CN105041340A - Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering - Google Patents

Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering Download PDF

Info

Publication number
CN105041340A
CN105041340A CN201510493919.3A CN201510493919A CN105041340A CN 105041340 A CN105041340 A CN 105041340A CN 201510493919 A CN201510493919 A CN 201510493919A CN 105041340 A CN105041340 A CN 105041340A
Authority
CN
China
Prior art keywords
vault
valve
template
union
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510493919.3A
Other languages
Chinese (zh)
Inventor
鲁承桂
唐喜明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN MINING ENGINEERING Co Ltd
Original Assignee
TIANJIN MINING ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN MINING ENGINEERING Co Ltd filed Critical TIANJIN MINING ENGINEERING Co Ltd
Priority to CN201510493919.3A priority Critical patent/CN105041340A/en
Publication of CN105041340A publication Critical patent/CN105041340A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a structure and construction method for increasing the arch crown concrete pouring speed in tunnel engineering. The structure comprises a framework, a pipe connector and a valve. A hole is formed in the middle of the framework. The pipe connector is downwards and fixedly connected with the hole. The portion, corresponding to the hole, of the upper surface of the framework is transversely provided with the valve in a sliding mode. According to the structure and construction method, arch concrete pouring is conducted through the improved pipe connector, and working efficiency is improved greatly and improved by more than 10 times. By means of the structure and construction method, the labor resources are reduced greatly, the working strength of workers is low, working efficiency is high, and the structure is easy and safe to manage; less slurry is leaked through connection openings of pumping pipes, no obvious slurry leakage phenomenon exists at the sealed positions, conveying pipes are flexible and convenient to disassemble, and time is saved; meanwhile due to the fact that pressing pouring is adopted for arch crown concrete, no empty-support site is generated, the quality and safety problems are avoided, and the advantages that the pumping construe construction is high in speed and high in quality, and the labor intensity of workers is lowered are fully played.

Description

Accelerate structure and the construction method of construction of tunnel vault pouring concrete speed
Technical field
The invention belongs to tunnel vault pouring concrete technical field, especially at building materials mine and non-metal mine tunnel or tunnel secondary lining, a kind of structure and the method accelerating construction of tunnel vault pouring concrete speed under adopting combined steel plate to spell mould condition.
Background technology
Current, in building materials mine or non-metal mine industry, consider the factors such as cost investment, integral mold plate not yet large scale investment uses, and tunnel or tunnel secondary lining mainly adopt combined steel formwork to spell mould.In use pumping of concrete process, side wall concrete can have been built smoothly, but when building vault, pumping directly cannot enter mould, need adopt and manually enter modeling method, namely build concrete with spade one spade one spade toward arch crown part, workman's operation intensity is large, and work efficiency is extremely low, concrete waste is large, build the vault that a 6.0m is long, need more than 20 people's work about 12 hours, had a strong impact on the progress of engineering.And easily occur empty head space side phenomenon at arch crown part, manually enter die worker's effect extremely low, the concreting time is long, and concrete workability is deteriorated, and exacerbates the existing sky top phenomenon gone out because of vault concrete flowability difference in addition.Sometimes because of concrete poor fluidity, there is the violation way adding water to improve its mobility in field operation personnel, this construction method, along with the activity duration increases, concrete performance (comprising the performance such as workability, intensity) all can be affected, even can the phenomenon of generating pump pipe plug pipe.The empty head space that arch crown part occurs simultaneously helps phenomenon, adds the difficulty of secondary grouting process.
Particularly occur needing repairing in operation belt porch tunnel in building materials mine, or construction project needs to hand in advance peace to occur feeding intake and produce when serving as a contrast cross-operation with two, vault coagulation earth is built employing and is manually entered mould and cannot construct.
To sum up, there is larger quality and potential safety hazard in traditional concrete casting building technology, and takies human resources, and work efficiency is low waits deficiency.
Find following disclosed patent document through retrieval, concrete disclosure is as follows:
Patent document: a kind of Middle Wall of Multi-Arch Highway Tunnel vault concreting method (notification number CN103835728A), comprise the following steps: the making of a steel form and setting, b lays concrete pump line, and c builds middle and lower part concrete and middle and upper part concrete, and arch concrete is built in d supercharging.
Find through contrast, above-mentioned documents and present patent application have relatively big difference in technical scheme.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, a kind of structure and the construction method of accelerating construction of tunnel vault pouring concrete speed are provided, vault concreting speed are fast, construction quality is high to reach, alleviate the object of labor strength and quickening duration progress.
The solution of the present invention is achieved in that
Accelerate a structure for construction of tunnel vault pouring concrete speed, comprise template, union and valve, be shaped with hole in the middle part of described template, this hole place is fixedly mounted with union downwards, the horizontal valve that is slidably installed of template upper surface of corresponding described hole.
And described valve is two of left and right symmetry.
And described template thickness is the steel plate of 10mm, described valve thickness is the steel plate of 6mm.
And the soffit symmetry of described valve is fixedly mounted with handle, to the template of handle being shaped with rectangle chute.
And, tilt to be fixedly mounted with multiple reinforcing rib between described union surrounding side and template.
Accelerate a construction method for construction of tunnel vault pouring concrete speed, step is as follows:
Step one, installation both sides, tunnel abutment wall and vault template, have at least a model sheetinstallat to have union and valve in vault template;
Step 2, both sides abutment wall symmetry are built;
Step 3, pump line terminal and union to be plugged into, last is installed across vault template and shutoff;
Step 4, vault concreting;
Step 5, built rear vibration compacting, valve-off also dismantles pump line;
Step 6, cleaning associated components, give over to and use next time.
And, in described step one, when once construct longer work cycle time, polylith vault template is all with union and valve;
Pump line terminal and first union start vault concreting after plugging into, and valve-off after vibration compacting also tears pipe open;
Then start vault concreting after pump line terminal and second union being plugged into, valve-off after vibration compacting also tears pipe open;
By that analogy, pump line terminal and last union are plugged into and are started vault concreting, and last is across vault model sheetinstallat and shutoff;
The same step 4 of all the other construction methods, step 5, step 6.
Advantage of the present invention and good effect are:
The present invention adopts the union after improvement and design to carry out arch concreting, greatly improve work efficiency, need more than 20 people's work about 12 hours from original 6.0m arch of building, become and only need 6-8 people's operation now, completed less than one hour, work efficiency improves more than ten doubly.Simultaneously, in construction after this, by increasing the steel form of a band union, 15.0m mono-circulation (note: work cycle length should not after length will be adjusted to by 6.0m secondary lining work cycle, need longitudinal rational position arrange settlement joint and carry out the process of constuction joint in tunnel), can complete in 3h that whole vault is concrete builds.Distribute human resources greatly, workman's operation intensity is low, and work efficiency is high, is easy to safety management.Pumping line connecting port place spillage is few, closed place also without obvious spillage phenomenon, substantially without waste, dismounting carrier pipe flexibly, convenient, save time.Simultaneously because vault concrete is pressure injection, there will not be empty top on-the-spot, quality and safety problem can not be produced, given full play to that pumping concrete construction speed is fast, quality is high, alleviate the advantage of labor strength.
Accompanying drawing explanation
Fig. 1 is front view of the present invention;
Fig. 2 is that the A-A of Fig. 1 is to sectional view;
Fig. 3 is the state diagram of valve open of the present invention;
Fig. 4 is 6m work cycle arch concreting schematic diagram of the present invention;
Fig. 5 is 15m work cycle arch concreting schematic diagram of the present invention;
Fig. 6 is construction process figure of the present invention.
Detailed description of the invention
Below in conjunction with accompanying drawing, also by specific embodiment, the invention will be further described.
A kind of structure accelerating construction of tunnel vault pouring concrete speed, as shown in Figure 1 and Figure 2, comprise template 1, union 3 and valve 2, in the middle part of described template, be shaped with φ 130mm hole, this hole place is fixedly mounted with union downwards, the horizontal valve that is slidably installed of template upper surface of corresponding described hole.Described template is one piece of thickness is the steel plate of 10mm, described valve is one piece of thickness is the steel plate of 6mm, and this valve is two pieces of left and right symmetry, conveniently mobile valve, the soffit symmetry of this valve is fixedly mounted with handle 6, to the template of handle being shaped with rectangle chute 4.
In the present embodiment, reinforce with φ 18mm reinforcing rib between described union surrounding side and template, ensure that the firmness of union.
Application example:
China Resources cement (Midu) Co., Ltd second phase cement producing line limestone conveying K0+160 ~ K0+899m section construction of tunnel Second Lining Construction condition is that belt porch takies the confined space, and execution conditions limit, and belt feeds intake and serves as a contrast with two cross-operation of constructing.This project Second Lining Construction adopts this transformation template to construct,
Once to construct 6.0m (namely four across arch mould) secondary lining, as shown in Figure 4, only sidewall template all need be installed, arch model sheetinstallat three across (i.e. 4.5m), the steel shutterings with union be contained in second across, after treating both sides abutment wall concreting, the transformation steel form of the terminal of pump line with band union can be plugged into, carry out simultaneously last across, namely the 4th across the installation of arch template, and the sizing plug made in advance is carried out front end shutoff process.After all preparation completes, can carry out concreting, make concrete under road gradient in highway tunnel condition, first built across arch bottom one, in figure, the direction of arrow is concrete flow direction, and sequence of flow is first left and then right; After under the pressure effect of the pump housing, by bottom one across arch concrete preliminary consolidation, concrete is pressed into top two across in the template of arch, built, after vibration compacting, valve-off tears pipe open, and cleans in time associated components simultaneously.
Accelerate a construction method for construction of tunnel vault pouring concrete speed, step is as follows:
Step one, installation both sides, tunnel abutment wall and vault template, have at least a model sheetinstallat to have union and valve in vault template;
Step 2, both sides abutment wall symmetry are built;
Step 3, pump line terminal and union to be plugged into, last is installed across vault template and shutoff;
Step 4, vault concreting;
Step 4, built rear vibration compacting, valve-off also dismantles pump line;
Step 5, cleaning associated components, give over to and use next time.
When shorter work cycle of once constructing, such as 6m secondary lining, can be positioned at by the template with union in second across being centre position;
In described step one, when once construct longer work cycle time, multiple vault template is with union;
Pump line terminal and first union start vault concreting after plugging into, and valve-off after vibration compacting also tears pipe open;
Then start vault concreting after pump line terminal and second union being plugged into, valve-off after vibration compacting also tears pipe open;
By that analogy, pump line terminal and last union are plugged into and are started vault concreting, and last is across vault model sheetinstallat and shutoff;
The same step 4 of all the other construction methods, step 5, step 6.
It is emphasized that; embodiment of the present invention is illustrative; instead of it is determinate; therefore the present invention includes the embodiment be not limited to described in detailed description of the invention; every other embodiments drawn by those skilled in the art's technical scheme according to the present invention, belong to the scope of protection of the invention equally.

Claims (7)

1. accelerate the structure of construction of tunnel vault pouring concrete speed for one kind, it is characterized in that: comprise template, union and valve, be shaped with hole in the middle part of described template, this hole place is fixedly mounted with union downwards, the horizontal valve that is slidably installed of template upper surface of corresponding described hole.
2. the structure of quickening construction of tunnel vault pouring concrete speed according to claim 1, is characterized in that: described valve is two of left and right symmetry.
3. the structure of quickening construction of tunnel vault pouring concrete speed according to claim 1 and 2, it is characterized in that: described template thickness is the steel plate of 10mm, described valve thickness is the steel plate of 6mm.
4. the structure of quickening construction of tunnel vault pouring concrete speed according to claim 1 and 2, is characterized in that: the soffit symmetry of described valve is fixedly mounted with handle, to the template of handle being shaped with rectangle chute.
5. the structure of quickening construction of tunnel vault pouring concrete speed according to claim 1 and 2, is characterized in that: tilt to be fixedly mounted with multiple reinforcing rib between described union surrounding side and template.
6. a construction method for the quickening construction of tunnel vault pouring concrete speed as described in any one of claim 1 to 5, is characterized in that: step is as follows:
Step one, installation both sides, tunnel abutment wall and vault template, have at least a model sheetinstallat to have union and valve in vault template;
Step 2, both sides abutment wall symmetry are built;
Step 3, pump line terminal and union to be plugged into, last is installed across vault template and shutoff;
Step 4, vault concreting;
Step 5, built rear vibration compacting, valve-off also dismantles pump line;
Step 6, cleaning associated components, give over to and use next time.
7. the construction method of quickening construction of tunnel vault pouring concrete speed according to claim 6, is characterized in that: in described step one, when once construct longer work cycle time, the spaced vault template of polylith is with union and valve;
Pump line terminal and first union start vault concreting after plugging into, and valve-off after vibration compacting also tears pipe open;
Then start vault concreting after pump line terminal and second union being plugged into, valve-off after vibration compacting also tears pipe open;
By that analogy, pump line terminal and last union are plugged into and are started vault concreting, and last is across vault model sheetinstallat and shutoff;
The same step 4 of all the other construction methods, step 5, step 6.
CN201510493919.3A 2015-08-12 2015-08-12 Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering Pending CN105041340A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510493919.3A CN105041340A (en) 2015-08-12 2015-08-12 Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510493919.3A CN105041340A (en) 2015-08-12 2015-08-12 Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering

Publications (1)

Publication Number Publication Date
CN105041340A true CN105041340A (en) 2015-11-11

Family

ID=54448262

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510493919.3A Pending CN105041340A (en) 2015-08-12 2015-08-12 Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering

Country Status (1)

Country Link
CN (1) CN105041340A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888694A (en) * 2016-06-08 2016-08-24 张济宏 Tunnel integral steel mould lining trolley capping device and seamless capping process
CN106522992A (en) * 2016-11-24 2017-03-22 中铁隧道集团有限公司 Concrete lining formwork trolley insertion-type concrete grouting construction method
CN106593473A (en) * 2016-12-23 2017-04-26 湖南五新隧道智能装备股份有限公司 Trolley for side and roof arch zone middle partition wall lining
CN117316830A (en) * 2023-11-28 2023-12-29 成都高投芯未半导体有限公司 Semiconductor packaging system and control method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01271600A (en) * 1988-04-25 1989-10-30 Fujita Corp Concrete placing for cast-in-place concrete lining construction
CN201649683U (en) * 2010-05-14 2010-11-24 攀钢集团冶金工程技术有限公司 Template for concrete injection
CN202012356U (en) * 2011-04-15 2011-10-19 中国葛洲坝集团股份有限公司 Concrete pouring and head sealing device through pump pipes
CN202176341U (en) * 2011-07-15 2012-03-28 蔡晓春 Model board trolley and grouting device of the same
CN102937027A (en) * 2012-11-30 2013-02-20 中铁十九局集团第二工程有限公司 Construction method of edge top arch and bottom arch of concrete pouring tunnel
CN202954824U (en) * 2012-11-07 2013-05-29 上海市政工程设计研究总院(集团)有限公司 Underground cavern baseboard pre-buried injected hole
CN204941567U (en) * 2015-08-12 2016-01-06 天津矿山工程有限公司 A kind of structure accelerating construction of tunnel vault pouring concrete speed

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01271600A (en) * 1988-04-25 1989-10-30 Fujita Corp Concrete placing for cast-in-place concrete lining construction
CN201649683U (en) * 2010-05-14 2010-11-24 攀钢集团冶金工程技术有限公司 Template for concrete injection
CN202012356U (en) * 2011-04-15 2011-10-19 中国葛洲坝集团股份有限公司 Concrete pouring and head sealing device through pump pipes
CN202176341U (en) * 2011-07-15 2012-03-28 蔡晓春 Model board trolley and grouting device of the same
CN202954824U (en) * 2012-11-07 2013-05-29 上海市政工程设计研究总院(集团)有限公司 Underground cavern baseboard pre-buried injected hole
CN102937027A (en) * 2012-11-30 2013-02-20 中铁十九局集团第二工程有限公司 Construction method of edge top arch and bottom arch of concrete pouring tunnel
CN204941567U (en) * 2015-08-12 2016-01-06 天津矿山工程有限公司 A kind of structure accelerating construction of tunnel vault pouring concrete speed

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
唐永: "大伙房水库输水工程15#洞TBM段衬砌混凝土施工技术分析", 《黑龙江水利科技》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888694A (en) * 2016-06-08 2016-08-24 张济宏 Tunnel integral steel mould lining trolley capping device and seamless capping process
CN106522992A (en) * 2016-11-24 2017-03-22 中铁隧道集团有限公司 Concrete lining formwork trolley insertion-type concrete grouting construction method
CN106593473A (en) * 2016-12-23 2017-04-26 湖南五新隧道智能装备股份有限公司 Trolley for side and roof arch zone middle partition wall lining
CN106593473B (en) * 2016-12-23 2019-08-02 湖南五新隧道智能装备股份有限公司 A kind of side and roof arch band mid-board lining cutting trolley
CN117316830A (en) * 2023-11-28 2023-12-29 成都高投芯未半导体有限公司 Semiconductor packaging system and control method
CN117316830B (en) * 2023-11-28 2024-02-02 成都高投芯未半导体有限公司 Semiconductor packaging system and control method

Similar Documents

Publication Publication Date Title
CN105908862B (en) A kind of production method of masonry shell in 3D printing reinforced masonry shear wall
CN205638482U (en) Be used for tunnel concrete secondary lining to take template slip casting device
CN105041340A (en) Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering
CN101936065A (en) Template with rigid-flexible composite structure and partition wall construction method by retaining roadway along goaf thereof
CN105459253A (en) Large-volume lining model pouring device for tunnel model test and method of large-volume lining model pouring device
CN109322505A (en) A kind of roofing reserved opening concrete plugging device and preparation method thereof
CN204040078U (en) A kind of alter-pouring strips mould plate installs structure
CN107191006B (en) Dismantling and repairing method for refractory concrete layer of diversion trench
CN204941567U (en) A kind of structure accelerating construction of tunnel vault pouring concrete speed
CN103741949B (en) Treatment of juncture between vertical structure and horizontal structure
CN104790381B (en) Lining wall concrete pouring inversing method based on UEA micro-expanding agent
CN102865087B (en) Embedded grout pipe device in lining concrete of chamber and construction method
CN203096762U (en) Anti-frost ground beam
CN207475147U (en) A kind of half assembly type cable slot of vcehicular tunnel
CN204418229U (en) Poured band of outer wall of basement concrete draw-in groove
CN204510810U (en) A kind of formwork structure for shutoff exterior wall reserved opening
CN108222656A (en) The construction method of Prefabricated enclosure wall
CN103741651A (en) Concrete tooth groove stilling pool and construction method thereof
CN105133630A (en) Prefabricated part for constructing foundation forming molds
CN103321184B (en) Cured plane-interlocking stereo-stacking engineering block and production method thereof
CN206625437U (en) A kind of building block water proof structure
CN105201278A (en) Assembly type fence wall made of construction waste
CN206267523U (en) A kind of constructional column based on standard knot combination is poured uses template
CN215519946U (en) Wall body corner constructional column exempts from formwork construction structures
CN203145028U (en) Corrugated pipe water-collecting well

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151111