CN109958119A - A kind of underground engineering water level observation well construction method - Google Patents
A kind of underground engineering water level observation well construction method Download PDFInfo
- Publication number
- CN109958119A CN109958119A CN201910262025.1A CN201910262025A CN109958119A CN 109958119 A CN109958119 A CN 109958119A CN 201910262025 A CN201910262025 A CN 201910262025A CN 109958119 A CN109958119 A CN 109958119A
- Authority
- CN
- China
- Prior art keywords
- gate valve
- bottom plate
- water level
- level observation
- underground engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D1/00—Investigation of foundation soil in situ
- E02D1/08—Investigation of foundation soil in situ after finishing the foundation structure
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Analytical Chemistry (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Sewage (AREA)
Abstract
The invention discloses a kind of underground engineering water level observation well construction methods, comprising the following steps: a, is abolished plain concrete surface layer in the region to structure base slab according to inspection well positioning boundary and installs the first gate valve;B, it drills through the first gate valve to bottom plate direction, stops drilling after drilling through bottom plate water outlet, drainage duct is connected on the first gate valve and is drained;C, after clear water to be discharged, the first gate valve is closed, drainage duct is removed, path changing head is installed on the first gate valve, and connect aqueduct in path changing head;D, the second gate valve is installed on aqueduct, and transparent sighting tube is installed on the second gate valve, elevation scale strip is pasted according to elevation in observation pipe surface;E, after inspection well debugging, region is abolished to bottom plate and is backfilled.This method observes level of ground water to realize by the way that sighting tube is drilled and installed on structure base slab, and this method construction is simple is convenient, is particluarly suitable for the case where adding water level observation well after completion of works.
Description
Technical field
The present invention relates to underground engineering field, in particular to a kind of underground engineering water level observation well construction method.
Background technique
In order to develop and use Underground Space Resource, people built as lower room, underground railway, vcehicular tunnel, underwater
The underground engineerings such as tunnel, underground common trench and street crossing underpass.In underground engineering construction, concrete structure often will do it
It pours, to separate the underground space and stratum.Certain Project is in rich groundwater region, especially at rainy season, if ground
Lower water level is excessively high, in fact it could happen that the situation of underground engineering anti-floating ability deficiency then needs to carry out counterweight to underground engineering in time, to increase
Strong underground engineering anti-floating ability.It since the engineering original designs not set water level observation well, is required, is needed according to this engineering Anti-floating design
Water level observation well is added on minus two layers of original structure bottom plate top, to observe level of ground water situation.For this purpose, after completion of works how
Water level observation well is added, is badly in need of construction personnel and accounts for and study.
Summary of the invention
Present invention aims at: for the underground engineering that need to monitor level of ground water situation, how to be added after completion of works
The problem of water level observation well, provides a kind of underground engineering water level observation well construction method, by boring on engineering structure bottom plate
Sighting tube is simultaneously installed in hole, observes to realize level of ground water situation, and this method construction is simple is convenient, is particluarly suitable for work
The case where water level observation well is added after completion of works.
To achieve the goals above, the technical solution adopted by the present invention are as follows:
A kind of underground engineering water level observation well construction method, comprising the following steps:
A, line setting is carried out in inspection well construction location, plain concrete surface layer in the region is abolished according to positioning boundary
To structure base slab, the first gate valve is installed on bottom plate after clearing up residue;
B, it after fully opening the first gate valve, drills through the first gate valve to bottom plate direction, stops after drilling through bottom plate water outlet
It drills and removes drilling machine, drainage duct is connected on the first gate valve and is drained;
C, after water to be discharged is clear water, the first gate valve is closed, drainage duct is removed, variable diameter is installed on the first gate valve
Head, and aqueduct is connected in path changing head;
D, the second gate valve is installed on aqueduct, and transparent sighting tube is installed on the second gate valve, in observation pipe surface
Elevation scale strip is pasted according to elevation;
E, after inspection well debugging, region is abolished to bottom plate using concrete and is backfilled.
This method is by installing the first gate valve after abolishing to bottom plate surface layer plain concrete, and through the first gate valve to bottom plate
Direction drills to underground water and is connected to, and path changing head is then installed on the first gate valve, and aqueduct is connected in path changing head, and
Second gate valve is installed on aqueduct, and transparent sighting tube is installed on the second gate valve, to realize to level of ground water situation
It is observed, this method construction is simple is convenient, is particluarly suitable for the case where adding water level observation well after completion of works.
As a preferred solution of the present invention, when installing the first gate valve, according to the first gate valve ring flange hole location on bottom plate
It drills and is implanted into thread, after bar planting reaches design strength, the first gate valve is fixed on bottom plate using nut, thus will
First gate valve is securely connect by ring flange with bottom plate.
As a preferred solution of the present invention, first gate valve is cast iron valve.
As a preferred solution of the present invention, the drainage duct includes ring flange compatible with the first gate valve, Yi Jiyu
The drainpipe of ring flange welding, and the water outlet of drainpipe abolishes region far from bottom plate.Using the drainage duct of this structure, both
Convenient for being connected with the first gate valve, and water can be drained into bottom plate and abolished except region, after avoiding bottom plate from abolishing the influence of region ponding
Continuous construction.
As a preferred solution of the present invention, the path changing head is in cone shape, and both ends are equipped with ring flange, and are located at variable diameter
The ring flange of head big end is adapted with the first gate valve.The path changing head completes pipeline smoothly transitting from major diameter to minor diameter,
Avoid the first gate valve to the hydraulic pressure mutation between aqueduct.
As a preferred solution of the present invention, the aqueduct is stainless steel pipes, and both ends are equipped with steel flange disk, and
The ring flange is adapted with the ring flange of path changing head small end.By using stainless steel pipes as aqueduct, be able to bear compared with
Big water pressure, and steel flange disk is set at both ends, it is convenient to be connect with the installation of path changing head, the second gate valve.
As a preferred solution of the present invention, second gate valve is stainless steel sluice valve.
As a preferred solution of the present invention, the sighting tube is attached lengthening using sleeve, and sighting tube lower end is equipped with
Ring flange facilitates and carries out spreading according to Ground-water level situation.
As a preferred solution of the present invention, the first gate valve, path changing head, aqueduct, the second gate valve and sighting tube company
Junction is respectively provided with water stop spacer, to avoid that leak occurs at each component faying face.
As a preferred solution of the present invention, when inspection well is debugged, water should be first filled in sighting tube and aqueduct, then
The first gate valve is opened again, and record can be observed after stable level.In this way mainly in advance to sighting tube and
Aqueduct carries out filling of pouring water, and can occur level of ground water to avoid opening when the first gate valve and quickly changes and measurement error occur.
In conclusion by adopting the above-described technical solution, the beneficial effects of the present invention are:
This method is by installing the first gate valve after abolishing to bottom plate surface layer plain concrete, and through the first gate valve to bottom plate
Direction drills to underground water and is connected to, and path changing head is then installed on the first gate valve, and aqueduct is connected in path changing head, and
Second gate valve is installed on aqueduct, and transparent sighting tube is installed on the second gate valve, to realize to level of ground water situation
It is observed, this method construction is simple is convenient, is particluarly suitable for the case where adding water level observation well after completion of works.
Detailed description of the invention
Fig. 1 is underground engineering water level observation well construction method flow chart of the present invention.
Fig. 2 is underground engineering water level observation well structural schematic diagram of the present invention.
Marked in the figure: 1- bottom plate, 11- bottom plate abolishes region, the first gate valve of 2-, 3- path changing head, 4- aqueduct, the second lock of 5-
Valve, 6- sighting tube.
Specific embodiment
With reference to the accompanying drawing, the present invention is described in detail.
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right
The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not
For limiting the present invention.
Embodiment
The present embodiment provides a kind of underground engineering water level observation well construction methods;
As Figure 1-Figure 2, the underground engineering water level observation well construction method in the present embodiment, comprising the following steps:
A, line setting determination is carried out in inspection well construction location and abolish region, according to positioning boundary using electric pick to the area
Plain concrete surface layer is abolished to structure base slab 1 in domain, and is cleaned out after residue and installed the first gate valve 2 on bottom plate;
B, it after fully opening the first gate valve, drills through the first gate valve to bottom plate direction, stops after drilling through bottom plate water outlet
It drills and removes drilling machine, drainage duct is connected on the first gate valve and is drained;
C, after water to be discharged is clear water, the first gate valve is closed, drainage duct is removed, variable diameter is installed on the first gate valve 2
First 3, and aqueduct 4 is connected in path changing head 3;
D, the second gate valve 5 is installed on aqueduct 4, and transparent sighting tube 6 is installed on the second gate valve 5, in sighting tube
Surface elevation scale strip is pasted according to elevation;
E, after inspection well debugging, region 11 is abolished to bottom plate using concrete and is backfilled.
This method is by installing the first gate valve after abolishing to bottom plate surface layer plain concrete, and through the first gate valve to bottom plate
Direction drills to underground water and is connected to, and path changing head is then installed on the first gate valve, and aqueduct is connected in path changing head, and
Second gate valve is installed on aqueduct, and transparent sighting tube is installed on the second gate valve, to realize to level of ground water situation
It is observed, this method construction is simple is convenient, is particluarly suitable for the case where adding water level observation well after completion of works.
In the present embodiment, first gate valve 2 is DN150 cast iron valve, both ends band mounting flange, according to the first lock
Valve base ring flange hole location marks on bottom plate, drilling implantationHigh-strength thread, implantation depth 200mm, outside
Reveal 100mm, clean out hole before bar planting, hole reinforcement planting glue is answered full when bar planting, forbids shaking after implantation, it is ensured that bar planting
Quality.After bar planting reaches design strength, the first gate valve bottom end ring flange is inserted in after being inserted in water stop spacer, and uses high-strength spiral shell
Mother is fixed, which is the double-deck high pressure rubber water stop spacer, can be to avoid leak at the first gate valve bottom end ring flange.
In the present embodiment, the drainage duct includes ring flange compatible with the first gate valve, and is welded with ring flange
Drainpipe, and the water outlet of drainpipe abolishes region far from bottom plate.Using the drainage duct of this structure, both it was convenient for and first
Gate valve is connected, and water can be drained into bottom plate and abolished except region, and avoiding bottom plate from abolishing region ponding influences subsequent construction.Specifically
, it usesRing flange (internal orifice dimension 150mm)Cast iron steel-pipe welding, the long 600mm~800mm of cast iron steel pipe are advisable
(can be adjusted according to construction site foundation depth).When installing drainage duct, by drainage ductOn ring flange and the first gate valve
Portion's ring flange usesPlain bolt is fixed, and centre adds rubber water-proof gasket, prevents ring flange leak.
In the present embodiment, after the completion of high-strength nut fastening, drilled using hidden hole drilling, aperture 100mm.First gate valve peace
After dress is fixed, the first gate valve is opened, drilling machine calibrate that (drill bit deviations are controlled goes through the within 2cm, before drilling in place
Whether one gate valve is fully open, prevents from destroying the first gate valve when drilling, checks whether drilling machine frame body consolidates), when drilling through under bottom plate
Portion impermeable stratum Mao Shuihou stops drilling, removes drilling machine, ready water band (or transparent hose) is covered on drainage duct,
Water is led to gutter (or sump) nearby, then cleans out ponding (or silt) for flowing into foundation pit etc., it is to be discharged
Water is closes the first gate valve, the temporary partition to underground water can be realized after clear water, so that underground water is avoided to emerge always, shadow
Ring subsequent construction;Then drainage duct is removed, can start to carry out subsequent parts installation.
In the present embodiment, the path changing head 3 is in cone shape, and both ends are equipped with ring flange, and are located at path changing head big end
Ring flange is adapted with the ring flange on the first gate valve.The path changing head completes smooth mistake of the pipeline from major diameter to minor diameter
It crosses, avoids the first gate valve to the hydraulic pressure mutation between aqueduct.Specifically, path changing head using cast iron welding fabrication (Become), each welding flange in path changing head both ends, (top isRing flange, bottom areRing flange), weld seam is answered full
And meet related specification requirement.Preservative treatment is carried out after path changing head molding.When installing path changing head, by path changing head big end ring flange
It is fastened with the first gate valve top flange dish using M20 high-strength bolt, centre adds rubber water-proof gasket, prevents ring flange leak.
In the present embodiment, the aqueduct 4 is stainless steel pipes, and both ends are equipped with steel flange disk, and the ring flange
It is adapted with the ring flange of path changing head small end.By using stainless steel pipes as aqueduct, it is able to bear biggish hydraulic pressure
Power, and steel flange disk is set at both ends, it is convenient to be connect with the installation of path changing head, the second gate valve.Specifically, aqueduct usesStainless-steel pipe, steel pipe both ends are respectively weldedSteel flange disk, weld seam answer full and meet related specification requirement.
When aqueduct is installed, aqueduct end flange disk and path changing head small end ring flange are fastened using M16 high-strength bolt, centre adds
Rubber water-proof gasket prevents ring flange leak.
In the present embodiment, second gate valve 5 isStainless steel sluice valve.When installing the second gate valve, by the second gate valve bottom
Portion's ring flange connect fastening using M16 high-strength bolt with aqueduct top flange dish, and centre adds rubber water-proof gasket, prevents method
Blue disk leak.
In the present embodiment, the sighting tube 6 is attached lengthening using sleeve, and sighting tube lower end is equipped with ring flange, side
Just spreading is carried out according to Ground-water level situation.Specifically, sighting tube usesTransparent KBG pipe, 3 meters of every root long use
Sleeve connection, sleeve cover internal thread, the outer silk of two end cap of KBG pipe, lower partRing flange mantle fiber.When installing sighting tube, first by second
Gate valve upper flange disk and sighting tube lower partRing flange is fastened with M16 high-strength bolt, and centre adds rubber water-proof gasket, is prevented
Only ring flange leak.When assembling sighting tube, in sighting tube end, mantle fiber is wrapped with unsintered tape, pays attention to winding direction, is such as being screwed into set
It when in cylinder, rotates clockwise to the right, the direction that we twine unsintered tape on observation pipe end is exactly inverse time to the left
The more stubborn needle winding, can be the tighter when twisting sighting tube in this way, will not loosen), it should be noted that dynamics and direction when twisting sighting tube, not
Have to centainly be screwed to twist really it is motionless just do not leak, as long as twist when feel can be able to eat strength.Answer this engineering level of ground water
Higher, sighting tube pipe mounting height is advisable away from negative one layer top plate lower part 20cm.After sighting tube is installed, on its surface according to height
Journey glues elevation scale strip.
In the present embodiment, first gate valve, path changing head, aqueduct, the second gate valve and sighting tube be it is vertically-mounted,
It should be guaranteed at vertical state as far as possible when installing, and be respectively provided with water stop spacer in each ring flange faying face, to avoid each portion
Leak occurs at part faying face.
In the present embodiment, in inspection well debugging, water should be first filled in sighting tube and aqueduct, then opens first again
Gate valve can be observed record after stable level.Mainly sighting tube and aqueduct are carried out in advance in this way
It pours water filling, can occur level of ground water to avoid opening when the first gate valve and quickly change and measurement error occur.
In the present embodiment, after items check no problem, region is abolished using concrete backfill bottom plate.It should be checked before backfill
Whether each connecting portion has whether drainage, the first gate valve are opened.After inspection, casting concrete pours height with negative
Two layers of ground elevation.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in original of the invention
Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within reason.
Claims (10)
1. a kind of underground engineering water level observation well construction method, which comprises the following steps:
A, line setting is carried out in inspection well construction location, plain concrete surface layer in the region is abolished to knot according to positioning boundary
Structure bottom plate installs the first gate valve after clearing up residue on bottom plate;
B, it after fully opening the first gate valve, drills through the first gate valve to bottom plate direction, stops drilling after drilling through bottom plate water outlet
And drilling machine is removed, drainage duct is connected on the first gate valve to be drained;
C, after water to be discharged is clear water, the first gate valve is closed, drainage duct is removed, path changing head is installed on the first gate valve, and
Aqueduct is connected in path changing head;
D, the second gate valve is installed on aqueduct, and transparent sighting tube is installed on the second gate valve, observation pipe surface according to
Elevation pastes elevation scale strip;
E, after inspection well debugging, region is abolished to bottom plate using concrete and is backfilled.
2. underground engineering water level observation well construction method according to claim 1, which is characterized in that installing the first gate valve
When, it is drilled on bottom plate according to the first gate valve ring flange hole location and is implanted into thread, after bar planting reaches design strength, used
First gate valve is fixed on bottom plate by nut.
3. underground engineering water level observation well construction method according to claim 2, which is characterized in that first gate valve is
Cast iron valve.
4. underground engineering water level observation well construction method according to claim 1, which is characterized in that the drainage duct packet
Ring flange compatible with the first gate valve, and the drainpipe with ring flange welding are included, and the water outlet of drainpipe is far from bottom plate
Abolish region.
5. underground engineering water level observation well construction method according to claim 1, which is characterized in that the path changing head is in circle
Cone-shaped, both ends are equipped with ring flange, and the ring flange for being located at path changing head big end is adapted with the first gate valve.
6. underground engineering water level observation well construction method according to claim 5, which is characterized in that the aqueduct is not
Become rusty steel conduit, and both ends are equipped with steel flange disk, and the ring flange is adapted with the ring flange of path changing head small end.
7. underground engineering water level observation well construction method according to claim 1, which is characterized in that second gate valve is
Stainless steel sluice valve.
8. underground engineering water level observation well construction method according to claim 1, which is characterized in that the sighting tube uses
Sleeve is attached lengthening, and sighting tube lower end is equipped with ring flange.
9. underground engineering water level observation well construction method according to claim 1, which is characterized in that in the first gate valve, become
Diameter head, aqueduct, the second gate valve and sighting tube joint face be respectively provided with water stop spacer.
10. underground engineering water level observation well construction method according to claim 1, which is characterized in that debugged in inspection well
When, water should be first filled in sighting tube and aqueduct, then opens the first gate valve again, and note can be observed after stable level
Record.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910262025.1A CN109958119A (en) | 2019-04-02 | 2019-04-02 | A kind of underground engineering water level observation well construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910262025.1A CN109958119A (en) | 2019-04-02 | 2019-04-02 | A kind of underground engineering water level observation well construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109958119A true CN109958119A (en) | 2019-07-02 |
Family
ID=67025514
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910262025.1A Pending CN109958119A (en) | 2019-04-02 | 2019-04-02 | A kind of underground engineering water level observation well construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109958119A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112595380A (en) * | 2020-12-10 | 2021-04-02 | 广东天衡工程建设咨询管理有限公司 | Underground water level monitoring method for starting stage and receiving stage of shield tunneling machine |
CN112814659A (en) * | 2021-02-04 | 2021-05-18 | 中国煤炭地质总局水文地质工程地质环境地质勘查院 | Hydrogeological exploration ground water level observation device |
CN114183126A (en) * | 2021-12-16 | 2022-03-15 | 上海长凯岩土工程有限公司 | Implementation method for ectopic water level observation of dewatering well |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20090031004A (en) * | 2007-09-21 | 2009-03-25 | 주식회사 로벤텍 | Underground water level observation device |
CN204831448U (en) * | 2015-05-26 | 2015-12-02 | 中国电建集团中南勘测设计研究院有限公司 | A warning water gauge for water level monitoring |
CN105625481A (en) * | 2016-03-21 | 2016-06-01 | 上海长凯岩土工程有限公司 | Construction method for drainage holes for underground constructions |
CN107190720A (en) * | 2017-06-07 | 2017-09-22 | 深圳市工勘岩土集团有限公司 | Observation of groundwater levels is bored into well |
-
2019
- 2019-04-02 CN CN201910262025.1A patent/CN109958119A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20090031004A (en) * | 2007-09-21 | 2009-03-25 | 주식회사 로벤텍 | Underground water level observation device |
CN204831448U (en) * | 2015-05-26 | 2015-12-02 | 中国电建集团中南勘测设计研究院有限公司 | A warning water gauge for water level monitoring |
CN105625481A (en) * | 2016-03-21 | 2016-06-01 | 上海长凯岩土工程有限公司 | Construction method for drainage holes for underground constructions |
CN107190720A (en) * | 2017-06-07 | 2017-09-22 | 深圳市工勘岩土集团有限公司 | Observation of groundwater levels is bored into well |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112595380A (en) * | 2020-12-10 | 2021-04-02 | 广东天衡工程建设咨询管理有限公司 | Underground water level monitoring method for starting stage and receiving stage of shield tunneling machine |
CN112814659A (en) * | 2021-02-04 | 2021-05-18 | 中国煤炭地质总局水文地质工程地质环境地质勘查院 | Hydrogeological exploration ground water level observation device |
CN112814659B (en) * | 2021-02-04 | 2022-05-24 | 中国煤炭地质总局水文地质工程地质环境地质勘查院 | Hydrogeological exploration ground water level observation device |
CN114183126A (en) * | 2021-12-16 | 2022-03-15 | 上海长凯岩土工程有限公司 | Implementation method for ectopic water level observation of dewatering well |
CN114183126B (en) * | 2021-12-16 | 2023-09-19 | 上海长凯岩土工程有限公司 | Implementation method for abnormal observation water level of precipitation well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109958119A (en) | A kind of underground engineering water level observation well construction method | |
CN106013265B (en) | Basement is met an urgent need the construction method of float Structure | |
CN206874310U (en) | Be applicable to high-pressure rich water district tunnel decompression drainage device | |
CN106320353B (en) | A kind of construction method of basement construction Yield rainfall relation device | |
CN109184672A (en) | Coal seam depression angle drilling gas pressure measuring device and pressure measuring method | |
CN109025899B (en) | Well sealing device | |
CN105484277A (en) | Component for tubular well precipitation construction in elevator foundation pit or sump and construction method | |
CN205205844U (en) | Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit | |
JP2006336338A (en) | Drain pipe and drain method using drain pipe | |
CN205894121U (en) | Emergent anti structure of floating of basement | |
CN207988044U (en) | A kind of co-layer draining special single standpipe three-way fitting of cast-in-place pre-buried type | |
CN205990655U (en) | A kind of urban drainage pipe network defense sector sinking device | |
CN207121916U (en) | Shut-in well structure | |
CN201165703Y (en) | Leak detection plastic inspection shaft for collapsible loess area | |
CN106065622B (en) | The double sleeves of the efficient drag reduction of pullout tests stake and pullout tests stake drag reduction method | |
CN107975127A (en) | The outer antipriming of vertical jacking | |
CN209443551U (en) | A kind of prefabricated concrete inspection well | |
CN206477349U (en) | Stifled, the water blockoff structure of drainpipe through walls | |
CN109295990A (en) | A kind of band opening blade foot has bottom steel boxed cofferdam | |
CN205877435U (en) | Rigid water -proofing sleeve pipe watertight fittings | |
JP2019099994A (en) | Drain piping structure and drain piping method | |
CN212983913U (en) | Pressure-bearing downcomer well back cover is from waterproof one-way water outlet layer board piece of burying | |
KR101396514B1 (en) | Coupling structure of leading pipe for underwater prefabricating intake tower | |
CN212001206U (en) | Structure for controlling diving and confined water stop and precipitation | |
CN208364174U (en) | A kind of tunnel crystallization-preventive drainage system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190702 |