CN105863313A CN201510026094.4A CN201510026094A CN105863313A CN 105863313 A CN105863313 A CN 105863313A CN 201510026094 A CN201510026094 A CN 201510026094A CN 105863313 A CN105863313 A CN 105863313A
Authority
CN
China
Prior art keywords
tobacco room
production line
flue
tobacco
streamline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510026094.4A
Other languages
Chinese (zh)
Inventor
姜永辉
索明朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Neixiang Lifu Deere Energy Equipment Co. Ltd.
Original Assignee
姜永辉
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 姜永辉 filed Critical 姜永辉
Priority to CN201510026094.4A priority Critical patent/CN105863313A/en
Publication of CN105863313A publication Critical patent/CN105863313A/en
Pending legal-status Critical Current

Links

Landscapes

  • Greenhouses (AREA)

Abstract

The invention provides a production line tobacco room assembly technology. A production line tobacco room assembly device is formed by splice bolts, a steel frame, and module boards. The flue-cured tobacco room steel frame is fixed on good hardening ground, and by using the bolts, each module board of the flue-cured tobacco room is fixed, and the production line tobacco room is formed. All assemblies are produced in a factory, and after the assemblies are transported to a site, the assemblies are spliced in a bolt connection method. The technology is advantaged by short construction cycle, low cost, high construction efficiency, and high installation precision.

Description

Streamline tobacco curing barn assembling technique
Technical field
The present invention relates to tobacco curing barn package technique, concrete structure streamline tobacco curing barn assembling technique.
Background technology
Traditional tobacco flue-curing house makes and forms with brick, can not remove use again, so cause the biggest inconvenience after fixing;Existing streamline flue-cured tobacco Room, uses field erected pattern, long construction period, and cost is high, inefficient, in order to make more convenient, streamline tobacco flue-curing house efficiently, Using spelling to connect form to install, all component, all in plant produced, only carries out bolt connecting mode after transporting scene and carries out assembly, has construction week Phase is short, low cost, the plurality of advantages that efficiency of construction is high, installation accuracy is high.
Summary of the invention
It is an object of the invention to provide a kind of streamline Nicotiana tabacum L. tobacco flue-curing house steel structure assembling technology, reach the purpose that Fast Installation uses.
The technical scheme is that assembled steel structure streamline tobacco curing barn, be made up of splice bolt, steelframe, module board;Hardened Fix tobacco flue-curing house steelframe on ground, utilize bolt to be fixed by the modules plate of tobacco flue-curing house and be streamline tobacco flue-curing house.
It is an advantage of the current invention that: factorial praluction steelframe, splice bolt, module board, fixing modules plate being carried out splicing with installing, tool There are short construction period, low cost, installation accuracy high.
Accompanying drawing explanation
Fig. 1 is the present invention spliced steel construction tobacco flue-curing house splice point site plan;
Fig. 2 is the present invention spliced steel construction tobacco flue-curing house side view;
Fig. 3 is the present invention spliced steel construction tobacco flue-curing house plain splice figure;
Detailed description of the invention
As it can be seen, streamline tobacco curing barn assembly contact such as the splice point 1 on Fig. 1 of the present invention is distributed, specifically two pieces of straight wall modules 2 are fixed On hardened ground 6, form a flue-cured tobacco tunnel, then by bolt 7 trapped orbit crossbeam module 3 on certain altitude straight wall module 2, and At track cross beam module 3 chain track installed below 5, then tobacco flue-curing house roof 4 fixed by certain altitude bolt 7 on crossbeam module, spelling Connect formula steel construction streamline tobacco flue-curing house.

Claims (1)

1. streamline tobacco curing barn assembling technique, it is characterised in that streamline tobacco curing barn splicing apparatus is made up of splice bolt, steelframe, module board, The ground hardened fixes tobacco flue-curing house steelframe, utilizes bolt to be fixed by the modules plate of tobacco flue-curing house and be streamline tobacco flue-curing house.
CN201510026094.4A 2015-01-20 2015-01-20 Production line tobacco room assembly technology Pending CN105863313A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510026094.4A CN105863313A (en) 2015-01-20 2015-01-20 Production line tobacco room assembly technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510026094.4A CN105863313A (en) 2015-01-20 2015-01-20 Production line tobacco room assembly technology

Publications (1)

Publication Number Publication Date
CN105863313A true CN105863313A (en) 2016-08-17

Family

ID=56622861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510026094.4A Pending CN105863313A (en) 2015-01-20 2015-01-20 Production line tobacco room assembly technology

Country Status (1)

Country Link
CN (1) CN105863313A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04293864A (en) * 1991-03-20 1992-10-19 Hitachi Ltd Building construction method for nuclear power station, building module and nuclear power station building
CN201343883Y (en) * 2008-11-17 2009-11-11 贵州省烟草科学研究所 Combined type movable curing barn
CN201902034U (en) * 2010-11-03 2011-07-20 四川华汉科技工程有限公司 Corrosion-resistant insulating plate type curing barn
CN202722471U (en) * 2012-07-27 2013-02-13 山东潍坊烟草有限公司高密分公司 Small bamboo comb basket for tobacco flue-curing
CN202722472U (en) * 2012-07-27 2013-02-13 山东潍坊烟草有限公司 Assembled baking room of strawboards for tobaccos
CN202774089U (en) * 2012-09-21 2013-03-13 姜永辉 Full-automatic production line tobacco curing chamber

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04293864A (en) * 1991-03-20 1992-10-19 Hitachi Ltd Building construction method for nuclear power station, building module and nuclear power station building
CN201343883Y (en) * 2008-11-17 2009-11-11 贵州省烟草科学研究所 Combined type movable curing barn
CN201902034U (en) * 2010-11-03 2011-07-20 四川华汉科技工程有限公司 Corrosion-resistant insulating plate type curing barn
CN202722471U (en) * 2012-07-27 2013-02-13 山东潍坊烟草有限公司高密分公司 Small bamboo comb basket for tobacco flue-curing
CN202722472U (en) * 2012-07-27 2013-02-13 山东潍坊烟草有限公司 Assembled baking room of strawboards for tobaccos
CN202774089U (en) * 2012-09-21 2013-03-13 姜永辉 Full-automatic production line tobacco curing chamber

Similar Documents

Publication Publication Date Title
CN204019700U (en) Stair prefabricated components mould
PL406240A1 (en) Modular system for the mobile SAGD process
KR101826011B1 (en) Pipe module and construction method thereof
MX2009013516A (en) Method for mounting in sections an annular tower for wind power generator, heliostatic power generator or chimney composed from three concrete segments or more.
RS54062B1 (en) Device and method for erecting a tower for a wind energy plant
CN203783827U (en) Novel longitudinal joint structure of wind power generation prefabricated concrete tower component
CN101224840A (en) Sectionalizing device for girders of passenger conveying equipment
CN103982038A (en) Construction method for solar separate house modular rapid assembly
ATE498745T1 (en) MULTIPLE-MODULE BUILDING
MX2018008505A (en) Pre-assembly slab system for concrete wind turbine towers and method for assembling a pre-assembly slab system for concrete wind turbine towers.
CN202007967U (en) Machine frame installing structure for air showering equipment
CN108824719A (en) A kind of assembled architecture stair
CN205058265U (en) Supporting device about bridge hollow core slab side form
CN105863313A (en) Production line tobacco room assembly technology
CN104060841B (en) Large-span steel girder construction method of installation
CN205219409U (en) Sleeve pipe positioner in precast beam
CN203983929U (en) Assemble type underground cable ditch based on city integrated wiring
CN203741989U (en) Light steel structure for integrated house
CN106088579A (en) The erection method of reinforced concrete wall template
CN103573018B (en) The building that can reuse encircles and hunts down enclosure wall and construction method thereof
CN104612063A (en) Concrete box beam first-aid repair method with prefabricated part on-site assembling combination beam
CN103633927A (en) Method for installing integrated photovoltaic support of solar panel
CN201211997Y (en) Truss sectioned device of passenger transportation device
CN207392740U (en) A kind of assemble type concrete slab support system
CN203346778U (en) Box girder splicing assembly joint

Legal Events

Date Code Title Description
DD01 Delivery of document by public notice

Addressee: Jiang Yonghui

Document name: Notification of Passing Preliminary Examination of the Application for Invention

DD01 Delivery of document by public notice

Addressee: Zhang Zhaowei

Document name: Notification of Passing Examination on Formalities

C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20161104

Address after: 474350, Henan County, Nanyang County, Neixiang Province industrial agglomeration Road

Applicant after: Neixiang Lifu Deere Energy Equipment Co. Ltd.

Address before: Sheqi County in Henan province 473300 Mo Po Xiang Jia Zhai Cun Jia Building No. 94

Applicant before: Jiang Yonghui

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160817