CN108416076A - 一种基于bim技术的装配式建筑设计方法 - Google Patents
一种基于bim技术的装配式建筑设计方法 Download PDFInfo
- Publication number
- CN108416076A CN108416076A CN201711369889.0A CN201711369889A CN108416076A CN 108416076 A CN108416076 A CN 108416076A CN 201711369889 A CN201711369889 A CN 201711369889A CN 108416076 A CN108416076 A CN 108416076A
- Authority
- CN
- China
- Prior art keywords
- data
- simulation
- assembled architecture
- design
- threshold value
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Abstract
本发明涉及一种基于BIM技术的装配式建筑设计方法,包括如下步骤:S1、数据获取;S2、参数预设;S3、建模成型;S4、软件模拟;S5、数据判定;S6、发送结果;S7后期复核;提高设计效率,改善设计质量,减少设计成本,具有可视化、高协同、高准确性。
Description
技术领域
本发明涉及一种设计方法,尤其涉及一种基于BIM技术的装配式建筑设计方法。
背景技术
BIM(Building Information Modeling建筑信息模型)是以建筑工程项目的各项相关信息数据作为模型的基础,进行建筑模型的建立,通过数字信息仿真模拟建筑物所具有的真实信息。它将数字化的三维建筑模型作为核心应用于建筑工程的设计、施工等过程中的工作方法。它是用协调一致的信息对建筑全周期进行管理,对建筑物进行分析、模拟、可视化、统计、计算等工作,从而很好的降低生产成本,大幅的缩短建设周期,并减少对资源的浪费。现有技术中缺乏利用BIM技术进行的装配式建筑设计方法,利用不全面,尚存在不足。
发明内容
本发明要解决的技术问题是;为了克服现有二维设计技术中存在的不足和缺陷,本发明提供了一种基于BIM技术的三维设计装配式建筑设计方法,提高设计效率,改善设计质量,减少设计成本,具有可视化、高协同、高准确性的优点。
本发明解决其技术问题所采用的技术方案是;一种基于BIM技术的装配式建筑设计方法,包括如下步骤;
S1、数据获取;
获取项目装配式建筑的设计图纸、设计参数以及该项目装配式建筑选址用地的相关地理信息数据;
S2、参数预设;
将项目装配式建筑具体划分为外墙板、叠合板、附加空间、预埋件以及钢筋各部分,并对各个部分进行编号,同时将各部分的结构数据阈值提前输入中控平台中的数据判定部,并在中控平台内的求和单元中预先设置N的数值;
S3、建模成型;
对外墙板、叠合板、附加空间、预埋件以及钢筋各部分进行BIM单元建模,并将建立好的各部分的BIM单元模型组装成为整体模型;
S4、软件模拟;
通过软件模拟,将整体模型中各编号对应部分的结构进行各项模拟,得到各编号对应部分的结构模拟数据,并将其传输进入中控平台;
S5、数据判定;
中控平台中的信息接收部接收步骤S4中得到的各项结构模拟数据,并将其按照编号依次发送给数据判定部,数据判定部将其与步骤S2中提前输入的结构数据阈值按照编号依次进行判定,如果有一个结构模拟数据超出结构数据阈值,则数据判定部中的计数器数据+1,并将计数发送给求和单元;
S6、发送结果;
当求和结果达到步骤S2中预先设置的N的数值时,求和单元将数据发送给外部显示单元,同时通过声光报警装置向工作人员发出提示;当求和结果未达到步骤S2中预先设置的N的数值时,求和单元仅将数据发送给外部显示单元;
S7、后期复核;
检查并记录设计完成后的装配式建筑的各项数据,并与结构数据阈值、结构模拟数据进行比较、分析和复核,然后通过步骤S6中的外部显示单元进行集中显示,通过数据存档,为后续的设计工作提供依据和参考。
进一步地,步骤S2中的附加空间包括楼梯、阳台、空调外机安装平台、阁楼、底层商铺以及停车区域。
进一步地,步骤S2中的结构数据包括形状尺寸、耐受温度、抗压强度、结构重量。
进一步地,各项模拟包括地震模拟、风雪模拟,雨水模拟、火灾模拟以及构件碰撞模拟。
进一步地,步骤S6中的外部显示单元通过电子表格的形式显示数据,且同时包含结构数据阈值和结构模拟数据,且为每一次经过数据判定部的数据提供存档。
本发明的有益效果是;
(1)将BIM技术应用到装配式建筑设计中来,由原有二维到三维的升华,使设计可视化、高协同、高准确性,为装配式建筑设计提供理论参考和实践应用,为今后装配式建筑设计提供一种新的思路和设计方法;
(2)通过结构模拟数值和结构数据阈值的相互比较,可以有效提高设计效率,在改善设计质量的同时,减少设计成本;
(3)通过求和单元中N的数值的设定,可以根据实际工作过程中的优先需要和精度需求确定设计的精度等级,从而进一步改善设计质量,减少设计成本。
附图说明
图1为本发明一种基于BIM技术的装配式建筑设计方法的步骤流程图。
具体实施方式
现在结合附图对本发明作进一步详细的说明。这些附图均为简化的示意图,仅以示意方式说明本发明的基本结构,因此其仅显示与本发明有关的构成。
如图1所示,一种基于BIM技术的装配式建筑设计方法,包括如下步骤;
S1、数据获取;
获取该项目装配式建筑的设计图纸、设计参数以及该项目装配式建筑选址用地的相关地理信息数据;
S2、参数预设;
将该项目装配式建筑具体划分为外墙板、叠合板、附加空间、预埋件以及钢筋各部分,并对各个部分进行编号,同时将各部分的结构数据阈值提前输入中控平台中的数据判定部,并在中控平台内的求和单元中预先设置N的数值;
S3、建模成型;
对外墙板、叠合板、附加空间、预埋件以及钢筋各部分进行BIM单元建模,并将建立好的各部分的BIM单元模型组装成为整体模型;
S4、软件模拟;
通过软件模拟,将整体模型中各编号对应部分的结构进行各项模拟,得到各编号对应部分的结构模拟数据,并将其传输进入中控平台;
S5、数据判定;
中控平台中的信息接收部接收步骤S4中得到的各项结构模拟数据,并将其按照编号依次发送给数据判定部,数据判定部将其与步骤S2中提前输入的结构数据阈值按照编号依次进行判定,如果有一个结构模拟数据超出结构数据阈值,则数据判定部中的计数器数据+1,并将计数发送给求和单元;
S6、发送结果;
当求和结果达到步骤S2中预先设置的N的数值时,求和单元将数据发送给外部显示单元,同时通过声光报警装置向工作人员发出提示;当求和结果未达到步骤S2中预先设置的N的数值时,求和单元仅将数据发送给外部显示单元;
S7、后期复核;
检查并记录设计完成后的装配式建筑的各项数据,并与结构数据阈值、结构模拟数据进行比较、分析和复核,然后通过步骤S6中的外部显示单元进行集中显示,通过数据存档,为后续的设计工作提供依据和参考。
具体地,步骤S2中的附加空间包括楼梯、阳台、空调外机安装平台、阁楼、底层商铺以及停车区域。
具体地,步骤S2中的结构数据包括形状尺寸、耐受温度、抗压强度、结构重量。
具体地,各项模拟包括地震模拟、风雪模拟、雨水模拟、火灾模拟、以及构件碰撞模拟。
具体地,步骤S6中的外部显示单元通过电子表格的形式显示数据,且同时包含结构数据阈值和结构模拟数据,且为每一次经过数据判定部的数据提供存档。
具体地,中控平台中还设置有优先级判定单元,其对各部分的结构模拟数据超出结构数据阈值的部分进行排序,并根据排序后的结果优先在计数器数据+1,并将计数发送给求和单元,而忽略原先的编号顺序;
以上述依据本发明的理想实施例为启示,通过上述的说明内容,相关工作人员完全可以在不偏离本项发明技术思想的范围内,进行多样的变更以及修改。本项发明的技术性范围并不局限于说明书上的内容,必须要根据权利要求范围来确定其技术性范围。
Claims (5)
1.一种基于BIM技术的装配式建筑设计方法,包括如下步骤;
S1、数据获取;
获取项目装配式建筑的设计图纸、设计参数以及项目装配式建筑选址用地的相关地理信息数据;
S2、参数预设;
将项目装配式建筑具体划分为外墙板、叠合板、附加空间、预埋件以及钢筋各部分,并对各个部分进行编号,同时将各部分的结构数据阈值提前输入中控平台中的数据判定部,并在中控平台内的求和单元中预先设置N的数值;
S3、建模成型;
对外墙板、叠合板、附加空间、预埋件以及钢筋各部分进行BIM单元建模,并将建立好的各部分的BIM单元模型组装成为整体模型;
S4、软件模拟;
通过软件模拟,将整体模型中各编号对应部分的结构进行各项模拟,得到各编号对应部分的结构模拟数据,并将其传输进入中控平台;
S5、数据判定;
中控平台中的信息接收部接收步骤S4中得到的各项结构模拟数据,并将其按照编号依次发送给数据判定部,数据判定部将其与步骤S2中提前输入的结构数据阈值按照编号依次进行判定,如果有一个结构模拟数据超出结构数据阈值,则数据判定部中的计数器数据+1,并将计数发送给求和单元;
S6、发送结果;
当求和结果达到步骤S2中预先设置的N的数值时,求和单元将数据发送给外部显示单元,同时通过声光报警装置向工作人员发出提示;当求和结果未达到步骤S2中预先设置的N的数值时,求和单元仅将数据发送给外部显示单元;
S7、后期复核;
检查并记录设计完成后的装配式建筑的各项数据,并与结构数据阈值、结构模拟数据进行比较、分析和复核,然后通过步骤S6中的外部显示单元进行集中显示,通过数据存档,为后续的设计工作提供依据和参考。
2.根据权利要求1所述的方法,其特征在于;所述步骤S2中的附加空间包括楼梯、阳台、空调外机安装平台、阁楼、底层商铺以及停车区域。
3.根据权利要求1所述的方法,其特征在于;所述步骤S2中的结构数据包括形状尺寸、耐受温度、抗压强度、结构重量。
4.根据权利要求1所述的方法,其特征在于;所述步骤S4中的各项模拟包括地震模拟、风雪模拟、雨水模拟、火灾模拟、以及构件碰撞模拟。
5.根据权利要求1所述的方法,其特征在于;所述步骤S6中的外部显示单元通过电子表格的形式显示数据,且同时包含结构数据阈值和结构模拟数据,且为每一次经过数据判定部的数据提供存档。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711369889.0A CN108416076B (zh) | 2017-12-19 | 2017-12-19 | 一种基于bim技术的装配式建筑设计方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711369889.0A CN108416076B (zh) | 2017-12-19 | 2017-12-19 | 一种基于bim技术的装配式建筑设计方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108416076A true CN108416076A (zh) | 2018-08-17 |
CN108416076B CN108416076B (zh) | 2020-06-09 |
Family
ID=63125494
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711369889.0A Active CN108416076B (zh) | 2017-12-19 | 2017-12-19 | 一种基于bim技术的装配式建筑设计方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108416076B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110782523A (zh) * | 2019-10-11 | 2020-02-11 | 上海建工五建集团有限公司 | 基于bim的建筑模型检查方法及系统 |
CN111353191A (zh) * | 2020-02-28 | 2020-06-30 | 中国十七冶集团有限公司 | 一种多曲率异形曲面屋盖钢结构施工方法 |
CN112052490A (zh) * | 2020-05-22 | 2020-12-08 | 杭州嗡嗡科技有限公司 | 基于bim的装配式深化设计方法及其设计工具 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104349141A (zh) * | 2013-08-08 | 2015-02-11 | 霍尼韦尔国际公司 | 使用bim模型可视化事件历史的系统和方法 |
CN104468243A (zh) * | 2014-12-31 | 2015-03-25 | 湖南华宽通科技股份有限公司 | 综合网元管理设备 |
US20160033946A1 (en) * | 2014-07-31 | 2016-02-04 | Honeywell International Inc. | Building management system analysis |
CN105929770A (zh) * | 2016-04-19 | 2016-09-07 | 广西电网有限责任公司电力科学研究院 | 一种基于cim模型的变电站运行工况可视化方法 |
CN106971028A (zh) * | 2017-03-10 | 2017-07-21 | 福州众衡时代信息科技有限公司 | 一种将虚拟现实技术用于装配式建筑行业的方法 |
CN107292068A (zh) * | 2017-08-21 | 2017-10-24 | 上海中建东孚投资发展有限公司 | 一种装配式建筑bim模型处理方法及处理系统 |
CN107391862A (zh) * | 2017-07-28 | 2017-11-24 | 中建局集团建设发展有限公司 | 一种装配式混凝土结构三维协同设计方法 |
-
2017
- 2017-12-19 CN CN201711369889.0A patent/CN108416076B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104349141A (zh) * | 2013-08-08 | 2015-02-11 | 霍尼韦尔国际公司 | 使用bim模型可视化事件历史的系统和方法 |
US20160033946A1 (en) * | 2014-07-31 | 2016-02-04 | Honeywell International Inc. | Building management system analysis |
CN104468243A (zh) * | 2014-12-31 | 2015-03-25 | 湖南华宽通科技股份有限公司 | 综合网元管理设备 |
CN105929770A (zh) * | 2016-04-19 | 2016-09-07 | 广西电网有限责任公司电力科学研究院 | 一种基于cim模型的变电站运行工况可视化方法 |
CN106971028A (zh) * | 2017-03-10 | 2017-07-21 | 福州众衡时代信息科技有限公司 | 一种将虚拟现实技术用于装配式建筑行业的方法 |
CN107391862A (zh) * | 2017-07-28 | 2017-11-24 | 中建局集团建设发展有限公司 | 一种装配式混凝土结构三维协同设计方法 |
CN107292068A (zh) * | 2017-08-21 | 2017-10-24 | 上海中建东孚投资发展有限公司 | 一种装配式建筑bim模型处理方法及处理系统 |
Non-Patent Citations (3)
Title |
---|
冯洪飞: ""基于BIM的虚拟施工技术与施工期监测分析在钢结构施工中的应用研究"", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
吴琳,王光炎: "《BIM建模及应用基础》", 28 February 2017 * |
金永超,张宇帆: "《BIM与建模》", 31 May 2016 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110782523A (zh) * | 2019-10-11 | 2020-02-11 | 上海建工五建集团有限公司 | 基于bim的建筑模型检查方法及系统 |
CN111353191A (zh) * | 2020-02-28 | 2020-06-30 | 中国十七冶集团有限公司 | 一种多曲率异形曲面屋盖钢结构施工方法 |
CN112052490A (zh) * | 2020-05-22 | 2020-12-08 | 杭州嗡嗡科技有限公司 | 基于bim的装配式深化设计方法及其设计工具 |
Also Published As
Publication number | Publication date |
---|---|
CN108416076B (zh) | 2020-06-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108319755B (zh) | 一种超高层液压爬模脚手架施工的全过程优化方法 | |
CN111400812B (zh) | 一种基于bim的装配式结构剪力墙加工图设计方法 | |
Kim et al. | Generating construction schedules through automatic data extraction using open BIM (building information modeling) technology | |
CN107341290B (zh) | 基于bim的梁板预制与现浇结构工程量提取系统及方法 | |
KR101607886B1 (ko) | 3차원 모델을 이용한 건축물 배근시공도 자동생성 시스템 | |
CN106934163A (zh) | 基于bim的桥梁三维模型构建方法 | |
Brumana et al. | HBIM challenge among the paradigm of complexity, tools and preservation: the Basilica di Collemaggio 8 years after the earthquake (L'Aquila) | |
CN108550020A (zh) | 基于bim技术的工程造价控制方法 | |
CN107977487A (zh) | 一种基于bim技术的装配式混凝土建筑设计方法 | |
CN108763710A (zh) | 一种基于bim的装配式建筑正向深化设计方法 | |
CN107391862A (zh) | 一种装配式混凝土结构三维协同设计方法 | |
CN104102765A (zh) | 一种基于bim的幕墙参数化设计方法 | |
CN108268715B (zh) | 一种基于bim技术的钢桥面铺装施工仿真模拟方法 | |
CN109684662A (zh) | 一种智能式装配式建筑的构建方法 | |
CN108416076A (zh) | 一种基于bim技术的装配式建筑设计方法 | |
CN111008420A (zh) | 基于bim的钢筋数据生成方法、装置、设备及介质 | |
CN110080114A (zh) | 一种基于bim技术的可视化预制立柱承台施工方法 | |
JP2001357075A (ja) | 二次元cadインターフェースを利用した物量割出しシステムとその方法 | |
CN108268707A (zh) | 一种基于revit的转运站标准模板绘制方法及转运站构建方法 | |
CN107516161A (zh) | 一种基于bim的工程进度管控方法 | |
CN106779476A (zh) | 一种基于bim‑ifc技术的建筑施工进度管理平台及方法 | |
KR101755901B1 (ko) | 건설생산계획 산출을 위한 bim 연동 생산성 시뮬레이션 방법 | |
KR100309582B1 (ko) | 2차원 캐드인터페이스를 이용한 물량산출 시스템과 그 방법 | |
CN113626911A (zh) | 基于第一主应力矢量分布的混凝土3d打印路径优化方法 | |
JP7277876B2 (ja) | 建設物の施工管理装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |