CN105666686B - A kind of reinforcing bar production and supply system for being used to produce precast concrete - Google Patents

A kind of reinforcing bar production and supply system for being used to produce precast concrete Download PDF

Info

Publication number
CN105666686B
CN105666686B CN201610074255.1A CN201610074255A CN105666686B CN 105666686 B CN105666686 B CN 105666686B CN 201610074255 A CN201610074255 A CN 201610074255A CN 105666686 B CN105666686 B CN 105666686B
Authority
CN
China
Prior art keywords
reinforcing bar
reinforcing
bar
finished product
production line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610074255.1A
Other languages
Chinese (zh)
Other versions
CN105666686A (en
Inventor
叶浩文
李栋
周冲
胡游
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Technology Group Co Ltd
Original Assignee
China Construction Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Science and Technology Co Ltd filed Critical China Construction Science and Technology Co Ltd
Priority to CN201610074255.1A priority Critical patent/CN105666686B/en
Publication of CN105666686A publication Critical patent/CN105666686A/en
Application granted granted Critical
Publication of CN105666686B publication Critical patent/CN105666686B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses a kind of reinforcing bar production and supply system for being used to produce precast concrete, including:Reinforcing steel bar production line, it is extends laterally, and reinforcing steel bar production line has two to ranked first reinforcing bar finished product area in position in the outer part, and often ranked first reinforcing bar finished product area has the multiple first reinforcing bar finished product areas for being used for depositing the first steel reinforcement cage;Two groups of KBK cranes;Wherein, two precast concrete wall panel production lines extend transversely, and are respectively arranged in the both sides of reinforcing steel bar production line;Each precast concrete wall panel production line includes multiple the first stations for being used to for the first steel reinforcement cage to be installed on die station, and the first station and the first reinforcing bar finished product area correspond;One KBK crane is arranged in a manner of reciprocally between the first station to correspond to each other and the first reinforcing bar finished product area.The reinforcing bar production and supply system of the present invention, which is realized, supplies the high efficiency of precast concrete wall panel production line, and invention also improves the production efficiency of reinforcing steel bar production line itself.

Description

A kind of reinforcing bar production and supply system for being used to produce precast concrete
Technical field
The invention belongs to precast concrete production technical field, more particularly to one kind to be used to produce precast concrete structure The reinforcing bar production and supply system of part.
Background technology
Architectural industrialization theory using novel building industrialization as one of main contents is just obtaining extensively in residential housing field General popularization, prefabricated concrete structure are also gradually concerned as a kind of form of industrialized building structure.According to different Prefabricated concrete structure, the product design system of concrete structure can be related to prefabricated inside and outside wall board, precast floor slab, prefabricated sun Platen, prefabricated air-conditioning plate, prefabricated cladding panel and prefabricated beam column etc. PC components (i.e. precast concrete) product.Different is prefabricated In component, the form of configuration reinforcement distinguishes larger, steel in the two-dimensional elements such as prefabricated inner-outer wall, prefabricated balcony plate and prefabricated air-conditioning plate Muscle mainly with double-layer double-direction reinforced mesh by stirrup, lacing wire formed steel reinforcement cage based on, reinforcing bar in the one-dimensional component such as prefabricated beam column Mainly based on the straight line steel bar with crotch and stirrup, lacing wire formation steel reinforcement cage.
The important component that the process layout of PC components factory produces as PC components, the production effect to prefabricated components Rate serves decisive role.PC components factory is typically made up of PC components production line, reinforcing steel bar production line and mixing plant, PC structures Each bar production line needs mixing plant to supply concrete, reinforcing bar production equipment supply finished product or rerolled steel in the production process of part The supply mode of muscle, wherein concrete and position, the mode of reinforcing bar supply and position are the most heavy of influence PC component production efficiencys The factor wanted.Every production line is intended to that most short supply time can be obtained and meets the supply of production, therefore rational deployment Position of the reinforcing steel bar production line in whole PC process layouts figure, ensure that every production line has the confession of optimal concrete and reinforcing bar It should be related to, be the precondition that PC components factory can efficiently produce.And the efficient production of reinforcing steel bar production line depends on raw material of reinforcement rebar Can fast transport to each reinforcing bar production equipment, the finished product of each equipment production and semi-finished product reinforcing bar fast transport and each The position of reinforcing bar production equipment whether reasonable Arrangement.Therefore, rationally set transport channel and the finished product transport of raw material of reinforcement rebar logical Road and the position of arrangement reinforcing bar production equipment are most important to the production efficiency of reinforcing bar.
The content of the invention
For above-mentioned technical problem, the invention provides a kind of reinforcing bar production for being used to produce precast concrete and supply System is answered, the system layout is reasonable, improves the production efficiency of precast concrete.
Technical scheme provided by the invention is:
A kind of reinforcing bar production and supply system for being used to produce precast concrete, it is used for prefabricated mixed at least two Solidifying native component production line supply reinforcing bar finished product, including:
Reinforcing steel bar production line, it is extends laterally, and the reinforcing steel bar production line has two to ranked first steel in position in the outer part Muscle finished product area, often ranked first reinforcing bar finished product area has the multiple first reinforcing bar finished product areas for being used for depositing the first steel reinforcement cage;
Two groups of KBK cranes;
Wherein, the precast concrete member production line includes two precast concrete wall panel production lines, and two prefabricated mixed Solidifying cob wall board assembly line extends transversely, and is respectively arranged in the both sides of the reinforcing steel bar production line;Each pre-cast concrete walling Board assembly line includes multiple the first stations for being used to for the first steel reinforcement cage to be installed on die station, each precast concrete wall panel production line pair Ying Yuyi ranked first reinforcing bar finished product area, and the first station and the first reinforcing bar finished product area correspond;Each pre-cast concrete walling Board assembly line corresponds to one group of KBK crane, and a KBK crane is arranged at what is corresponded to each other in a manner of reciprocally Between first station and the first reinforcing bar finished product area, the KBK cranes are used for first steel reinforcement cage of the first reinforcing bar finished product area It is delivered to the first station.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, including:
Control device, it is used to control two groups of KBK cranes to work in the following manner:Every group of KBK crane is at interval of pre- Fix time and be spaced while work, first steel reinforcement cage of corresponding first reinforcing bar finished product area is delivered to corresponding prefabricated mixed First station of solidifying cob wall board assembly line, the predetermined time interval A are designed as:A=B+C, wherein, B represents the concrete The first steel reinforcement cage is installed on die station on one the first station of cob wall board assembly line and formed shared by an operation product Activity duration, C represent operation product on all first stations of the precast concrete wall panel production line with the concrete Continuously running for cob wall board assembly line and all leave time shared by the first station.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, two prefabricated Concrete walls board assembly line includes an exterior wall board assembly line and an interior wall board assembly line.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, the reinforcing bar The tail end of production line and there is the second reinforcing bar finished product area, the second reinforcing bar finished product area close to the side of the exterior wall board assembly line The first reinforced mesh of exterior wall siphonal lobe is made for depositing, the tail end of the exterior wall board assembly line, which has, to be used to install the first reinforcing bar The second station of mesh sheet;First transfer passage is longitudinally disposed at outside and the Side fascia life of the tail end of the reinforcing steel bar production line The outside of the tail end of producing line, the second station is extended to from the second reinforcing bar finished product area, by the first reinforced mesh from institute State the second reinforcing bar finished product area and be delivered to the second station.
Preferably, it is described to be used to producing in the reinforcing bar production and supply system of precast concrete, it is described at least Two precast concrete member production lines also include an overlapping board assembly line and a fixed die station production line, the superimposed sheet Production line is laterally set, and is disposed therein the outside of a precast concrete wall panel production line, and the fixed die station production line is horizontal To setting, and it is arranged in the outside of another precast concrete wall panel production line.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, the reinforcing bar The head end of production line, there is the 3rd reinforcing bar finished product area, the 3rd reinforcing bar finished product close to the side of the overlapping board assembly line Area is used to deposit the second reinforced mesh for making steel bar girder;The outside of the head end of the overlapping board assembly line has steel bar girder Production equipment, wherein, the steel bar girder production equipment is used to produce steel bar girder and supplies institute to the overlapping board assembly line State steel bar girder;Second transfer passage is longitudinally disposed at outside and the steel bar girder production of the head end of the reinforcing steel bar production line The outside of equipment, the steel bar girder production equipment is extended to from the 3rd reinforcing bar finished product area, by second bar-mat reinforcement Piece is delivered to the steel bar girder production equipment.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, the reinforcing bar Also there is the 4th reinforcing bar finished product area and the 5th reinforcing bar finished product area near truss production equipment, wherein, the 4th reinforcing bar finished product Area is used to deposit second reinforced mesh, and the 5th reinforcing bar finished product area is used to deposit the steel bar girder, the 5th steel Muscle finished product area is located at the position of the head end close to the overlapping board assembly line.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, the reinforcing bar The head end of production line, the side of the close fixed die station production line have the 6th reinforcing bar finished product area, the 6th reinforcing bar finished product Area is used to deposit the second steel reinforcement cage for making die station;3rd transfer passage is longitudinally disposed at the outer of the head end of the reinforcing steel bar production line The outside of the head end of side and the fixed die station production line, the fixed die station production line is extended to from the reinforcing steel bar production line, So that second steel reinforcement cage is delivered into the fixed die station production line from the reinforcing steel bar production line.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, the reinforcing bar Production line, which also has, two ranked first reinforcing bar colligation area, often ranked first reinforcing bar colligation area and has and multiple is used to make the first steel reinforcement cage First reinforcing bar colligation area, it often ranked first reinforcing bar colligation area and be set in parallel in an inner side that ranked first reinforcing bar finished product area, described first Reinforcing bar colligation area corresponds with the first reinforcing bar finished product area, and each first reinforcing bar colligation area is used to make the first steel reinforcement cage simultaneously The first steel reinforcement cage is supplied to corresponding first reinforcing bar finished product area.
Preferably, in the described reinforcing bar production and supply system for being used to produce precast concrete, the reinforcing bar Production line also includes:
For depositing the first raw material area of the first armature wire, it is arranged in the side in the first reinforcing bar colligation area, and Positioned at the side of the tail end close to the reinforcing steel bar production line;
For by the concrete-bar straightening-cutting machine of the first armature wire straightening, it is attached that it is arranged in the first raw material area Closely;
For depositing the second raw material area of reinforcing bar bar, it is arranged in the side in the first reinforcing bar colligation area, and is located at Close to the side of the tail end of the reinforcing steel bar production line;
For the bar steel shearing equipment sheared to the reinforcing bar bar, it is attached that it is arranged in the second raw material area Closely;
For the steel bar bending device bent to the reinforcing bar bar after shearing, it is arranged in the bar steel shearing Near equipment;
For the first armature wire after straightening to be fabricated into the first reinforced mesh and for by bar reinforcement after bending Material is fabricated to the steel bar welding net production equipment of the second reinforced mesh, and it is arranged in the concrete-bar straightening-cutting machine and the reinforcing bar is curved Near bent equipment, and the steel bar welding net production equipment is arranged in described two and ranked first near reinforcing bar colligation area, with to two rows First reinforcing bar colligation area supplies the second reinforced mesh for making the first steel reinforcement cage;
For depositing the 3rd raw material area of the second armature wire, it is arranged in the opposite side in the first reinforcing bar colligation area, And positioned at the side of the head end close to the reinforcing steel bar production line;
For making the second reinforcing bar colligation area of the second steel reinforcement cage, it is arranged in parallel in the inner side of the 6th reinforcing bar finished product area, And with the 6th reinforcing bar finished product area alignment;And
For second armature wire to be fabricated into stirrup and the stirrup bender of lacing wire, it is arranged in two and ranked first reinforcing bar Between colligation area and the second reinforcing bar colligation area, to be supplied to the first reinforcing bar colligation area and the second reinforcing bar colligation area for making The stirrup of first steel reinforcement cage and lacing wire.
The invention has the advantages that:
Reinforcing bar production and supply system of the present invention is used to supply at least two precast concrete member production lines Reinforcing bar finished product, specifically reinforcing steel bar production line have two to ranked first reinforcing bar finished product area, two precast concretes in position in the outer part Wallboard production line is arranged in parallel in the both sides of reinforcing steel bar production line, and the first steel reinforcement cage is installed on by the first reinforcing bar finished product area with being used for First station of die station corresponds, and sets a KBK to rise between the first station to correspond to each other and the first reinforcing bar finished product area Heavy-duty machine, the first steel reinforcement cage is delivered to the first station using KBK cranes, to realize the height to precast concrete wall panel production line Efficiency is supplied.The present invention will give birth in precast concrete member production line to the maximum precast concrete wall panel of reinforcing bar product demand amount Producing line is arranged in the both sides of reinforcing steel bar production line, and the conveying of shortest path is carried out using KBK cranes, greatly improves prefabricated mixed The production efficiency of solidifying cob wall board assembly line.
The present invention also arranges overlapping board assembly line and fixed die station again in the outside of two precast concrete member production lines Production line, and rational deployment is carried out to the reinforcing bar products storage position required for each precast concrete member production line, to improve To the efficiency of overlapping board assembly line and fixed die station production line supply reinforcing bar finished product.
Each production equipment and raw material area of the present invention also to reinforcing steel bar production line itself carry out rational deployment, so as to improve reinforcing bar The production efficiency of production line itself.
Brief description of the drawings
Fig. 1 is the structural representation of reinforcing bar production and supply system of the present invention.
Fig. 2 is the structural representation of reinforcing steel bar production line of the present invention.
Embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings, to make those skilled in the art with reference to specification text Word can be implemented according to this.
As depicted in figs. 1 and 2, the present invention provides a kind of reinforcing bar production and supply system for being used to produce precast concrete System, it is used to supply reinforcing bar finished product at least two precast concrete member production lines, including:Reinforcing steel bar production line 1, it is laterally Extension, and the reinforcing steel bar production line 1 has in position in the outer part and two ranked first reinforcing bar finished product area 2,5, often ranked first reinforcing bar into Product area has the multiple first reinforcing bar finished product areas for being used for depositing the first steel reinforcement cage;Two groups of KBK cranes 7,8;Wherein, it is described prefabricated Concrete component production line includes two precast concrete wall panel production lines 10,11, two precast concrete wall panel production lines 10, 11 extend transversely, and are respectively arranged in the both sides of the reinforcing steel bar production line 1;Each precast concrete wall panel production line includes Multiple the first stations 6,9 for being used to for the first steel reinforcement cage to be installed on die station, each precast concrete wall panel production line correspond to a row First reinforcing bar finished product area, and the first station and the first reinforcing bar finished product area correspond;Each precast concrete wall panel production line Corresponding to one group of KBK crane, and a KBK crane is arranged at the first station to correspond to each other in a manner of reciprocally And first between reinforcing bar finished product area, the KBK cranes are used to first steel reinforcement cage of the first reinforcing bar finished product area being delivered to the One station.
In all precast concrete member production lines, demand of the precast concrete wall panel production line to reinforcing bar finished product Maximum, therefore, in order to meet the production requirement of precast concrete wall panel production line, improve the production effect of precast concrete wall panel Rate, and two precast concrete wall panel production lines are arranged in parallel in the both sides of reinforcing steel bar production line, and be used in the first steel Muscle cage is installed on the first station of die station and the first reinforcing bar finished product area for depositing the first steel reinforcement cage corresponds, right each other One KBK crane is set between the first station answered and the first reinforcing bar finished product area.So ensure that reinforcing steel bar production line and prefabricated The fed distance of the first steel reinforcement cage is most short between concrete walls board assembly line, so as to improve the production of precast concrete wall panel effect Rate.
Specifically, the first reinforcing bar finished product area depends on the number of the first station, and the number of the first station is depending on prefabricated The subsequent work stations of the productive temp of concrete walls board assembly line, the production capacity of precast concrete wall panel production line and the first station Operating efficiency.
The job content of first station is that the first steel reinforcement cage is installed on into die station, and the job content belongs to existing pre- A link in concrete walls board assembly line processed, will not be repeated here.
Above-mentioned two precast concrete wall panel 10,11 can be interior wall board assembly line and exterior wall board assembly line, can also be Two interior wall board assembly lines, or two exterior wall board assembly lines.
In one embodiment, the described reinforcing bar production and supply system for being used to produce precast concrete, including: Control device, it is used to control two groups of KBK cranes 7,8 to work in the following manner:Every group of KBK crane is at interval of the scheduled time Interval is worked simultaneously, and first steel reinforcement cage of corresponding first reinforcing bar finished product area is delivered into corresponding pre-cast concrete walling First station of board assembly line, the predetermined time interval A are designed as:A=B+C, wherein, B represents the precast concrete wall panel When the first steel reinforcement cage being installed on into die station on one the first station of production line and forming the operation shared by an operation product Between, C represents operation product on all first stations of the precast concrete wall panel production line with the precast concrete wall panel Continuously running for production line and all leave time shared by the first station.
In this embodiment, in order to further improve the production efficiency of precast concrete wall panel production line, corresponding to same One group of KBK crane of precast concrete wall panel production line needs to cooperate, specifically, i.e., at interval of predetermined time interval Simultaneously from hanged first steel reinforcement cage in the first reinforcing bar finished product area, and first steel reinforcement cage is delivered to the first station.It is described pre- Fix time interval A calculation formula be A=B+C.Wherein B is represented the first steel reinforcement cage on first station loaded on die station and shape Into the activity duration shared by an operation product, due to being to carry out operation simultaneously on multiple first stations, therefore, to pre- Interval fix time when being calculated, only calculates one of them activity duration.C represents all first works of the precast concrete wall panel Operation product on position all leaves the time shared by the first work, i.e., when all first stations while completes operation, then With continuously running for precast concrete wall panel production line, these operation products can be transported to leave the first station, and enter one by one Enter the subsequent work stations of the first station, when all operation products all leave the first station, the first all stations enters vacant State, this group of KBK crane can continue hanged first steel reinforcement cage to the first station, to ensure that precast concrete wall panel produces The continuous production of line.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, two Individual precast concrete wall panel production line 10,11 includes an exterior wall board assembly line 10 and an interior wall board assembly line 11.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, institute State the tail end of reinforcing steel bar production line 1 and there is the second reinforcing bar finished product area 14 in the side of the close exterior wall board assembly line 10, second Reinforcing bar finished product area 14 is used to deposit the first reinforced mesh for making exterior wall siphonal lobe, and the tail end of the exterior wall board assembly line 10, which has, to be used In the second station 15 for installing the first reinforced mesh;First transfer passage 16 is longitudinally disposed at the tail end of the reinforcing steel bar production line 1 Outside and the exterior wall board assembly line 10 tail end outside, extend to second work from the second reinforcing bar finished product area 14 Position 15, the second station is delivered to by the first reinforced mesh from the second reinforcing bar finished product area.
When a precast concrete wall panel production line is exterior wall board assembly line wherein, reinforcing steel bar production line is except will be to exterior wall Board assembly line supplies the first steel reinforcement cage, also to supply the first reinforced mesh for making exterior wall siphonal lobe.Specifically, will be used to deposit The the second reinforcing bar finished product area 14 for putting the first reinforced mesh is arranged in the tail end of reinforcing steel bar production line 1, and because reinforcing steel bar production line 1 is vertical There is certain span upwards, therefore, the second reinforcing bar finished product area 14 is also arranged in one close to exterior wall board assembly line 15 Side, to shorten the fed distance of the first reinforced mesh as far as possible.First transfer passage 16 extends on the outside of the tail end of reinforcing steel bar production line 1 To the tail end of exterior wall board assembly line 10, it is possible to achieve the most efficiently conveying to the first reinforced mesh.First conveying Passage 16 can be the road for being available for haulage vehicle to travel or be moved along it for lifting appliance, be set up in factory building half Empty track.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, institute Stating at least two precast concrete member production lines also includes an overlapping board assembly line 13 and a fixed die station production line 12, The overlapping board assembly line 13 is laterally set, and is disposed therein the outside of a precast concrete wall panel production line, the fixation Die station production line 12 is laterally set, and is arranged in the outside of another precast concrete wall panel production line.
The reinforcing steel bar production line of the embodiment is also to overlapping board assembly line and fixed die station production line supply reinforcing bar finished product.Consider Reinforcing bar product demand amount to overlapping board assembly line 13 and fixed die station production line 12 will be much smaller than precast concrete production Line, therefore, board assembly line will be overlapped and fixed die station production line is arranged in the outer of two precast concrete member production lines Side.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, institute State the head end of reinforcing steel bar production line 1, there is the 3rd reinforcing bar finished product area 20 close to the side of the overlapping board assembly line 13, described the Three reinforcing bar finished product areas 20 are used to deposit the second reinforced mesh for making steel bar girder;Outside the head end of the overlapping board assembly line 13 Side has steel bar girder production equipment 17, wherein, the steel bar girder production equipment 17 is used to produce steel bar girder and to described Overlapping board assembly line 13 supplies the steel bar girder;Second transfer passage 21 is longitudinally disposed at the head end of the reinforcing steel bar production line 1 Outside and the steel bar girder production equipment 17 outside, extend to the steel bar girder from the 3rd reinforcing bar finished product area 20 Production equipment 17, second reinforced mesh is delivered to the steel bar girder production equipment.
The embodiment will be arranged in the head of reinforcing steel bar production line 1 for depositing the 3rd reinforcing bar finished product area 20 of the second reinforced mesh End;Because reinforcing steel bar production line 1 has certain span in the vertical, produced to further reduce the second reinforced mesh to superimposed sheet The fed distance of line, the 3rd reinforcing bar finished product area is disposed adjacent to overlap to the side of board assembly line.The longitudinal direction of second transfer passage 21 Be arranged on the outside of the head end of reinforcing steel bar production line 1 and the outside of steel bar girder production equipment 17, i.e. the second reinforced mesh directly by Second transfer passage is delivered to steel bar girder production equipment from the 3rd reinforcing bar finished product area, and transport path is most short.Wherein, this is second defeated Send passage can be the road for being available for haulage vehicle to travel or be moved along it for lifting appliance, be set up in factory building half Empty track.
Furthermore, it is contemplated that the space layout of factory building, farthest using the space in factory building, and it is all in factory building In production line, only overlapping board assembly line needs steel bar girder, therefore steel bar girder production equipment is individually arranged in into superimposed sheet The outside of the head end of production line.So it is also ensured that the steel bar girder that steel bar girder production equipment is produced can be directly by short The equipment such as the crane of distance transport are delivered to overlapping board assembly line.
Specifically, steel bar girder production equipment 17 can be digital control steel bar truss-welding production lines.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, institute Stating also has the 4th reinforcing bar finished product area 18 and the 5th reinforcing bar finished product area 19 near steel bar girder production equipment 17, wherein, it is described 4th reinforcing bar finished product area 18 is used to deposit second reinforced mesh, and the 5th reinforcing bar finished product area 19 is used to deposit the reinforcing bar Truss, the 5th reinforcing bar finished product area 19 are located at the position of the head end close to the overlapping board assembly line 13.
In this embodiment, it is contemplated that steel bar girder production equipment and the productive temp of overlapping board assembly line will not complete one Cause, therefore, the 4th reinforcing bar finished product area 18 and the 5th reinforcing bar finished product area are also arranged in the outside of the head end of overlapping board assembly line 13 19, wherein, the 4th reinforcing bar finished product area 18 is used to deposit the second reinforced mesh, i.e., the by the conveying of the 3rd reinforcing bar finished product area 20 to be come Two reinforced mesh can be deposited in formerly herein, and the 5th reinforcing bar finished product area 19 is then used to deposit to be produced by steel bar girder production equipment The steel bar girder gone out, it is further according to the productive temp of overlapping board assembly line that the steel bar girder for depositing in the 5th reinforcing bar finished product area 19 is defeated Deliver to overlapping board assembly line.5th reinforcing bar finished product area 19 is located at the position of the head end close to overlapping board assembly line 13, ensures reinforcing bar The fed distance of truss to overlapping board assembly line is most short.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, institute State the head end of reinforcing steel bar production line 1, there is the 6th reinforcing bar finished product area 22 close to the side of the fixed die station production line 12, described the Six reinforcing bar finished product areas 22 are used to deposit the second steel reinforcement cage for making die station;3rd transfer passage 23 is longitudinally disposed at the reinforcing bar life The outside of the head end of the outside of the head end of producing line 1 and the fixed die station production line 12, institute is extended to from the reinforcing steel bar production line 1 Fixed die station production line 12 is stated, second steel reinforcement cage is delivered into the fixed die station from the reinforcing steel bar production line produces Line.
In the embodiment, in order to ensure that the fed distance of the second steel reinforcement cage to fixed die station production line is most short, it will be used to deposit The 6th reinforcing bar finished product area 22 for putting the second steel reinforcement cage is arranged in the head end of reinforcing steel bar production line 1, and close to fixed die station production line 12 Side.3rd transfer passage 23 is longitudinally disposed at the outside of the head end of reinforcing steel bar production line and fixes the outer of die station production line Side, the second steel reinforcement cage is delivered to fixed die station production line.Wherein, the 3rd transfer passage 23 can be available for haulage vehicle The road of traveling or be moved along it for lifting appliance, the track that is set up in factory building in midair.Also, due to the 3rd defeated Send passage and the second transfer passage to be located at the homonymy of reinforcing steel bar production line, therefore, in order to build and means of transport operation convenience, 3rd transfer passage 23 and the second transfer passage 21 can be designed to an entirety.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, institute State reinforcing steel bar production line 1 and also have and two ranked first reinforcing bar colligation area 3,4, often ranked first reinforcing bar colligation area and have and multiple be used to making the First reinforcing bar colligation area of one steel reinforcement cage, often ranked first reinforcing bar colligation area and is set in parallel in one and ranked first the interior of reinforcing bar finished product area Side, the first reinforcing bar colligation area correspond with the first reinforcing bar finished product area, and each first reinforcing bar colligation area is used to make First steel reinforcement cage simultaneously supplies the first steel reinforcement cage to corresponding first reinforcing bar finished product area.
Because the first steel reinforcement cage is a kind of larger reinforcing bar finished product of yield of reinforcing steel bar production line, in order to ensure the first steel reinforcement cage Production efficiency, also at utmost shortening the fed distance of the first steel reinforcement cage for just having produced to the first reinforcing bar finished product area, To be arranged on the inner side of the first reinforcing bar finished product area for making the first reinforcing bar colligation area of the first steel reinforcement cage, and with the first reinforcing bar Finished product area is corresponded, and each first steel reinforcement cage one is produced, and will be transferred to the first reinforcing bar finished product area.Above-mentioned transfer Process can be by artificial lift (because the first reinforcing bar colligation area and the first reinforcing bar finished product area are apart from close, spent by artificial lift Time and manpower be still very little), can also be conveyed by lifting appliance.
In one embodiment, in the described reinforcing bar production and supply system for being used to produce precast concrete, institute Stating reinforcing steel bar production line also includes:For depositing the first raw material area 26 of the first armature wire, it is arranged in first reinforcing bar and tied up Zha Qu side, and positioned at the side of the tail end close to the reinforcing steel bar production line 1;For by the first armature wire straightening Concrete-bar straightening-cutting machine 27, it is arranged near the first raw material area 26;For depositing the second raw material area 29 of reinforcing bar bar, It is arranged in the side in the first reinforcing bar colligation area, and positioned at the side of the tail end close to the reinforcing steel bar production line 1;For right The bar steel shearing equipment 30 that the reinforcing bar bar is sheared, it is arranged near the second raw material area 29;For right The steel bar bending device 31 that reinforcing bar bar after shearing is bent, it is arranged near the bar steel shearing equipment 30; For the first armature wire after straightening to be fabricated into the first reinforced mesh and for reinforcing bar bar after bending to be fabricated to The steel bar welding net production equipment 28 of second reinforced mesh, it is arranged in the concrete-bar straightening-cutting machine 27 and the bar bending is set Near standby 31, and the steel bar welding net production equipment 28 is arranged in described two and ranked first near reinforcing bar colligation area, with to two rows First reinforcing bar colligation area 3,4 supplies the second reinforced mesh for making the first steel reinforcement cage;For depositing the second armature wire 3rd raw material area 24, it is arranged in the opposite side in the first reinforcing bar colligation area, and positioned at the head close to the reinforcing steel bar production line 1 The side at end;For making the second reinforcing bar colligation area 32 of the second steel reinforcement cage, it is arranged in parallel in the 6th reinforcing bar finished product area 22 Inner side, and with the alignment of the 6th reinforcing bar finished product area 22;And for by second armature wire be fabricated to stirrup and The stirrup bender 25 of lacing wire, be arranged in two and ranked first between reinforcing bar colligation area 3,4 and the second reinforcing bar colligation area 32, with to First reinforcing bar colligation area and the second reinforcing bar colligation area supply the stirrup and lacing wire for making the first steel reinforcement cage.
The embodiment is also designed and improved to the layout of reinforcing steel bar production line, to improve the production of reinforcing steel bar production line itself Efficiency.
Due to being arranged in the tail end of reinforcing steel bar production line 1 for depositing the second reinforcing bar finished product area 14 of the first reinforced mesh, because This, in order to improve production efficiency, is easy to production equipment to draw materials nearby and is produced, for making the raw material of the first reinforced mesh And production equipment is arranged at the side for the tail end for being closer to reinforcing steel bar production line.As shown in Fig. 2 the tail from reinforcing steel bar production line End is inwardly sequentially distributed the first raw material area 26 for the first armature wire of storage, carries out straightening processing to the first armature wire Concrete-bar straightening-cutting machine 27 and steel bar welding net for the first armature wire after straightening to be fabricated to the first reinforced mesh Production equipment 28, the first reinforced mesh produced deposit in the second reinforcing bar finished product area nearby.
Because steel bar welding net production equipment is in addition to the first reinforced mesh is produced, also producing the second reinforced mesh, (this second Reinforced mesh is for making the first steel reinforcement cage), in order that steel bar welding net production equipment 28 can just proximad the first reinforcing bar be tied up Zha Qu supplies the second reinforced mesh, and steel bar welding net production equipment is arranged near the first reinforcing bar colligation area.
Meanwhile as shown in Fig. 2 from the tail end of reinforcing steel bar production line inwardly there also is provided successively for deposit reinforcing bar bar Two raw material areas 29, for the bar steel shearing equipment 30 to reinforcing bar bar material cutting and to after shearing reinforcing bar bar carry out it is curved Bent steel bar bending device 31.And in order that steel bar welding net production equipment 28 can be got nearby makes the second reinforced mesh Material, steel bar welding net production equipment 28 is also located near steel bar bending device.Specifically, steel bar welding net production equipment can be with It is digital control steel bar weldering net production line, bar steel shearing equipment can be bar steel shear line, and steel bar bending device can be Bar bending center.
Fig. 2 is please seen again, and the 3rd original for depositing the second armature wire is there also is provided on the right side of the first reinforcing bar colligation area Expect area 24 and make stirrup and the stirrup bender 25 of lacing wire using second armature wire.The two is close to arrangement, with side Just stirrup bender feeding.Because stirrup bender 25 is needed to the second reinforcing bar colligation area and the first reinforcing bar colligation area supply stirrup And lacing wire, to ensure efficiency of supply, shorten fed distance, stirrup bender is arranged at the second reinforcing bar colligation area and the first reinforcing bar Between colligation area.
Second reinforcing bar colligation area 32 is used to make second steel reinforcement cage relevant with die station, in order that the second steel reinforcement cage is to the 6th The fed distance of reinforcing bar finished product area is most short, the second reinforcing bar colligation area and the 6th reinforcing bar finished product area alignment.
An axial transport passage 33 is also arranged in the centre of reinforcing steel bar production line, with transporting raw materials, reinforcing bar semi-finished product or Reinforcing bar finished product.
In the present invention, for ease of description, present invention employs " head end of reinforcing steel bar production line " or " tail of reinforcing steel bar production line The describing mode at end ", " head end " and " tail end " can be interpreted as the right-hand end of the reinforcing steel bar production line in Fig. 1 and Fig. 2 respectively Portion and the left end of reinforcing steel bar production line, but it is not meant to that technical scheme can only be realized in the above described manner.
Although embodiment of the present invention is disclosed as above, it is not restricted in specification and embodiment listed With it can be applied to various suitable the field of the invention completely, can be easily for those skilled in the art Other modification is realized, therefore under the universal limited without departing substantially from claim and equivalency range, it is of the invention and unlimited In specific details and shown here as the legend with description.

Claims (10)

1. a kind of reinforcing bar production and supply system for being used to produce precast concrete, it is used at least two concretes Native component production line supplies reinforcing bar finished product, it is characterised in that including:
Reinforcing steel bar production line, it is extends laterally, and the reinforcing steel bar production line respectively has one to ranked first reinforcing bar on both sides in the outer part Finished product area, often ranked first reinforcing bar finished product area has the multiple first reinforcing bar finished product areas for being used for depositing the first steel reinforcement cage;
Two groups of KBK cranes;
Wherein, the precast concrete member production line includes two precast concrete wall panel production lines, two precast concretes Wallboard production line extends transversely, and is respectively arranged in the both sides of the reinforcing steel bar production line;Each precast concrete wall panel life Producing line includes multiple the first stations for being used to for the first steel reinforcement cage to be installed on die station, and each precast concrete wall panel production line corresponds to One ranked first reinforcing bar finished product area, and the first station and the first reinforcing bar finished product area correspond;Each precast concrete wall panel life Producing line corresponds to one group of KBK crane, and a KBK crane is arranged at first to correspond to each other in a manner of reciprocally Between station and the first reinforcing bar finished product area, the KBK cranes are used to convey first steel reinforcement cage of the first reinforcing bar finished product area To the first station.
2. the reinforcing bar production and supply system as claimed in claim 1 for being used to produce precast concrete, it is characterised in that Including:
Control device, it is used to control two groups of KBK cranes to work in the following manner:Every group of KBK crane is at interval of pre- timing Between be spaced and work simultaneously, first steel reinforcement cage of corresponding first reinforcing bar finished product area is delivered to corresponding precast concrete First station of wallboard production line, the predetermined time interval A are designed as:A=B+C, wherein, B represents the pre-cast concrete walling The first steel reinforcement cage is installed on die station on one the first station of board assembly line and forms the operation shared by an operation product Time, C represent operation product on all first stations of the precast concrete wall panel production line with the pre-cast concrete walling Continuously running for board assembly line and all leave time shared by the first station.
3. the reinforcing bar production and supply system as claimed in claim 1 or 2 for being used to produce precast concrete, its feature exist In two precast concrete wall panel production lines include an exterior wall board assembly line and an interior wall board assembly line.
4. the reinforcing bar production and supply system as claimed in claim 3 for being used to produce precast concrete, it is characterised in that The tail end of the reinforcing steel bar production line and there is the second reinforcing bar finished product area, the second steel close to the side of the exterior wall board assembly line Muscle finished product area is used to deposit the first reinforced mesh for making exterior wall siphonal lobe, and the tail end of the exterior wall board assembly line, which has, to be used to install The second station of first reinforced mesh;First transfer passage is longitudinally disposed at the outside of the tail end of the reinforcing steel bar production line and described The outside of the tail end of exterior wall board assembly line, the second station is extended to from the second reinforcing bar finished product area, by the first reinforcing bar Mesh sheet is delivered to the second station from the second reinforcing bar finished product area.
5. the reinforcing bar production and supply system as claimed in claim 4 for being used to produce precast concrete, it is characterised in that At least two precast concrete member production line also includes an overlapping board assembly line and a fixed die station production line, institute State overlapping board assembly line laterally to set, be disposed therein the outside of a precast concrete wall panel production line, the fixed die station Production line is laterally set, and is arranged in the outside of another precast concrete wall panel production line.
6. the reinforcing bar production and supply system as claimed in claim 5 for being used to produce precast concrete, it is characterised in that The head end of the reinforcing steel bar production line, there is the 3rd reinforcing bar finished product area close to the side of the overlapping board assembly line, the described 3rd Reinforcing bar finished product area is used to deposit the second reinforced mesh for making steel bar girder;The outside of the head end of the overlapping board assembly line has Steel bar girder production equipment, wherein, the steel bar girder production equipment is used to produce steel bar girder and produced to the superimposed sheet Line supplies the steel bar girder;Second transfer passage is longitudinally disposed at the outside of the head end of the reinforcing steel bar production line and the reinforcing bar The outside of truss production equipment, the steel bar girder production equipment is extended to from the 3rd reinforcing bar finished product area, by described Two reinforced mesh are delivered to the steel bar girder production equipment.
7. the reinforcing bar production and supply system as claimed in claim 6 for being used to produce precast concrete, it is characterised in that Also there is the 4th reinforcing bar finished product area and the 5th reinforcing bar finished product area near the steel bar girder production equipment, wherein, the described 4th Reinforcing bar finished product area is used to deposit second reinforced mesh, and the 5th reinforcing bar finished product area is used to deposit the steel bar girder, institute State the position that the 5th reinforcing bar finished product area is located at the head end close to the overlapping board assembly line.
8. the reinforcing bar production and supply system as claimed in claim 5 for being used to produce precast concrete, it is characterised in that The head end of the reinforcing steel bar production line, close to the side of the fixed die station production line there is the 6th reinforcing bar finished product area, the described 6th Reinforcing bar finished product area is used to deposit the second steel reinforcement cage for making die station;3rd transfer passage is longitudinally disposed at the reinforcing steel bar production line The outside of the head end of the outside of head end and the fixed die station production line, the fixed die station is extended to from the reinforcing steel bar production line Production line, second steel reinforcement cage is delivered to the fixed die station production line from the reinforcing steel bar production line.
9. the reinforcing bar production and supply system as claimed in claim 8 for being used to produce precast concrete, it is characterised in that The reinforcing steel bar production line, which also has, two ranked first reinforcing bar colligation area, often ranked first reinforcing bar colligation area and has and multiple is used to make first First reinforcing bar colligation area of steel reinforcement cage, often ranked first reinforcing bar colligation area and is set in parallel in an inner side that ranked first reinforcing bar finished product area, The first reinforcing bar colligation area corresponds with the first reinforcing bar finished product area, and each first reinforcing bar colligation area is used to make first Steel reinforcement cage simultaneously supplies the first steel reinforcement cage to corresponding first reinforcing bar finished product area.
10. the reinforcing bar production and supply system as claimed in claim 9 for being used to produce precast concrete, its feature exist In the reinforcing steel bar production line also includes:
For depositing the first raw material area of the first armature wire, it is arranged in the side in the first reinforcing bar colligation area, and is located at Close to the side of the tail end of the reinforcing steel bar production line;
For by the concrete-bar straightening-cutting machine of the first armature wire straightening, it to be arranged near the first raw material area;
For depositing the second raw material area of reinforcing bar bar, it is arranged in the side in the first reinforcing bar colligation area, and positioned at close The side of the tail end of the reinforcing steel bar production line;
For the bar steel shearing equipment sheared to the reinforcing bar bar, it is arranged near the second raw material area;
For the steel bar bending device bent to the reinforcing bar bar after shearing, it is arranged in the bar steel shearing equipment Near;
For the first armature wire after straightening to be fabricated into the first reinforced mesh and for by reinforcing bar bar system after bending The steel bar welding net production equipment of the second reinforced mesh is made, it is arranged in the concrete-bar straightening-cutting machine and the bar bending is set Near standby, and the steel bar welding net production equipment is arranged in described two and ranked first near reinforcing bar colligation area, ranked first to two Reinforcing bar colligation area supplies the second reinforced mesh for making the first steel reinforcement cage;
For depositing the 3rd raw material area of the second armature wire, it is arranged in the opposite side in the first reinforcing bar colligation area, and position In the side of the head end close to the reinforcing steel bar production line;
For making the second reinforcing bar colligation area of the second steel reinforcement cage, it is arranged in parallel in the inner side of the 6th reinforcing bar finished product area, and with 6th reinforcing bar finished product area alignment;And
For second armature wire to be fabricated into stirrup and the stirrup bender of lacing wire, it is arranged in two and ranked first reinforcing bar colligation Between area and the second reinforcing bar colligation area, to be supplied to the first reinforcing bar colligation area and the second reinforcing bar colligation area for making first The stirrup of steel reinforcement cage and lacing wire.
CN201610074255.1A 2016-02-02 2016-02-02 A kind of reinforcing bar production and supply system for being used to produce precast concrete Active CN105666686B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610074255.1A CN105666686B (en) 2016-02-02 2016-02-02 A kind of reinforcing bar production and supply system for being used to produce precast concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610074255.1A CN105666686B (en) 2016-02-02 2016-02-02 A kind of reinforcing bar production and supply system for being used to produce precast concrete

Publications (2)

Publication Number Publication Date
CN105666686A CN105666686A (en) 2016-06-15
CN105666686B true CN105666686B (en) 2018-03-27

Family

ID=56303405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610074255.1A Active CN105666686B (en) 2016-02-02 2016-02-02 A kind of reinforcing bar production and supply system for being used to produce precast concrete

Country Status (1)

Country Link
CN (1) CN105666686B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108789814B (en) * 2018-06-21 2020-02-14 江西抚州中恒管桩有限公司 Automatic manufacturing machine for cement partition plate of building sewage discharge tank
CN111496026A (en) * 2020-04-30 2020-08-07 湖南三一快而居住宅工业有限公司 Bar forming and processing system and control method thereof
CN113481865A (en) * 2021-07-26 2021-10-08 湖南中铁五新钢模有限责任公司 Construction method of reinforcement cage binding assembly line

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001322115A (en) * 2000-05-17 2001-11-20 Shimizu Corp Site factory facility
CN103660027A (en) * 2013-12-30 2014-03-26 中铁二十三局集团轨道交通工程有限公司 Automatic production process of concrete precast products
KR101434913B1 (en) * 2014-07-04 2014-08-29 삼표이앤씨 주식회사 Manufacturing device for precast concrete slab panel and manufacturing method by using manufacturing device for precast concrete slab Panel
CN104647577A (en) * 2013-11-19 2015-05-27 任丘市永基建筑安装工程有限公司 Automatic production lien for assembling type housing prefabricated panels
CN104786367A (en) * 2015-02-16 2015-07-22 中交四航局第二工程有限公司 Pipe joint prefabricating workshop
CN105082346A (en) * 2015-02-09 2015-11-25 中交第三航务工程局有限公司 Intelligent flow production line for shield segment prefabrication

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001322115A (en) * 2000-05-17 2001-11-20 Shimizu Corp Site factory facility
CN104647577A (en) * 2013-11-19 2015-05-27 任丘市永基建筑安装工程有限公司 Automatic production lien for assembling type housing prefabricated panels
CN103660027A (en) * 2013-12-30 2014-03-26 中铁二十三局集团轨道交通工程有限公司 Automatic production process of concrete precast products
KR101434913B1 (en) * 2014-07-04 2014-08-29 삼표이앤씨 주식회사 Manufacturing device for precast concrete slab panel and manufacturing method by using manufacturing device for precast concrete slab Panel
CN105082346A (en) * 2015-02-09 2015-11-25 中交第三航务工程局有限公司 Intelligent flow production line for shield segment prefabrication
CN104786367A (en) * 2015-02-16 2015-07-22 中交四航局第二工程有限公司 Pipe joint prefabricating workshop

Also Published As

Publication number Publication date
CN105666686A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN105666686B (en) A kind of reinforcing bar production and supply system for being used to produce precast concrete
CN105690552B (en) Precast concrete production system
CN85108069A (en) The improvement of prefabricated modules, and the application in construction industry
CN105382149A (en) Welding production line for reinforcing mesh
CN210820155U (en) Concrete prefabricated square pile manufacturing system
CN108699851B (en) Steel bar prefabricating and processing system
HRP20140058T1 (en) Method and machine for automatic assembly of complex cages formed from electro-welded metal nets
EP1302257A2 (en) Device to produce reinforcement metal cages and relative method
CN110287591A (en) The modular method of architectural design, manufacture, construction
CN102888957A (en) Prefabricated light slab stair
CN204382485U (en) Prefabricated components production system
CN208629675U (en) Concrete prefabricated element process units
CN105312457A (en) Reinforcing cage forming system
CN204524120U (en) The vertical loopful of large diameter pile foundation steel reinforcement cage is to location moulding bed device
CN101905488A (en) Track plate prefabrication concrete transport and distribution system
CN109719843A (en) It concrete prefabricated element production line and its pours and smashes device
WO2019183948A1 (en) Method for preparing movable steel bar
CN116851591A (en) Processing method of precast beam steel rib frame
CN202656296U (en) Concrete tubular pile production line
CN102094417B (en) Method for producing steel reinforcement cage by using setting die
CN109203211B (en) Assembly line for component compatible production
CN211447361U (en) Interior wall of prefabricated building
CN108748655A (en) A kind of mesh sheet steel reinforcement framework cage for small box girder
CN108748643A (en) A kind of intelligent production line of novel fabricated construction material
CN211007821U (en) Immersed tube prefabrication automation reinforcing bar processing production base arrangement structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant