CN105735129A - Full-welding truss section modularized splicing method - Google Patents

Full-welding truss section modularized splicing method Download PDF

Info

Publication number
CN105735129A
CN105735129A CN201610106419.4A CN201610106419A CN105735129A CN 105735129 A CN105735129 A CN 105735129A CN 201610106419 A CN201610106419 A CN 201610106419A CN 105735129 A CN105735129 A CN 105735129A
Authority
CN
China
Prior art keywords
module
assembled
unit
purlin
sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610106419.4A
Other languages
Chinese (zh)
Other versions
CN105735129B (en
Inventor
宋红飞
冯志敏
曹东威
王建国
刘洋
岳长勇
郑毅
许超众
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Shanqiao Nantong Co ltd
Original Assignee
Jiangsu Zhongtie Shanqiao Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Zhongtie Shanqiao Heavy Industry Co Ltd filed Critical Jiangsu Zhongtie Shanqiao Heavy Industry Co Ltd
Priority to CN201610106419.4A priority Critical patent/CN105735129B/en
Publication of CN105735129A publication Critical patent/CN105735129A/en
Application granted granted Critical
Publication of CN105735129B publication Critical patent/CN105735129B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D6/00Truss-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The invention relates to a full-welding truss section modularized splicing method. According to the method, each assembly of each truss section is divided into multiple modules, and each module is independently spliced. The method includes firstly, a truss sheet module splicing method, secondly, a transverse connecting sheet module splicing method, thirdly, an upper-layer road bridge face module splicing method, fourthly, a lower-layer railway bridge face module splicing method, fifthly, a road combination section longitudinal and transverse beam splicing method and sixthly, a truss whole section module splicing method. A bridge is spliced in a modularized manner, part of the modules of the bridge can be spliced on a bridge production site, the difficulty of constructing the bridge on the site is lowered, the labor amount for manufacturing the bridge is reduced, the manufacturing time of the bridge is shortened, and the working efficiency is improved.

Description

A kind of full weldering truss sections modularization assemble method
Technical field
The present invention relates to a kind of full weldering truss sections modularization assemble method, belong to bridge technical field.
Background technology
Develop rapidly along with socioeconomic, the pressure of land transportation increasingly highlights, in order to solve this pressure, building of the projects such as substantial amounts of railway, highway is imperative, in order to cross over the great rivers that road passes through, the use of the bridge of large span tends to certainty, and people are also designed in the structure of the bridge to different distance.
nullIn the bridge of present invention research,The logical bridge in Shanghai includes main channel bridge、Special purpose channel bridge、Freely-supported steel truss girder bridge and land route, two sides access bridge,Total length 11.072km,Bridge is divided into upper and lower two-layer by function,Respectively upper strata highway layer,Lower floor's railway layer,If adopting traditional assembling process loaded down with trivial details,And time assembled at the scene setting accuracy it is difficult to ensure that,If so assembling process traditionally can not meet far away the requirement of construction period,And need workpiece Left on/Left off in operation,Add so again security risk,Traditional bridge manufacture method is suitable for manufacturing the bridge that span is little,The bridge of total length 11.072km is used conventional methods manufacture comparatively laborious,Inconvenient operation,And bridging cost is high,Therefore it is badly in need of developing a kind of manufacture method simple、The truss section assembling technique that easy to operate and precision is high,The logical bridge in this Shanghai adopts 95 modules assembled,Gross weight 127927.976t.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of full weldering truss sections modularization assemble method, it is possible to reduces the difficulty that bridge manufactures on river surface, promotes bridging efficiency.
For solving above-mentioned technical problem, the technical scheme is that
A kind of full weldering truss sections modularization assemble method, its innovative point is in that: the method is divided into several modules each assembly of truss sections, and each module is independent assembled;Including: the assembling method of S1. purlin sheet module;S2. the assembling method of horizontal-associate sheet module;S3. the assembling method of upper strata highway bridge module;S4. the assembling method of lower floor's railway deck module;S5. highway adapter section beam assembling method in length and breadth;S6. the assembling method of the whole sections module of truss;Specifically include following steps:
S1. the assembling method of purlin sheet module: purlin sheet module includes top boom, lower boom and diagonal web member, purlin sheet module be assembled on moulding bed A to complete;First by top boom and lower boom positioned parallel on moulding bed A, it is linear that top boom and lower boom are adjusted complying with camber, after adjusting the dimensional requirement in each orientation, adopts interim location measure top boom and lower boom to be fixed on the positioning;Diagonal web member is pushed up pick cooperation and is arranged between top boom and lower boom, again diagonal web member is welded with top-bottom chord node, first burn-on the weld seam between chord member and diagonal web member, the centrage coupling deviation welding the weld seam between lower boom and diagonal web member, top-bottom chord and diagonal web member again controls at≤± 0.5mm;The overall purlin sheet welded is disintegrated so that it is become single purlin sheet module, stay the module of one section of single purlin sheet as parent segment, participate in the splicing of next round;
S2. the assembling method of horizontal-associate sheet module: horizontal-associate sheet module includes node, web member and horizontal-associate sheet lower boom, and horizontal-associate sheet module completes on moulding bed B;First positioning horizontal-associate sheet lower boom on moulding bed B, horizontal-associate sheet lower boom, according to single making, becomes work shape chord member and two ends node reserves two amount of cutting with assembly welding after cover plate splicing;Assembled welding web member and node on moulding bed B successively, node is reserved two amounts of cutting in horizontal-associate sheet short transverse;After welding and having repaired horizontal-associate sheet, according to the length of horizontal-associate lamellar body and cutting node of highly ruling;Transport and hoisting process adopt temporary connection reinforce, to avoid deformation;
S3. the assembling method of upper strata highway bridge module: upper strata highway bridge module includes highway bridge Slab element and T-shaped crossbeam unit, upper strata highway bridge module be assembled on moulding bed C to complete;Road spelling adopts continuously coupling assembly welding and the assembled parallel process program of examination, often wheel four whole sections of spelling, stays one section of parent segment as next round to participate in assembly after last round of assembly completes;First highway bridge panel is carried out two-in-one assembled formation highway single-unit floorings, and then T-shaped crossbeam is positioned on the moulding bed C of simulation chord member, then highway single-unit floorings carry out assembly according to by middle part to the order of both sides on T-shaped crossbeam, longitudinal seam welding between assembled Hou Xianjiang highway single-unit floorings is got up, again transverse joint is welded, finally weld other weld seam, highway single-unit floorings after welding are drawn two and cuts non-referenced end line, cut non-referenced end line according to drawn two and carry out adjacent middle part highway single-unit floorings assembly, then the highway single-unit floorings of assembled adjacent highway single-unit floorings both sides, middle part again, repeat upper strata highroad module is installed according to above order;For ensureing the Interface Matching precision of highway bridge panel and main truss chord member horizontal plate, after highway bridge panel welding completes, line cutting both sides, control bridge deck width;
S4. the assembling method of lower floor's railway deck module: lower floor's railway deck module includes top plate unit, bottom board unit, longeron unit and board-like crossbeam unit, lower floor's railway deck module be assembled on moulding bed D to complete;Top plate unit and bottom board unit are carried out respectively two-in-one assembled formation railway single-unit bridge floor top board and railway single-unit bridge floor base plate, railway single-unit bridge floor base plate is laid to both sides by centre, railway single-unit bridge floor base plate is welded, first weld longitudinal joint, weld transverse joint again, last welded plate type crossbeam unit and top plate unit, the weld seam of bottom board unit, moulding bed D is placed on individual railroad bridge floor base plate, board-like crossbeam unit is positioned on the moulding bed D of simulation chord member, longeron unit is vertically embedded into board-like crossbeam unit carry out assembly and wouldn't weld, top plate unit assembly is laid on the upper end of longeron unit and board-like crossbeam, according to the top plate unit first laying middle part, the order of the top plate unit re-laying both sides carries out;Top plate unit and bottom board unit connect with the upper lower horizontal board penetration weld of the lower boom of purlin sheet module respectively, and board-like crossbeam unit is welded with the lower boom of purlin sheet module;
S5. highway adapter section beam assembling method in length and breadth: highway adapter section includes crossbeam, longeron and connection beam;Highway adapter section beam in length and breadth is assembled on moulding bed E and completes, and moulding bed E is provided with longeron, crossbeam positioner and portraitlandscape baseline;First the height that under being relied on moulding bed E by crossbeam according to the horizontal baseline on moulding bed, buttress sets positions, crossbeam is cut cut-to-measure by reserved for crossbeam two ends two after having positioned and is cut, then moulding bed E end gauge and Longitudinal Base location is relied on to assemble longeron, the twice connection beam being perpendicular to longeron it is equipped with again between two crossbeams, finally carry out weld seam, welding adopts first weldering crossbeam and longeron weld seam, and the rear order welding connection beam weld seam carries out;
S6. the assembling method of truss whole sections module: the whole sections of truss includes purlin sheet module, horizontal-associate sheet module, upper strata highway bridge module and lower floor's railway deck module;The whole sections module spliced of truss is contained on moulding bed F and completes, and moulding bed F to arrange temporary support and fixing device, it is ensured that assembled stable safety and splicing accuracy;First on moulding bed F, position lower floor's railway deck module of side, secondly adopt interim location measure that middle purlin sheet module is installed at the side of the railway deck module of lower floor, then adopt interim location measure that lower floor's railway deck module of opposite side is carried out assembly at the opposite side of middle purlin sheet module, by Liang Kuai lower floor railway deck module after the location assembly of middle sheet module both sides, purlin completes, it is respectively mounted side purlin sheet module again in the both sides of Liang Kuai lower floor railway deck module, then adopt interim location measure auxiliary that horizontal-associate sheet module is installed between middle purlin sheet module and dual-side purlin sheet module, last again in horizontal-associate sheet upper strata installed above highway bridge module;Assembly carries out quality halt detection after completing, lower tire transhipment of disintegrating after qualified, stays parent segment to participate in the lower whole section assembling of round;The whole sections of truss is installed first section and is carried out assembly in the following order: (1) side lower floor railway deck module location;(2) in the middle of, purlin sheet module is assembled;(3) opposite side lower floor railway deck module is assembled;(4) sheet module in purlin, both sides is assembled;(5) horizontal-associate sheet module is assembled;(6) highway bridge module in upper strata is assembled;The whole sections of follow-up truss is assembled in the following order to be advanced: in the middle of (1), purlin sheet module is assembled;(2) both sides lower floor railway deck module is assembled;(3) sheet module in purlin, both sides is assembled;(4) horizontal-associate sheet module is assembled;(5) highway bridge module in upper strata is assembled;The highway bridge panel of upper strata highway bridge module and crossbeam all adopt penetration to weld when welding with the top boom of purlin sheet module, when lower floor's railway deck module connects between whole sections, its roof and floor unit is connected as the docking of penetration building site, and except being welded to connect except the employing of levels floorings between whole sections, all the other all adopt high strength exploitation.
Described purlin sheet module is in the whole sections module assembly of truss, and the chord member between two purlin sheets adopts high strength exploitation, is also adopted by high strength exploitation between the brace of purlin sheet module.
In described purlin sheet environment in the open, location assembles and measures needs before sunrise, avoiding solar radiation, to consider fetalism and the impact of purlin sheet linear expansion coefficient under sunshine during welding, in case fetalism deformation effect dimensional accuracy.
Web member and the top boom spacing not spot welding in spacing shelves angle when described purlin sheet assembles, relocate after web member completes with lower boom weld seam and weld, so as to web member has the space freely stretched in the longitudinal direction when lower-chord panel point welds, reduce welding and shrink the impact that purlin is high.
When being assembled in assembled purlin sheet module of the whole sections module of described truss, sheet purlin, the three overall purlins high bias direction of same whole sections is consistent, and within the scope of tolerance.
The position of described welding needs to utilize the position that ultrasonic listening instrument butt welding connects to carry out carrying out flaw detection after having welded.
The positioner of the upper setting of described moulding bed E arranges keyhole and utilizes punch to position with end longeron keyhole in its end.
It is an advantage of the current invention that: this entirely welds truss sections modularization assemble method and achieves the modularization assemble of bridge, it is that some little modules carry out independent assembly truss sections Module Division, the coupling between relevant little module can be realized assembled, assembled operation is reasonable and assembled simple to operate, just the part of module assembly of bridge can be got up in the place produced, reduce the difficulty of on-the-spot bridging, decrease the amount of labour that bridge manufactures, shorten the time that bridge manufactures, improve the efficiency of work;The steel structure material of bridge adopts the 6th generation high strength steel of Q500qE, adds the intensity of Parameters of Bridge Steel Under;In the full process welding truss section assembling, the assembly of each module adopts special moulding bed, it is ensured that the precision that each sections module is assembled;All adopt ultrasonic listening instrument butt welding to connect position after each welding position has welded to detect a flaw, it is ensured that the effect of welding.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the present invention is further detailed explanation.
Fig. 1 is the axonometric chart of truss sections modularization assemble.
Fig. 2 is the splicing structure figure of purlin sheet module.
Fig. 3 is the assembled flow chart of purlin sheet module.
Fig. 4 is the splicing structure figure of horizontal-associate sheet module.
Fig. 5 is the assembled flow chart of horizontal-associate sheet module.
Fig. 6 is upper strata highway bridge module process flow chart.
Fig. 7 is the splicing structure figure of lower floor's railway deck module.
Fig. 8 is lower floor's railway deck module assembly flow chart.
Fig. 9 is the assembled flow chart of truss whole sections module.
As shown in Figures 1 to 9: 1, purlin sheet module;11, top boom;12, lower boom;13, diagonal web member;2, horizontal-associate sheet module;21, node;22, web member;23, horizontal-associate sheet lower boom;3, upper strata highway bridge module;31, floorings unit;32, T-shaped crossbeam unit;4, lower floor's railway deck module;41, top plate unit;42, bottom board unit;43, longeron unit;44, board-like crossbeam unit;5, highway adapter section;51, crossbeam;52, longeron;53, connection beam;
6, the whole sections module of truss.
Detailed description of the invention
The following examples can make professional and technical personnel more fully understand the present invention, but does not therefore limit the present invention among described scope of embodiments.
A kind of full weldering truss sections modularization assemble method as shown in Figures 1 to 9: the method is divided into several modules each assembly of truss sections, and each module is independent assembled;Including: the assembling method of S1. purlin sheet module 1;S2. the assembling method of horizontal-associate sheet module 2;S3. the assembling method of upper strata highway bridge module 3;S4. the assembling method of lower floor's railway deck module 4;S5. highway adapter section 5 beam assembling method in length and breadth;S6. the assembling method of the whole sections module 6 of truss;Specifically include following steps:
S1. the assembling method of purlin sheet module 1: purlin sheet module includes top boom 11, lower boom 12 and diagonal web member 13, purlin sheet module 1 be assembled on moulding bed A to complete;First by top boom 11 and lower boom 12 positioned parallel on moulding bed A, it is linear that top boom 11 and lower boom 12 are adjusted complying with camber, after adjusting the dimensional requirement in each orientation, adopts interim location measure top boom 11 and lower boom 12 to be fixed on the positioning;Being coordinated with top pick by diagonal web member 13 is arranged between top boom 11 and lower boom 12, again diagonal web member 13 is welded with top-bottom chord node, first burn-on the weld seam between chord member 11 and diagonal web member 13, welding the weld seam between lower boom 12 and diagonal web member 13 again, the centrage coupling deviation of top-bottom chord and diagonal web member 13 controls at≤± 0.5mm;The overall purlin sheet welded is disintegrated so that it is become single purlin sheet module, stay the module of one section of single purlin sheet as parent segment, participate in the splicing of next round.
S2. the assembling method of horizontal-associate sheet module 2: horizontal-associate sheet module 2 includes node 21, web member 22 and horizontal-associate sheet lower boom 23, and horizontal-associate sheet module 2 completes on moulding bed B;First positioning horizontal-associate sheet lower boom 23 on moulding bed B, horizontal-associate sheet lower boom 23, according to single making, becomes work shape chord member and two ends node reserves two amount of cutting with assembly welding after cover plate splicing;Assembled welding web member 22 and node 21 on moulding bed B successively, node is reserved two amounts of cutting in horizontal-associate sheet module 2 short transverse;After welding and having repaired horizontal-associate sheet module 2, according to the length of horizontal-associate sheet module 2 and cutting node of highly ruling;Transport and hoisting process adopt temporary connection reinforce, to avoid deformation.
S3. the assembling method of upper strata highway bridge module 3: upper strata highway bridge module 3 includes highway bridge Slab element 31 and T-shaped crossbeam unit 32, upper strata highway bridge module 3 be assembled on moulding bed C to complete;Road spelling adopts continuously coupling assembly welding and the assembled parallel process program of examination, often wheel four whole sections of spelling, stays one section of parent segment as next round to participate in assembly after last round of assembly completes;First highway bridge panel is carried out two-in-one assembled formation highway single-unit floorings, and then T-shaped crossbeam unit 32 is positioned on the moulding bed C of simulation chord member, then highway single-unit floorings carry out assembly according to by middle part to the order of both sides unit 32 on T-shaped crossbeam, longitudinal seam welding between assembled Hou Xianjiang highway single-unit floorings is got up, again transverse joint is welded, finally weld other weld seam, highway single-unit floorings after welding are drawn two and cuts non-referenced end line, cut non-referenced end line according to drawn two and carry out adjacent middle part highway single-unit floorings assembly, then the highway single-unit floorings of assembled adjacent highway single-unit floorings both sides, middle part again, repeat upper strata highway bridge module 3 is installed according to above order;For ensureing the Interface Matching precision of highway bridge panel 31 and main truss chord member horizontal plate, after highway bridge panel welding completes, line cutting both sides, control bridge deck width.
S4. the assembling method of lower floor's railway deck module 4: lower floor's railway deck module 4 includes top plate unit 41, bottom board unit 42, longeron unit 43 and board-like crossbeam unit 44, lower floor's railway deck module 4 be assembled on moulding bed D to complete;Top plate unit 41 and bottom board unit 42 are carried out respectively two-in-one assembled formation railway single-unit bridge floor top board and railway single-unit bridge floor base plate, railway single-unit bridge floor base plate is laid to both sides by centre, railway single-unit bridge floor base plate is welded, first weld longitudinal joint, weld transverse joint again, last welded plate type crossbeam unit 44 and top plate unit 41, the weld seam of bottom board unit 42, moulding bed D is placed on individual railroad bridge floor base plate, board-like crossbeam unit 44 is positioned on the moulding bed D of simulation chord member, longeron unit 43 is vertically embedded into board-like crossbeam unit 44 carry out assembly and wouldn't weld, top plate unit 41 assembly is laid on the upper end of longeron unit 43 and board-like crossbeam 44, according to the top plate unit 41 first laying middle part, the order of the top plate unit 41 re-laying both sides carries out;Top plate unit 41 and bottom board unit 42 connect with the upper lower horizontal board penetration weld of the lower boom 12 of purlin sheet module 1 respectively, and board-like crossbeam unit 44 is welded with the lower boom 12 of purlin sheet module 1.
S5. highway adapter section 5 beam assembling method in length and breadth: highway adapter section includes crossbeam 51, longeron 52 and connection beam 53;Highway adapter section 5 beam in length and breadth is assembled on moulding bed E and completes, and moulding bed E is provided with longeron 52, crossbeam 51 positioner and portraitlandscape baseline;First the height that under being relied on moulding bed E by crossbeam 51 according to the horizontal baseline on moulding bed, buttress sets positions, crossbeam 51 is cut cut-to-measure by reserved for crossbeam 51 two ends two after having positioned and is cut, then moulding bed E end gauge and Longitudinal Base location is relied on to assemble longeron 52, the twice connection beam 53 being perpendicular to longeron 52 it is equipped with again between two crossbeams 51, finally carry out weld seam, welding adopts first weldering crossbeam 51 and longeron 52 weld seam, and the rear order welding connection beam 53 weld seam carries out.
S6. the assembling method of truss whole sections module 6: the whole sections of truss includes purlin sheet module 1, horizontal-associate sheet module 2, upper strata highway bridge module 3 and lower floor's railway deck module 4;The whole sections module 6 of truss is assembled on moulding bed F and completes, and moulding bed F to arrange temporary support and fixing device, it is ensured that assembled stable safety and splicing accuracy;First on moulding bed F, position the lower floor railway deck module 4a of side, secondly adopt interim location measure that middle purlin sheet module 1 is installed at the side of the railway deck module 4 of lower floor, then adopt interim location measure that the lower floor railway deck module 4b of opposite side is carried out assembly at the opposite side of middle purlin sheet module 1a, by Liang Kuai lower floor railway deck module 4 after the location assembly of middle sheet module 1a both sides, purlin completes, it is respectively mounted side purlin sheet module 1b again in the both sides of Liang Kuai lower floor railway deck module 4, then adopt interim location measure auxiliary that horizontal-associate sheet module 2 is installed between middle purlin sheet module 1a and dual-side purlin sheet module 1b, last again in horizontal-associate sheet upper strata installed above highway bridge module 3;Assembly carries out quality halt detection after completing, lower tire transhipment of disintegrating after qualified, stays parent segment to participate in the lower whole section assembling of round;The whole sections of truss is installed first section and is carried out assembly in the following order: (1) side lower floor railway deck module 4a positions;(2) in the middle of, purlin sheet module 1a is assembled;(3) opposite side lower floor railway deck module 4b is assembled;(4) sheet module 1b in purlin, both sides is assembled;(5) horizontal-associate sheet module 2 is assembled;(6) upper strata highway bridge module 3 is assembled;The whole sections of follow-up truss is assembled in the following order to be advanced: in the middle of (1), purlin sheet module 1a is assembled;(2) both sides lower floor railway deck module 4 is assembled;(3) sheet module 1b in purlin, both sides is assembled;(4) horizontal-associate sheet module 2 is assembled;(5) upper strata highway bridge module 3 is assembled;The highway bridge panel of upper strata highway bridge module 3 and crossbeam all adopt penetration to weld when welding with the top boom 11 of purlin sheet module 1, when lower floor's railway deck module 4 connects between whole sections, its roof and floor unit is connected as the docking of penetration building site, and except being welded to connect except the employing of levels floorings between whole sections, all the other all adopt high strength exploitation.
Purlin sheet module 1 is in the whole sections module assembly of truss, and the chord member between two purlin sheets adopts high strength exploitation, is also adopted by high strength exploitation between the brace of purlin sheet module 1.
In purlin sheet module 1 environment in the open, location assembles and measures needs before sunrise, avoiding solar radiation, to consider fetalism and the impact of purlin sheet linear expansion coefficient under sunshine during welding, in case fetalism deformation effect dimensional accuracy.
Web member and the top boom 11 spacing not spot welding in spacing shelves angle when purlin sheet module 1 assembles, relocate after web member completes with lower boom weld seam and weld, so as to web member has the space freely stretched in the longitudinal direction when lower-chord panel point welds, reduce welding and shrink the impact that purlin is high.
When being assembled in assembled purlin sheet module of the whole sections module 6 of truss, sheet module 1 purlin, the three overall purlins high bias direction of same whole sections is consistent, and within the scope of tolerance.
The position of welding needs to utilize the position that ultrasonic listening instrument butt welding connects to carry out carrying out flaw detection after having welded.
The positioner of the upper setting of moulding bed E arranges keyhole and utilizes punch to position with end longeron keyhole in its end.
Skilled person will appreciate that of the industry; the present invention is not restricted to the described embodiments; described in above-described embodiment and description is that principles of the invention is described; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications, and these changes and improvements both fall within the claimed scope of the invention.Claimed scope is defined by appending claims and equivalent thereof.

Claims (7)

1. a full weldering truss sections modularization assemble method, it is characterised in that: the method is divided into several modules each assembly of truss sections, and each module is independent assembled;Including: the assembling method of S1. purlin sheet module;S2. the assembling method of horizontal-associate sheet module;S3. the assembling method of upper strata highway bridge module;S4. the assembling method of lower floor's railway deck module;S5. highway adapter section beam assembling method in length and breadth;S6. the assembling method of the whole sections module of truss;Specifically include following steps:
S1. the assembling method of purlin sheet module: purlin sheet module includes top boom, lower boom and diagonal web member, purlin sheet module be assembled on moulding bed A to complete;First by top boom and lower boom positioned parallel on moulding bed A, it is linear that top boom and lower boom are adjusted complying with camber, after adjusting the dimensional requirement in each orientation, adopts interim location measure top boom and lower boom to be fixed on the positioning;Diagonal web member is pushed up pick cooperation and is arranged between top boom and lower boom, again diagonal web member is welded with top-bottom chord node, first burn-on the weld seam between chord member and diagonal web member, the centrage coupling deviation welding the weld seam between lower boom and diagonal web member, top-bottom chord and diagonal web member again controls at≤± 0.5mm;The overall purlin sheet welded is disintegrated so that it is become single purlin sheet module, stay the module of one section of single purlin sheet as parent segment, participate in the splicing of next round;
S2. the assembling method of horizontal-associate sheet module: horizontal-associate sheet module includes node, web member and horizontal-associate sheet lower boom, and horizontal-associate sheet module completes on moulding bed B;First positioning horizontal-associate sheet lower boom on moulding bed B, horizontal-associate sheet lower boom, according to single making, becomes work shape chord member and two ends node reserves two amount of cutting with assembly welding after cover plate splicing;Assembled welding web member and node on moulding bed B successively, node is reserved two amounts of cutting in horizontal-associate sheet short transverse;After welding and having repaired horizontal-associate sheet, according to the length of horizontal-associate lamellar body and cutting node of highly ruling;Transport and hoisting process adopt temporary connection reinforce, to avoid deformation;
S3. the assembling method of upper strata highway bridge module: upper strata highway bridge module includes highway bridge Slab element and T-shaped crossbeam unit, upper strata highway bridge module be assembled on moulding bed C to complete;Road spelling adopts continuously coupling assembly welding and the assembled parallel process program of examination, often wheel four whole sections of spelling, stays one section of parent segment as next round to participate in assembly after last round of assembly completes;First highway bridge panel is carried out two-in-one assembled formation highway single-unit floorings, and then T-shaped crossbeam is positioned on the moulding bed C of simulation chord member, then highway single-unit floorings carry out assembly according to by middle part to the order of both sides on T-shaped crossbeam, longitudinal seam welding between assembled Hou Xianjiang highway single-unit floorings is got up, again transverse joint is welded, finally weld other weld seam, highway single-unit floorings after welding are drawn two and cuts non-referenced end line, cut non-referenced end line according to drawn two and carry out adjacent middle part highway single-unit floorings assembly, then the highway single-unit floorings of assembled adjacent highway single-unit floorings both sides, middle part again, repeat upper strata highway bridge module is installed according to above order;For ensureing the Interface Matching precision of highway bridge panel and main truss chord member horizontal plate, after upper strata highway bridge panel welding completes, line cutting both sides, control bridge deck width;
S4. the assembling method of lower floor's railway deck module: lower floor's railway deck module includes top plate unit, bottom board unit, longeron unit and board-like crossbeam unit, lower floor's railway deck module be assembled on moulding bed D to complete;Top plate unit and bottom board unit are carried out respectively two-in-one assembled formation railway single-unit bridge floor top board and railway single-unit bridge floor base plate, railway single-unit bridge floor base plate is laid to both sides by centre, railway single-unit bridge floor base plate is welded, first weld longitudinal joint, weld transverse joint again, last welded plate type crossbeam unit and top plate unit, the weld seam of bottom board unit, moulding bed D is placed on individual railroad bridge floor base plate, board-like crossbeam unit is positioned on the moulding bed D of simulation chord member, longeron unit is vertically embedded into board-like crossbeam unit carry out assembly and wouldn't weld, top plate unit assembly is laid on the upper end of longeron unit and board-like crossbeam, according to the top plate unit first laying middle part, the order of the top plate unit re-laying both sides carries out;Top plate unit and bottom board unit connect with the upper lower horizontal board penetration weld of the lower boom of purlin sheet module respectively, and board-like crossbeam unit is welded with the lower boom of purlin sheet module;
S5. highway adapter section beam assembling method in length and breadth: highway adapter section includes crossbeam, longeron and connection beam;Highway adapter section beam in length and breadth is assembled on moulding bed E and completes, and moulding bed E is provided with longeron, crossbeam positioner and portraitlandscape baseline;First the height that under being relied on moulding bed E by crossbeam according to the horizontal baseline on moulding bed, buttress sets positions, crossbeam is cut cut-to-measure by reserved for crossbeam two ends two after having positioned and is cut, then moulding bed E end gauge and Longitudinal Base location is relied on to assemble longeron, the twice connection beam being perpendicular to longeron it is equipped with again between two crossbeams, finally carry out weld seam, welding adopts first weldering crossbeam and longeron weld seam, and the rear order welding connection beam weld seam carries out;
S6. the assembling method of truss whole sections module: the whole sections of truss includes purlin sheet module, horizontal-associate sheet module, upper strata highway bridge module and lower floor's railway deck module;The whole sections module spliced of truss is contained on moulding bed F and completes, and moulding bed F to arrange temporary support and fixing device, it is ensured that assembled stable safety and splicing accuracy;First on moulding bed F, position lower floor's railway deck module of side, secondly adopt interim location measure that middle purlin sheet module is installed at the side of the railway deck module of lower floor, then adopt interim location measure that lower floor's railway deck module of opposite side is carried out assembly at the opposite side of middle purlin sheet module, by Liang Kuai lower floor railway deck module after the location assembly of middle sheet module both sides, purlin completes, it is respectively mounted side purlin sheet module again in the both sides of Liang Kuai lower floor railway deck module, then adopt interim location measure auxiliary that horizontal-associate sheet module is installed between middle purlin sheet module and dual-side purlin sheet module, last again in horizontal-associate sheet upper strata installed above highway bridge module;Assembly carries out quality halt detection after completing, lower tire transhipment of disintegrating after qualified, stays parent segment to participate in the lower whole section assembling of round;The whole sections of truss is installed first section and is carried out assembly in the following order: (1) side lower floor railway deck module location;(2) in the middle of, purlin sheet module is assembled;(3) opposite side lower floor railway deck module is assembled;(4) sheet module in purlin, both sides is assembled;(5) horizontal-associate sheet module is assembled;(6) highway bridge module in upper strata is assembled;The whole sections of follow-up truss is assembled in the following order to be advanced: in the middle of (1), purlin sheet module is assembled;(2) both sides lower floor railway deck module is assembled;(3) sheet module in purlin, both sides is assembled;(4) horizontal-associate sheet module is assembled;(5) highway bridge module in upper strata is assembled;The highway bridge panel of upper strata highway bridge module and crossbeam all adopt penetration to weld when welding with the top boom of purlin sheet module, when lower floor's railway deck module connects between whole sections, its roof and floor unit is connected as the docking of penetration building site, and except being welded to connect except the employing of levels floorings between whole sections, all the other all adopt high strength exploitation.
2. one according to claim 1 welds truss sections modularization assemble method entirely, it is characterized in that: described purlin sheet module is in the whole sections module assembly of truss, chord member between two purlin sheets adopts high strength exploitation, is also adopted by high strength exploitation between the brace of purlin sheet module.
3. one according to claim 1 welds truss sections modularization assemble method entirely, it is characterized in that: in described purlin sheet module environment in the open, location assembles and measures needs before sunrise, avoid solar radiation, fetalism and the impact of purlin sheet linear expansion coefficient is considered during welding under sunshine, in case fetalism deformation effect dimensional accuracy.
4. one according to claim 1 welds truss sections modularization assemble method entirely, it is characterized in that: web member and the top boom spacing not spot welding in spacing shelves angle during described purlin sheet module assembled, relocate after web member completes with lower boom weld seam and weld, so as to web member has the space freely stretched in the longitudinal direction when lower-chord panel point welds, reduce welding and shrink the impact that purlin is high.
5. one according to claim 1 welds truss sections modularization assemble method entirely, it is characterized in that: when being assembled in assembled purlin sheet module of the whole sections module of described truss, sheet module purlin, the three overall purlins high bias direction of same whole sections is consistent, and within the scope of tolerance.
6. one according to claim 1 welds truss sections modularization assemble method entirely, it is characterised in that: the position of described welding needs to utilize the position that ultrasonic listening instrument butt welding connects to carry out carrying out flaw detection after having welded.
7. one according to claim 1 welds truss sections modularization assemble method entirely, it is characterised in that: the positioner of the upper setting of described moulding bed E arranges keyhole and utilizes punch to position with end longeron keyhole in its end.
CN201610106419.4A 2016-02-26 2016-02-26 Full-welding truss section modularized splicing method Active CN105735129B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610106419.4A CN105735129B (en) 2016-02-26 2016-02-26 Full-welding truss section modularized splicing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610106419.4A CN105735129B (en) 2016-02-26 2016-02-26 Full-welding truss section modularized splicing method

Publications (2)

Publication Number Publication Date
CN105735129A true CN105735129A (en) 2016-07-06
CN105735129B CN105735129B (en) 2017-05-10

Family

ID=56248562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610106419.4A Active CN105735129B (en) 2016-02-26 2016-02-26 Full-welding truss section modularized splicing method

Country Status (1)

Country Link
CN (1) CN105735129B (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106238865A (en) * 2016-08-27 2016-12-21 江苏中铁山桥重工有限公司 A kind of welding method between bridge chord member unlike material
CN107201726A (en) * 2017-06-08 2017-09-26 宁波市交通规划设计研究院有限公司 The all welded steel structured bridge of section assembling eliminates the construction method of residual stress
CN107700360A (en) * 2017-09-19 2018-02-16 武船重型工程股份有限公司 A kind of assembling method of truss bridge section
CN107775240A (en) * 2016-08-29 2018-03-09 西尼机电(杭州)有限公司 A kind of truss welding frock technique
CN108071076A (en) * 2017-11-27 2018-05-25 武船重型工程股份有限公司 A kind of welding technique of truss-type bridges floorings
CN108755449A (en) * 2017-11-28 2018-11-06 江苏中铁山桥重工有限公司 A kind of manufacturing method of novel Steel Bridge Deck for bridge deck renewal
CN109235769A (en) * 2018-11-16 2019-01-18 中建二局安装工程有限公司 Truss structure and its installation method are reinforced in a kind of recessed fish-bellied type combination of large span
CN109868748A (en) * 2019-03-15 2019-06-11 中铁九桥工程有限公司 A kind of three wide controllers in the main truss purlin bolting and welding cable-stayed bridge girder steel whole segment Zong Pin
CN109972492A (en) * 2019-04-26 2019-07-05 江苏京沪重工有限公司 A kind of bridge floor segmentation module and joining section module assembled system
CN109989352A (en) * 2019-04-26 2019-07-09 江苏京沪重工有限公司 A kind of Steel Truss Beam top boom and lower boom assembly moulding bed and splicing structure
CN110373989A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 A kind of whole segment manufacturing method of non-major P.E.subject steel truss girder closure section
CN110373988A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 The big segment steel truss girder and manufacturing technology of a kind of band pair purlin
CN110900084A (en) * 2019-12-16 2020-03-24 浙江蓝炬星电器有限公司 Device for setting boundary line between arc panel and straight panel for steaming and baking oven
CN111648243A (en) * 2020-05-08 2020-09-11 江苏中铁山桥重工有限公司 Method for assembling large sections of bolted and welded combined steel truss girder
CN112644585A (en) * 2020-12-18 2021-04-13 巨力索具股份有限公司 Method for assembling body of beam transporting vehicle and beam transporting vehicle body manufactured by method
CN113047153A (en) * 2021-02-07 2021-06-29 中铁四局集团有限公司 Method for manufacturing all-welded U-shaped steel structure aqueduct
CN113042981A (en) * 2021-04-21 2021-06-29 中国水利水电第十工程局有限公司 End column structure assembling tool and rigid water-stopping herringbone gate manufacturing method
CN113585098A (en) * 2021-09-28 2021-11-02 南通华川交通装备有限责任公司 Construction method of steel structure bridge of super-large bridge
CN113789729A (en) * 2021-10-13 2021-12-14 南通华川交通装备有限责任公司 Road and bridge steel box girder assembling construction method
CN114808750A (en) * 2022-04-25 2022-07-29 中铁山桥(南通)有限公司 Manufacturing and assembling process for double-layer highway bridge deck steel truss girder segments
CN114808751A (en) * 2022-04-25 2022-07-29 中铁山桥(南通)有限公司 Whole section assembling process for steel truss girder of main channel bridge

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2120513C1 (en) * 1997-05-15 1998-10-20 Петербургский государственный университет путей сообщения Bridge metal framework with continuous welded railroad track
CN101158143A (en) * 2007-11-23 2008-04-09 清华大学 Double-deck bridge floor combined trussed girder bridge
CN101603288A (en) * 2009-07-03 2009-12-16 中铁大桥局股份有限公司 A kind of three-truss main girder structure of highway and railway bi-purpose cable-stayed bridge and mounting method thereof
KR20110113444A (en) * 2010-04-09 2011-10-17 안경수 Joint unit structure of pipe truss for temporary assembly and method constructing the truss bridge with it
CN102352604A (en) * 2011-08-05 2012-02-15 中铁大桥局股份有限公司 Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof
CN102979033A (en) * 2012-11-16 2013-03-20 中铁大桥勘测设计院集团有限公司 Steel truss girder all-welded joist slice and construction method thereof
CN202899015U (en) * 2012-11-07 2013-04-24 湖北华舟重工应急装备股份有限公司 Modular highway steel truss bridge
CN104018427A (en) * 2014-05-14 2014-09-03 中铁大桥勘测设计院集团有限公司 All-welded box girder combination section constructing method
CN204212058U (en) * 2014-10-09 2015-03-18 中铁十局集团有限公司 For the steel truss girder assembling support in the construction of steel concrete composite truss beam
CN104594176A (en) * 2013-11-01 2015-05-06 湖北华舟重工应急装备股份有限公司 Long-span assembly type road steel truss bridge
CN104878699A (en) * 2015-06-18 2015-09-02 上海振华重工(集团)股份有限公司 Pitching type truss bridge manufacturing method

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2120513C1 (en) * 1997-05-15 1998-10-20 Петербургский государственный университет путей сообщения Bridge metal framework with continuous welded railroad track
CN101158143A (en) * 2007-11-23 2008-04-09 清华大学 Double-deck bridge floor combined trussed girder bridge
CN101603288A (en) * 2009-07-03 2009-12-16 中铁大桥局股份有限公司 A kind of three-truss main girder structure of highway and railway bi-purpose cable-stayed bridge and mounting method thereof
KR20110113444A (en) * 2010-04-09 2011-10-17 안경수 Joint unit structure of pipe truss for temporary assembly and method constructing the truss bridge with it
CN102352604A (en) * 2011-08-05 2012-02-15 中铁大桥局股份有限公司 Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof
CN202899015U (en) * 2012-11-07 2013-04-24 湖北华舟重工应急装备股份有限公司 Modular highway steel truss bridge
CN102979033A (en) * 2012-11-16 2013-03-20 中铁大桥勘测设计院集团有限公司 Steel truss girder all-welded joist slice and construction method thereof
CN104594176A (en) * 2013-11-01 2015-05-06 湖北华舟重工应急装备股份有限公司 Long-span assembly type road steel truss bridge
CN104018427A (en) * 2014-05-14 2014-09-03 中铁大桥勘测设计院集团有限公司 All-welded box girder combination section constructing method
CN204212058U (en) * 2014-10-09 2015-03-18 中铁十局集团有限公司 For the steel truss girder assembling support in the construction of steel concrete composite truss beam
CN104878699A (en) * 2015-06-18 2015-09-02 上海振华重工(集团)股份有限公司 Pitching type truss bridge manufacturing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐伟 等: "沪通长江大桥主航道桥主梁结构设计", 《桥梁建设》 *

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106238865A (en) * 2016-08-27 2016-12-21 江苏中铁山桥重工有限公司 A kind of welding method between bridge chord member unlike material
CN107775240A (en) * 2016-08-29 2018-03-09 西尼机电(杭州)有限公司 A kind of truss welding frock technique
CN107775240B (en) * 2016-08-29 2019-08-09 西尼机电(杭州)有限公司 A kind of welding procedure of truss
CN107201726B (en) * 2017-06-08 2018-12-04 宁波市交通规划设计研究院有限公司 The all welded steel structured bridge of section assembling eliminates the construction method of residual stress
CN107201726A (en) * 2017-06-08 2017-09-26 宁波市交通规划设计研究院有限公司 The all welded steel structured bridge of section assembling eliminates the construction method of residual stress
CN107700360A (en) * 2017-09-19 2018-02-16 武船重型工程股份有限公司 A kind of assembling method of truss bridge section
CN108071076A (en) * 2017-11-27 2018-05-25 武船重型工程股份有限公司 A kind of welding technique of truss-type bridges floorings
CN108755449A (en) * 2017-11-28 2018-11-06 江苏中铁山桥重工有限公司 A kind of manufacturing method of novel Steel Bridge Deck for bridge deck renewal
CN109235769B (en) * 2018-11-16 2023-06-20 中建二局安装工程有限公司 Large-span concave fish belly type combined reinforced truss structure and installation method thereof
CN109235769A (en) * 2018-11-16 2019-01-18 中建二局安装工程有限公司 Truss structure and its installation method are reinforced in a kind of recessed fish-bellied type combination of large span
CN109868748A (en) * 2019-03-15 2019-06-11 中铁九桥工程有限公司 A kind of three wide controllers in the main truss purlin bolting and welding cable-stayed bridge girder steel whole segment Zong Pin
CN109972492A (en) * 2019-04-26 2019-07-05 江苏京沪重工有限公司 A kind of bridge floor segmentation module and joining section module assembled system
CN109989352A (en) * 2019-04-26 2019-07-09 江苏京沪重工有限公司 A kind of Steel Truss Beam top boom and lower boom assembly moulding bed and splicing structure
CN110373989A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 A kind of whole segment manufacturing method of non-major P.E.subject steel truss girder closure section
CN110373988A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 The big segment steel truss girder and manufacturing technology of a kind of band pair purlin
CN110900084A (en) * 2019-12-16 2020-03-24 浙江蓝炬星电器有限公司 Device for setting boundary line between arc panel and straight panel for steaming and baking oven
CN111648243A (en) * 2020-05-08 2020-09-11 江苏中铁山桥重工有限公司 Method for assembling large sections of bolted and welded combined steel truss girder
CN112644585A (en) * 2020-12-18 2021-04-13 巨力索具股份有限公司 Method for assembling body of beam transporting vehicle and beam transporting vehicle body manufactured by method
CN112644585B (en) * 2020-12-18 2024-06-07 巨力索具股份有限公司 Beam transporting vehicle body assembling method and beam transporting vehicle body manufactured by same
CN113047153A (en) * 2021-02-07 2021-06-29 中铁四局集团有限公司 Method for manufacturing all-welded U-shaped steel structure aqueduct
CN113042981A (en) * 2021-04-21 2021-06-29 中国水利水电第十工程局有限公司 End column structure assembling tool and rigid water-stopping herringbone gate manufacturing method
CN113042981B (en) * 2021-04-21 2022-02-01 中国水利水电第十工程局有限公司 End column structure assembling tool and rigid water-stopping herringbone gate manufacturing method
CN113585098A (en) * 2021-09-28 2021-11-02 南通华川交通装备有限责任公司 Construction method of steel structure bridge of super-large bridge
CN113585098B (en) * 2021-09-28 2021-12-28 南通华川交通装备有限责任公司 Construction method of steel structure bridge of super-large bridge
CN113789729A (en) * 2021-10-13 2021-12-14 南通华川交通装备有限责任公司 Road and bridge steel box girder assembling construction method
CN114808751A (en) * 2022-04-25 2022-07-29 中铁山桥(南通)有限公司 Whole section assembling process for steel truss girder of main channel bridge
CN114808750A (en) * 2022-04-25 2022-07-29 中铁山桥(南通)有限公司 Manufacturing and assembling process for double-layer highway bridge deck steel truss girder segments

Also Published As

Publication number Publication date
CN105735129B (en) 2017-05-10

Similar Documents

Publication Publication Date Title
CN105735129A (en) Full-welding truss section modularized splicing method
CN108049302B (en) A kind of manufacturing method of full welding steel case and full bolt truss combined bridge lower edge steel box-girder
CN108103938B (en) A kind of double deck module solid trial assembly method of large steel girder
CN201128956Y (en) Assembled integral flat-plate or curve type vierendeel steel lattice structure
CN101397822A (en) Assembly of integral flat-plate type or hood face section steel hollow lattice construction and production method
CN113585098B (en) Construction method of steel structure bridge of super-large bridge
CN111648243A (en) Method for assembling large sections of bolted and welded combined steel truss girder
CN212895948U (en) Curved steel beam pushing system
CN114178736B (en) Method for controlling total splicing transverse slope of ultra-wide steel box girder
CN107386451A (en) Assembled Box Modular Building
CN112536542A (en) Manufacturing method of ramp steel box girder
CN202099719U (en) Steel truss bridge
CN207176924U (en) Assembled Box Modular Building
CN109252451A (en) One kind for welding steel truss girder bridge closure mouth accurately matched method entirely
CN105089177A (en) Prefabricated sectional steel truss concrete shear wall and manufacturing method of prefabricated sectional steel truss concrete shear wall
CN103212928B (en) Prevent the method for cantilever beam base plate welding deformation
CN104563525B (en) A kind of box steel arch beam Integral horizontal type group is to method
CN110696994B (en) Ship double-bottom segmented construction method
CN114790695B (en) Manufacturing method of special-shaped independent tower matched hinged steel bridge pier system cable-stayed landscape steel bridge
CN113718636B (en) Special-shaped double-layer tower bridge structure and manufacturing method thereof
CN114799753B (en) Manufacturing method of space special-shaped multi-curved-surface steel structure
CN108755449A (en) A kind of manufacturing method of novel Steel Bridge Deck for bridge deck renewal
CN113503030A (en) Arc-shaped cornice modular prefabrication and spaced hoisting construction method thereof
CN204826306U (en) Prefabricated shaped steel truss concrete shear force wall
CN210031455U (en) Small box girder bridge floor connecting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 226500 Wenjin Road, Yangtze River Town, Rugao City, Nantong City, Jiangsu Province

Patentee after: China Railway Shanqiao (Nantong) Co.,Ltd.

Address before: 226500 Wenjin Road, Yangtze River Town, Rugao City, Nantong City, Jiangsu Province

Patentee before: JIANGSU CHINA RAILWAY SHANHAIGUAN BRIDGE HEAVY INDUSTRY Co.,Ltd.