CN105888694A - Tunnel integral steel mould lining trolley capping device and seamless capping process - Google Patents

Tunnel integral steel mould lining trolley capping device and seamless capping process Download PDF

Info

Publication number
CN105888694A
CN105888694A CN201610408756.9A CN201610408756A CN105888694A CN 105888694 A CN105888694 A CN 105888694A CN 201610408756 A CN201610408756 A CN 201610408756A CN 105888694 A CN105888694 A CN 105888694A
Authority
CN
China
Prior art keywords
binds
capping
pipe
cover plate
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610408756.9A
Other languages
Chinese (zh)
Inventor
张济宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610408756.9A priority Critical patent/CN105888694A/en
Publication of CN105888694A publication Critical patent/CN105888694A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a tunnel integral steel mould lining trolley capping device and a seamless capping process, and aims to solve the problem of faulting of slab ends at a capping position of a tunnel secondary lining concrete surface. The tunnel integral steel mould lining trolley capping device comprises a panel, a capping cover plate, a lifting rotating shaft, a shaft seat, a limiting device and a capping pipe, wherein a capping porthole is formed in the panel; the capping pipe is fixed to the lower surface of the panel; a gap is formed in the panel on one side of the capping porthole; a groove is formed in one side, which is in contact with the capping pipe, in the gap; the upper end of the lifting rotating shaft is vertically fixed to a lug part; the lifting rotating shaft penetrates through the gap and the shaft seat. According to the tunnel integral steel mould lining trolley capping device and the seamless capping process, a novel capping device technology that the capping cover plate can rotate and realize axial lifting is adopted, and smooth and close attachment of the capping cover plate and a steel mould panel can be realized, so that the problem of faulting of the slab ends at the capping position of the tunnel secondary lining concrete surface is solved fundamentally, the concrete surface at the capping position has no faulting of the slab ends after a mould is detached, and the whole body is smooth.

Description

Tunnel overall steel die bush platform building cart binds device and seamless closed-top technology
Technical field
This invention relates to technical field of tunnel construction, and specifically one is applicable to tunnel overall steel die bush block Bind device and the seamless closed-top technology of chassis.
Background technology
At present, the length of home and abroad, big tunnel use overall punching block hydraulic lining trolley to construct mostly, Pumped concrete earth process is used to carry out Tunnel Second Lining Construction.Overall punching block hydraulic lining trolley has One functional part is called the device that binds, as the term suggests, it is simply that during placing of binding, concrete is to pass through The tube pump that binds of device of binding sends into mould, after placing of binding completes, utilizes the device that binds to close hole of binding and reaches to bind Purpose.
In existing overall punching block hydraulic lining trolley pump concrete capping technology, the device that binds typically uses Inner side board plug type or outer side rotary bind device structure, as a example by the board plug type of inner side, it is simply that on the top binding pipe Portion inserts a plate, due to the existence of plate, after pouring complete and maintenance, will necessarily form one at this Cylindrical faulting of slab ends.For another example, outer side rotary, is to be previously implanted rotation cover at the top of the pipe that binds, and rotates The existence of cover plate, will necessarily cause depression, and then form reverse cylindrical faulting of slab ends.
So, the pump concrete in reality is when binding staged construction, and bound device structure design limit, Concrete surface can leave cylindrical faulting of slab ends (recessed or prominent lining concrete surface), nothing in hole site of binding Method fundamentally solves capping position concrete surface residual faulting of slab ends problem, have impact on tunnel two to a certain extent Secondary lining cutting overall appearance quality.
Summary of the invention
In order to solve the deficiencies in the prior art, present invention mainly solves Tunnel Second Lining concrete surface and bind Position faulting of slab ends problem, reaches improve overall punching block hydraulic lining trolley pump concrete capping technology level and carry The purpose of high Tunnel Second Lining concrete surface overall appearance quality.
The technical solution adopted for the present invention to solve the technical problems is:
Tunnel overall steel die bush platform building cart binds device, it is characterised in that include panel, the cover plate that binds, lifting Rotating shaft, axle bed, stopping means and the pipe that binds, wherein said panel is provided with aperture of binding, under panel The fixing pipe that binds in surface, described in bind side, aperture panel on jagged, and bind with described in breach The side of pipe contact is provided with groove;
The cover plate that binds described in diameter is identical with described aperture of binding is provided with chamfering and ear;
Described lift shaft upper end is vertically fixed on described ear;
Outside the described pipe that binds, it is provided with the axle bed for installing lift shaft, and described lift shaft passes Breach and axle bed posterior end are operating side.
Further, at described lift shaft with bind and be provided with stopping means between tube wall.
Further, at lift shaft with bind and arrange alignment scale between pipe, when both alignment scale weights During conjunction, described in the cover plate upper surface that binds concordant with described panel upper surface.
A kind of seamless closed-top technology, it is characterised in that order follows the steps below:
The first step, pump concrete binds before placing, the cover plate jacking rotating to outside aperture of binding of binding, Bind cover plate and panel attachment;
Second step, snaps connection the described pipe that binds with concrete conveying pipeline, and concrete is pumped through piping into Mould, until filling slurry by mould;
3rd step, rotates backward lift shaft immediately so that the cover plate that binds turns to bind at the mouth of pipe, described The cover plate that binds declines under the pressure of concrete slurry and closes the mouth of pipe that binds;
4th step, dismantling concrete conveying pipe, and maintenance;
5th step, maintenance removes, after completing, the device that binds.
Further, in step 3, sentence by observing lift shaft and the alignment scale bound between pipe The disconnected cover plate upper surface that binds is the most concordant with described panel upper surface.
The invention has the beneficial effects as follows:
The present invention have developed novel overall punching block hydraulic lining trolley pump concrete capping technology, uses envelope Lamina tecti is rotatable and realizes the Novel sealing apical organ technology axially lifted, and the cover plate that binds can be real with steel die Now smooth closely connected, fundamentally solve Tunnel Second Lining concrete surface capping position faulting of slab ends problem, tear open After mould, capping position concrete surface is without faulting of slab ends, overall smooth-going.
Secondary lining concrete surface outward appearance entirety smoothes out, and can effectively promote overall punching block hydraulic lining trolley pump Send concrete capping technology level and Tunnel Second Lining concrete surface overall appearance quality.
The present invention very Lay Importance on Practical, enters at the overall punching block hydraulic lining trolley pumped concrete earth process of application In the long tunnel of row secondary moulded lining construction, overall punching block hydraulic lining trolley pump can be effectively improved Send concrete capping technology level and improve the purpose of Tunnel Second Lining concrete surface overall appearance quality, Have broad application prospects in constructing tunnel field.
Accompanying drawing explanation
Fig. 1 is the axonometric chart of device of originally binding.
Fig. 2 is the full sectional view of device of originally binding.
Fig. 3 is the state diagram that cover plate opens of binding.
Fig. 4 is the part-structure schematic diagram of device of binding.
Fig. 5 is the axonometric chart of cover plate of binding.
In figure: 1 panel, 11 bind aperture, 12 breach, 13 grooves, and 2 bind cover plate, 21 ears, and 22 Chamfer design, 3 lift shafts, 31 operating sides, 4 axle beds, 41 alignment scales, 5 stopping means, 6 bind Pipe.
Detailed description of the invention
As shown in Figures 1 to 5, for existing defect, the protection main body of the present invention is as follows: exploitation is one Kind of tunnel overall steel die bush platform building cart binds device, is made up of following structure.
The novel device structure that binds is mainly by panel 1, the cover plate 2 that binds, lift shaft 3, axle bed 4, spacing Device 5 and the pipe 6 that binds etc. form, and wherein panel 1 is with a big plate of monoblock, use steel plate to make, Panel is determined a major diameter bind aperture 11, such as, the aperture of binding of 20 cm diameters, envelope The diameter of apical pore mouth is identical with the internal diameter of the corresponding pipe that binds.Corresponding welds one at the lower surface of panel Bind pipe 5, and the pipe that binds is pipe, for connecting with concrete conveying pipeline.
A breach 12 determined by the panel of above-mentioned side, aperture 11 of binding, is used for rotating shaft is installed.? The side contacted with the above-mentioned pipe that binds in breach 12 is provided with a groove 13, is used for discharging slurry.
The cover plate 2 that binds uses chamfer design 22, and the side of the cover plate 2 that binds arranges an ear 21, ear 21 for connecting with lift shaft 3, and connected mode is for being welded to connect, and lift shaft 3 is and the cover plate that binds Vertical.
Above-mentioned pipe 6 side of binding is provided with some axle beds 4, axle bed about 4 orientation be coaxially disposed and with After the lift shaft 3 that above-mentioned breach 12 position is the most corresponding, above-mentioned passes breach and axle bed, lower end Extend out and be provided with the operating side 31 being easy to wrench operated.
The above-mentioned cover plate 2 that binds uses chamfering, band plate ear to design;Lift shaft 3 is fixed with the cover plate 2 that binds Connect, can lift vertically and rotate;The pipe that binds is fixed as one with the panel 1 of lining trolley, and bind pipe The indentation, there corresponding with the ear of the cover plate that binds uses bevel design, and concrete binds to manage and is fixed as one with axle bed Body.
Above-mentioned each parts use process for machining, assemble and complete carry out outer surface grinding process, it is ensured that envelope The cover plate that binds under apical organ closed mode smooths with slab joint.
Seamless closed-top technology process is as follows:
First, pump concrete binds before placing, the cover plate jacking rotating to outside aperture of binding of binding, Avoid the orifice position that binds, fit with template, open the mouth of pipe that binds;
Second step, the device concrete that will bind binds to manage and snaps connection with concrete conveying pipeline, and concrete is by pipe Road is pumped into mould, until filling slurry by mould, and end of binding,
3rd step, binds after end, rotates backward rotation and lifting rotating shaft so that the cover plate that binds turns to bind At the mouth of pipe, the cover plate that binds falls under the pressure of concrete slurry and closes the mouth of pipe that binds, it is achieved coagulation grave Top;Binding after cover closure, cover plate smooths with panel outer surface seam, eliminates the faulting of slab ends phenomenon that binds.? During the above-mentioned cover plate that binds falls, the chamfering on cover plate that binds is arranged so that the cover plate that binds has Automatic capturing function.
4th step, dismantling concrete conveying pipe, and maintenance,
5th step, maintenance removes, after completing, the device that binds.
By the application of said structure, overall punching block hydraulic lining trolley pumped concrete earth process Novel sealing top skill The technological process of art: axially jacking lift shaft, rotary seal lamina tecti open hole → connections of binding bind manage and Concrete delivery pipe → pump concrete → rotation and lifting rotating shaft is until cover plate coincide with aperture of binding and closes envelope Apical pore → → bound.
The key problem in technology point of the present invention is the perfect knot of covering plate structure, liftable pivot structure and panel of binding Close, and after closure, the cover plate that binds forms coordinating of a near seamless with panel.Operating process is simple, logical Cross simple rotation to operate, the structure design that the cover plate that binds axially lifts so that the cover plate that binds can be with steel Die face plate realizes smooth closely connected, eliminates concrete surface faulting of slab ends phenomenon when binding placing.
As improving further, a limited block can be welded on lift shaft 3 so that bind cover plate After overlapping with aperture of binding spacing, do not rotating, preventing from rotating excessively, formed and preferably coordinate, form limit Position device 5.
Lift shaft 3 and the pipe 6 that binds arrange alignment scale 41 simultaneously, when both scales overlap, Represent that the cover plate upper surface that binds is concordant with panel upper surface, form a complete plane.
Embodiment described above is only to be described the preferred embodiment of the present invention, not to this Bright scope is defined, on the premise of designing spirit without departing from the present invention, and relevant technical staff in the field Various deformation and improvement to the present invention, all should expand in protection domain as determined by claims of the present invention.

Claims (5)

1. tunnel overall steel die bush platform building cart binds device, it is characterised in that include panel (1), bind lid Plate (2), lift shaft (3), axle bed (4), stopping means (5) and the pipe (6) that binds, wherein said Plate is provided with aperture of binding (11), the fixing pipe (5) that binds of lower surface at panel, described in bind aperture (11) On the panel of side jagged (12), and the side contacted with the described pipe that binds in breach (12) is provided with Groove (13);
The cover plate (2) that binds described in diameter is identical with described aperture of binding is provided with chamfering and ear (21);
Described lift shaft (3) upper end is vertically fixed on described ear (21);
Described pipe (6) outside of binding is provided with the axle bed (4) for installing lift shaft, and described liter Fall rotating shaft (3) is operating side (31) through breach and axle bed posterior end.
Tunnel the most according to claim 1 overall steel die bush platform building cart binds device, it is characterised in that At described lift shaft (3) with bind and be provided with stopping means (5) between tube wall.
Tunnel the most according to claim 1 overall steel die bush platform building cart binds device, it is characterised in that Alignment scale (41) is set at lift shaft (3) and binding, when both alignment scale weights between pipe (6) During conjunction, described in the cover plate upper surface that binds concordant with described panel upper surface.
Tunnel the most as claimed in any of claims 1 to 3 overall steel die bush platform building cart binds device Carry out the seamless technique bound, it is characterised in that order follows the steps below:
The first step, pump concrete binds before placing, the cover plate jacking rotating to outside aperture of binding of binding, Bind cover plate and panel attachment;
Second step, snaps connection the described pipe that binds with concrete conveying pipeline, and concrete is pumped through piping into Mould, until filling slurry by mould;
3rd step, rotates backward lift shaft immediately so that the cover plate that binds turns to bind at the mouth of pipe, described The cover plate that binds declines under the pressure of concrete slurry and closes the mouth of pipe that binds;
4th step, dismantling concrete conveying pipe, and maintenance;
5th step, maintenance removes, after completing, the device that binds.
Seamless closed-top technology the most according to claim 1, it is characterised in that in step 3, pass through Observe lift shaft and the alignment scale bound between pipe judges bind cover plate upper surface and table on described panel Face is the most concordant.
CN201610408756.9A 2016-06-08 2016-06-08 Tunnel integral steel mould lining trolley capping device and seamless capping process Pending CN105888694A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610408756.9A CN105888694A (en) 2016-06-08 2016-06-08 Tunnel integral steel mould lining trolley capping device and seamless capping process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610408756.9A CN105888694A (en) 2016-06-08 2016-06-08 Tunnel integral steel mould lining trolley capping device and seamless capping process

Publications (1)

Publication Number Publication Date
CN105888694A true CN105888694A (en) 2016-08-24

Family

ID=56730264

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610408756.9A Pending CN105888694A (en) 2016-06-08 2016-06-08 Tunnel integral steel mould lining trolley capping device and seamless capping process

Country Status (1)

Country Link
CN (1) CN105888694A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000002093A (en) * 1998-06-16 2000-01-07 Ohbayashi Corp Form device for tunnel lining concrete
CN202012356U (en) * 2011-04-15 2011-10-19 中国葛洲坝集团股份有限公司 Concrete pouring and head sealing device through pump pipes
CN202176341U (en) * 2011-07-15 2012-03-28 蔡晓春 Model board trolley and grouting device of the same
CN105041340A (en) * 2015-08-12 2015-11-11 天津矿山工程有限公司 Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering
CN205714222U (en) * 2016-06-08 2016-11-23 张济宏 Tunnel overall steel die bush platform building cart binds device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000002093A (en) * 1998-06-16 2000-01-07 Ohbayashi Corp Form device for tunnel lining concrete
CN202012356U (en) * 2011-04-15 2011-10-19 中国葛洲坝集团股份有限公司 Concrete pouring and head sealing device through pump pipes
CN202176341U (en) * 2011-07-15 2012-03-28 蔡晓春 Model board trolley and grouting device of the same
CN105041340A (en) * 2015-08-12 2015-11-11 天津矿山工程有限公司 Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering
CN205714222U (en) * 2016-06-08 2016-11-23 张济宏 Tunnel overall steel die bush platform building cart binds device

Similar Documents

Publication Publication Date Title
CN204098928U (en) Tunnel vault two serves as a contrast the location pre-embedded device of front Grouting Pipe
CN106869949A (en) A kind of method that shield machine is received with steel bushing
CN107326918A (en) A kind of concealed type, which passes through raft plate, can block impervious sump and its construction technology
CN205714222U (en) Tunnel overall steel die bush platform building cart binds device
CN207094051U (en) A kind of holing and sealing machine
CN204491645U (en) A kind of deep foundation pit precipitation well-sealing device
CN109958119A (en) A kind of underground engineering water level observation well construction method
CN105888694A (en) Tunnel integral steel mould lining trolley capping device and seamless capping process
CN203320703U (en) Connecting node of reinforced concrete column and newly added steel beam
CN204082057U (en) Bored pile faces fills with front gaslift hole cleaning device
CN207194016U (en) The spliced prefabricated inspection-pit of multistage
CN204039979U (en) A kind of spilled water hole plugging device
CN207131449U (en) Region of FuShui tunnel inverted arch discharge structure
CN108049425A (en) A kind of pipe gallery temporary plugging wall construction and construction method
CN205298949U (en) Disconnect -type grout clamp tip sealing device
CN205077480U (en) Double cannula bored concrete pile structure
CN211141515U (en) Asphalt tank truck oil filling riser residual oil recovery device
CN107268602A (en) A kind of construction method of interlocking pile
CN104018475B (en) A kind of embedded penstock backfill grouting structure and grouting process thereof
CN207829180U (en) A kind of band is rotatably connected the prefabricated steel tube shear horizontal joint connection structure of part
CN203113349U (en) Foundation trench shoring lattice type end structure
CN207193994U (en) A kind of concealed type, which passes through raft plate, can block impervious sump
CN207419484U (en) Penstock surface grouting built-in pipe arrangement
CN216339683U (en) Novel pipeline horse riding well
CN205136843U (en) All steel sealed interface of heavy -calibre reinforced concrete push pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160824

RJ01 Rejection of invention patent application after publication