Method for installing integrated photovoltaic support of solar panel Download PDFInfo
- Publication number
- CN103633927A CN103633927A CN201310693639.8A CN201310693639A CN103633927A CN 103633927 A CN103633927 A CN 103633927A CN 201310693639 A CN201310693639 A CN 201310693639A CN 103633927 A CN103633927 A CN 103633927A
- Authority
- CN
- China
- Prior art keywords
- support
- installation
- beams
- longeron
- cant beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Landscapes
- Foundations (AREA)
- Photovoltaic Devices (AREA)
Abstract
The invention discloses a method for installing an integrated photovoltaic support of a solar panel, and belongs to the technical field of installation of solar photovoltaic components. The method is characterized by comprising the following steps: (1) clearing weeds and surface soil at the support installation place in the installation site; (2) connecting longitudinal beams, cross beams and support diagonal beams, wherein the lengths of the longitudinal beams and the support diagonal beams are determined according to the situation of the installation position; (3) installing horizontal reinforced bars at the installation root parts of the longitudinal beams and the support diagonal beams; (4) placing the support at the support installation position and adjusting the position and the installation angle of the support; and (5) pouring concrete to the installation root parts of the longitudinal beams and the support diagonal beams for fixing, thereby installing the integrated photovoltaic support. The construction process is simple, and the construction cost is saved; the installation speed is high, and the construction cycle is short; the natural feature and the peripheral environment are protected, and the construction process has an environment protection effect.
Description
Technical field
The present invention relates to a kind of construction method that the integral photovoltaic support of solar panels is installed.Belong to solar photovoltaic assembly mounting technique field.
Background technology
The support of existing installation solar panel, in industry, be called " photovoltaic bracket ", mostly by two parts, formed, a part is by some longerons and be fixed on some crossbeams on longeron and the ground support of the installation solar panel that some support cant beams form, and a part is to be embedded in the underground concrete foundation pile with metal embedded part.Foot rest by ground support bottom has been connected the installation of support with foundation pile with anchor ear.Or by bolt or jockey, be connected the installation of support by the bottom of longeron and support cant beam with the metal embedded part in the concrete foundation of front and back.The shortcoming of the installation method of (disclosing " a kind of photovoltaic bracket system " referring to Chinese patent 201220178508.7) this photovoltaic bracket is that the making of its concrete foundation need to first be driven piles and deep-cut, lay reinforcing bar inclosure and carry out again concreting built-in metal connector, long construction period, inefficiency, construction cost is higher, especially when photovoltaic bracket in enormous quantities is installed, is difficult to adapt to the requirement of project progress.While connecting ground support by anchor ear or bolt, be the setting angle that guarantees support, its adjustment workload is large, has both affected installation effectiveness, also may cause bracket component stressed bad and affect the life-span.In addition, Chinese patent ZL201220201444.8 discloses " stake of integral photovoltaic bracket basis ", and the supporting structure of this scheme is complicated, and foundation pile need be driven piles and be laid reinforcing bar inclosure and carry out concreting at subsurface again.Have equally long construction period, inefficiency and being difficult to adapts to the shortcoming of the requirement of project progress.Above-mentioned various existing photovoltaic bracket does not meet national environmental protection policy, very large to the destruction of surface of job site when mounted, especially easily accelerates the desertification in grassland and Gobi desert soil, and weathering destroys natural feature and surrounding enviroment.
Summary of the invention
The object of the invention is to overcome the above-mentioned shortcoming of prior art, provide a kind of easy for installation simple, construction cost is low, short construction period, and installation quality is good, environmental protection, checking the wind and fixing the shifting sand, the construction method of the integral photovoltaic support of conservation of nature landforms.
The content of installation method that realizes the integral photovoltaic support of the object of the invention is: 1, remove weeds and the surface dust of support installation site, erecting bed, 2, connect longeron, crossbeam and support cant beam, and determine longeron and the length that supports cant beam according to the situation of installation site, 3, installation root at longeron and support cant beam arranges transverse steel, 4, above-mentioned support is placed in to position and the setting angle that support is installed station and adjusted support, 5, by the fixing installation that completes integral photovoltaic support of concreting for the installation root of longeron and support cant beam.
The present invention is by the length of carrying out on-the-spot decision longeron and supporting cant beam to adapt to the actual conditions of support installation site, and the processing that the installation root of longeron and support cant beam is strengthened to force structure, after adjusting the position of support and setting angle, with concrete, longeron and installation root and the solid earth's surface of supporting cant beam are consolidated, each parts that effectively guaranteed the steadiness of photovoltaic bracket and made to form support are all in good stress.Simplified traditional concrete foundation complicated technology flow process of mounting bracket again of first making, construction technology is simple, the geographical situation of erecting bed is required low, substantially can not do the foundation works such as smooth in place, greatly saves construction cost; Installation rate is fast, short construction period.Can meet the requirement to project progress when photovoltaic bracket in enormous quantities is installed completely.When photovoltaic bracket is installed to the earth's surface of job site without any destruction, checking the wind and fixing the shifting sand, conservation of nature landforms and surrounding enviroment, meet national environmental protection policy.
Accompanying drawing explanation
The front view of Fig. 1 integral photovoltaic support
The A view of Fig. 2 Fig. 1
Fig. 3 transverse steel schematic diagram of arranging
Embodiment
The Specific construction step of the inventive method is:
1, remove weeds and the surface dust of support installation site, erecting bed,
2, referring to Fig. 1 and Fig. 2, by existing mode, connect longeron 2, crossbeam 1 and support cant beam 3, and according to the situation of installation site, determining the length of longeron 2 and support cant beam 3,
3, at the installation root of longeron 2, transverse steel 7 is set, reinforcing bar 7 can arrange by insert the form of reinforcing bar in longeron perforate, also can weld, be arranged side by side (referring to Fig. 3) or be crisscross arranged all can,
4, at the installation root that supports cant beam 3, transverse steel 6 is set, reinforcing bar 6 can arrange by insert the form of reinforcing bar in longeron perforate, also can weld, be arranged side by side (referring to Fig. 3) or be crisscross arranged all can,
5, above-mentioned support is placed in to position and the setting angle that support is installed station and adjusted support, now the installation root of longeron and support cant beam is supported on solid earth's surface,
6, mould is built in installation, with concrete 5, the installation root with transverse steel 7 of longeron 2 and solid earth's surface are consolidated, with concrete 4, the installation root with transverse steel 6 and the solid earth's surface of supporting cant beam 3 are consolidated, complete the installation of integral photovoltaic support.
Claims (1)
1. the installation method of integral photovoltaic support, is characterized in that the content of described method is:
1), remove weeds and the surface dust of support installation site, erecting bed,
2), connect longeron, crossbeam and support cant beam, and according to the situation of installation site, determine the length of longeron and support cant beam,
3), at longeron and the installation root that supports cant beam, transverse steel is set,
4), above-mentioned support is placed in to position and the setting angle that support is installed station and adjusted support,
5), by the fixing installation that completes integral photovoltaic support of concreting for the installation root of longeron and support cant beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310693639.8A CN103633927A (en) | 2013-12-18 | 2013-12-18 | Method for installing integrated photovoltaic support of solar panel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310693639.8A CN103633927A (en) | 2013-12-18 | 2013-12-18 | Method for installing integrated photovoltaic support of solar panel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103633927A true CN103633927A (en) | 2014-03-12 |
Family
ID=50214631
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310693639.8A Pending CN103633927A (en) | 2013-12-18 | 2013-12-18 | Method for installing integrated photovoltaic support of solar panel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103633927A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103968221A (en) * | 2014-05-21 | 2014-08-06 | 苏州瑞得恩光能科技有限公司 | Triangular support foundation fixing box |
CN104179193A (en) * | 2014-09-16 | 2014-12-03 | 中国建材国际工程集团有限公司 | Wind-resistant moment sinking-resistant reinforced improved-stability photovoltaic support base structure |
CN104213574A (en) * | 2014-09-28 | 2014-12-17 | 北京万阳天力新能源科技有限公司 | Adjustable foundation connecting buckle of solar photovoltaic power generation assembly bracket |
-
2013
- 2013-12-18 CN CN201310693639.8A patent/CN103633927A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103968221A (en) * | 2014-05-21 | 2014-08-06 | 苏州瑞得恩光能科技有限公司 | Triangular support foundation fixing box |
CN104179193A (en) * | 2014-09-16 | 2014-12-03 | 中国建材国际工程集团有限公司 | Wind-resistant moment sinking-resistant reinforced improved-stability photovoltaic support base structure |
CN104213574A (en) * | 2014-09-28 | 2014-12-17 | 北京万阳天力新能源科技有限公司 | Adjustable foundation connecting buckle of solar photovoltaic power generation assembly bracket |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104234385B (en) | Construction method of installation after a kind of terrace heavy steel plate built-in fitting | |
CN202125105U (en) | Buried single column small photovoltaic bracket | |
JP3184322U (en) | Solar panel mount | |
CN104060617B (en) | The prefabricated assembled inner support system of foundation pit support system and construction method | |
CN104294769B (en) | A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement | |
CN204662455U (en) | Foundation pit support device reinforced by a kind of adjustable diagonal brace | |
CN103967019A (en) | Fish-bellied beam device for supporting foundation ditch | |
CN103633927A (en) | Method for installing integrated photovoltaic support of solar panel | |
CN202672162U (en) | Combined type retaining structure | |
KR101258043B1 (en) | Eco-friendly reinforced retainaing wall and construction method thereof | |
CN103741708A (en) | Prefabricated concrete pole sleeve base | |
CN103967021A (en) | Prestress support system for strip rectangular foundation ditch | |
CN204040556U (en) | A telescopic graduation two electronic box protection canopy | |
CN204097889U (en) | A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement | |
CN204531575U (en) | Cement pole Reinforcement Reinforced Concrete Structure | |
CN105220809A (en) | The syndeton of a kind of arch top board and bracket stake and construction method thereof | |
CN104695290A (en) | Installation method of railway concrete protection fences | |
CN203308109U (en) | External carrying net device | |
KR100879973B1 (en) | Beamcreen rhombic dam | |
CN103498573B (en) | Set up the existing frame strengthening method of band frame bracing members | |
CN203429557U (en) | Anchor pole back beam applied to underpass bridge jacking construction | |
CN206267103U (en) | The protection device of Face Rockfill Dam Copper water stop | |
CN205676917U (en) | A kind of steel frame basis of tower mast structure | |
CN205171540U (en) | A stock combination rock foundation builds in for transmission tower | |
CN205088832U (en) | Connection structure of arch roof and bracket stake |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20140312 |
|
WD01 | Invention patent application deemed withdrawn after publication |