CN105844016A - 一种基于建筑模型切割的获得拟建建筑工程量的方法 - Google Patents
一种基于建筑模型切割的获得拟建建筑工程量的方法 Download PDFInfo
- Publication number
- CN105844016A CN105844016A CN201610169545.4A CN201610169545A CN105844016A CN 105844016 A CN105844016 A CN 105844016A CN 201610169545 A CN201610169545 A CN 201610169545A CN 105844016 A CN105844016 A CN 105844016A
- Authority
- CN
- China
- Prior art keywords
- building
- module
- model
- build
- buildings models
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Theoretical Computer Science (AREA)
- Mathematical Optimization (AREA)
- Computational Mathematics (AREA)
- Architecture (AREA)
- Mathematical Analysis (AREA)
- Structural Engineering (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及一种基于建筑模型切割的获得拟建建筑工程量的方法,属于建筑模型的建模领域。具体方法为在已完建筑模型在建筑类型的基础上再分解成桩基础、地下砼结构、地上砼结构、外幕墙结构以及地上钢结构局部模块。建立模型局部模块工程量与模型局部模块设计参数的逻辑联系数据库。对已完项目建筑模型的统计分析结果,通过拟建建筑模型局部设计参数与已完项目建筑模型局部设计参数一致性对比,将已完项目建筑局部模块工程量应用到拟建项目模型对应的局部模块中,并将局部模块工程量进行汇总。本方法实现已完项目建筑模型数据的再利用。
Description
技术领域
本发明涉及一种基于建筑模型切割的获得拟建建筑工程量的方法,属于建筑模型的建模领域。
背景技术
现行的建筑模型工程量是以构件为单位,没有层次性,没有分解成局部模块;现行建筑模型中没有建立模型局部模块工程量与建立模型局部模块设计参数的逻辑联系数据库,对已完建模模型工程量不能提供再利用。
发明内容
本发明的目的
将已完项目建筑模型的统计分析结果,应用到拟建项目模型中,得到拟建建筑模型模拟工程量,实现已完项目建筑模型数据的再利用。
本发明的技术方案
提供了一种基于切割的获得拟建建筑工程量的方法,具体包括以下步骤
步骤1、建立已完工程数据库,该数据库中建立了建筑局部模块(其设计参数包含建筑类型、荷载类型、荷载大小、地上建筑面积、地下建筑面积、幕墙面积)与工程量的对应关系,每个建筑局部模块都具有对应的工程量;所述的建筑局部模块包括桩基础、地下砼结构、地上砼结构、外幕墙结构以及地上钢结构;
步骤2、获得拟建建筑模型,对建筑模型的类别进行确定,所述的类型包括:砼结构建筑模型、混合结构建筑模型、钢结构建筑模型;
当拟建建筑模型为砼结构建筑模型时,按照桩基础、地下砼结构、地上砼结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
当拟建建筑模型为混合结构建筑模型时,按照桩基础、地下砼结构、地上砼结构、地上钢结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
当拟建建筑模型为钢结构结构建筑模型时,按照桩基础、地下砼结构、地上钢结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
步骤3,获得拟建建筑模型的总工程量
根据拟建建筑模型划分出来的多个建筑局部模块,在已完工程数据库中找到各个建筑局部模块对应的工程量,并将拟建建筑模型划分出来的各个建筑局部模块的工程量求和,得到拟建建筑模型的总工程量。
本发明的技术效果
提高拟建项目建筑模型工程量估计的准确性,提供估算效率。
具体实施方式
提供了一种基于切割的获得拟建建筑工程量的方法,具体包括以下步骤
步骤1、建立已完工程数据库,该数据库中建立了建筑局部模块与工程量的对应关系,每个建筑局部模块都具有一个工程量;所述的建筑局部模块包括桩基础、地下砼结构、地上砼结构、外幕墙结构以及地上钢结构;
步骤2、获得拟建建筑模型,对建筑模型的类别进行确定,所述的类型包括:砼结构建筑模型、混合结构建筑模型、钢结构建筑模型;
当拟建建筑模型为砼结构建筑模型时,按照桩基础、地下砼结构、地上砼结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
当拟建建筑模型为混合结构建筑模型时,按照桩基础、地下砼结构、地上砼结构、地上钢结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
当拟建建筑模型为钢结构结构建筑模型时,按照桩基础、地下砼结构、地上钢结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
步骤3,获得拟建建筑模型的总工程量
根据拟建建筑模型划分出来的多个建筑局部模块,在已完工程数据库中找到各个建筑局部模块对应的工程量,并将拟建建筑模型划分出来的各个建筑局部模块的工程量求和,得到拟建建筑模型的总工程量。
Claims (2)
1.一种基于切割的获得拟建建筑工程量的方法,具体包括以下步骤:
步骤1、建立已完工程数据库,该数据库中建立了建筑局部模块与工程量的对应关系,每个建筑局部模块都具有对应的工程量;所述的建筑局部模块包括桩基础、地下砼结构、地上砼结构、外幕墙结构以及地上钢结构;
步骤2、获得拟建建筑模型,对建筑模型的类别进行确定,所述的类型包括:砼结构建筑模型、混合结构建筑模型、钢结构建筑模型;
当拟建建筑模型为砼结构建筑模型时,按照桩基础、地下砼结构、地上砼结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
当拟建建筑模型为混合结构建筑模型时,按照桩基础、地下砼结构、地上砼结构、地上钢结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
当拟建建筑模型为钢结构结构建筑模型时,按照桩基础、地下砼结构、地上钢结构、外幕墙结构将获得的建筑模型进行划分为多个建筑局部模块;
步骤3,获得拟建建筑模型的总工程量
根据拟建建筑模型划分出来的多个建筑局部模块,在已完工程数据库中找到各个建筑局部模块对应的工程量,并将拟建建筑模型划分出来的各个建筑局部模块的工程量求和,得到拟建建筑模型的总工程量。
2.根据权利要求1所述的一种基于切割的获得拟建建筑工程量的方法,其特征在于:所述的建筑局部模块的设计参数包括建筑类型、荷载类型、荷载大小、地上建筑面积、地下建筑面积、幕墙面积。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610169545.4A CN105844016B (zh) | 2016-03-23 | 2016-03-23 | 一种基于建筑模型切割的获得拟建建筑工程量的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610169545.4A CN105844016B (zh) | 2016-03-23 | 2016-03-23 | 一种基于建筑模型切割的获得拟建建筑工程量的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105844016A true CN105844016A (zh) | 2016-08-10 |
CN105844016B CN105844016B (zh) | 2019-06-07 |
Family
ID=56583126
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610169545.4A Active CN105844016B (zh) | 2016-03-23 | 2016-03-23 | 一种基于建筑模型切割的获得拟建建筑工程量的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105844016B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107100175A (zh) * | 2017-02-21 | 2017-08-29 | 贵州省交通规划勘察设计研究院股份有限公司 | 一种在路基边坡立面图上指定基点快速准确布置抗滑桩的方法 |
CN109710649A (zh) * | 2018-11-14 | 2019-05-03 | 中交第二航务工程局有限公司 | 周转材料推荐方法及系统 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008033101A1 (en) * | 2006-09-13 | 2008-03-20 | National University Of Singapore | System and method for generating a bill of quantities |
CN103337005A (zh) * | 2013-05-31 | 2013-10-02 | 中建钢构有限公司 | 一种工程进度及造价管理系统的管理方法 |
CN105302978A (zh) * | 2015-11-10 | 2016-02-03 | 上海建工集团股份有限公司 | 一种工程量计算方法和设备 |
CN105335905A (zh) * | 2015-11-24 | 2016-02-17 | 广州拓欧信息技术有限公司 | 一种建筑工程算量和估价系统及方法 |
-
2016
- 2016-03-23 CN CN201610169545.4A patent/CN105844016B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008033101A1 (en) * | 2006-09-13 | 2008-03-20 | National University Of Singapore | System and method for generating a bill of quantities |
CN103337005A (zh) * | 2013-05-31 | 2013-10-02 | 中建钢构有限公司 | 一种工程进度及造价管理系统的管理方法 |
CN105302978A (zh) * | 2015-11-10 | 2016-02-03 | 上海建工集团股份有限公司 | 一种工程量计算方法和设备 |
CN105335905A (zh) * | 2015-11-24 | 2016-02-17 | 广州拓欧信息技术有限公司 | 一种建筑工程算量和估价系统及方法 |
Non-Patent Citations (1)
Title |
---|
李国强 等: "高层建筑钢-混凝土混合结构设计实例", 《建筑钢结构进展》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107100175A (zh) * | 2017-02-21 | 2017-08-29 | 贵州省交通规划勘察设计研究院股份有限公司 | 一种在路基边坡立面图上指定基点快速准确布置抗滑桩的方法 |
CN107100175B (zh) * | 2017-02-21 | 2019-11-19 | 贵州省交通规划勘察设计研究院股份有限公司 | 一种在路基边坡立面图上指定基点快速准确布置抗滑桩的方法 |
CN109710649A (zh) * | 2018-11-14 | 2019-05-03 | 中交第二航务工程局有限公司 | 周转材料推荐方法及系统 |
Also Published As
Publication number | Publication date |
---|---|
CN105844016B (zh) | 2019-06-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109710990B (zh) | 基于bim技术的碾压混凝土坝施工进度-成本协同控制方法 | |
CN105781064A (zh) | 基于bim的地砖铺设施工方法 | |
CN106709660A (zh) | 基于bim的建筑设计方法 | |
CN108268715B (zh) | 一种基于bim技术的钢桥面铺装施工仿真模拟方法 | |
CN104537447A (zh) | 一种建设工程施工碳排放运算系统 | |
CN108268707A (zh) | 一种基于revit的转运站标准模板绘制方法及转运站构建方法 | |
CN108280276A (zh) | 基于Revit软件楼梯模型标准创建和用量统计方法 | |
CN108427819A (zh) | 一种完整装配式bim建筑模型的生成方法及装置 | |
CN108681879A (zh) | 一种基于bim技术的灌注桩施工管理方法及系统 | |
CN105844016A (zh) | 一种基于建筑模型切割的获得拟建建筑工程量的方法 | |
CN212613903U (zh) | 一种砖混结构老旧楼体复合加固结构 | |
CN113536411A (zh) | 一种精确定位构件边线的bim建模方法及系统 | |
Laurini et al. | Technology 4.0 for buildings management: from building site to the interactive building book | |
Nowotarski et al. | Lean and agile management synergy in construction of high-rise office building | |
CN108416076A (zh) | 一种基于bim技术的装配式建筑设计方法 | |
CN111563651A (zh) | 一种基于bim技术的沥青路面施工工程量动态追踪管理系统 | |
CN107092764A (zh) | 一种基于bim的混凝土装配式施工方法 | |
CN110008534B (zh) | 一种基于bim的模型体系层级划分方法和装置 | |
CN106096260B (zh) | 一种获取沥青路面养护能耗碳排放可靠性评价的方法 | |
KR20120068114A (ko) | 초고층 건물 공사계획 방법 | |
Marzouk et al. | Quantifying weather impact on formwork shuttering and removal operation using system dynamics | |
Moon et al. | Evaluation of environmental stress for highway construction project by life cycle assessment method | |
Lundgren et al. | Adapting for shared use–evaluating the lifecycle carbon impact | |
Marzouk et al. | Framework for sustainable low-income housing projects in Egypt | |
CN102708226A (zh) | 基于工艺流的水利水电工程仿真建模方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |