CN105926657B - Construction method of concrete foundation precast slab - Google Patents
Construction method of concrete foundation precast slab Download PDFInfo
- Publication number
- CN105926657B CN105926657B CN201610442174.2A CN201610442174A CN105926657B CN 105926657 B CN105926657 B CN 105926657B CN 201610442174 A CN201610442174 A CN 201610442174A CN 105926657 B CN105926657 B CN 105926657B
- Authority
- CN
- China
- Prior art keywords
- concrete foundation
- prefabricated board
- reinforcing bar
- construction method
- substrate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 61
- 238000010276 construction Methods 0.000 title claims abstract description 34
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 5
- 239000010959 steel Substances 0.000 claims abstract description 5
- 230000003014 reinforcing effect Effects 0.000 claims description 31
- 239000000758 substrate Substances 0.000 claims description 28
- 239000004744 fabric Substances 0.000 claims description 10
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 8
- 238000005266 casting Methods 0.000 claims description 5
- 229910052742 iron Inorganic materials 0.000 claims description 4
- 208000002193 Pain Diseases 0.000 claims description 3
- 238000005056 compaction Methods 0.000 claims description 3
- 238000009826 distribution Methods 0.000 claims description 3
- 238000012423 maintenance Methods 0.000 claims description 3
- 239000000725 suspension Substances 0.000 claims 1
- 238000005336 cracking Methods 0.000 abstract description 4
- 239000011449 brick Substances 0.000 description 6
- 238000000034 method Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 235000019994 cava Nutrition 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
- Retaining Walls (AREA)
Abstract
The invention relates to a concrete foundation precast slab and a construction method thereof, wherein the concrete foundation precast slab comprises a base plate, an anti-cracking net, a plurality of steel bars and a plurality of cushion blocks, the size of the concrete foundation precast slab can be configured according to the foundation size of a building, and the concrete foundation precast slab can be conveniently carried to a required position by lifting hooks.
Description
Technical field
The present invention relates to building material technical field more particularly to a kind of construction methods of concrete foundation prefabricated board.
Background technology
At present in construction site, the side forms such as raft plate, stub, catch pit are not easy the position removed and generally use brick tire
Mould replaces plank sheathing, but brick mold masonry project amount is larger, and needs the processes such as plastering, and the manpower and materials of input are more, needs
Equal bonding mortar strengths can just carry out next procedure construction after reaching, long construction period, and cost is higher.
Invention content
In order to solve the above problem of the existing technology, the present invention provides it is a kind of it is simple in structure, be easy to dismounting, can have
Effect shortens the construction period and reduces the concrete foundation prefabricated board of cost and the concrete foundation prefabricated board is used to construct
Method.
The technical solution adopted in the present invention is:A kind of concrete foundation prefabricated board, including substrate, anti-crack net, more steel
Muscle and multiple cushion blocks, the reinforcing bar, the anti-crack net and the cushion block are arranged at the inside of the substrate, the side of the substrate
Hook is provided on wall, the substrate, the reinforcing bar, the anti-crack net, the cushion block and the hook pass through concrete
Pour integrated fixation.
Further, the anti-crack net is arranged on the reinforcing bar.
Further, the steel-bar arrangement is in the centre position of the substrate.
Further, the reinforcing bar is by regular distribution, the intersection of the reinforcing bar are fixed with steel wire rope in length and breadth.
Further, the cushion block is arranged in the lower section of the intersection of the reinforcing bar.
Further, two sides opposite on the substrate are respectively arranged with occlusal crib, the length of the occlusion slot cross-section
It spends and of same size.
Further, the edge of the occlusal crib is provided with grid cloth.
The construction method of concrete foundation prefabricated board provided by the invention includes:Step A is sequentially placed into described in a mold
Cushion block, the reinforcing bar and the anti-crack net simultaneously place the hook on the side wall of mold, then carry out concreting, pour
Shake mold is struck when building concrete so that concrete compaction, prevents pitted skin;Step B carries out covering mould after the completion of concreting
Watering maintenance, prevents that crack, curing time are at least 7 days;The concrete foundation prefabricated board is installed to pad by step C
In the reserved groove of layer, the adjacent concrete foundation prefabricated board is mutually twisted by the occlusal crib, is set stinging commissure
Set the grid cloth;Step D:Timber wedge is played in side slope, and passes through iron wire and the concrete foundation prefabricated board being mutually twisted
On the hook be fixed;Step E:It is backfilled in the sideshake formed around the concrete foundation prefabricated board and heatable adobe sleeping platform
Soil is simultaneously tamped, and should observe the deviation situation of prefabricated board during compacting constantly, it is found that deviation should be adjusted in time.
Further, mold is reinforced with step fastener at occlusal crib when casting concrete.
Further, when side form height is more than 1m, by the way of the upper and lower two pieces concrete foundation prefabricated board assemblings,
And grid cloth anticracking is set between levels.
Beneficial effects of the present invention are:The concrete foundation prefabricated board can configure institute according to the key dimension of building
The size of the concrete foundation prefabricated board needed, and prefabricated board is easily transported to by required position by hook, by base
Anti-crack net is arranged on plate can be effectively prevented the cracking of substrate, and by the way that grid cloth is arranged on occlusal crib, ensure adjacent
Close connection between two pieces of prefabricated boards can avoid occurring when the backfilling of earthwork around prefabricated board crack and what is caved in show
As ensureing the quality of construction.
By the construction method of the concrete foundation prefabricated board, it can effectively shorten the construction that tradition builds brick mold by laying bricks or stones
Time reduces labour's input, shortens the construction period, reduction construction cost, but also the avoidable elevator built under main building raft plate,
Cushion cap plank sheathing removes difficult problem.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention;
Fig. 2 is the vertical view of the present invention.
In figure:1, substrate;11, occlusal crib;12, hook;2, reinforcing bar;3, anti-crack net;4, cushion block.
Specific implementation mode
As depicted in figs. 1 and 2, the present invention provides a kind of concrete foundation prefabricated board, including it is substrate 1, anti-crack net 3, more
Root reinforcing bar 2 and multiple cushion blocks 4 can in advance be carried out making concrete foundation prefabricated board according to building key dimension, be shortened
Tradition builds the construction time of brick mold by laying bricks or stones, can substantially shorten the construction period.
Reinforcing bar 2, anti-crack net 3 and cushion block 4 are arranged at the inside of substrate 1, and hook 12 is provided on the side wall of substrate 1,
Can lifting operation easily be carried out to concrete foundation prefabricated board by hook 12 and fix the one end for reinforcing iron wire
On hook 12, the side wall of concrete foundation prefabricated board is fixed on soil body timber, ensures the safety of construction.
Substrate 1, reinforcing bar 2, anti-crack net 3, cushion block 4 and hook 12 are integrally fixed by concreting, ensure coagulation
The strength and stiffness of earth foundation prefabricated board.Reinforcing bar 2 is arranged at the intermediate position of substrate 1, can enhance concrete foundation prefabricated board
Intensity.Reinforcing bar 2 is by regular distribution in length and breadth, to ensure substrate 1 with enough strength and stiffness and pour rear concrete foundation
Prefabricated board internal stress is smaller.The intersection of reinforcing bar 2 is fixed with steel wire rope, and reinforcing bar 2 will not when making casting concrete
Offset is generated, ensures the quality of substrate 1.Cushion block 4 is arranged in the lower section of 2 intersection of reinforcing bar, can either support reinforcing bar 2
Come, ensures that reinforcing bar 2 is in the centre position of substrate 1, and the intensity of substrate 1 can be increased, it can be according to the size selection pad of substrate 1
The quantity of block 4, cushion block 4 are distributed in blossom type, can ensure the levelness of reinforcing bar 2 in larger-size substrate 1, in making for later stage
With in the process, everywhere all uniform stresseds of substrate 1, are not in the place of stress weakness, ensure construction in later period it is normal into
Row.Anti-crack net 2 is arranged in the top of reinforcing bar 2, and anti-crack net 2 can be effectively prevented the cracking of substrate 1, ensures the quality of construction.
Two opposite sides are respectively arranged with occlusal crib 11 on substrate 1, and occlusal crib 11 can ensure adjacent two block concretes basis
It fits closely, crack is not likely to produce when the concrete foundation prefabricated board surrounding earthwork is backfilled and caves between prefabricated board, have
Effect improves construction quality.The length and width in 11 section of occlusal crib is identical, keeps the interchangeability of occlusal crib 11 more preferable, and occlusal contact area
Maximum ensures the intensity at occlusion position.The edge of occlusal crib 11 is provided with grid cloth, and two adjacent block concrete bases are prefabricated
After plate is engaged, grid cloth is sticked in the edge of occlusal crib 11, and carry out plastering processing, ensure two adjacent block concretes
Being completely embedded between basic prefabricated board.
The construction method of concrete foundation prefabricated board provided by the invention includes:The first step is sequentially placed into pad in a mold
Block 4, reinforcing bar 2 and anti-crack net 3 simultaneously place hook 12 on the side wall of mold, are carried out to mold with step fastener at occlusal crib 11
It reinforces, prevents the Forming Quality for running mould phenomena impair concrete foundation prefabricated board from then carrying out concreting, casting concrete
Shi Jinhang fully vibrates, and strikes shake mold so that concrete compaction, prevents pitted skin;Second step, after the completion of concreting
It carries out covering mould watering maintenance, prevents that crack, curing time are at least 7 days;Third walks, and concrete foundation prefabricated board is installed
In the groove reserved to bed course, in a pre-installation if it find that voids and pits is repaired in time, adjacent concrete foundation is prefabricated
Plate is mutually twisted by occlusal crib, and grid cloth is arranged stinging commissure;4th step:Play timber wedge in side slope, and by iron wire with
The hook on the concrete foundation prefabricated board being mutually twisted is fixed;5th step:Concrete foundation prefabricated board with
It backfill and is tamped in the sideshake formed around heatable adobe sleeping platform, the deviation situation of prefabricated board should be observed during compacting constantly, found inclined
Position should be adjusted in time.
When side form height is more than 1m, by the way of the assembling of upper and lower two block concrete basis prefabricated board, and in levels
Between setting grid cloth prevent from cracking.
To sum up, the present invention provides a kind of concrete foundation prefabricated board and its construction method, the concrete foundation is prefabricated
Plate has the characteristics that intensity is high, rigidity is high, not easy to crack, convenient disassembly, and facilitates carrying.It is pre- using the concrete foundation
When the construction method of making sheet is constructed, labor intensity can be effectively reduced, reduction labour puts into, shortens the construction period, reduces
Construction cost, and can ensure construction quality.
The present invention is not limited to above-mentioned preferred forms, anyone can show that other are various under the inspiration of the present invention
The product of form, however, make any variation in its shape or structure, it is every that there is skill identical or similar to the present application
Art scheme, is within the scope of the present invention.
Claims (7)
1. a kind of construction method of concrete foundation prefabricated board, including substrate (1), anti-crack net (3), more reinforcing bars (2) and multiple
Cushion block (4), the reinforcing bar (2), the anti-crack net (3) and the cushion block (4) are arranged at the inside of the substrate (1), described
Hook (12), the substrate (1), the reinforcing bar (2), the anti-crack net (3), the pad are provided on the side wall of substrate (1)
Block (4) and the hook (12) are integrally fixed by concreting;On the substrate (1) on two opposite sides respectively
It is provided with occlusal crib (11), the length and width in occlusal crib (11) section is identical;The edge of the occlusal crib (11) is set
It is equipped with grid cloth;
It is characterized in that:The construction method includes the following steps:
Step A:It is sequentially placed into the cushion block (4), the reinforcing bar (2) and the anti-crack net (3) and the side in mold in a mold
The hook (12) to be placed on wall, then carries out concreting, when casting concrete, strikes shake mold so that concrete compaction,
Prevent pitted skin;
Step B:It carries out covering mould watering maintenance after the completion of concreting, prevents that crack, curing time are at least 7 days;
Step C:The concrete foundation prefabricated board is installed in the reserved groove of bed course, the adjacent concrete foundation is pre-
Making sheet is mutually twisted by the occlusal crib (11), and the grid cloth is arranged stinging commissure;
Step D:Play timber wedge in side slope, and by iron wire on the concrete foundation prefabricated board that is mutually twisted described in rise
Suspension hook (12) is fixed;And
Step E:It backfill and is tamped in the sideshake formed around the concrete foundation prefabricated board and heatable adobe sleeping platform, during compacting
The deviation situation of prefabricated board should be observed constantly, it is found that deviation should be adjusted in time.
2. the construction method of concrete foundation prefabricated board according to claim 1, it is characterised in that:The anti-crack net (2)
Top in the reinforcing bar (2) is set.
3. the construction method of concrete foundation prefabricated board according to claim 2, it is characterised in that:The reinforcing bar (2) sets
Set the centre position in the substrate (1).
4. the construction method of concrete foundation prefabricated board according to claim 3, it is characterised in that:The reinforcing bar (2) is pressed
The intersection of regular distribution in length and breadth, the reinforcing bar (2) is fixed with steel wire rope.
5. the construction method of concrete foundation prefabricated board according to claim 4, it is characterised in that:The cushion block (4) sets
It sets in the lower section of the reinforcing bar (2) intersection.
6. a kind of construction method of concrete foundation prefabricated board described in claim 1, it is characterised in that:When casting concrete
The occlusal crib(11)Place reinforces mold with step fastener.
7. the construction method of concrete foundation prefabricated board according to claim 1 or 6, it is characterised in that:Side form height is big
When 1m, by the way of the upper and lower two pieces concrete foundation prefabricated board assemblings, and grid is set between levels and is deployed troops on garrison duty
It splits.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610442174.2A CN105926657B (en) | 2016-06-20 | 2016-06-20 | Construction method of concrete foundation precast slab |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610442174.2A CN105926657B (en) | 2016-06-20 | 2016-06-20 | Construction method of concrete foundation precast slab |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105926657A CN105926657A (en) | 2016-09-07 |
CN105926657B true CN105926657B (en) | 2018-08-21 |
Family
ID=56830373
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610442174.2A Active CN105926657B (en) | 2016-06-20 | 2016-06-20 | Construction method of concrete foundation precast slab |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105926657B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106677200A (en) * | 2016-12-30 | 2017-05-17 | 广州市第建筑工程有限公司 | Construction method for sludge soil precast concrete cushion |
CN109371895A (en) * | 2018-11-12 | 2019-02-22 | 交通运输部天津水运工程科学研究所 | It is a kind of for increasing the pitch non-slip mat of coefficient of friction |
CN114855884B (en) * | 2022-06-09 | 2024-03-29 | 安徽建工集团股份有限公司总承包分公司 | Construction method for facilitating advanced backfilling of post-cast strip of underground foundation structure |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS56100931A (en) * | 1980-01-18 | 1981-08-13 | Hanjirou Soda | Foundation work for concrete block stacking |
CN1298946C (en) * | 2003-12-28 | 2007-02-07 | 昆明理工大学 | Steel-steel concrete fully prefabricated assembling structure |
KR20080064670A (en) * | 2007-01-05 | 2008-07-09 | 주식회사 대우일렉트로닉스 | Apparatus for simple power off of television and method thereof |
CN102248577B (en) * | 2011-02-28 | 2012-12-05 | 唐山北极熊建材有限公司 | Superlight-foamed-cement-based manufacturing process for thermal-insulation bearing wall panel |
CN103290967B (en) * | 2013-06-28 | 2016-08-10 | 中国建筑第四工程局有限公司 | A kind of multi-ribbed hollow composite floor slab and manufacture method |
CN205712151U (en) * | 2016-06-20 | 2016-11-23 | 中国建筑第二工程局有限公司 | Concrete foundation prefabricated slab |
-
2016
- 2016-06-20 CN CN201610442174.2A patent/CN105926657B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN105926657A (en) | 2016-09-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107119574B (en) | A kind of Cantilever Construction Method of arch rib bridge girder | |
CN105926657B (en) | Construction method of concrete foundation precast slab | |
CN107653894A (en) | A kind of construction technology that foundation platform is made by precast concrete | |
CN104631677B (en) | Super thick concrete hollow terrace gradation construction technology | |
CN105350559B (en) | A kind of construction method of diamond dust structural floor suitable for large-sized workshop | |
CN209482591U (en) | Prefabricated molds shell structure column construction structure | |
US10895055B1 (en) | Molded concrete blocks having simulated brick or stone outer surfaces | |
CN104213565A (en) | Die supporting system for large deep pit steep slope surface cushion layer and supporting die casting construction method thereof | |
CN106939663A (en) | A kind of concrete hollow double-storied floor and its construction method | |
CN106217639B (en) | Ladder-type sleepers prefabricated construction device and method | |
US3879914A (en) | Method of making a platform structure | |
CN108005255A (en) | Wall construction method | |
CN205712151U (en) | Concrete foundation prefabricated slab | |
CN206844444U (en) | A kind of steel bar girder concrete hollow building roof based on non-dismantling formwork | |
CN207988292U (en) | Prefabricated stacking floor | |
JP2013159905A (en) | Cooling method of concrete structure | |
CN209907616U (en) | Cast-in-place floor construction joint side keeps off structure | |
CN105926807B (en) | A kind of cast-in-place integral concrete frame wall filled with masonry system and its construction method | |
CN106368362A (en) | Hollow floor for GBF high-infusion alloy thin-walled square boxes and manufacturing method | |
CN110439162A (en) | The construction technology of cast-in-situ hollow building roof | |
CN1132985C (en) | Formwork and its use method in building construction and outside decoration | |
CN107217865B (en) | A kind of increasing reinforced construction method of the flat beam section of main body frame | |
CN111287486B (en) | Construction method for underpinning hollow floor slab into cast-in-place floor slab | |
AU2016200205B2 (en) | Concrete Block Mat Installation by Gravity Flow | |
CN212176547U (en) | Building floor bathroom falls board construction template device in building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |