CN105775991A - 大直径管束起吊装配工装及其使用方法 - Google Patents

大直径管束起吊装配工装及其使用方法 Download PDF

Info

Publication number
CN105775991A
CN105775991A CN201610318182.6A CN201610318182A CN105775991A CN 105775991 A CN105775991 A CN 105775991A CN 201610318182 A CN201610318182 A CN 201610318182A CN 105775991 A CN105775991 A CN 105775991A
Authority
CN
China
Prior art keywords
assembly
tube bank
tube bundle
wire rope
steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610318182.6A
Other languages
English (en)
Inventor
周斌
陈宏伟
朱生萍
张涛
姚金杉
张建晓
高亚萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanzhou LS Heavy Equipment Co Ltd
Original Assignee
Lanzhou LS Heavy Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanzhou LS Heavy Equipment Co Ltd filed Critical Lanzhou LS Heavy Equipment Co Ltd
Priority to CN201610318182.6A priority Critical patent/CN105775991A/zh
Publication of CN105775991A publication Critical patent/CN105775991A/zh
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/42Gripping members engaging only the external or internal surfaces of the articles
    • B66C1/422Gripping members engaging only the external or internal surfaces of the articles actuated by lifting force

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Automatic Assembly (AREA)

Abstract

大直径管束起吊装配工装及其使用方法,涉及换热器管束装配领域,克服了现有技术操作不便,吊装风险大的困难。其结构有:管束吊板组件1、固定滑轮组件2、管束受拉组件3;管束吊板组件1是由弧板4和吊耳5组成;所述的固定滑轮组件2固定在基础平台上。使用时:将管束受拉组件3安装在管束前端的中间位置;钢丝绳绕过固定滑轮组件2,其一端穿过管束,与管束受拉组件3相连,钢丝绳另一端与另一台吊车连接;钢丝绳通过固定滑轮组件2,拉动管束水平方向匀速进入壳体。大直径管束在组装吊装进出壳体时,速度均匀可控,操作风险小;通用性强,可适用于各种不同直径的管束组装;大幅提高了管束组装效率,降低了管束组装成本。

Description

大直径管束起吊装配工装及其使用方法
技术领域
本发明装置涉及换热器管束起吊及装配领域。
背景技术
换热器是化工、石油、制药及能源等行业中应用相当广泛的单元设备之一。近年来我国在大型炼油、大型煤化工、大乙烯等项目的建设中投资力度加大,规模也越来越大。和大型化的成套装置相适应,换热器也在向大型化发展,这对换热器的制造和安装提出了更高的要求。大型换热器管束组装中由于设备直径过大、管束质量超重,存在操作困难、危险性较大等问题。目前在组装管束时,通常在换热器壳体内需要安装管束滑道,这势必增加了设备投资成本。组装管束时,依靠人力通过倒链进行牵引,安装难度大、管束牵引速度不均匀容易导致管束变形;安装效率低,不适于大批量生产。
发明内容
我们要解决的问题是:克服现有技术中大直径管束起吊及组装过程中操作不便,吊装风险较大的困难。
本发明提供了大直径管束起吊装配工装,其结构有:管束吊板组件1、固定滑轮组件2、管束受拉组件3;其中所述的管束吊板组件1是由弧板4和弧板两端的两个对称吊耳5组成;所述的固定滑轮组件2是由固定在基础平台上的定滑轮组成;所述的管束受拉组件3是由强度好的钢管组成,可以与管束端平面贴合。
大直径管束起吊装配工装的使用方法是:
①置管束于管束吊板组件1的弧板4上,吊车通过固定在管束吊板组件1上面的对称吊耳5上的钢丝绳把管束吊起到一定高度位置,再平行移动把管束约1/3长度送入壳体内,使管束滑道落实在壳体上;
②固定管束,更换管束吊板组件1的起吊位置,并提前把密封垫片组装到位;
③将管束受拉组件3安装在管束前端的中间位置;钢丝绳绕过固定滑轮组件2,其一端穿过管束,与管束受拉组件3相连,钢丝绳另一端与另一台吊车连接;
④另一台吊车向上匀速拉紧钢丝绳,钢丝绳绕过固定滑轮2拉紧管束受拉组件3;同时垂直方向吊车配合动作,通过管束吊板组件1使管束保持一定高度;管束通过钢丝绳的拉力水平方向匀速进入壳体,进行管束组装。
本发明的有益效果是:大直径管束在组装吊装进出壳体时,速度均匀可控,操作风险小;通用性强,可适用于各种不同直径的管束组装;大幅提高了管束组装效率,降低了管束组装成本;操作简便,安全可靠,降低了对管束组装施工人员的操作水平要求。解决了大型换热器管束吊装及装配过程中的难点。
附图说明
图1大直径管束起吊及装配工装结构及操作示意图,
图中:1管束吊板组件、2固定滑轮组件、3管束受拉组件。
图2管束吊板组件结构示意图,
图中:4弧板,5吊耳。
具体实施方案
如图所示,本发明结构包括管束吊板组件1、固定滑轮组件2、管束受拉组件3;其中所述的管束吊板组件1是由弧板4和弧板两端的两个对称吊耳5组成;所述的固定滑轮组件2是由固定在基础平台上的定滑轮组成;所述的管束受拉组件3是由强度好的钢管组成,可以与管束端平面贴合。
使用方法:
起吊时管束吊板组件1的弧板4垫在管束的下面,管束的重力均匀分布在弧板4上,可对管束起缓冲和保护作用,保证管束起吊平稳,可防止管束变形;
吊车通过固定在管束吊板组件1上面的对称吊耳5上的钢丝绳把管束吊起到一定高度位置,再平行移动把管束约1/3长度送入壳体内,使管束滑道落实在壳体上起到支撑作用;
然后固定管束,更换管束吊板组件1的起吊位置,并提前把密封垫片组装到位;
将管束受拉组件3安装在管束前端的中间位置;钢丝绳绕过固定滑轮组件2,其一端穿过管束,与管束受拉组件3相连,拉力作用在受拉组件3钢管的两端,保证管束受到均匀的水平方向拉力;钢丝绳另一端与另一台吊车连接,钢丝绳通过固定滑轮2把垂直方向的拉力转换成水平方向的拉力;
操作时垂直方向吊车同时配合动作,通过管束吊板组件1使管束保持一定高度;在壳体内的管束利用滑道通过另一台吊车钢丝绳的拉力水平方向匀速进入壳体;进行管束组装。
注意防止钢丝绳与管束直接接触、摩擦、刮伤管束。
本发明保证管束拉入壳体平稳,速度可控。

Claims (2)

1.大直径管束起吊装配工装,其特征是:其结构有管束吊板组件⑴、固定滑轮组件⑵、管束受拉组件⑶;其中所述的管束吊板组件⑴是由弧板⑷和弧板两端的两个对称吊耳⑸组成;所述的固定滑轮组件⑵是由固定在基础平台上的定滑轮组成;所述的管束受拉组件⑶是由强度好的钢管组成,可以与管束端平面贴合。
2.权利要求1所述的大直径管束起吊装配工装的使用方法,其特征是:
①置管束于管束吊板组件⑴的弧板⑷上,吊车通过固定在管束吊板组件⑴上面的对称吊耳⑸上的钢丝绳把管束吊起到一定高度位置,再平行移动把管束约1/3长度送入壳体内,使管束滑道落实在壳体上;
②固定管束,更换管束吊板组件⑴的起吊位置,并提前把密封垫片组装到位;
③将管束受拉组件⑶安装在管束前端的中间位置;钢丝绳绕过固定滑轮组件⑵,其一端穿过管束,与管束受拉组件⑶相连,钢丝绳另一端与另一台吊车连接;
④另一台吊车向上匀速拉紧钢丝绳,钢丝绳绕过固定滑轮组件⑵拉紧管束受拉组件⑶;同时垂直方向吊车配合动作,通过管束吊板组件⑴使管束保持一定高度;管束通过另一台吊车钢丝绳的拉力水平方向匀速进入壳体;进行管束组装。
CN201610318182.6A 2016-05-16 2016-05-16 大直径管束起吊装配工装及其使用方法 Pending CN105775991A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610318182.6A CN105775991A (zh) 2016-05-16 2016-05-16 大直径管束起吊装配工装及其使用方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610318182.6A CN105775991A (zh) 2016-05-16 2016-05-16 大直径管束起吊装配工装及其使用方法

Publications (1)

Publication Number Publication Date
CN105775991A true CN105775991A (zh) 2016-07-20

Family

ID=56379638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610318182.6A Pending CN105775991A (zh) 2016-05-16 2016-05-16 大直径管束起吊装配工装及其使用方法

Country Status (1)

Country Link
CN (1) CN105775991A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106392536A (zh) * 2016-11-02 2017-02-15 上海航天设备制造总厂 一种空间站工作舱大型整体机柜装舱方法
CN109552983A (zh) * 2017-09-25 2019-04-02 中石化重型起重运输工程有限责任公司 立式细长集合管束的吊装装置及方法
CN109648513A (zh) * 2019-01-15 2019-04-19 中盐安徽红四方股份有限公司 卧式u型管换热器管束拆除方法
CN109720989A (zh) * 2019-01-15 2019-05-07 中盐安徽红四方股份有限公司 卧式换热器管束安装方法
CN109911760A (zh) * 2017-12-13 2019-06-21 兰州兰石重型装备股份有限公司 一种大直径换热器密封盘装卸工装及其使用方法
CN109956393A (zh) * 2017-12-22 2019-07-02 兰州兰石重型装备股份有限公司 大直径换热器内套筒装卸工装及其使用方法
CN114273883A (zh) * 2021-12-28 2022-04-05 南京宝色股份公司 大型换热器管束套装装置及方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6053890A (ja) * 1983-09-02 1985-03-27 株式会社東芝 燃料集合体の移送装置
NL1035440C2 (nl) * 2008-05-19 2009-11-30 Peinemann Equipment Bv Inrichting en werkwijze voor het verwijderen van een bundel uit een warmtewisselaar.
CN102384693A (zh) * 2011-10-14 2012-03-21 江苏普格机械有限公司 大型换热器中折流板的安装方法
CN203439898U (zh) * 2013-07-16 2014-02-19 江联重工股份有限公司 大型换热器管束吊装装置
CN203474657U (zh) * 2013-08-29 2014-03-12 上海宝冶建设工业炉工程技术有限公司 套筒石灰窑换热器管束与筒体装配工具
CN203998596U (zh) * 2014-07-29 2014-12-10 中国海洋石油总公司 易于与大直径圆管配合的垂直吊装结构
CN104531931A (zh) * 2015-01-19 2015-04-22 中国十九冶集团有限公司 高炉出铁场下部除尘管道安装方法
CN205603037U (zh) * 2016-05-16 2016-09-28 兰州兰石重型装备股份有限公司 大直径管束起吊装配工装

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6053890A (ja) * 1983-09-02 1985-03-27 株式会社東芝 燃料集合体の移送装置
NL1035440C2 (nl) * 2008-05-19 2009-11-30 Peinemann Equipment Bv Inrichting en werkwijze voor het verwijderen van een bundel uit een warmtewisselaar.
CN102384693A (zh) * 2011-10-14 2012-03-21 江苏普格机械有限公司 大型换热器中折流板的安装方法
CN203439898U (zh) * 2013-07-16 2014-02-19 江联重工股份有限公司 大型换热器管束吊装装置
CN203474657U (zh) * 2013-08-29 2014-03-12 上海宝冶建设工业炉工程技术有限公司 套筒石灰窑换热器管束与筒体装配工具
CN203998596U (zh) * 2014-07-29 2014-12-10 中国海洋石油总公司 易于与大直径圆管配合的垂直吊装结构
CN104531931A (zh) * 2015-01-19 2015-04-22 中国十九冶集团有限公司 高炉出铁场下部除尘管道安装方法
CN205603037U (zh) * 2016-05-16 2016-09-28 兰州兰石重型装备股份有限公司 大直径管束起吊装配工装

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106392536A (zh) * 2016-11-02 2017-02-15 上海航天设备制造总厂 一种空间站工作舱大型整体机柜装舱方法
CN109552983A (zh) * 2017-09-25 2019-04-02 中石化重型起重运输工程有限责任公司 立式细长集合管束的吊装装置及方法
CN109911760A (zh) * 2017-12-13 2019-06-21 兰州兰石重型装备股份有限公司 一种大直径换热器密封盘装卸工装及其使用方法
CN109956393A (zh) * 2017-12-22 2019-07-02 兰州兰石重型装备股份有限公司 大直径换热器内套筒装卸工装及其使用方法
CN109648513A (zh) * 2019-01-15 2019-04-19 中盐安徽红四方股份有限公司 卧式u型管换热器管束拆除方法
CN109720989A (zh) * 2019-01-15 2019-05-07 中盐安徽红四方股份有限公司 卧式换热器管束安装方法
CN114273883A (zh) * 2021-12-28 2022-04-05 南京宝色股份公司 大型换热器管束套装装置及方法

Similar Documents

Publication Publication Date Title
CN105775991A (zh) 大直径管束起吊装配工装及其使用方法
CN201381166Y (zh) 吊点可调式横吊梁
CN201501729U (zh) 设备空中翻转装置
CN202785258U (zh) 大型钢柱空中翻转的吊装装置
CN201850080U (zh) 一种全角吊机
CN205603037U (zh) 大直径管束起吊装配工装
CN212503731U (zh) 一种锅炉安装吊运装置
CN205397854U (zh) 气化炉吊装提升装置
CN202231327U (zh) 电气柜中的重型器件吊装工具
CN202417595U (zh) 传感器升降装置
CN205603125U (zh) 横管冷却器换热管更换的专用吊装装置
CN205527435U (zh) 安装和拆卸起重臂的装置
CN203877726U (zh) 一种多吊点设备翻转与吊装用的吊梁
CN102384693B (zh) 大型换热器中折流板的安装方法
CN205590168U (zh) 一种翻转吊具
CN204609267U (zh) 一种用于储罐内部施工的吊架
CN209507286U (zh) 一种电缆放置支架
CN202657821U (zh) 一种无中分面离心压缩机的叶轮装拆起吊装置
CN202785254U (zh) 一种吊具
CN207209896U (zh) 一种大型可拆卸的下端轴检修平台
CN201980890U (zh) 高空特殊环境下吊装用人字起重桅杆
CN202011709U (zh) 风力发电机组安装工作平台
CN201298682Y (zh) 变电站隔离开关起吊装置
CN205662284U (zh) 双杆变台起重器
CN104495645A (zh) 一种塔机自安装和自拆卸平衡重的结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160720

WD01 Invention patent application deemed withdrawn after publication