CN105736040A - Method for pumping and exhausting gas of coal beds in front of parallel adit and main cave by means of parallel adit drilling construction - Google Patents

Method for pumping and exhausting gas of coal beds in front of parallel adit and main cave by means of parallel adit drilling construction Download PDF

Info

Publication number
CN105736040A
CN105736040A CN201610073190.9A CN201610073190A CN105736040A CN 105736040 A CN105736040 A CN 105736040A CN 201610073190 A CN201610073190 A CN 201610073190A CN 105736040 A CN105736040 A CN 105736040A
Authority
CN
China
Prior art keywords
adit
parallel
construction
flat
coal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610073190.9A
Other languages
Chinese (zh)
Inventor
翟富强
杨琨
张忠爱
刘伟帮
张志和
王广科
孙世龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Yichu Co Ltd
Original Assignee
China Railway Tunnel Group Yichu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Yichu Co Ltd filed Critical China Railway Tunnel Group Yichu Co Ltd
Priority to CN201610073190.9A priority Critical patent/CN105736040A/en
Publication of CN105736040A publication Critical patent/CN105736040A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose

Abstract

The invention discloses a method for pumping and exhausting gas of coal beds in front of a parallel adit and a main cave by means of parallel adit drilling construction. The method comprises the steps that (1) construction of the parallel adit is conducted before construction of the main cave till an outburst elimination position in front of a coal measure stratum is reached; (2) a working chamber is formed in the side, close to the main cave, of the interior of the parallel adit; (3) punching is conducted in the parallel adit area of a parallel adit face and then pumping and exhausting are conducted in the parallel adit area of the parallel adit face, so that outburst elimination is completed; (4) pumping and exhausting holes in the main cave area are punched with the working chamber as the starting point during pumping and exhausting of the parallel adit; (5) after outburst elimination of the parallel adit succeeds, construction of the pumping and exhausting holes in the main cave area is completed and pumping and exhausting are conducted, checking of the outburst elimination effect of the parallel adit area and coal uncovering construction are conducted, tunneling of the parallel adit is recovered, and pumping and exhausting of the working chamber continue to be conducted; and (6) pumping and exhausting do not need to be conducted any more when the main cave continues to be excavated to the outburst elimination position of the main cave area, checking and coal uncovering construction are conducted directly, and tunneling of the main cave is recovered. By pumping and exhausting the gas of the coal beds within the ranges of the parallel adit and the main cave in advance by means of the parallel adit, the construction period is greatly shortened.

Description

Flat construction drill pump drainage of leading is utilized to put down and lead and the method for each coal-bed gas in Zheng Dong front
Technical field
The invention belongs to tunnel boring technical field of construction, be specifically related to a kind of utilize flat combined layout construction drill pump drainage of leading to put down and lead and the method for each coal-bed gas in Zheng Dong front.
Background technology
At present, coal measure strata construction in tunnel is generally adopted, at face, this front of tunnel heading region is carried out the mode of gas extinction construction, and the face that namely positive hole peace is led needs to take a whole set of extinction measure respectively.Lead that to only have about 22 meters of rock pillars between positive hole alternate as it is shown in figure 1, flat, less than the outer minimum span of control sum of 14m of both excavation contour lines.Putting down and lead advanced just wide open digging, positive hole peace is led and is carried out pump drainage hole drilling operation and gas exhaust respectively, and the duration is very long, and efficiency of construction is low.
Summary of the invention
It is contemplated that utilize the flat feature leading advanced positive hole construction, using whole Tunnel Passing coal measure strata section as an overall region, in flat leading, carry out extinction measure, to save the duration, improve efficiency of construction.
For this, the technical solution adopted in the present invention is: a kind of utilize flat construction drill pump drainage of leading to put down and lead and the method for each coal-bed gas in Zheng Dong front, comprises the following steps:
(1) construct in flat positive hole in advance of leading, and puts down and leads the extinction position constructed to coal measure strata front, positive hole normal construction;
(2) work chamber is set in the flat side leading interior close positive hole;
(3) carry out putting down the first punching leading in region, rear pump drainage at flat face of leading, to complete extinction;
(4) utilize the flat time leading pump drainage, with the chamber that works for starting point, carry out the drilling operation in pump drainage hole, Zheng Dong region;
(5) flat lead extinction success and the construction of pump drainage hole, Zheng Dong region is complete and after starting pump drainage, carry out flat leading region extinction validity check, exposed coal construction, and recover the flat driving led;Meanwhile, the pump drainage of work chamber is proceeded;
(6) positive hole is continued when propelling is excavated to extinction position, Zheng Dong region without carrying out pump drainage, is made directly checking, exposed coal construction, and recovers the driving in positive hole.
It is preferably, described flat leads, the extinction position in positive hole is positioned at, 20~50 meters of coal measure strata front.
Beneficial effects of the present invention: utilize and flat lead advanced pump drainage and put down the coal-bed gas led with within the scope of positive hole, it is directly entered exposed coal construction according to checking situation when positive hole is advanced into coal measure strata front, without carrying out pump drainage, can effectively solve the gas extinction of big region to process, substantially reduce the construction period, and economy is high, it is adaptable to highway, railway large-bore gas tunnel gas exhaust control construction.
Accompanying drawing explanation
Fig. 1 be traditional utilize flat lead, schematic diagram is arranged in the boring of the independent drawing-off gas in positive hole.
Fig. 2 is the Construction Arrangement schematic diagram of the present invention.
Detailed description of the invention
By the examples below and in conjunction with accompanying drawing, the invention will be further described:
Utilize flat construction drill pump drainage of leading to put down and lead and the method for each coal-bed gas in Zheng Dong front as in figure 2 it is shown, a kind of, comprise the following steps:
(1) flat lead must positive hole construction in advance, flat lead can positive about about 500 meters of hole in advance, flat lead the extinction position constructed to coal measure strata front, positive hole normal construction;
(2) according to coal measure strata feature, flat lead the interior side near positive hole arrange work chamber, the particular location of work chamber and size bore according to executing it needs to be determined that;
(3) flat lead face carry out flat lead in region first punching, rear pump drainage, to complete gas extinction, flat lead interior exhaust pipe and stretch in coal measure strata, the approximate divergent shape distribution of exhaust pipe;
(4) utilizing the flat time leading pump drainage, with the chamber that works for starting point, carry out the drilling operation in pump drainage hole, Zheng Dong region, the extinction for positive hole is ready;
(5) flat lead extinction success and the construction of pump drainage hole, Zheng Dong region is complete and after starting pump drainage, carry out flat leading region extinction validity check, exposed coal construction, and recover the flat driving led;Meanwhile, proceeding the pump drainage of work chamber, its objective is to be the extinction of positive hole in advance, the exhaust pipe of work chamber stretches in coal measure strata, approximate divergent shape distribution;
(6) positive hole is continued when propelling is excavated to extinction position, Zheng Dong region without carrying out pump drainage, is made directly checking, exposed coal construction, and recovers the driving in positive hole.
Utilize flat advanced feature of leading, increase work chamber, concentrate carry out flat leading, Zheng Dong region gas exhaust drilling construction, reduce quantities, reduction of erection time.
Generally, flat lead, the extinction position in positive hole is positioned at, 20~50 meters of coal measure strata front.

Claims (2)

1. one kind utilizes flat construction drill pump drainage of leading to put down and lead and the method for each coal-bed gas in Zheng Dong front, it is characterised in that comprise the following steps:
(1) construct in flat positive hole in advance of leading, and puts down and leads the extinction position constructed to coal measure strata front, positive hole normal construction;
(2) work chamber is set in the flat side leading interior close positive hole;
(3) carry out putting down the first punching leading in region, rear pump drainage at flat face of leading, to complete extinction;
(4) utilize the flat time leading pump drainage, with the chamber that works for starting point, carry out the drilling operation in pump drainage hole, Zheng Dong region;
(5) flat lead extinction success and the construction of pump drainage hole, Zheng Dong region is complete and after starting pump drainage, carry out flat leading region extinction validity check, exposed coal construction, and recover the flat driving led;Meanwhile, the pump drainage of work chamber is proceeded;
(6) positive hole is continued when propelling is excavated to extinction position, Zheng Dong region without carrying out pump drainage, is made directly checking, exposed coal construction, and recovers the driving in positive hole.
2. the flat construction drill pump drainage of leading that utilizes described in claim 1 is put down and is led and the method for each coal-bed gas in Zheng Dong front, it is characterised in that: described flat lead, the extinction position in positive hole is positioned at, 20~50 meters of coal measure strata front.
CN201610073190.9A 2016-02-02 2016-02-02 Method for pumping and exhausting gas of coal beds in front of parallel adit and main cave by means of parallel adit drilling construction Pending CN105736040A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610073190.9A CN105736040A (en) 2016-02-02 2016-02-02 Method for pumping and exhausting gas of coal beds in front of parallel adit and main cave by means of parallel adit drilling construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610073190.9A CN105736040A (en) 2016-02-02 2016-02-02 Method for pumping and exhausting gas of coal beds in front of parallel adit and main cave by means of parallel adit drilling construction

Publications (1)

Publication Number Publication Date
CN105736040A true CN105736040A (en) 2016-07-06

Family

ID=56244766

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610073190.9A Pending CN105736040A (en) 2016-02-02 2016-02-02 Method for pumping and exhausting gas of coal beds in front of parallel adit and main cave by means of parallel adit drilling construction

Country Status (1)

Country Link
CN (1) CN105736040A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091111A (en) * 2017-04-18 2017-08-25 中交路桥华南工程有限公司 The gas preprocess method in tunnel
CN107489443A (en) * 2017-08-22 2017-12-19 西南交通大学 Toxic and harmful gas constructing tunnel hydrogen sulfide mash gas harnessing method
CN110067591A (en) * 2018-01-24 2019-07-30 中铁二院工程集团有限责任公司 Tunnel and flat lead pass through coal seam construction gas drainage method
CN111396118A (en) * 2020-03-19 2020-07-10 贵州盘江精煤股份有限公司 Coal seam group rapid rock cross-cut coal uncovering outburst eliminating method
CN112196610A (en) * 2020-09-23 2021-01-08 贵州大学 Water drilling mining structure for eliminating gas outburst of inclined coal seam and mining method thereof
CN112324489A (en) * 2020-12-08 2021-02-05 湖南科技大学 Gas drainage drill hole arrangement method for large-section tunnel penetrating through coal seam with small included angle

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101514637A (en) * 2009-04-02 2009-08-26 中铁二局股份有限公司 Execution system of gas tunnel outburst prevention comprehensive measures
CN102116171A (en) * 2011-04-09 2011-07-06 中铁十七局集团第五工程有限公司 Method for rapid discharge of gas in tunnel
CN202520369U (en) * 2012-03-06 2012-11-07 中铁二十二局集团第五工程有限公司 Gas outburst tunnel crosscut coal uncovering construction system
KR101508661B1 (en) * 2014-09-26 2015-04-08 주식회사 리트코 Tunnel air purification system mounted at the exit of the tunnel
CN204299612U (en) * 2014-12-11 2015-04-29 中铁二十局集团第六工程有限公司 Flat the leading in a kind of tunnel passes through coal seam construction drawing-off gas structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101514637A (en) * 2009-04-02 2009-08-26 中铁二局股份有限公司 Execution system of gas tunnel outburst prevention comprehensive measures
CN102116171A (en) * 2011-04-09 2011-07-06 中铁十七局集团第五工程有限公司 Method for rapid discharge of gas in tunnel
CN202520369U (en) * 2012-03-06 2012-11-07 中铁二十二局集团第五工程有限公司 Gas outburst tunnel crosscut coal uncovering construction system
KR101508661B1 (en) * 2014-09-26 2015-04-08 주식회사 리트코 Tunnel air purification system mounted at the exit of the tunnel
CN204299612U (en) * 2014-12-11 2015-04-29 中铁二十局集团第六工程有限公司 Flat the leading in a kind of tunnel passes through coal seam construction drawing-off gas structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭晨 等: "天坪隧道横洞工区揭煤防突技术", 《价值工程》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091111A (en) * 2017-04-18 2017-08-25 中交路桥华南工程有限公司 The gas preprocess method in tunnel
CN107489443A (en) * 2017-08-22 2017-12-19 西南交通大学 Toxic and harmful gas constructing tunnel hydrogen sulfide mash gas harnessing method
CN110067591A (en) * 2018-01-24 2019-07-30 中铁二院工程集团有限责任公司 Tunnel and flat lead pass through coal seam construction gas drainage method
CN111396118A (en) * 2020-03-19 2020-07-10 贵州盘江精煤股份有限公司 Coal seam group rapid rock cross-cut coal uncovering outburst eliminating method
CN112196610A (en) * 2020-09-23 2021-01-08 贵州大学 Water drilling mining structure for eliminating gas outburst of inclined coal seam and mining method thereof
CN112324489A (en) * 2020-12-08 2021-02-05 湖南科技大学 Gas drainage drill hole arrangement method for large-section tunnel penetrating through coal seam with small included angle

Similar Documents

Publication Publication Date Title
CN105736040A (en) Method for pumping and exhausting gas of coal beds in front of parallel adit and main cave by means of parallel adit drilling construction
CN105240013B (en) Broadwall N00 engineering methods
CN101915083B (en) Method for extracting coalbed gases from coal mines by upper and lower combination
CN101614135B (en) Drilling-explosion-pumping triadic gas extraction method
CN103306714B (en) Coal seam group with near interval Di Chou holes in lane the mash gas harnessing method in a hole three
CN107882565B (en) A kind of adopt without driving without coal column stays integrated production practice
CN103670496A (en) Gob-side entry retaining and sectional coal seam gas pre-extracting method for single low-permeability outburst coal seam
CN103670433B (en) Short distance coincidence section boring machine
CN102587960A (en) Arrangement method of high gas coal seam extraction working face roadway
CN101915086B (en) Coal mine underground gas borehole fracturing method
CN108397227A (en) A kind of progressive extinction roadway layout method of tendency
CN102678166B (en) Method for increasing gas extraction rate by permeability increasing of single thick coal seam
CN208619156U (en) Mine gas drilling is grouped extraction pipe-line system
CN106468177A (en) A kind of coal and gas harmonic extraction method
CN105401973A (en) Method for performing extraction treatment on corner gas on work faces of adjacent roadways
CN105275487A (en) Long-arm mining N00 construction method ventilation system
CN204327107U (en) The TBM of a kind of fragmented rock body hole section tunnels structure
CN104594943A (en) Ground composite L-shaped drilling well for gas control and gas control method
CN103362508B (en) Mine development method
CN107178388A (en) Pressure coal gas device is taken out in heading pulse
CN103362514B (en) Speedy tunneling method for gas drainage roadway
CN103216258B (en) Km rig concentrates strip-type to draw out methane method
CN207111096U (en) TBM construction tunnel fault belts hole section processing structure
CN102787845B (en) Segmented construction method of extra-long tunnels by adopting development machines to construct inclined shafts and headings first
CN105257333A (en) Kilometer rig concentrated stripe type drainage method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160706