CN105586978B - Soil removal and replacement stirring water-stop curtain construction method based on gravel - Google Patents

Soil removal and replacement stirring water-stop curtain construction method based on gravel Download PDF

Info

Publication number
CN105586978B
CN105586978B CN201610103716.3A CN201610103716A CN105586978B CN 105586978 B CN105586978 B CN 105586978B CN 201610103716 A CN201610103716 A CN 201610103716A CN 105586978 B CN105586978 B CN 105586978B
Authority
CN
China
Prior art keywords
construction
pile
water
stake
gravel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610103716.3A
Other languages
Chinese (zh)
Other versions
CN105586978A (en
Inventor
张生雨
白汉民
王冬生
邱太刚
温支生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201610103716.3A priority Critical patent/CN105586978B/en
Publication of CN105586978A publication Critical patent/CN105586978A/en
Application granted granted Critical
Publication of CN105586978B publication Critical patent/CN105586978B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The soil removal and replacement stirring water-stop curtain construction method based on gravel that the present invention relates to a kind of the steps include: to discharge pilot hole stake position (1), by cement mixing pile axis;(2) steel pile casting, is buried, hole wall is stablized using mud, matter to be cut the earth in hole is taken out in Spiral digging machine wet work;(3), drilling stablizes hole wall until pilot hole and backfilling operation space are met the requirements using mud;(4) mud in stake holes, is excluded using gaslift plasma discharge machinery, backfills pile earth material;(5) backfill completes distance and meets cement mixing pile to work continuously requirements, digging plasma discharge guide channel;(6) cement mixer is in place, cement mixing pile driving construction;(7) the remaining untreated sandwich portion in adjacent two pilot holes stake holes position completes the water-stop curtain construction of soil removal and replacement stirring by Mixing Machine action of forced stirring.The design of the invention is scientific and reasonable, is used for water seal for deep foundation pit curtain, simple process, construction cost are low, make full use of common construction machinery, the water-stop curtain water-stagnating effect of completion is good, and construction safety is reliable.

Description

Soil removal and replacement stirring water-stop curtain construction method based on gravel
The application is that number of patent application is 201410813752.X, and patent name is the construction of the water-stop curtain of soil removal and replacement stirring Method, the original bill applying date are the divisional application of 2014.12.23.
Technical field
The invention belongs to water-stop curtain field, especially a kind of soil removal and replacement stirring water-stop curtain construction method based on gravel.
Background technique
When the higher Construction of Deep Excavation Engineering of underground engineering especially level of ground water, it is often necessary to be set on the outside of support pile Water-stop curtain is set, water-stop curtain is generally formed using continuous cement mixing method.When water-stop curtain is in the depth bounds of design It inside encounters the geological stratification for being difficult to pass through, such as when gravel layer, hard skerry and erratic boulder, is stirred using conventional soil cement Stake machinery is mixed, such as two axis cement-soil mixing pile machines, triaxial cement mixing pile machine are difficult to completion of constructing.
For the skerry for being difficult to pass through, can be used single tube high-pressure rotary-spray equipment it is stirred point by point in advance it is loose, then It constructs again cement mixing method, but this method can not still implement deep gravel layer and erratic boulder.
Interlocking pile or ground-connecting-wall can be used for deep gravel layer and erratic boulder, while playing supporting and sealing Effect.It is high to the quality stability requirement of ultra-retardation concrete but when occlusion pile driving construction, and the A stake of interlocking pile and B Between easily leaked due to being glanced off in the direction perpendicular to wall.Ground-connecting-wall seam crossing is the easy hair position for generating leakage, It can effectively avoid joint using two-wheel flute milling machine to leak, but the high process cost, and ground-connecting-wall cost itself is higher, Be not suitable for all engineerings.
TRD engineering method can easily cope with hardpan, such as cobblestone, sticky mud, sandstone, oil shale, limestone, Hua Gang Rock etc., stirs evenly, and malocclusion is not present, it is ensured that the high continuity of wall and high sealing, but TRD engineering method cost is high.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of soil removal and replacement stirring water-stop curtain based on gravel Construction method, design is scientific and reasonable for this method, is used for water seal for deep foundation pit curtain, and simple process, construction cost are low, makes full use of often Water-stop curtain water-stagnating effect with construction machinery, completion is good, and construction safety is reliable.
The present invention solves its technical problem and is achieved through the following technical solutions:
A kind of the step of soil removal and replacement stirring water-stop curtain construction method based on gravel, method are as follows:
(1), pilot hole stake position is discharged by cement mixing pile axis;
(2) steel pile casting, is buried, hole wall is stablized using mud, matter to be cut the earth in hole is taken out in Spiral digging machine wet work;
(3), observation drilling bucket takes out matter situation to be cut the earth, and determines and removes churning driven after pilot hole depth, drilling reach pilot hole depth Machine continues to stablize using mud hole wall until pilot hole and backfilling operation space are met the requirements;
(4) mud in stake holes, is excluded using gaslift plasma discharge machinery, backfills pile earth material, controls plasma discharge amount and backfill amount phase It answers;
(5) backfill completes distance and meets cement mixing pile to work continuously requirements, leads in the digging plasma discharge of cement mixing pile axis both sides Ditch;
(6) cement mixer is in place, and cement slurry stirring system operation pump slurry, starting stake machine carries out cement mixing pile driving construction;
(7) the remaining untreated sandwich portion in adjacent two pilot holes stake holes position is completed soil removal and replacement and is stirred by Mixing Machine action of forced stirring The water-stop curtain construction mixed.
Moreover, 1000@1200 of pilot hole stake position φ is discharged by three axes agitating pile axis in the pilot hole stake position.
Moreover, the high 2m of the steel pile casting, steel pile casting diameter are 20cm bigger than design stake diameter, it is flat that steel pile casting top surface is higher by construction Platform 30cm.
Moreover, manual labour skill is jumped in the Spiral digging machine wet work draws stake holes, drawing stake holes is φ 1000mm.
Moreover, the matter to be cut the earth is gravel, cobble or erratic boulder.
Moreover, the starting stake machine carries out cement mixing pile driving construction as the construction of 850 1200 three axes agitating pile of φ.
The advantages and benefits of the present invention are:
1, the water-stop curtain of this soil removal and replacement stirring is to be unfavorable for pile containing taking-up in the stratum such as dust, cobble, erratic boulder Soil property, while the material for being conducive to pile (at wall) is backfilled, continue the construction of mixing pile.This method construction quality is protected Card, construction machinery tissue is limited smaller by market.
2, the technology maturation of water-stop curtain, simple process of this soil removal and replacement stirring, low in cost, make full use of common construction machine The water-stop curtain water-stagnating effect of tool, completion is good.
Detailed description of the invention
Fig. 1 is the schematic diagram of rotary digging pilot hole of the present invention;
Fig. 2 is the schematic diagram that the present invention completes construction cement mixing pile.
Wherein 1 is cement mixing pile, and 2 be pilot hole, and 3 be original ground, and 4 be the unfavorable interlayers such as dust, cobble, erratic boulder, and 5 are back The earth material filled out, 6 be level of ground water, and H1 is water-stop curtain supporting column length, H2 be dust in water-stop curtain support post depth bounds, The unfavorable interlayer geology buried depth such as cobble, erratic boulder, H3 are unfavorable interlayer geology thickness.
Specific embodiment
Below by specific embodiment, the invention will be further described, and it is not limit that following embodiment, which is descriptive, Qualitatively, this does not limit the scope of protection of the present invention.
A kind of the step of soil removal and replacement stirring water-stop curtain construction method based on gravel, method are as follows:
(1), pilot hole stake position is discharged by cement mixing pile axis;Pilot hole stake position is discharged by three axes agitating pile axis in pilot hole stake position φ1000@1200。
(2) steel pile casting, is buried, hole wall is stablized using mud, mud is formed using tonerde and water mix and mixed certain The bentonite of ratio, prepares mud.Matter to be cut the earth in hole is taken out in Spiral digging machine wet work;The high 2m of steel pile casting, steel pile casting diameter 20cm bigger than design stake diameter, steel pile casting top surface is higher by operation platform 30cm.Spiral digging machine wet work jumps manual labour skill and draws stake holes, draws stake Hole is φ 1000mm.Matter to be cut the earth is gravel, cobble or erratic boulder.
(3), observation drilling bucket takes out matter situation to be cut the earth, and determines and removes churning driven after pilot hole depth, drilling reach pilot hole depth Machine continues to stablize using mud hole wall until pilot hole and backfilling operation space are met the requirements;
(4) mud in stake holes, is excluded using gaslift plasma discharge machinery, backfills pile earth material, controls plasma discharge amount and backfill amount phase It answers;
(5) backfill completes distance and meets cement mixing pile to work continuously requirements, leads in the digging plasma discharge of cement mixing pile axis both sides Ditch;
(6) cement mixer is in place, and cement slurry stirring system operation pump slurry, starting stake machine carries out cement mixing pile driving construction;It opens Dynamic stake machine carries out cement mixing pile driving construction as the construction of 850 1200 three axes agitating pile of φ.
(7) the remaining untreated sandwich portion in adjacent two pilot holes stake holes position is completed soil removal and replacement and is stirred by Mixing Machine action of forced stirring The water-stop curtain construction mixed.

Claims (3)

1. a kind of soil removal and replacement stirring water-stop curtain construction method based on gravel, it is characterised in that: steps of the method are:
(1), pilot hole stake position is discharged by cement mixing pile axis;Pilot hole stake position is discharged by three axes agitating pile axis in pilot hole stake position
(2) steel pile casting, is buried, hole wall is stablized using mud, gravel in hole is taken out in Spiral digging machine wet work;
(3), observation drilling bucket takes out gravel situation, determines and removes Spiral digging machine after pilot hole depth, drilling reach pilot hole depth, continues to adopt Stablize hole wall until pilot hole and backfilling operation space are met the requirements with mud;
(4) mud in stake holes, is excluded using gaslift plasma discharge machinery, backfills pile earth material, control plasma discharge amount is corresponding to backfill amount;
(5), backfill completes distance and meets cement mixing pile to work continuously requirements, in cement mixing pile axis both sides digging plasma discharge guide channel;
(6), cement mixer is in place, and cement slurry stirring system operation pump slurry, starting stake machine carries out cement mixing pile driving construction;
(7), the remaining untreated sandwich portion in adjacent two pilot holes stake position completes stopping for soil removal and replacement stirring by Mixing Machine action of forced stirring The construction of water curtain.
2. the soil removal and replacement stirring water-stop curtain construction method according to claim 1 based on gravel, it is characterised in that: described The high 2m of steel pile casting, steel pile casting diameter are 20cm bigger than design stake diameter, and steel pile casting top surface is higher by operation platform 30cm.
3. the soil removal and replacement stirring water-stop curtain construction method according to claim 1 based on gravel, it is characterised in that: described Starting stake machine carries out cement mixing pile driving constructionThree axes agitating pile construction.
CN201610103716.3A 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel Active CN105586978B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610103716.3A CN105586978B (en) 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610103716.3A CN105586978B (en) 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel
CN201410813752.XA CN104631479B (en) 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201410813752.XA Division CN104631479B (en) 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain

Publications (2)

Publication Number Publication Date
CN105586978A CN105586978A (en) 2016-05-18
CN105586978B true CN105586978B (en) 2019-01-18

Family

ID=53210677

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201410813752.XA Active CN104631479B (en) 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain
CN201610103716.3A Active CN105586978B (en) 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201410813752.XA Active CN104631479B (en) 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain

Country Status (1)

Country Link
CN (2) CN104631479B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631479B (en) * 2014-12-23 2016-08-31 中冶天工集团有限公司 Construction method of soil-changing and stirring waterproof curtain
CN110241836A (en) * 2019-07-04 2019-09-17 嘉盛建设集团有限公司 A kind of construction method of embedding rock water-stop curtain
CN111042061B (en) * 2019-12-30 2020-09-25 中国水电基础局有限公司 Construction method of ultra-deep impervious wall

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631479B (en) * 2014-12-23 2016-08-31 中冶天工集团有限公司 Construction method of soil-changing and stirring waterproof curtain

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19832935C1 (en) * 1997-11-19 1999-12-16 Bauer Spezialtiefbau Method of production high pressure injected building foundation
CN1635223A (en) * 2003-12-26 2005-07-06 上海市基础工程公司 Bridge cofferdam waterstop construction process
CN101255689A (en) * 2008-03-12 2008-09-03 何世鸣 Long helical spraying-rotary stirring soilcement purdah pile as well as construction method thereof
CN102286981A (en) * 2011-07-15 2011-12-21 深圳市鸿荣轩建设工程有限公司 Waterproof curtain and construction method thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631479B (en) * 2014-12-23 2016-08-31 中冶天工集团有限公司 Construction method of soil-changing and stirring waterproof curtain

Also Published As

Publication number Publication date
CN104631479A (en) 2015-05-20
CN104631479B (en) 2016-08-31
CN105586978A (en) 2016-05-18

Similar Documents

Publication Publication Date Title
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN105201518B (en) Disassembling method is received in a kind of major diameter slurry balance shield hole
CN106759473A (en) The constructing structure and its construction method of underground pipe gallery and road
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN109098175A (en) A kind of tri-axes deep mixing pile construction method
CN204253056U (en) A kind of shield machine export & import reinforcing structure
CN204080789U (en) The preparing structure of underground continuous wall width breach
CN111042249A (en) Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN110952528A (en) Construction method of cement-soil underground continuous wall under complex geological conditions
CN110424434A (en) For filling out the stirring pile water stopping curtain and construction method in the deep area Kuai Shi in sea
CN201395793Y (en) Long spiral high-pressure spraying mud injecting stirring pile-forming device
CN105586978B (en) Soil removal and replacement stirring water-stop curtain construction method based on gravel
KR101441929B1 (en) Foundation method for complex pile
CN110306531A (en) High water level erratic boulder stratum construction of diaphragm wall technique
CN110241836A (en) A kind of construction method of embedding rock water-stop curtain
Gerressen et al. CSM-Cutter Soil Mixing-Worldwide Experiences of a young soil mixing method
US3839871A (en) Earthen dam repair
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
CN104153347B (en) Preparing structure and the construction method thereof of underground continuous wall width breach
KR101416869B1 (en) Boring apparatus for complex pile and foundation method using the same
KR102297853B1 (en) Mortar pile formation method that can reduce the occurrence of floating soil
CN105735332B (en) A kind of soil removal and replacement stirring water-stop curtain construction method
CN105350544A (en) Waterproof curtain used for stone-contained area and construction method thereof
CN104612164A (en) Reinforced composite envelope structure construction method
CN205296194U (en) Rich irrigated land layer undercut tunnel interlock pipe curtain

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant