CN107201726A - The all welded steel structured bridge of section assembling eliminates the construction method of residual stress - Google Patents

The all welded steel structured bridge of section assembling eliminates the construction method of residual stress Download PDF

Info

Publication number
CN107201726A
CN107201726A CN201710427878.7A CN201710427878A CN107201726A CN 107201726 A CN107201726 A CN 107201726A CN 201710427878 A CN201710427878 A CN 201710427878A CN 107201726 A CN107201726 A CN 107201726A
Authority
CN
China
Prior art keywords
section
cable
hoist cable
truss
interim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710427878.7A
Other languages
Chinese (zh)
Other versions
CN107201726B (en
Inventor
朱汉华
陈孟冲
方晓庆
李志勇
王开太
翁沙羚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO COMMUNICATIONS PLANNING INSTITUTE CO., LTD.
Tibet Ganoderma Lucidum Construction Consulting Group Co., Ltd.
Original Assignee
Ningbo Communications Planning Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Communications Planning Institute Co Ltd filed Critical Ningbo Communications Planning Institute Co Ltd
Priority to CN201710427878.7A priority Critical patent/CN107201726B/en
Publication of CN107201726A publication Critical patent/CN107201726A/en
Application granted granted Critical
Publication of CN107201726B publication Critical patent/CN107201726B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Abstract

The invention discloses the construction method that a kind of all welded steel structured bridge of section assembling eliminates residual stress, belong to construction method field.This method comprises the following steps:It is provided for hanging the weight cable of interim hoist cable on the Sarasota of bridge both sides;Using hoist cable is played, the lifting of each section truss section is in place successively, its bolt is anchored and welded after per in place one section truss section, then it is fixed in by an interim hoist cable on weight cable, cancel the hoist cable that rises on the truss section, and adjust the cable force that hangs of all mounted interim hoist cables and be each equal to its lower fixed truss section gravity of itself;After main span is closed up, all interim hoist cables are removed, subsequent construction is carried out.The present invention, which is set, can constrain the compatibility of deformation control of truss section after the interim hoist cable, joggle truss is not subjected to the weight of section below, therefore splicing welding joint no longer stress, the welding residual stress that can be produced with successive elimination external load, it is to avoid the fatigue rupture of steel construction.

Description

The all welded steel structured bridge of section assembling eliminates the construction method of residual stress
Technical field
The invention belongs to construction method field, and in particular to a kind of all welded steel structured bridge of section assembling eliminates residual stress Construction method.
Background technology
Large-span steel trussed bridge is big due to across footpath, and the weight of truss in itself is very big, it is necessary to carry out at the scene multiple Weld assembling construction in section.The free cantilever erection construction of such current bridge generally by section truss of first constructing bear after construct section Weight, knotted rope is set again when jib-length is larger, cantilever segment is held.But the construction method can cause the fatigue life of bridge It is affected, the current problem not yet draws attention.
It is main in terms of the type selecting of material, preprocessing in fatigue rupture for preventing steel construction, current construction method It is adjusted.For example postwelding is heat-treated at the appointed time, eliminates residual stress;Or leveling eliminates stress before steel blanking, Leveling eliminates stress again after blanking, part internal stress is fully discharged.
But, applicant is had found under study for action, for large-span steel trussed bridge, and above-mentioned processing still can not The fatigue rupture of steel construction is avoided completely, and its basic reason is that after the completion of this kind of construction method is welded in section, welding point will The load of section below is constantly born, is not eliminated because section weld has welding residual stress, by influence fatigue Life-span.
For example, the steel truss arch bridge of certain domestic rice of main span more than 300, main span arch rib is installed using " cable hoisting, cantilever are spelled Connect " construction method, as shown in Figure 1.Section splicing welding joint starts to bear the vertical of lower section load generation after the cooling period quickly Pressure that power and moment of flexure and knotted rope are produced etc..Because welding residual stress is not completely eliminated yet, to the steel under dynamic loading Structural fatigue intensity can produce adverse effect.So, how effectively to eliminate the welding residual stress of all welded steel structured trussed bridge Influence the fatigue life for raising bridge most important.
The content of the invention
It is an object of the invention in current large-span steel bridge installation process, and a kind of section assembling is provided welded entirely Steel structure bridge eliminates the construction method of residual stress.
Concrete technical scheme of the present invention is as follows:
The all welded steel structured bridge of section assembling eliminates the construction method of residual stress, comprises the following steps:
S1:Truss section can be constrained by being provided for hanging the weight cable of interim hoist cable on the Sarasota of bridge both sides Compatibility of deformation is controlled;
S2:The first truss section is lifted by crane in place using hoist cable is played, and to being welded after section bolt anchoring; One end of first interim hoist cable is fixed on weight cable, the other end is fixed on the first truss section;Cancel hoist cable, and Adjust the first interim hoist cable hangs cable force equal to the first truss section gravity of itself;
S2:The second truss section is lifted by crane in place using hoist cable is played, and to being welded after section bolt anchoring; One end of second interim hoist cable is fixed on weight cable, the other end is fixed on the second truss section;Cancel hoist cable, and Adjust the first interim hoist cable, the cable force that hangs of the second interim hoist cable is respectively equal to the first truss section, the second truss section itself Gravity;
S3:Remaining truss section is lifted by crane in place successively using hoist cable is played, it faced after saving truss section per in place one When bolt anchoring and weld, be then fixed on weight cable, cancelled on the truss section by an interim hoist cable Hoist cable is played, and adjusts the cable force that hangs of all mounted interim hoist cables and is each equal to its lower fixed truss section weight of itself Power;
S4:After main span is closed up, all interim hoist cables are removed, subsequent construction is carried out.
Cancel knotted rope in this method, truss section is fixed using interim hoist cable form, for bearing the vertical of each section Power, while the compatibility of deformation control of truss section can be constrained for fixing each interim hoist cable by adding a weight cable.When After often the welding of section truss section is finished, the total weight of its own is supported by interim hoist cable so that the truss section itself Weight will not be transferred to welding position, so that the residual stress of welding position can be progressively released.Comparatively speaking, Fig. 1 It is middle to apply the form of pulling force using the inclination knotted rope being fixed on Sarasota, welding position can be caused while by truss section certainly The inclination pulling force effect that body vertical gravity, moment of flexure and knotted rope are produced so that welding position is chronically at load state, remnants should Power can not be discharged completely.As can be seen here, the present invention is by the improvement on construction, is residual during welding for steel structure The release of residue stress provides advantage, can necessarily improve its fatigue life.
Preferably, each truss section is from both sides toward the two-way erection of span centre during construction, in Middle span closing.
Preferably, because the load born on weight cable is very big, described weight cable is provided at both ends with rear anchor.
Preferably, described interim hoist cable uses steel wire rope or high-tensile steel wires, and do preservative treatment.
Preferably, described weight cable uses steel wire rope, steel strand wires or high-tensile steel wires, and do preservative treatment.
Preferably, one end of described interim hoist cable is stretching end, for adjusting Suo Li.
The present invention in terms of existing technologies, has the advantages that:
The present invention is directed to all welded steel structured trussed bridge, it is proposed that one kind eliminates full weldering section assembling steel structure truss arch bridge The construction method of welding residual stress influence.In work progress, truss section is lifted by crane in place with hoist cable is played, bolt anchoring Welded afterwards, then the interim hoist cable being fixed on weight cable, bear the weight of truss completely by interim hoist cable.Set The compatibility of deformation control of truss section can be constrained after the interim hoist cable, joggle truss is not subjected to the weight of section below, Therefore splicing welding joint no longer stress, the welding residual stress that can be produced with successive elimination external load, it is to avoid the fatigue rupture of steel construction.
Brief description of the drawings
Fig. 1 is the lifting facade arrangement schematic diagram constructed using knotted rope mode;
Fig. 2 lifting construction sequential schematics of the present invention, wherein a)~e) it is followed successively by construction procedure;
Fig. 3 present invention lifting facade arrangement schematic diagrames;
Fig. 4 present invention lifting horizontal layout schematic diagrames.
Embodiment
The present invention is further elaborated and illustrated with reference to the accompanying drawings and detailed description.Each in the present invention is implemented The technical characteristic of mode can carry out respective combination on the premise of not colliding with each other.
(only illustrated as shown in Figure 1 in the present embodiment by taking the left part of bridge as an example, right part is similar), in rope Weight cable is set on tower, and for fixing interim hoist cable, then with rising, hoist cable is assembled successively in order (section and to be hung by truss section Rope numbering is respectively 1#~n# from main pier to span centre direction), after bolt anchoring, welding, interim hoist cable is installed, cancels lifting Section, which has been completed, before rope, and adjustment hangs cable force.
The construction procedure that all welded steel structured bridge of section assembling eliminates residual stress is as follows:
(1) Sarasota is set up in bridge both sides, plays hoist cable and 1# truss section is lifted by crane in place, welded after bolt anchoring Connect.Then one end of the interim hoist cables of 1# is fixed on weight cable, the other end is fixed on 1# truss section, has cancelled hoist cable The other end of the interim hoist cable of simultaneous tension, adjustment 1# hangs the weight that cable force is equal to 1# sections, such as Fig. 2 .a temporarily) shown in.Hang Rope vertical hanging and extended line need guiding through the center of gravity of the truss section, truss section is not produced rotation under by suspension status and incline To reducing the moment of flexure stress of welding position, follow-up remaining interim hoist cable way identical with use as far as possible.
In the present embodiment, the construction technology of weight cable:(1) material can use steel wire rope, high-tensile steel wires etc., and anti-corrosion Processing.(2) weight cable is arranged on Sarasota, and cable two ends are anchored on interim anchorage.
In the present embodiment, the construction technology of hoist cable:(1) material can use steel wire rope, high-tensile steel wires, steel strand wires etc., and Preservative treatment.(2) hoist cable one end is fixed on cable, and the other end is fixed on truss, and one end of hoist cable is stretching end, for adjusting Whole Suo Li.
(2) play hoist cable and 2# truss section is lifted by crane in place, welded after bolt anchoring, then as before The interim hoist cables of 2# are installed.Hoist cable is cancelled, will change original 1# due to increasing the interim hoist cables of 2# on weight cable and hang temporarily The Suo Li of rope, so when need simultaneously adjust 1#, 2# hang cable force temporarily, make 1#, 2# hang temporarily cable force be respectively equal to 1#, The weight of 2# sections, such as Fig. 2 .b) shown in.
(3) play hoist cable and 3# truss section is lifted by crane in place, welded after bolt anchoring, then as before Install the interim hoist cables of 3#, has cancelled hoist cable, at the same adjustment 1#, 2#, 3# hang cable force temporarily, make every group of Suo Li be respectively equal to 1#, The weight of 2#, 3# section, such as Fig. 2 .c) shown in.
Each truss section is installed successively in the above described manner, during construction each truss section from both sides toward the two-way erection of span centre, Middle span closing, successively, such as Fig. 2 .d)~Fig. 2 .f) shown in ...
(n) truss section in both sides is respectively mounted finish after, play hoist cable and in place, interim spiral shell lifted by crane in final section n# truss section Welded after bolt anchoring, then the interim hoist cables of n# are installed, cancelled hoist cable, while adjusting 1~n# hangs cable force temporarily, made every Group Suo Li is respectively equal to the weight of 1~n# sections.
Finally, 1~n# hoist cables are removed after main span is closed up, continue it is follow-up mat formation to wait construct.Final integral installation schematic diagram is such as Shown in Fig. 3 and 4, thus, each section truss section carries its own weight, adjacent truss section by corresponding interim hoist cable Between welding position be not stressed or Moment, residual stress is gradually discharged, and does not result in fatigue rupture.
Embodiment described above is a kind of preferably scheme of the present invention, and so it is not intended to limiting the invention.Have The those of ordinary skill for closing technical field, without departing from the spirit and scope of the present invention, can also make various changes Change and modification.Therefore the technical scheme that all modes for taking equivalent substitution or equivalent transformation are obtained, all falls within the guarantor of the present invention In the range of shield.

Claims (6)

1. a kind of all welded steel structured bridge of section assembling eliminates the construction method of residual stress, it is characterised in that including following step Suddenly:
S1:It is provided for hanging the weight cable of interim hoist cable on the Sarasota of bridge both sides;
S2:The first truss section is lifted by crane in place using hoist cable is played, and to being welded after section bolt anchoring;By One end of one interim hoist cable is fixed on weight cable, and the other end is fixed on the first truss section;Hoist cable is cancelled, and has adjusted The cable force that hangs of first interim hoist cable is equal to the first truss section gravity of itself;
S2:The second truss section is lifted by crane in place using hoist cable is played, and to being welded after section bolt anchoring;By One end of two interim hoist cables is fixed on weight cable, and the other end is fixed on the second truss section;Hoist cable is cancelled, and has adjusted First interim hoist cable, the cable force that hangs of the second interim hoist cable are respectively equal to the first truss section, the second truss section weight of itself Power;
S3:Remaining truss section is lifted by crane in place successively using hoist cable is played, saved per in place one behind truss section to its interim spiral shell Bolt is anchored and welded, and is then fixed in by an interim hoist cable on weight cable, is cancelled the lifting on the truss section Rope, and adjust the truss section gravity of itself that cable force is each equal to its lower fixation that hangs of all mounted interim hoist cables;
S4:After main span is closed up, all interim hoist cables are removed, subsequent construction is carried out.
2. all welded steel structured bridge of section assembling as claimed in claim 1 eliminates the construction method of residual stress, its feature exists In each truss section is from both sides toward the two-way erection of span centre during construction, in Middle span closing.
3. all welded steel structured bridge of section assembling as claimed in claim 1 eliminates the construction method of residual stress, its feature exists In described weight cable is provided at both ends with rear anchor.
4. all welded steel structured bridge of section assembling as claimed in claim 1 eliminates the construction method of residual stress, its feature exists In described interim hoist cable uses steel wire rope or high-tensile steel wires, and does preservative treatment.
5. all welded steel structured bridge of section assembling as claimed in claim 1 eliminates the construction method of residual stress, its feature exists In described weight cable uses steel wire rope, steel strand wires or high-tensile steel wires, and does preservative treatment.
6. all welded steel structured bridge of section assembling as claimed in claim 1 eliminates the construction method of residual stress, its feature exists In one end of described interim hoist cable is stretching end, for adjusting Suo Li.
CN201710427878.7A 2017-06-08 2017-06-08 The all welded steel structured bridge of section assembling eliminates the construction method of residual stress Active CN107201726B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710427878.7A CN107201726B (en) 2017-06-08 2017-06-08 The all welded steel structured bridge of section assembling eliminates the construction method of residual stress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710427878.7A CN107201726B (en) 2017-06-08 2017-06-08 The all welded steel structured bridge of section assembling eliminates the construction method of residual stress

Publications (2)

Publication Number Publication Date
CN107201726A true CN107201726A (en) 2017-09-26
CN107201726B CN107201726B (en) 2018-12-04

Family

ID=59907387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710427878.7A Active CN107201726B (en) 2017-06-08 2017-06-08 The all welded steel structured bridge of section assembling eliminates the construction method of residual stress

Country Status (1)

Country Link
CN (1) CN107201726B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109972845A (en) * 2019-04-11 2019-07-05 中国十九冶集团有限公司 The installation method of steel roof truss

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000110117A (en) * 1998-08-06 2000-04-18 Kobe Steel Ltd Floor slab and construction method therefor
CN1804216A (en) * 2006-01-20 2006-07-19 中铁三局集团有限公司 Short-sleeper long-lump integrated ballast bed seamless track construction method
CN101235624A (en) * 2008-01-24 2008-08-06 中铁工程设计咨询集团有限公司 Construction method for steel structure arch rib of arch-type bridge
CN102936962A (en) * 2012-11-20 2013-02-20 永升建设集团有限公司 Construction method of slanting cantilever steel structure supported by temporary steel frame
CN104612058A (en) * 2014-12-26 2015-05-13 中铁大桥勘测设计院集团有限公司 Construction method of flexible arch bridge with rigid beams
CN105735129A (en) * 2016-02-26 2016-07-06 江苏中铁山桥重工有限公司 Full-welding truss section modularized splicing method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000110117A (en) * 1998-08-06 2000-04-18 Kobe Steel Ltd Floor slab and construction method therefor
CN1804216A (en) * 2006-01-20 2006-07-19 中铁三局集团有限公司 Short-sleeper long-lump integrated ballast bed seamless track construction method
CN101235624A (en) * 2008-01-24 2008-08-06 中铁工程设计咨询集团有限公司 Construction method for steel structure arch rib of arch-type bridge
CN102936962A (en) * 2012-11-20 2013-02-20 永升建设集团有限公司 Construction method of slanting cantilever steel structure supported by temporary steel frame
CN104612058A (en) * 2014-12-26 2015-05-13 中铁大桥勘测设计院集团有限公司 Construction method of flexible arch bridge with rigid beams
CN105735129A (en) * 2016-02-26 2016-07-06 江苏中铁山桥重工有限公司 Full-welding truss section modularized splicing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109972845A (en) * 2019-04-11 2019-07-05 中国十九冶集团有限公司 The installation method of steel roof truss

Also Published As

Publication number Publication date
CN107201726B (en) 2018-12-04

Similar Documents

Publication Publication Date Title
CN105443871B (en) A kind of new suspension and support and construction technology for the connection of horizontal multi-pipeline counterpart
CN108643057B (en) A kind of interim anchor cable in girder of suspension bridge erection process balances construction method
CN102071644A (en) Lifting installation method of integral bridge arch rib
CN104746883B (en) A kind of arcuate space truss lifts construction method of installation with three machines
CN107152078B (en) Hinge device and construction method for releasing welding internal stress of steel gallery by using hinge device
WO2012030018A1 (en) Partially/completely earth-anchored and cable-stayed bridge using a main span tension means, and method for constructing same
CN105735113A (en) Pier pile transition connection structure for concrete-filled steel tube bridge and construction method of pier pile transition connection structure
CN108643584A (en) A kind of construction method of the steel construction overlength overhanging crossbeam without support installation
CN102261067A (en) Method for installing reinforcement cage of large-diameter ultra-long pile
CN107476581B (en) Hoisting and mounting method for steel structure double-layer overhanging structure
CN105256728B (en) A kind of cantilever erection method of the Chinese human relations formula steel truss girder of cable-stayed bridge
CN101413291A (en) Cable sky dome tower frame raising cable rod accumulation mounting method
CN109505243A (en) Cable-stayed bridge combination beam bridge floor anti-cracking method
CN107201726B (en) The all welded steel structured bridge of section assembling eliminates the construction method of residual stress
CN106012841A (en) Cable crane and installation method thereof
CN106351454A (en) Method for combined installation of steel structure roof with steel plant
CN2644490Y (en) Hoisting, installing and adjusting device for large tonnage arch rib
CN107012797A (en) Construction system and method that a kind of Support Method is combined with stayed knotting method
CN209194361U (en) A kind of fixed structure of suspension cable bridge section lifting hoisting platform
CN104085832B (en) A kind of method for improving of flexible member lifting device
CN106968178A (en) A kind of cable-stayed type suspension bridge main girder construction method
CN210976318U (en) Beam string mounting structure of spoke type beam string structure roof
CN110175389B (en) Main span and side span constant load configuration method for cable-stayed bridge
CN207633519U (en) A kind of decorative closed annular steel construction for building external
CN106245530A (en) A kind of universal rod body CABLEWAY ERECTION SYSTEM removes engineering method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190822

Address after: 315 000 No. 72 Songzhaoqiao Road, Ningbo City, Zhejiang Province

Co-patentee after: Tibet Ganoderma Lucidum Construction Consulting Group Co., Ltd.

Patentee after: NINGBO COMMUNICATIONS PLANNING INSTITUTE CO., LTD.

Address before: 315 000 No. 72 Songzhaoqiao Road, Ningbo City, Zhejiang Province

Patentee before: NINGBO COMMUNICATIONS PLANNING INSTITUTE CO., LTD.

TR01 Transfer of patent right