CN106217639B - Ladder-type sleepers prefabricated construction device and method - Google Patents

Ladder-type sleepers prefabricated construction device and method Download PDF

Info

Publication number
CN106217639B
CN106217639B CN201610609302.8A CN201610609302A CN106217639B CN 106217639 B CN106217639 B CN 106217639B CN 201610609302 A CN201610609302 A CN 201610609302A CN 106217639 B CN106217639 B CN 106217639B
Authority
CN
China
Prior art keywords
ladder
type sleepers
mold
drawing beam
side form
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610609302.8A
Other languages
Chinese (zh)
Other versions
CN106217639A (en
Inventor
柴海云
张劭明
张恩龙
赵秀丽
冯敏娟
邢海瑞
王宪东
金雁鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
China Railway Fengqiao Bridge Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
China Railway Fengqiao Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, China Railway Fengqiao Bridge Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201610609302.8A priority Critical patent/CN106217639B/en
Publication of CN106217639A publication Critical patent/CN106217639A/en
Application granted granted Critical
Publication of CN106217639B publication Critical patent/CN106217639B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/12Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed to form prestressed circumferential reinforcements
    • B28B23/16Prestressed reinforcing nets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/087Producing shaped prefabricated articles from the material by vibrating or jolting by means acting on the mould ; Fixation thereof to the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/043Wire anchoring or tensioning means for the reinforcements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/24Unitary mould structures with a plurality of moulding spaces, e.g. moulds divided into multiple moulding spaces by integratable partitions, mould part structures providing a number of moulding spaces in mutual co-operation
    • B28B7/241Detachable assemblies of mould parts providing only in mutual co-operation a number of complete moulding spaces

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

A kind of ladder-type sleepers prefabricated construction device and method.Device includes foundation ditch type production pedestal, mold, more dither motors;It includes two big stretch-drawing beam, four jack, twice load wall, small stretch-drawing beam, more finish rolling deformed bars that foundation ditch type, which produces pedestal,;Bottom plate and polylith elastomer block is turned up including side form, four pieces of end moulds, four side form closing devices, more foundation mould supporting legs, more foundation mould connecting cross beams, polyliths in two pieces of bed dies, four pieces of outer side molds, four pieces in mold;Dither motor is arranged at intervals on different bed die connecting cross beams.Existing foundation ditch type can be produced the capital equipment that pedestal repacks ladder-type sleepers production line by the ladder-type sleepers prefabricated construction device and method of the present invention, and it can rationally increase the quantity of production pedestal according to production task and duration, solve the problems, such as that other domestic producers carry out the inefficiency of fixation and the dismounting of bed die and side form using bolt, pre-stress construction synchronous control is realized, the working efficiency of filling concrete process is improved.

Description

Ladder-type sleepers prefabricated construction device and method
Technical field
The invention belongs to the prefabricating technique fields of city track traffic engineering ladder-type sleepers, are specifically related to a kind of trapezoidal Sleeper fabricated device and construction method.
Background technology
In recent years, with the fast development of domestic city urban rail transit construction, to the high reliability of track structure, it is low at Originally, few repair, low vibration, low noise, high shock resistance etc. have requirements at the higher level.Ladder-type sleepers are anti-using at certain intervals The material that shakes is support, realizes the low vibration of city rail, low noise is widely used to Beijing, Shanghai, Ningbo, depth at present In the Rail Transit System in multiple cities such as ditch between fields.But the construction method of domestic existing production ladder-type sleepers there are it is following not Foot:
1, ladder-type sleepers mold be using bolt carry out bed die and side form fixation and dismounting, therefore dismantle the efficiency of loading and unloading compared with It is low;
2, the pre-stress construction of ladder-type sleepers is carried out by the way of manual operation jack, therefore the synchronization of work progress Property is affected by human factor;
3, concrete process carries out cloth, the mode that dynamic stick vibrates using hopper, therefore working efficiency is relatively low.
Invention content
To solve the above-mentioned problems, the purpose of the present invention is to provide a kind of ladder-type sleepers prefabricated construction device and methods.
In order to achieve the above object, ladder-type sleepers prefabricated construction device provided by the invention include foundation ditch type production pedestal, Mold, more dither motors;The foundation ditch type production pedestal includes two big stretch-drawing beam, four jack, twice Load wall, small stretch-drawing beam, more finish rolling deformed bars;The big stretch-drawing beam of two of which along foundation pit length direction can move Mode is arranged in parallel in the both ends of foundation pit;Twice load wall is arranged in parallel in the both sides of foundation pit, per pass along the length direction of foundation pit The both ends of load wall are connected with one end of a jack respectively, and the other end of every jack is connected to is located at the same side with it One big stretch-drawing beam one end;Small stretch-drawing beam is arranged in a manner of parallel with big stretch-drawing beam in the inside of foundation pit, and And it is connected with one big stretch-drawing beam by more finish rolling deformed bars disposed in parallel;The mold includes two pieces of bottoms Mould, four pieces of outer side molds, side form, four pieces of end moulds, four side form closing devices, more foundation mould supporting legs, the connection of more foundation moulds in four pieces Bottom plate and polylith elastomer block is turned up in crossbeam, polylith;Wherein be turned up bottom plate using bolt along foundation pit length direction in the middle part of foundation pit Two row are arranged side by side on bottom surface;One piece of elastomer block is installed in lower end per foundation mould supporting leg, and every piece of elastomer block is placed on one piece of height-regulating The surface of bottom plate, the vibration for reducing dither motor;One piece of bed die is fixed in the upper end of each column bed die supporting leg simultaneously;Every piece The interior outer ledge of bed die is respectively equipped with the interior side form and outer side mold that one piece can be opened and closed using side form closing device, front and back End is respectively equipped with a reassembling type end mould;More foundation mould connecting cross beam intervals are connected between two pieces of bed dies;More high-frequency vibrations Motor is arranged at intervals on different bed die connecting cross beams.
The end mould is made of the bottom plate, intermediate end plate and upper head plate set gradually from bottom to up, wherein bottom plate Upper end-face edge and the lower edge of upper head plate be respectively formed multiple U-shaped prestress wire impenetrating mouths for being separated by setting, and And positioning pin is added on bottom plate, corner when form removal can be avoided to knock damage under the premise of ensuring registration in this way.
The interior side form is at fastener for connection and outer side mold is detachable structure at boss, thus can be by inside Mould and outer side mold split into multistage, are beneficial for disassembly and assembly in this way and reinforcing bar enters mould conveniently, and can avoid knocking caused by form removal at boss Damage.
When producing the ladder-type sleepers with track form, sliding rail is additionally provided between each column elastomer block and height-regulating bottom plate Slot, when prestressing force being made to put, a mold energy whole slide, and the reset after a sliding is put convenient for mold, when ladder-type sleepers being made to put Stress can transmit naturally without damaging track position thereon or mold.
The jack uses the jack of 3000KN.
The construction method of the prefabricated ladder-type sleepers of ladder-type sleepers prefabricated construction device provided by the invention includes carrying out in order The following steps:
1) tie up ladder-type sleepers steel reinforcement cage on the ground first, steel reinforcement cage by more prestress wires, polylith sub-wire every Plate and multi-turn stirrup are constituted, wherein more prestress wires are arranged in parallel, and cross section is rectangular;It is formed on sub-wire partition board There are multiple circular holes for through prestress wire, polylith sub-wire partition board interval in a manner of vertical with prestress wire is set It sets in the middle part of prestress wire;Stirrup is looped around the both sides position of more prestress wires;
2) each steel reinforcement cage is placed on to the surface of one piece of bed die, is then anchored at the both ends of prestress wire respectively small On stretch-drawing beam and another the big stretch-drawing beam not being connected with small stretch-drawing beam;
3) lateral connection steel pipe between two steel reinforcement cages, reinforcing bar at boss, the accessory at suspension-center pre-embedded including bolt are installed;
4) it is synchronized using four jack and ejects two big stretch-drawing beam outward to carry out the two-way whole of prestress wire Body initial tensioning, then on small stretch-drawing beam using centre-hole jack by root carry out prestress wire it is single look for it is even, then It is synchronized using four jack and ejects two big stretch-drawing beam outward to carry out two-way whole whole tensioning, until reaching required Clamp force;
5) side form closing device is utilized to mold interior side form and outer side mold, end mould installs bottom plate first when installing, under making Every prestress wire on layer prestress wire is located at each U-shaped prestress steel of bottom plate upper end-face edge In twisted wire impenetrating mouth, then intermediate end plate is installed, upper head plate is installed again later, makes every on the prestress wire of upper layer to answer in advance Power steel strand wires are located in each U-shaped prestress wire impenetrating mouth of upper head plate lower edge;
6) concrete is gradually poured in from one end of foundation pit to the other end by bed die, outer side mold, inside using material distributing machine In the space that mould and end mould are constituted, starts dither motor during perfusion and vibrated, so that concrete compaction is molded, later Top surface is caught up with to pressure in time, is smoothed out;And the pre-buried temperature sensor when last block ladder-type sleepers is perfused, so that real-time tracking detects Temperature variations inside ladder-type sleepers;
7) ladder-type sleepers are conserved using steam, until the intensity of ladder-type sleepers reaches 48Mpa;
8) it utilizes side form closing device to mold interior side form and outer side mold, while end mould and above-mentioned accessory being dismantled;
9) it synchronizes retraction using four jack and makes two big stretch-drawing beam inward against movement, to carry out prestress steel Putting for twisted wire is opened;
10) ladder-type sleepers that the polylith on every piece of bed die links together are demoulded using lifting appliance, it is thus complete At entire work progress.
Existing foundation ditch type can be produced pedestal and repacked by ladder-type sleepers prefabricated construction device and method provided by the invention The capital equipment of ladder-type sleepers production line, and can rationally increase the quantity of production pedestal according to production task and duration, it solves Other domestic producers carry out the inefficiency problem of fixation and the dismounting of bed die and side form using bolt, realize pre-stress construction Synchronous control improves the working efficiency of filling concrete process.
Description of the drawings
Fig. 1 is that foundation ditch type produces pedestal part-structure vertical view in ladder-type sleepers prefabricated construction device provided by the invention.
Fig. 2 is that foundation ditch type produces pedestal structure vertical view in ladder-type sleepers prefabricated construction device provided by the invention.
Fig. 3 is ladder-type sleepers mould structure vertical view in ladder-type sleepers prefabricated construction device provided by the invention.
Fig. 4 is ladder-type sleepers prefabricated construction apparatus structure side view provided by the invention.
Fig. 5 is sub-wire diaphragm structure schematic diagram employed in ladder-type sleepers precast construction method provided by the invention.
Fig. 6 is reinforcement cage structure vertical view employed in ladder-type sleepers precast construction method provided by the invention.
Fig. 7 be in Fig. 6 A-A to sectional view.
Fig. 8 is vertical view when being constructed using ladder-type sleepers prefabricated construction device provided by the invention.
Specific implementation mode
Ladder-type sleepers prefabricated construction device and method provided by the invention is carried out in the following with reference to the drawings and specific embodiments It is described in detail.
As Figure 1-Figure 8, ladder-type sleepers prefabricated construction device provided by the invention includes foundation ditch type production pedestal, mould Tool, more dither motors 4;The foundation ditch type production pedestal includes two big stretch-drawing beam 1, four jack 2, twice Load wall 3, small stretch-drawing beam 5, more finish rolling deformed bars 6;The big stretch-drawing beam of two of which 1 along foundation pit length direction can move Dynamic mode is arranged in parallel in the both ends of foundation pit;Twice load wall 3 is arranged in parallel in the both sides of foundation pit along the length direction of foundation pit, The both ends of per pass load wall 3 are connected with one end of a jack 2 respectively, and the other end of every jack 2 is connected to and its position In one end of the one big stretch-drawing beam 1 of the same side;Small stretch-drawing beam 5 is arranged in a manner of parallel with big stretch-drawing beam 1 in base The inside in hole, and be connected with one big stretch-drawing beam 1 by more finish rolling deformed bars 6 disposed in parallel;The mould Tool includes 9, four pieces of ends mould 10, four side form closing devices 11, more foundation of side form in two pieces of 7, four pieces of bed die, 8, four pieces of outer side molds Bottom plate 14 and polylith elastomer block 15 is turned up in mould supporting leg 12, more foundation mould connecting cross beams 13, polylith;Bottom plate 14 is wherein turned up and utilizes spiral shell Two row are arranged side by side in the middle part of the foundation pit along the length direction of foundation pit for bolt on bottom surface;Lower end per foundation mould supporting leg 12 is installed by one piece of bullet Property block 15, every piece of elastomer block 15 be placed on one piece height-regulating bottom plate 14 surface, the vibration for reducing dither motor 4;Often One piece of bed die 7 is fixed in the upper end of row bed die supporting leg 12 simultaneously;The interior outer ledge of every piece of bed die 7 is respectively equipped with one piece and can utilize The interior side form 9 and outer side mold 8 that side form closing device 11 is opened and closed, front and back end are respectively equipped with a reassembling type end mould 10;More The interval of bed die connecting cross beam 13 is connected between two pieces of bed dies 7;More dither motors 4 are arranged at intervals on different bed die connections On crossbeam 13.
The end mould 10 is made of the bottom plate 25, intermediate end plate 16 and upper head plate 17 set gradually from bottom to up, The upper end-face edge of middle bottom plate 25 and the lower edge of upper head plate 17 are respectively formed multiple U-shaped prestress steel twists for being separated by setting Line impenetrating mouth, and positioning pin is added on bottom plate 25, when can avoid form removal under the premise of ensuring registration in this way Knock damage in corner.
The interior side form 9 at fastener for connection 23 and outer side mold 8 24 be detachable structure at boss, thus may be used Interior side form 9 and outer side mold 8 are split into multistage, is beneficial for disassembly and assembly in this way and reinforcing bar enters mould conveniently, and can avoid form removal at boss It is caused to knock damage.
When producing the ladder-type sleepers with track form, sliding is additionally provided between each column elastomer block 15 and height-regulating bottom plate 14 Track slot 18, when prestressing force being made to put, mold energy whole slide, and the reset after a sliding is put convenient for mold, so that ladder-type sleepers is put Stress when opening can be transmitted naturally without damaging track position or mold thereon.
The jack 2 uses the jack of 3000KN.
Construction method using the prefabricated ladder-type sleepers of ladder-type sleepers prefabricated construction device provided by the invention includes in order The following steps of progress:
1) ladder-type sleepers steel reinforcement cage is tied up on the ground first, steel reinforcement cage is by more prestress wires 19, polylith sub-wire Partition board 20 and multi-turn stirrup 21 are constituted, wherein more prestress wires 19 are arranged in parallel, and cross section is rectangular;Sub-wire every Be formed on plate 20 it is multiple for through prestress wire 19 circular holes 22, polylith sub-wire partition board 20 with prestress wire 19 vertical modes are arranged at intervals on the middle part of prestress wire 19, for levels prestress wire 19 to be separated and It determines the length of ladder-type sleepers, occurs to intersect torsion after capable of effectively avoiding prestress wire 19 from entering mould in this way;21 ring of stirrup It is wound on the both sides position of more prestress wires 19;
2) each steel reinforcement cage is placed on to the surface of one piece of bed die 7, then anchors at the both ends of prestress wire 19 respectively On another the big stretch-drawing beam 1 not being connected in small stretch-drawing beam 5 and with small stretch-drawing beam 5;
3) lateral connection steel pipe between two steel reinforcement cages, reinforcing bar at boss, the accessory at suspension-center pre-embedded including bolt are installed;
4) it is synchronized using four jack 2 and ejects two big stretch-drawing beam 1 outward to carry out the double of prestress wire 19 To whole initial tensioning, then the single of prestress wire 19 is carried out by root on small stretch-drawing beam 5 using centre-hole jack Look for even, recycling four jack 2 to synchronize outward, the two big stretch-drawing beam of ejection 1 is to carry out two-way whole whole tensioning, up to reaching To required tensile force;
5) interior side form 9 and outer side mold 8 are molded using side form closing device 11, end mould 10 installs bottom plate first when installing 25, make the every prestress wire 19 on lower layer's prestress wire 19 be located at 25 upper end-face edge of bottom plate each In U-shaped prestress wire impenetrating mouth, then intermediate end plate 16 is installed, upper head plate 17 is installed again later, makes upper layer prestressing force Every prestress wire 19 on steel strand wires 19 is located at each U-shaped prestress steel twist of 17 lower edge of upper head plate In line impenetrating mouth;
6) concrete is gradually poured in from one end of foundation pit to the other end using material distributing machine by bed die 7, outer side mold 8, interior Side form 9 and end mould 10 constitute space in, during perfusion start dither motor 4 vibrated so that concrete compaction at Pressure is caught up in top surface by type in time later, smoothes out, to ensure the thickness of ladder-type sleepers and the flatness of bottom surface;And last is being perfused Pre-buried temperature sensor when block ladder-type sleepers, so as to the temperature variations inside real-time tracking detection ladder-type sleepers;
7) ladder-type sleepers are conserved using steam, until the intensity of ladder-type sleepers reaches 48Mpa;
8) interior side form 9 and outer side mold 8 are molded using side form closing device 11, while end mould 10 and above-mentioned accessory is torn open It opens;
9) it synchronizes retraction using four jack 2 and makes two big stretch-drawing beam 1 inward against movement, to carry out prestressing force Putting for steel strand wires 19 is opened;
10) ladder-type sleepers that the polylith on every piece of bed die 7 links together are demoulded using lifting appliance, it is thus complete At entire work progress.

Claims (6)

1. a kind of ladder-type sleepers prefabricated construction device, it is characterised in that:The ladder-type sleepers prefabricated construction device includes foundation pit Formula produces pedestal, mold, more dither motors (4);The foundation ditch type production pedestal includes two big stretch-drawing beams (1), four jack (2), twice load wall (3), small stretch-drawing beam (5), more finish rolling deformed bars (6);Two of which is big Stretch-drawing beam (1) is arranged in parallel in the both ends of foundation pit in a manner of it can be moved along foundation pit length direction;Twice load wall (3) is along base The length direction in hole is arranged in parallel in the both sides of foundation pit, the both ends of per pass load wall (3) one end with a jack (2) respectively It is connected, the other end of every jack (2) is connected to is located at one end of one of the same side big stretch-drawing beam (1) with it;Xiao Zhang It draws crossbeam (5) to be arranged in a manner of parallel with big stretch-drawing beam (1) in the inside of foundation pit, and passes through more essences disposed in parallel Spiral (6) is rolled with one big stretch-drawing beam (1) to be connected;The mold includes two pieces of bed dies (7), four pieces of outer side molds (8), side form (9), four pieces of end moulds (10), four side form closing devices (11), more foundation mould supporting legs (12), more foundation moulds in four pieces Bottom plate (14) and polylith elastomer block (15) is turned up in connecting cross beam (13), polylith;Bottom plate (14) is wherein turned up using bolt along foundation pit Length direction two row are arranged side by side in the middle part of the foundation pit on bottom surface;Lower end per foundation mould supporting leg (12) is installed by one piece of elastomer block (15), every piece of elastomer block (15) is placed on one piece of surface that bottom plate (14) is turned up, for reducing shaking for dither motor (4) It is dynamic;One piece of bed die (7) is fixed in the upper end of each column bed die supporting leg (12) simultaneously;The interior outer ledge of every piece of bed die (7) is respectively equipped with One piece can be respectively equipped with one using the interior side form (9) and outer side mold (8), front and back end that side form closing device (11) are opened and closed Reassembling type end mould (10);More foundation mould connecting cross beam (13) intervals are connected between two pieces of bed dies (7);More dither motors (4) it is arranged at intervals on different bed die connecting cross beams (13).
2. ladder-type sleepers prefabricated construction device according to claim 1, it is characterised in that:The end mould (10) is by under The supreme bottom plate (25) set gradually, intermediate end plate (16) and upper head plate (17) are constituted, wherein the upper end edge of bottom plate (25) The lower edge of edge and upper head plate (17) is respectively formed multiple U-shaped prestress wire impenetrating mouths for being separated by setting, and under Positioning pin is added on end plate (25), corner when form removal can be avoided to knock damage under the premise of ensuring registration in this way.
3. ladder-type sleepers prefabricated construction device according to claim 1, it is characterised in that:The interior side form (9) is in steel Pipe junction and outer side mold (8) are detachable structure at boss, thus can split interior side form (9) and outer side mold (8) At multistage, it is beneficial for disassembly and assembly in this way and reinforcing bar enters mould conveniently, and can avoid knocking damage caused by form removal at boss.
4. ladder-type sleepers prefabricated construction device according to claim 1, it is characterised in that:In production with track form When ladder-type sleepers, each column elastomer block (15) and it is turned up between bottom plate (14) and is additionally provided with sliding rail groove (18), when prestressing force being made to put, A mold energy whole slide, and the reset after sliding is put convenient for mold, stress when ladder-type sleepers being made to put can transmit naturally and Track position or mold thereon is not damaged.
5. ladder-type sleepers prefabricated construction device according to claim 1, it is characterised in that:The jack (2) uses The jack of 3000KN.
6. a kind of construction method using the prefabricated ladder-type sleepers of ladder-type sleepers prefabricated construction device described in claim 1, special Sign is:The construction method includes the following steps carried out in order:
1) tie up ladder-type sleepers steel reinforcement cage on the ground first, steel reinforcement cage by more prestress wires (19), polylith sub-wire every Plate (20) and multi-turn stirrup (21) are constituted, wherein more prestress wires (19) are arranged in parallel, and cross section is rectangular;Point Be formed with multiple circular holes (22) for through prestress wire (19) on silk partition board (20), polylith sub-wire partition board (20) with The vertical mode of prestress wire (19) is arranged at intervals in the middle part of prestress wire (19);Stirrup (21) is looped around more in advance The both sides position of prestress steel strand (19);
2) each steel reinforcement cage is placed on to the surface of one piece of bed die (7), then anchors at the both ends of prestress wire (19) respectively On another the big stretch-drawing beam (1) not being connected in small stretch-drawing beam (5) and with small stretch-drawing beam (5);
3) lateral connection steel pipe between two steel reinforcement cages, reinforcing bar at boss, the accessory at suspension-center pre-embedded including bolt are installed;
4) it is synchronized using four jack (2) and ejects two big stretch-drawing beam (1) outward to carry out prestress wire (19) Two-way entirety initial tensioning, then carries out prestress wire (19) using centre-hole jack on small stretch-drawing beam (5) by root It is single look for it is even, recycle four jack (2) synchronize outward the two big stretch-drawing beam (1) of ejection to carry out two-way whole open eventually It draws, until reaching required tensile force;
5) side form closing device (11) is utilized to mold interior side form (9) and outer side mold (8), under being installed first when end mould (10) is installed End plate (25) makes the every prestress wire (19) on lower layer's prestress wire (19) be located at bottom plate (25) upper end In each U-shaped prestress wire impenetrating mouth at edge, intermediate end plate (16) is then installed, upper head plate is installed again later (17), the every prestress wire (19) on upper layer prestress wire (19) is made to be located at upper head plate (17) lower edge Each U-shaped prestress wire impenetrating mouth in;
6) concrete is gradually poured in from one end of foundation pit to the other end using material distributing machine by bed die (7), outer side mold (8), interior Start dither motor (4) in the space that side form (9) and end mould (10) are constituted, during perfusion to be vibrated, so that concrete Pressure is caught up in top surface by closely knit molding in time later, smoothes out;And the pre-buried temperature sensor when last block ladder-type sleepers is perfused, with Just the temperature variations inside real-time tracking detection ladder-type sleepers;
7) ladder-type sleepers are conserved using steam, until the intensity of ladder-type sleepers reaches 48Mpa;
8) it utilizes side form closing device (11) by interior side form (9) and outer side mold (8) die sinking, while by end mould (10) and above-mentioned matching Part is dismantled;
9) it utilizes the synchronous retraction of four jack (2) and makes two big stretch-drawing beam (1) inward against movement, to carry out prestressing force Putting for steel strand wires (19) is opened;
10) ladder-type sleepers that the polylith on every piece of bed die (7) links together are demoulded using lifting appliance, is thus completed Entire work progress.
CN201610609302.8A 2016-07-28 2016-07-28 Ladder-type sleepers prefabricated construction device and method Active CN106217639B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610609302.8A CN106217639B (en) 2016-07-28 2016-07-28 Ladder-type sleepers prefabricated construction device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610609302.8A CN106217639B (en) 2016-07-28 2016-07-28 Ladder-type sleepers prefabricated construction device and method

Publications (2)

Publication Number Publication Date
CN106217639A CN106217639A (en) 2016-12-14
CN106217639B true CN106217639B (en) 2018-10-26

Family

ID=57535286

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610609302.8A Active CN106217639B (en) 2016-07-28 2016-07-28 Ladder-type sleepers prefabricated construction device and method

Country Status (1)

Country Link
CN (1) CN106217639B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107460792A (en) * 2017-08-15 2017-12-12 北京交通大学 A kind of clad steel sleeper
CN108708228A (en) * 2018-07-05 2018-10-26 华东交通大学 The automatic compensation steel sleeper of symmetrical inclined block self locking formula sedimentation
CN109898371A (en) * 2019-04-11 2019-06-18 中国铁道科学研究院集团有限公司铁道建筑研究所 Sleeper, sleeper tooling and sleeper production method
CN111993558A (en) * 2020-08-11 2020-11-27 中铁第四勘察设计院集团有限公司 Production method of steel tube concrete sleeper
CN116890384B (en) * 2023-09-11 2024-01-23 中铁九局集团第三建设有限公司 Vibrating floating platform

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2487772Y (en) * 2001-03-20 2002-04-24 王胜利 Sleeper special for high-speed raiway
CN101177926A (en) * 2007-12-10 2008-05-14 中铁一局集团有限公司新运工程公司 City railway trapezoidal crosstie vibration-damping ballast construction method
CN101270559A (en) * 2007-03-21 2008-09-24 上海申通轨道交通研究咨询有限公司 Floating plate rail structure with combined spring support
CN101418535A (en) * 2008-10-10 2009-04-29 中铁十一局集团第三工程有限公司 Construction method of monolithic road-bed in rail tunnel
WO2012048664A1 (en) * 2010-10-14 2012-04-19 Liu Zhongchen Permanent magnet motor with outer spiral rotor and wheel-rail vehicle road system with permanent magnet suspension

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2487772Y (en) * 2001-03-20 2002-04-24 王胜利 Sleeper special for high-speed raiway
CN101270559A (en) * 2007-03-21 2008-09-24 上海申通轨道交通研究咨询有限公司 Floating plate rail structure with combined spring support
CN101177926A (en) * 2007-12-10 2008-05-14 中铁一局集团有限公司新运工程公司 City railway trapezoidal crosstie vibration-damping ballast construction method
CN101418535A (en) * 2008-10-10 2009-04-29 中铁十一局集团第三工程有限公司 Construction method of monolithic road-bed in rail tunnel
WO2012048664A1 (en) * 2010-10-14 2012-04-19 Liu Zhongchen Permanent magnet motor with outer spiral rotor and wheel-rail vehicle road system with permanent magnet suspension

Also Published As

Publication number Publication date
CN106217639A (en) 2016-12-14

Similar Documents

Publication Publication Date Title
CN106217639B (en) Ladder-type sleepers prefabricated construction device and method
CN103290967B (en) A kind of multi-ribbed hollow composite floor slab and manufacture method
CN103046465B (en) Reinforcing construction method for foam core die precast hollow plate beam
CN106217590A (en) Pre-tensioned rail plate flowing water unit method produces tooling device and method
WO2013119016A1 (en) Arch block assembly, method for manufacturing same, and method for constructing same
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN201872232U (en) Vertical cable channel formwork
CN101758544A (en) Core pulling molding device of pressure-type hollow brick machine
CN206140658U (en) Open track plate current water unit method production construction installation equipment earlier
CN108858690B (en) Mold for producing precast concrete member and use method
CN208197139U (en) A kind of pre-stress rail plate continuous production complete set of equipments
CN106884664B (en) Tunnel inverted arch template and tunnel inverted arch filling rapid construction method
CN105926657B (en) A kind of construction method of concrete foundation prefabricated board
CN112873527A (en) Manufacturing mold and method for supporting pile
CN105946099B (en) Fill the method for construction of core assembly concrete beam
CN205804745U (en) A kind of precast concrete shear wall component
RU117161U1 (en) STAND FOR MAKING PRELIMINARY STRESSED REINFORCED CONCRETE SUPPORTS
CN102363960A (en) Large-volume concrete pouring method for nuclear island raft foundation
CN210140941U (en) Hollow floor slab structure
CN107217790A (en) A kind of prefabricated assembling type reinforced concrete framework open tubular column and its construction method
CN202099748U (en) Hoisting device used for box girder embedding erection of box girder
CN109016086A (en) Prestressed solid square pile arranges mould and square pile processing method
CN105216095B (en) A kind of concrete prefabricated building block multimode cavity forming machine
CN110130280B (en) Cantilever bracket concrete lower template and support frame dismantling method
CN107214819A (en) A kind of building structural post is molded moulding box

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Yang Xuekun

Inventor after: Chai Haiyun

Inventor after: Zhang Shaoming

Inventor after: Zhang Enlong

Inventor after: Zhao Xiuli

Inventor after: Feng Minjuan

Inventor after: Xing Hairui

Inventor after: Wang Xiandong

Inventor after: Jin Yanpeng

Inventor before: Chai Haiyun

Inventor before: Zhang Shaoming

Inventor before: Zhang Enlong

Inventor before: Zhao Xiuli

Inventor before: Feng Minjuan

Inventor before: Xing Hairui

Inventor before: Wang Xiandong

Inventor before: Jin Yanpeng

CB03 Change of inventor or designer information