CN105672337A - 现浇沉井支模体系的施工方法 - Google Patents
现浇沉井支模体系的施工方法 Download PDFInfo
- Publication number
- CN105672337A CN105672337A CN201610049838.9A CN201610049838A CN105672337A CN 105672337 A CN105672337 A CN 105672337A CN 201610049838 A CN201610049838 A CN 201610049838A CN 105672337 A CN105672337 A CN 105672337A
- Authority
- CN
- China
- Prior art keywords
- borehole wall
- template
- open caisson
- fixed
- arranges
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Revetment (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610049838.9A CN105672337B (zh) | 2016-03-03 | 2016-03-03 | 现浇沉井支模体系的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610049838.9A CN105672337B (zh) | 2016-03-03 | 2016-03-03 | 现浇沉井支模体系的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105672337A true CN105672337A (zh) | 2016-06-15 |
CN105672337B CN105672337B (zh) | 2018-06-19 |
Family
ID=56304341
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610049838.9A Active CN105672337B (zh) | 2016-03-03 | 2016-03-03 | 现浇沉井支模体系的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105672337B (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106958256A (zh) * | 2017-03-22 | 2017-07-18 | 中建四局第五建筑工程有限公司 | 一种分层浇筑、多次下沉的沉井施工工艺 |
CN108316327A (zh) * | 2018-03-01 | 2018-07-24 | 中铁上海工程局集团有限公司 | 一种沉井模板及其施工方法 |
CN109577990A (zh) * | 2018-12-24 | 2019-04-05 | 中冶建工集团有限公司 | 一种顶管施工工作井的浇筑施工方法 |
CN110130460A (zh) * | 2019-05-21 | 2019-08-16 | 杭州悦为科技有限公司 | 抽拉式现浇雨水井支模装置的雨水井施工方法 |
CN111042172A (zh) * | 2020-01-16 | 2020-04-21 | 中建七局安装工程有限公司 | 一种大体积异形沉井基础施工工法 |
CN111926843A (zh) * | 2020-06-29 | 2020-11-13 | 中国二十冶集团有限公司 | 沉井刃脚模板及其施工方法 |
CN118110193A (zh) * | 2024-04-28 | 2024-05-31 | 中交二航局第三工程有限公司 | 复杂地质陆上大直径沉井全过程施工工法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2044855C1 (ru) * | 1992-05-14 | 1995-09-27 | Рашид Николаевич Яковлев | Переставная опалубочная форма |
JPH1018296A (ja) * | 1996-07-08 | 1998-01-20 | Kajima Corp | ケーソン構築用の内型枠及びそのリフトアップ装置 |
CN204435875U (zh) * | 2014-12-12 | 2015-07-01 | 中国建筑第八工程局有限公司 | 二层以上清水混凝土外墙模板体系与外脚手架的连接结构 |
CN104895108A (zh) * | 2015-05-28 | 2015-09-09 | 杭州江润科技有限公司 | 贝雷片拼装移动式桁架单侧支模体系施工方法 |
-
2016
- 2016-03-03 CN CN201610049838.9A patent/CN105672337B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2044855C1 (ru) * | 1992-05-14 | 1995-09-27 | Рашид Николаевич Яковлев | Переставная опалубочная форма |
JPH1018296A (ja) * | 1996-07-08 | 1998-01-20 | Kajima Corp | ケーソン構築用の内型枠及びそのリフトアップ装置 |
CN204435875U (zh) * | 2014-12-12 | 2015-07-01 | 中国建筑第八工程局有限公司 | 二层以上清水混凝土外墙模板体系与外脚手架的连接结构 |
CN104895108A (zh) * | 2015-05-28 | 2015-09-09 | 杭州江润科技有限公司 | 贝雷片拼装移动式桁架单侧支模体系施工方法 |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106958256A (zh) * | 2017-03-22 | 2017-07-18 | 中建四局第五建筑工程有限公司 | 一种分层浇筑、多次下沉的沉井施工工艺 |
CN108316327A (zh) * | 2018-03-01 | 2018-07-24 | 中铁上海工程局集团有限公司 | 一种沉井模板及其施工方法 |
CN109577990A (zh) * | 2018-12-24 | 2019-04-05 | 中冶建工集团有限公司 | 一种顶管施工工作井的浇筑施工方法 |
CN110130460A (zh) * | 2019-05-21 | 2019-08-16 | 杭州悦为科技有限公司 | 抽拉式现浇雨水井支模装置的雨水井施工方法 |
CN111042172A (zh) * | 2020-01-16 | 2020-04-21 | 中建七局安装工程有限公司 | 一种大体积异形沉井基础施工工法 |
CN111926843A (zh) * | 2020-06-29 | 2020-11-13 | 中国二十冶集团有限公司 | 沉井刃脚模板及其施工方法 |
CN118110193A (zh) * | 2024-04-28 | 2024-05-31 | 中交二航局第三工程有限公司 | 复杂地质陆上大直径沉井全过程施工工法 |
Also Published As
Publication number | Publication date |
---|---|
CN105672337B (zh) | 2018-06-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105672337A (zh) | 现浇沉井支模体系的施工方法 | |
CN104612695B (zh) | 一种剧烈垮塌立井井壁修复加固方法 | |
CN207003499U (zh) | 一种地铁隧道上方基坑开挖的抗浮起装置 | |
CN107542108A (zh) | 一种建筑物地下室结构的逆向施工方法 | |
CN112376589A (zh) | 滑坡带桩板式综合防护施工体系及施工方法 | |
CN102864781A (zh) | 一种斜桩基坑支护方法 | |
CN211898463U (zh) | 采用微钢管桩与锚杆联合的加固装置 | |
CN105155550A (zh) | 联合支护开挖大厚度强风化砂岩层深基坑的施工方法 | |
CN110158675A (zh) | 改建工程中地下室外墙抗侧支撑加固系统及其施工方法 | |
CN206428707U (zh) | 一种基坑支护降水一体化管桩护壁结构 | |
CN108316328A (zh) | 一种用于沉井施工的加压下沉装置及其施工方法 | |
CN210106749U (zh) | 一种软土地基超大断面顶管顶进作业的反力结构 | |
CN209723033U (zh) | 一种适用于沙漠无水砂层地区顶管工作井 | |
CN108222054B (zh) | 塔吊基础结构及其施工方法 | |
CN101509258A (zh) | 预先控制沉井下沉倾斜的方法 | |
CN207004520U (zh) | 一种地铁保护区竖井开挖的稳固结构 | |
CN117166510A (zh) | 一种深大直径沉井施工方法 | |
CN111075452A (zh) | 岩土混合竖井工程支护体系及竖井施工方法 | |
CN117090598A (zh) | 一种运营期隧道微型桩加嵌托梁组合结构的地基处理方法 | |
CN114875972B (zh) | 一种明挖逆作基坑主体结构施工方法 | |
CN205530315U (zh) | 现浇沉井支模体系 | |
CN113266038B (zh) | 基坑开挖地下建筑施工方法 | |
CN105484270A (zh) | 一种毗邻深基坑高陡老旧毛石挡土墙加固保护施工方法 | |
CN113266019B (zh) | 一种基坑钢管支撑体系的施工工法 | |
CN110863496B (zh) | 一种填石筑岛区域混凝土支护换撑开挖施工拱座基础方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Yang Jiannan Inventor after: Zhuang Lingxia Inventor after: Zhang Keyun Inventor after: Li Tao Inventor after: Qian Ting Inventor before: Wang Xinquan |
|
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20180518 Address after: No. 3388, Yinzhou District Cang Hai Road, Yinzhou District, Ningbo, Zhejiang Applicant after: Zhejiang sea Construction Co., Ltd. Address before: 310015 room 1901, unit 3, 3 Wanda Commercial Center, Gongshu District, Hangzhou, Zhejiang. Applicant before: Hangzhou Jiang Run Science and Technology Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant |