcing elements, e.g. rods or wires
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
A novel prefabricated building connecting joint comprises a prefabricated sandwich superposed wall and a prefabricated superposed top plate, the prefabricated sandwich superposed wall comprises prefabricated layers at the two sides and a sandwich layer in the middle, and the prefabricated superposed top plate comprises a top plate prefabricated layer and a top cast-in-situ layer; a vertical steel bar in the prefabricated layer at one side of the prefabricated sandwich superposed wall stretches out of the bottom end of the prefabricated layer, is bent and turned, and then enters the prefabricated layer at the other side to become a vertical steel bar, or vertical bars in the prefabricated layers at the two sides of the prefabricated sandwich superposed wall stretch out of the bottom ends of the prefabricated layers and are connected to form an overall bent and turned structure, the bent and turned steel bars are anchored in the top plate cast-in-situ layer of the prefabricated superposed top plate, and connection and fixation are achieved through cast-in-situ concrete. The steel bar stress mode in the prefabricated building connecting joint acts as the optimal selection, the strength of the joint is equivalent to that of a cast-in-situ structure, and the prefabricated building connecting joint is high in structural strength and bending resistance.
Description
Technical field
The invention belongs to construction engineering technical field, be specifically related to the connection node of a kind of assembled architecture.
Background technology
In existing assembled architecture, prefabricated sandwich overlapping wall with the connection node of top board is: in the preformed layer of prefabricated sandwich overlapping wall both sides, the vertical reinforcement of stress does not anchor into top board, but insert in top board by setting up two row's vertical reinforcements in prefabricated sandwich overlapping wall sandwich of layers, the bonding strength of node is ensured with this, but these two row's vertical reinforcement spacing set up are narrow, and this most greatly weakens the structural strength that prefabricated sandwich overlapping wall is connected with top board.Structural strength for making both connect is improved, sometimes can only the concrete layer of prefabricated sandwich overlapping wall both sides be made the thinnest, the spacing of two row's vertical reinforcements in sandwich of layers is set up to pull open as far as possible, but this way space fine-adjusting is limited, still can not fundamentally ensure bonding strength and the anti-bending strength of node.
Summary of the invention
The technical problem to be solved is: solve the problem that above-mentioned prior art exists, and provide a kind of novel fabricated building to connect node, making assembled architecture connect node reinforcing steel bar bear mode is optimum selection, node strength equivalent cast-in-place structural, structural strength is high, and anti-bending strength is good.
The technical solution used in the present invention is: novel fabricated building connects node, including prefabricated sandwich overlapping wall and prefabricated overlapping top board, described prefabricated sandwich overlapping wall includes the preformed layer of both sides and middle sandwich in-situ layer, described prefabricated overlapping top board includes top board preformed layer and top board in-situ layer, vertical reinforcement in the preformed layer of prefabricated sandwich overlapping wall side is after bending revolution is stretched out in preformed layer bottom, vertical reinforcement is become in entering back into opposite side preformed layer, or vertical reinforcement connects into Integral bending after preformed layer bottom is stretched out and turns back rotation structure in the preformed layer of prefabricated sandwich overlapping wall both sides, above-mentioned bending revolution Bar Anchorage is in the top board in-situ layer of prefabricated overlapping top board, cast concrete connects fixing.
In technique scheme, it is connected fixing inside described bending revolution reinforcing bar with many horizontal reinforcements.
Prominent substantive distinguishing features and remarkable result:
In existing assembled architecture, prefabricated sandwich overlapping wall inserts in top board by prefabricated sandwich overlapping two vertical reinforcements of in-situ layer within the walls completely with the connection of top board, and this connection node two vertical reinforcement spacing of prior art is little, and anti-bending strength is poor, and structural strength weakens.The present invention revolutionizes the connecting joint structure of this prior art, stretch out reserved from preformed layer bottom for vertical reinforcement in the both sides preformed layer of prefabricated sandwich overlapping wall, two Vertical bar connection stretched out are fixed, integral bending revolving structure, then anchor in the in-situ layer of prefabricated overlapping top board, pour into a mould concrete again and connect fixing, two vertical reinforcement spacing width, anti-bending strength is good, structural strength is high, its vertical reinforcement force way is optimal choice, its node strength is high, its vertical reinforcement force way is the same with tradition cast-in-place structural, its node strength equivalent cast-in-place structural, it it is the most best structural strength.
Accompanying drawing illustrates:
Fig. 1 is the embodiment of the present invention 1 structural representation;
Fig. 2 is the embodiment of the present invention 2 structural representation.
Accompanying drawing marks: 1 prefabricated sandwich overlapping wall, 2 preformed layers, 3 in-situ layers, vertical reinforcement in 4 preformed layers, 5 truss, 6 bending revolution reinforcing bars, 7 horizontal reinforcements, 8 prefabricated overlapping top boards, 9 top board preformed layers, 10 top board in-situ layers, 11 middle wall body.
Detailed description of the invention:
See Fig. 1, Fig. 2, the novel fabricated building of the present invention connects node, including prefabricated sandwich overlapping wall and prefabricated overlapping top board, described prefabricated sandwich overlapping wall includes the preformed layer of both sides and middle sandwich in-situ layer, described prefabricated overlapping top board includes top board preformed layer and top board in-situ layer, vertical reinforcement in the preformed layer of prefabricated sandwich overlapping wall side stretches out from preformed layer bottom in entering opposite side preformed layer after bending revolution becomes vertical reinforcement, or vertical reinforcement connects into Integral bending after preformed layer bottom is stretched out and turns back rotation structure in the preformed layer of prefabricated sandwich overlapping wall both sides, above-mentioned bending revolution Bar Anchorage is in the top board in-situ layer of prefabricated overlapping top board, cast concrete connects fixing, it is connected fixing inside described bending revolution reinforcing bar with many horizontal reinforcements.
Embodiment 2 shown in Fig. 2 is with the difference of the embodiment 1 shown in Fig. 1: in Fig. 2, prefabricated sandwich overlapping wall uses as middle wall body, but its structure and node are identical.
Claims (2)
1. a novel fabricated building connects node, it is characterized in that: include prefabricated sandwich overlapping wall and prefabricated overlapping top board, described prefabricated sandwich overlapping wall includes the preformed layer of both sides and middle sandwich in-situ layer, described prefabricated overlapping top board includes top board preformed layer and top board in-situ layer, vertical reinforcement in the preformed layer of prefabricated sandwich overlapping wall side is after bending revolution is stretched out in preformed layer bottom, vertical reinforcement is become in entering back into opposite side preformed layer, or vertical reinforcement connects into Integral bending after preformed layer bottom is stretched out and turns back rotation structure in the preformed layer of prefabricated sandwich overlapping wall both sides, above-mentioned bending revolution Bar Anchorage is in the top board in-situ layer of prefabricated overlapping top board, cast concrete connects fixing.
Novel fabricated the most according to claim 1 building connects node, it is characterised in that: it is connected fixing inside described bending revolution reinforcing bar with many horizontal reinforcements.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610385641.2A CN105937270A (en) | 2016-06-03 | 2016-06-03 | Novel prefabricated building connecting joint |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610385641.2A CN105937270A (en) | 2016-06-03 | 2016-06-03 | Novel prefabricated building connecting joint |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105937270A true CN105937270A (en) | 2016-09-14 |
Family
ID=57152263
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610385641.2A Pending CN105937270A (en) | 2016-06-03 | 2016-06-03 | Novel prefabricated building connecting joint |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105937270A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107893477A (en) * | 2017-12-12 | 2018-04-10 | 呼和浩特市中朵兴泰远大建筑工业有限公司 | Overlap wall and horizontal member connecting node and its construction method |
CN107893478A (en) * | 2017-12-12 | 2018-04-10 | 浙江新邦远大绿色建筑产业有限公司 | Overlap wall and horizontal member connecting node and its construction method |
CN111576618A (en) * | 2020-05-27 | 2020-08-25 | 殷宗亮 | Assembled concrete building connected node |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3100872B2 (en) * | 1995-06-19 | 2000-10-23 | クレハエラストマー株式会社 | How to join the impermeable sheet |
CN101586366A (en) * | 2008-05-21 | 2009-11-25 | 万科企业股份有限公司 | Connecting structure and construction method of precast concrete plates and beams, and building comprising same |
CN101787738A (en) * | 2010-03-12 | 2010-07-28 | 南通建筑工程总承包有限公司 | Stair connection joint device |
CN103572840A (en) * | 2012-08-05 | 2014-02-12 | 初明进 | Notch-key type prefabricated member connection node and connection method |
CN104074359A (en) * | 2014-07-17 | 2014-10-01 | 长沙远大住宅工业集团有限公司 | Construction method for connection joint of prefabricated sandwich side fascia |
CN205742549U (en) * | 2016-06-03 | 2016-11-30 | 长沙远大住宅工业集团股份有限公司 | Novel fabricated building connects node |
-
2016
- 2016-06-03 CN CN201610385641.2A patent/CN105937270A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3100872B2 (en) * | 1995-06-19 | 2000-10-23 | クレハエラストマー株式会社 | How to join the impermeable sheet |
CN101586366A (en) * | 2008-05-21 | 2009-11-25 | 万科企业股份有限公司 | Connecting structure and construction method of precast concrete plates and beams, and building comprising same |
CN101787738A (en) * | 2010-03-12 | 2010-07-28 | 南通建筑工程总承包有限公司 | Stair connection joint device |
CN103572840A (en) * | 2012-08-05 | 2014-02-12 | 初明进 | Notch-key type prefabricated member connection node and connection method |
CN104074359A (en) * | 2014-07-17 | 2014-10-01 | 长沙远大住宅工业集团有限公司 | Construction method for connection joint of prefabricated sandwich side fascia |
CN205742549U (en) * | 2016-06-03 | 2016-11-30 | 长沙远大住宅工业集团股份有限公司 | Novel fabricated building connects node |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107893477A (en) * | 2017-12-12 | 2018-04-10 | 呼和浩特市中朵兴泰远大建筑工业有限公司 | Overlap wall and horizontal member connecting node and its construction method |
CN107893478A (en) * | 2017-12-12 | 2018-04-10 | 浙江新邦远大绿色建筑产业有限公司 | Overlap wall and horizontal member connecting node and its construction method |
CN107893477B (en) * | 2017-12-12 | 2023-09-19 | 长沙远大住宅工业集团股份有限公司 | Connecting node of laminated wall and horizontal member and construction method thereof |
CN111576618A (en) * | 2020-05-27 | 2020-08-25 | 殷宗亮 | Assembled concrete building connected node |
CN111576618B (en) * | 2020-05-27 | 2021-12-24 | 隆恩建设工程有限公司 | Assembled concrete building connected node |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102900168B (en) | Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall | |
CN105937271A (en) | Novel prefabricated building connecting joint | |
CN208533764U (en) | A kind of panel structure | |
CN110469001B (en) | Superimposed shear wall and construction method thereof | |
CN106759865B (en) | A kind of U-shaped steel plate combination beam frame of steel core concrete column- | |
KR101026118B1 (en) | Truss structure with high bearing capacity against secondary moment at inner supports and construction method of truss bridge using it | |
CN109518858A (en) | Fabricated Beam-Slab connection structure and its construction method | |
CN208363404U (en) | A kind of prefabricated panel and its connection structure | |
CN203452228U (en) | Frame-shear wall architectural structure | |
CN105937270A (en) | Novel prefabricated building connecting joint | |
CN107905426A (en) | A kind of building method of bidirectional hollow laminated floor slab | |
CN108951955A (en) | A kind of assembled integral reinforced concrete band keyway Coupled Shear Wall structure | |
CN205742550U (en) | Novel fabricated building connects node | |
CN108179808A (en) | A kind of prefabricated beam column crimping joint strengthening stirrup construction and its construction method | |
CN103741809A (en) | Embedded column type prefabricated part connecting method | |
CN205444571U (en) | Wallboard connected node | |
CN105937280A (en) | Novel prefabricated building connecting joint | |
CN110284619A (en) | A kind of prefabricated superimposed sheet reinforced concrete shear wall of mortise and tenon type | |
CN101831868A (en) | Connecting node structure of steel rod elements and concrete plate | |
CN109868919B (en) | Connection structure of vertical piece of superimposed shear wall | |
CN207194228U (en) | Wall is overlapped with overlapping the vertical openings connecting node of wall | |
CN205742549U (en) | Novel fabricated building connects node | |
CN208088500U (en) | A kind of prefabricated beam column crimping joint strengthening stirrup construction | |
CN208748824U (en) | A kind of assembled beam-column node | |
CN207988293U (en) | A kind of bidirectional hollow laminated floor slab |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160914 |
|
RJ01 | Rejection of invention patent application after publication |