CN105586982B - A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap - Google Patents

A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap Download PDF

Info

Publication number
CN105586982B
CN105586982B CN201410647991.2A CN201410647991A CN105586982B CN 105586982 B CN105586982 B CN 105586982B CN 201410647991 A CN201410647991 A CN 201410647991A CN 105586982 B CN105586982 B CN 105586982B
Authority
CN
China
Prior art keywords
buried steel
steel framework
screwed hole
epoxy resin
gap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410647991.2A
Other languages
Chinese (zh)
Other versions
CN105586982A (en
Inventor
陈慧娟
刘玉成
许立正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Changhe Aviation Industries Co Ltd
Original Assignee
Jiangxi Changhe Aviation Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Changhe Aviation Industries Co Ltd filed Critical Jiangxi Changhe Aviation Industries Co Ltd
Priority to CN201410647991.2A priority Critical patent/CN105586982B/en
Publication of CN105586982A publication Critical patent/CN105586982A/en
Application granted granted Critical
Publication of CN105586982B publication Critical patent/CN105586982B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention provides a kind of pre-buried steel framework of lathe and the processing method in basic faying face gap, it is characterised in that comprises the following steps:Apertured position between the faying face of pre-buried steel framework and base concrete is searched, mark is made;The two ends drilling with tagged gap position on pre-buried steel framework, drilling depth should drill through steel framework up to concrete layer, in hole the inside fire attack M8 or M10 got out screwed hole;Screwed hole is cleared up, the dust in clear opening is dried up using compressed air;Pressurization pours into epoxide-resin glue:Epoxide-resin glue pressurization is poured into one of screwed hole by pump, until overflowing epoxy resin in the screwed hole of the other end, so carried out successively;Epoxy resin adhesive curing:After perfusion, after epoxy resin adhesive curing preserving period is full, the installation of equipment can be started by clearing up pre-buried steel frame table face.

Description

A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap
Technical field
The invention belongs to equipment installing area, it is related to a kind of pre-buried steel framework of lathe and the processing method on basis.
Background technology
Pre-buried steel framework is required on the foundation drawing of some large-scale high-precision machining tools to strengthen the rigidity that its is basic.Should Not only required precision is higher for built-in fitting, and generally every meter unevenness is less than 0.2MM, and requires that pre-buried steel framework is mixed with basis The combination for coagulating soil must be closely knit, and the phenomenon such as seamless, empty, difficulty of construction is very big.We are taken using micro- swollen under normal circumstances The method of swollen cement back-grouting solves the problems, such as the combination of steel framework and base concrete.But due to civil engineering process not The incompatibility of certainty and two kinds of materials, wants to be fully achieved and requires extremely difficult.We once occurred repeatedly because of pre-buried steel There is gap and cavitation in the faying face of framework and base concrete processed and whole basis of having to is done over again.
The content of the invention
The technical problems to be solved by the invention are:Propose that one kind can rapidly repair pre-buried steel framework and be mixed with basis The gap between the faying face of soil is coagulated, unreal, cavitation method is eliminated.
The technical scheme is that:A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap, its It is characterised by, comprises the following steps:
1.1 search apertured position between the faying face of pre-buried steel framework and base concrete, make mark;
The 1.2 two ends drillings with tagged gap position on pre-buried steel framework, drilling depth should drill through steel frame Frame is up to concrete layer, in hole the inside fire attack M8 or M10 got out screwed hole;
1.3 cleaning screwed holes, the dust in clear opening is dried up using compressed air;
1.4 pressurizations pour into epoxide-resin glue:Epoxide-resin glue pressurization is poured into one of screwed hole by pump, directly Epoxy resin is overflowed in the screwed hole of the other end, is so carried out successively;
1.5 epoxy resin adhesive curings:After perfusion, after epoxy resin adhesive curing preserving period is full, pre-buried steel framework is cleared up Surface can start the installation of equipment.
Further, step 1 is specially:
After machine tool basic health expires, the method for touching pre-buried steel frame upper surface paragraph by paragraph with hand hammer checks pre-buried steel The combination situation of framework and base concrete processed, and according to hammering sound it is dull and it is clear and melodious judge its combined with machine tool basic whether It is closely knit, and mark is made to the position in gap.
Embodiment
The present invention is described in further details below, comprised the following steps that:
1.1 search apertured position between the faying face of pre-buried steel framework and base concrete, make mark:In lathe After basic health expires, the method for touching steel framework upper surface paragraph by paragraph with hand hammer checks pre-buried steel framework and base concrete Combination situation, and according to hammering sound it is dull and it is clear and melodious judge its combined with machine tool basic it is whether closely knit, to there is gap Make mark in position.
1.2 on pre-buried steel framework (two ends for having gap position) drilling, attack M8 or M10 screwed hole:For existing The position in gap, (two ends for having gap position) drilling, tapping on pre-buried steel framework, drilling depth should drill through steel framework Until concrete layer.
1.3 cleaning screwed holes:The debris in clear opening is dried up using compressed air, it is ensured that without borings, concrete in hole The impurity such as fragment, dust, floating ash.
1.4 pressurizations pour into epoxide-resin glue:Epoxide-resin glue pressurization is poured into one of screwed hole by pump, directly Epoxy resin is overflowed in the screwed hole of the other end, is so carried out successively, until all having irrigated.
To ensure that it is closely knit that pre-buried steel framework and basis are combined, forbid to vibrate during encapsulating, perfusion must continuously enter after starting OK, it is impossible to be interrupted, infusion time and is shortened as far as possible;It should be carried out during filling from side, untill being overflowed from opposite side, with profit filling Exhaust during note, reduces the formation of stomata.Meanwhile, in order that epoxide-resin glue quickly penetrates into, filled up between composition surface Pump, must be adjusted to suitable pressure by gap during encapsulating, continue ground pressure encapsulating.
1.5 epoxy resin adhesive curings:After perfusion, after epoxy resin adhesive curing preserving period is full, pre-buried steel framework is cleared up Surface can start the installation of equipment.

Claims (1)

1. a kind of pre-buried steel framework of lathe and the processing method in basic faying face gap, it is characterised in that comprise the following steps:
1.1 search apertured position between the faying face of pre-buried steel framework and base concrete, make mark, are specially: After machine tool basic health expires, the method for touching pre-buried steel frame upper surface paragraph by paragraph with hand hammer checks pre-buried steel framework and base The combination situation of plinth concrete, and according to hammering sound it is dull and it is clear and melodious judge its combined with machine tool basic it is whether closely knit and right Make mark in the position in gap;
The 1.2 two ends drillings with tagged gap position on pre-buried steel framework, it is straight that drilling depth should drill through steel framework To concrete layer, in hole the inside fire attack M8 or M10 got out screwed hole;
1.3 cleaning screwed holes, the dust in clear opening is dried up using compressed air;
1.4 pressurizations pour into epoxide-resin glue:Epoxide-resin glue pressurization is poured into one of screwed hole by pump, Zhi Daoling Epoxy resin is overflowed in the screwed hole of one end, is so carried out successively;
1.5 epoxy resin adhesive curings:After perfusion, after epoxy resin adhesive curing preserving period is full, pre-buried steel frame table face is cleared up The installation of equipment can be started.
CN201410647991.2A 2014-11-14 2014-11-14 A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap Active CN105586982B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410647991.2A CN105586982B (en) 2014-11-14 2014-11-14 A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410647991.2A CN105586982B (en) 2014-11-14 2014-11-14 A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap

Publications (2)

Publication Number Publication Date
CN105586982A CN105586982A (en) 2016-05-18
CN105586982B true CN105586982B (en) 2017-08-25

Family

ID=55926866

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410647991.2A Active CN105586982B (en) 2014-11-14 2014-11-14 A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap

Country Status (1)

Country Link
CN (1) CN105586982B (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2999126B2 (en) * 1994-07-13 2000-01-17 三菱重工業株式会社 Foundation base for installation of various machines
CN1083518C (en) * 1998-10-20 2002-04-24 安固工程股份有限公司 Quick leak-blocking technology by pouring and filling of polyurethane
CN102733411A (en) * 2012-06-26 2012-10-17 华丰建设股份有限公司 Concrete foundation for fixing mechanical equipment and construction method for concrete foundation

Also Published As

Publication number Publication date
CN105586982A (en) 2016-05-18

Similar Documents

Publication Publication Date Title
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
CN109577674A (en) A kind of metope flexure type crack repairing structure and its construction method
CN109610865A (en) A kind of ruggedized construction and its construction method of wall crazing
JP2008115584A (en) Method of reinforcing reinforced concrete structure
CN105586982B (en) A kind of pre-buried steel framework of lathe and the processing method in basic faying face gap
CN104074183A (en) Drilling and concrete injected root composite pile implanting pile structure and construction method
CN106703836A (en) Treatment method of the bedding soft soil of existing circular shield tunnel
CN107354939A (en) A kind of minor diameter static mini steel-pipe pile grouting behind shaft or drift lining construction method
CN109322621B (en) Broken layer pipe fixing and grouting method
CN105781580A (en) Tunnel crack repair method
CN105862747A (en) L-shaped joint pile manufacturing appliance
CN106639344A (en) Concrete exposed reinforcing bar and hole repairing scheme
CN108714972A (en) Ceramic tile hole opening technology
JP6485686B2 (en) Ground improvement method
CN103726487A (en) Leaking stoppage method for waterproof curtain
CN204344048U (en) Foreign matter fisher in hole
CN103882859B (en) A kind of original state of Shi Hanzhang fetches earth cast-with-pressure concrete pile and construction method thereof
CN105156017B (en) A kind of impacting with high pressure whitewashing rig for applying to collapse hole stratum and construction method
CN105220695B (en) Compact sandy-pebble layer dynamic grouting curing construction method
CN102758443A (en) Novel enclosing structure applicable to connection change between new pipes and old pipes and construction method thereof
CN204782924U (en) Gun drilling sleeve pipe check valve for grouting behind shaft and drift lining
CN103924926A (en) Fast drilling construction method of superficial gravel stratum
CN204716184U (en) Shaft mouth operation oil pipe clean environment firendly device
JP2007262894A (en) High-pressure jet mixing method
CN105113608B (en) Molds for inspection wells and method for constructing inspection wells through same

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant