CN104612164A - Reinforced composite envelope structure construction method - Google Patents
Reinforced composite envelope structure construction method Download PDFInfo
- Publication number
- CN104612164A CN104612164A CN201410795100.8A CN201410795100A CN104612164A CN 104612164 A CN104612164 A CN 104612164A CN 201410795100 A CN201410795100 A CN 201410795100A CN 104612164 A CN104612164 A CN 104612164A
- Authority
- CN
- China
- Prior art keywords
- pile
- construction method
- enclosure structure
- construction
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/18—Placing by vibrating
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention provides a reinforced composite envelope structure construction method. The method comprises the steps that firstly, guide hole positions are constructed according to the axis of a reinforced composite envelope structure in a predesigned drawing; secondly, a rotary drilling machine is used for wet-method construction, and guide holes are constructed to the bottom of a stratum unfavorable for stirring pile-forming; thirdly, the guide holes are backfilled with earth materials suitable for stirring pile-forming to the pile tops; fourthly, after backfilling of the guide holes is completed, cement-mixed piles are constructed in situ through a mixing machine; finally, section steel is inserted into the formed cement-mixed piles. By means of the construction method, multiple cement-mixed piles can be formed at a time, and the production efficiency is high. The rotary drilling machine is used for excavating the guide holes to the bottom of the stratum unfavorable for pile-forming according to the pile positions of the reinforced composite envelope structure, the guide holes are filled with the replacing earth materials capable of being used for stirring pile-forming, and then the reinforced composite envelope structure is constructed. The construction method has the advantages that the method is simple and practicable, cost is low, the quality is reliable, the construction efficiency is high, commonly-used construction machinery is fully utilized, and the completed reinforced composite envelope structure is good in water stopping and earth retaining and supporting effect.
Description
Technical field
The invention belongs to Construction Technique of Underground Works field, especially relate to a kind of stiffness Composite Enclosure Structure construction method.
Background technology
During the underground construction Construction of Deep Excavation Engineering that particularly groundwater table is higher, often need to perform stiffness Composite Enclosure Structure, play the effect of sealing and retaining support, but when stiffness Composite Enclosure Structure runs into the geological stratification (as gravel layer, hard skerry) that is difficult to pass through and erratic boulder etc. in the depth bounds designed, use conventional triaxial cement mixing pile machine to be difficult to construction and complete.Traditional for the skerry way being difficult to pass through is, single tube high-pressure rotary-spray equipment is adopted its pointwise to be stirred in advance loose, and then stiffness Composite Enclosure Structure of constructing, but the method still cannot be implemented for deep gravel layer and erratic boulder, cause efficiency of construction low, workmanship is poor.
Summary of the invention
The problem to be solved in the present invention is to provide a kind of stiffness Composite Enclosure Structure construction method, makes full use of common construction machinery, and the stiffness Composite Enclosure Structure sealing completed, retaining support are effective, and technique is simple, with low cost, and efficiency of construction is high.
For solving the problems of the technologies described above, the technical solution used in the present invention is: a kind of stiffness Composite Enclosure Structure construction method, comprises the steps:
1. first discharge by stiffness Composite Enclosure Structure axis and draw position, hole;
2. use Spiral digging machine wet work, construction is drawn bottom hole to unfavorable stirring pile stratum;
3. to step 2. in backfill of drawing in hole be applicable to stirring the earth material of pile to stake top;
4. draw after hole backfilled, to construct in position cement mixing pile with Mixing Machine;
5. shaped steel is inserted in the cement mixing pile 4. formed in step.
Further, step is 2. middle adopts " jumping play " construction to draw hole.
Further, step 2. in draw bore dia than will the large 150mm ~ 200mm of the cement mixing pile diameter of construction molding.
Further, step 2. Spiral digging machine wet work time, utilize gas lift reverse circulation machinery coordinate discharge slurries.
Further, step 4. construct cement mixing pile time, remain untreated sandwich portion, by Mixing Machine action of forced stirring at the two adjacent hole interdigits that draw.
Further, described Mixing Machine is three axle mixers.
Further, step 5. Shaped Steel should insert before cement mixing pile initial set.
Further, step 5. in when inserting shaped steel, insert in agitation pile by shaped steel deadweight with crane lifting shaped steel, or make shaped steel sink to putting in place by the vibrating hammer with hydraulic tongs.
The advantage that the present invention has and good effect are: cement mixing pile one-shot forming many, production efficiency is high.Utilize Spiral digging machine to dig to unfavorable pile stratum according under stiffness Composite Enclosure Structure stake position, change the earth material filled out and may be used for stirring pile, and then carry out the construction of stiffness Composite Enclosure Structure.This construction method is simple, with low cost, makes full use of common construction machinery, and efficiency of construction is high, and the stiffness Composite Enclosure Structure sealing completed, retaining support are effective.
Accompanying drawing explanation
Fig. 1 revolves to dig to draw hole construction schematic diagram;
Fig. 2 is that construction schematic diagram is stirred in soil removal and replacement;
Fig. 3 be revolve dig draw hole before unfavorable stirring pile position of stratum schematic diagram;
Fig. 4 revolves to dig to draw pore structure schematic diagram;
Fig. 5 is the structural representation after hole is drawn in plain earthen backfill;
Fig. 6 is cement mixing pile driving construction schematic diagram;
Fig. 7 is the structural representation after cement mixing pile inserts shaped steel.
In figure: 1-draws position, hole; 2-cement mixing pile; 3-original ground; 4-groundwater table; 5-unfavorable stirring pile stratum; 6-draws hole; Bottom 7-unfavorable stirring pile stratum; 8-Mixing Machine; Bottom 9-agitation pile; 10-shaped steel, 11-earth material.
Detailed description of the invention
Below in conjunction with accompanying drawing, specific embodiments of the invention are elaborated.
A kind of stiffness Composite Enclosure Structure construction method, comprises the steps:
1. as shown in Figure 1, discharge by the stiffness Composite Enclosure Structure axis on design drawing and draw position, hole 1;
2. as shown in Figure 4, use Spiral digging machine wet work, construction to draw bottom hole 6 to unfavorable stirring pile stratum 7, will draw the taking-ups such as the gravel layer being unfavorable for pile in hole 6, hard skerry and erratic boulder;
3. as shown in Figure 5, reach after drawing hole 6 depth requirements, remove rotary drilling rig, continue to adopt mud to stablize hole wall, until draw hole and backfilling operation space meets the demands, to step 2. in backfill in hole 6 of drawing be applicable to stirring the earth material of pile to stake top;
4. as shown in Figure 6, draw after hole 6 backfilled, to construct in position cement mixing pile 2 with Mixing Machine 8, directly construction is to the agitation pile in design drawing 9;
5. as shown in Figure 7, shaped steel 10 is inserted in the cement mixing pile 4. formed in step.
It should be noted that, step 3. in be applicable to stirring the earth material 11 of pile and refer to element soil.Said stake top and the height residing for original ground 3.
Wherein, step is 2. middle adopts " jumping play " construction to draw hole.It should be noted that, when enclosed structure is constructed, be generally normally in groundwater table less than 4 containing unfavorable stirring pile stratum 5 such as gravel layer, hard skerry and erratic boulders, therefore, namely achieve wet work without the need to adding water or adding water on a small quantity.Therefore, bottom Spiral digging machine construction to unfavorable stirring pile stratum, the hole 6 of drawing of more than 7 positions is completed smoothly, and efficiency of construction is high.
Wherein, step 2. in draw hole 6 diameter than will the large 150mm ~ 200mm of the diameter of cement mixing pile 2 of construction molding, constructed and namely can obtain the cement mixing pile 2 of intended diameter in advance.
Wherein, step 2. Spiral digging machine wet work time, utilize gas lift reverse circulation machinery coordinate discharge slurries.
Wherein, as shown in Figure 2, step 4. construct cement mixing pile 2 time, remain untreated sandwich portion in two adjacent drawing between position, hole 2, stirred by Mixing Machine Final 8 system.
Wherein, described Mixing Machine 8 is three axle mixers, the multiple pile of one-shot forming, and can draw adjacent two between position, hole 2 simultaneously and remain untreated sandwich portion action of forced stirring, operating efficiency is high, and construction effect is good.
Wherein, step 5. Shaped Steel 10 should be inserted before cement mixing pile 2 initial set, avoids cement mixing pile 2 to condense causing shaped steel 10 to insert difficulty, not situation on earth of inserting occurs.
Wherein, step 5. in when inserting shaped steel 10, insert in agitation pile by shaped steel deadweight with crane lifting shaped steel 10, or make shaped steel 10 sink to putting in place by the vibrating hammer with hydraulic tongs.It should be noted that, shaped steel 10 must ensure that insertion puts in place here, to reach the effect designed in advance.
Run within the scope of stiffness Composite Enclosure Structure construction depth as shown in Figure 3 containing the unfavorable stirring pile stratum 5 such as gravel layer, hard skerry and erratic boulder time, with Spiral digging machine according to digging to unfavorable stirring pile stratum 7 under stiffness Composite Enclosure Structure stake position, change the earth material filled out and may be used for stirring pile, and then carry out the construction of stiffness Composite Enclosure Structure.The method technology maturation, technique are simple, with low cost, and efficiency of construction is high, and manufacturing schedule is fast, and take full advantage of conventional construction machinery, the stiffness Composite Enclosure Structure completed reaches well goes along with sb. to guard him effect.
Above one embodiment of the present of invention have been described in detail, but described content being only preferred embodiment of the present invention, can not being considered to for limiting practical range of the present invention.All equalizations done according to the present patent application scope change and improve, and all should still belong within patent covering scope of the present invention.
Claims (8)
1. a stiffness Composite Enclosure Structure construction method, is characterized in that, comprises the steps:
1. first discharge by stiffness Composite Enclosure Structure axis and draw position, hole;
2. use Spiral digging machine wet work, construction is drawn bottom hole to unfavorable stirring pile stratum;
3. to step 2. in backfill of drawing in hole be applicable to stirring the earth material of pile to stake top;
4. draw after hole backfilled, to construct in position cement mixing pile with Mixing Machine;
5. shaped steel is inserted in the cement mixing pile 4. formed in step.
2. a kind of stiffness Composite Enclosure Structure construction method according to claim 1, is characterized in that: step is 2. middle adopts " jumping play " construction to draw hole.
3. a kind of stiffness Composite Enclosure Structure construction method according to claim 1, is characterized in that: step 2. in draw bore dia than will the large 150mm ~ 200mm of the cement mixing pile diameter of construction molding.
4. a kind of stiffness Composite Enclosure Structure construction method according to claim 1, is characterized in that: step 2. Spiral digging machine wet work time, utilize gas lift reverse circulation machinery coordinate discharge slurries.
5. a kind of stiffness Composite Enclosure Structure construction method according to claim 1, is characterized in that: step 4. construct cement mixing pile time, remain untreated sandwich portion, by Mixing Machine action of forced stirring at the two adjacent hole interdigits that draw.
6. a kind of stiffness Composite Enclosure Structure construction method according to claim 1, is characterized in that: described Mixing Machine is three axle mixers.
7. a kind of stiffness Composite Enclosure Structure construction method according to claim 1, is characterized in that: step 5. Shaped Steel should be inserted before cement mixing pile initial set.
8. a kind of stiffness Composite Enclosure Structure construction method according to claim 1, it is characterized in that: step 5. in insert shaped steel time, with crane lifting shaped steel and by shaped steel deadweight insertion agitation pile, or shaped steel is made to sink to putting in place by the vibrating hammer with hydraulic tongs.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410795100.8A CN104612164A (en) | 2014-12-18 | 2014-12-18 | Reinforced composite envelope structure construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410795100.8A CN104612164A (en) | 2014-12-18 | 2014-12-18 | Reinforced composite envelope structure construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104612164A true CN104612164A (en) | 2015-05-13 |
Family
ID=53146792
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410795100.8A Pending CN104612164A (en) | 2014-12-18 | 2014-12-18 | Reinforced composite envelope structure construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104612164A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105507345A (en) * | 2015-12-04 | 2016-04-20 | 嘉库智能停车系统(上海)有限公司 | Reversed construction method for well type fully-automatic three-dimensional garage |
CN106567382A (en) * | 2016-10-25 | 2017-04-19 | 东通岩土科技(杭州)有限公司 | Foundation pit curtain construction method in gravel layer |
CN114215070A (en) * | 2021-12-23 | 2022-03-22 | 浙江省建筑设计研究院 | Super-deep TRD (blast furnace direct reduction) wall forming construction method for gravel water-rich stratum based on assembled L-shaped guide wall |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296630A (en) * | 2011-06-17 | 2011-12-28 | 北京中岩大地工程技术有限公司 | Construction method of long-screw high-pressure mix jetting cement diaphragm wall |
CN102493452A (en) * | 2011-11-30 | 2012-06-13 | 蔡嘉明 | Grouting pile-grafting construction method and equipment |
JP2013177808A (en) * | 2013-05-23 | 2013-09-09 | Ohbayashi Corp | Construction method for earth retaining wall, construction method for pile, pile, and boring machine |
CN103669339A (en) * | 2012-08-28 | 2014-03-26 | 李孝虎 | Wet jetting pile construction technology for strengthening soft soil foundation |
-
2014
- 2014-12-18 CN CN201410795100.8A patent/CN104612164A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296630A (en) * | 2011-06-17 | 2011-12-28 | 北京中岩大地工程技术有限公司 | Construction method of long-screw high-pressure mix jetting cement diaphragm wall |
CN102493452A (en) * | 2011-11-30 | 2012-06-13 | 蔡嘉明 | Grouting pile-grafting construction method and equipment |
CN103669339A (en) * | 2012-08-28 | 2014-03-26 | 李孝虎 | Wet jetting pile construction technology for strengthening soft soil foundation |
JP2013177808A (en) * | 2013-05-23 | 2013-09-09 | Ohbayashi Corp | Construction method for earth retaining wall, construction method for pile, pile, and boring machine |
Non-Patent Citations (2)
Title |
---|
刘永刚: "水泥搅拌桩的支承应用", 《中国科技信息》 * |
李闵等: "临江侧穿越抛石层的"三墙合一"地下连续墙施工技术", 《建筑施工》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105507345A (en) * | 2015-12-04 | 2016-04-20 | 嘉库智能停车系统(上海)有限公司 | Reversed construction method for well type fully-automatic three-dimensional garage |
CN106567382A (en) * | 2016-10-25 | 2017-04-19 | 东通岩土科技(杭州)有限公司 | Foundation pit curtain construction method in gravel layer |
CN114215070A (en) * | 2021-12-23 | 2022-03-22 | 浙江省建筑设计研究院 | Super-deep TRD (blast furnace direct reduction) wall forming construction method for gravel water-rich stratum based on assembled L-shaped guide wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105298507B (en) | A kind of underground pipe gallery construction method of top open cut bottom tunneler construction | |
CN108457283A (en) | Deep water hard rock steel sheet-pile cofferdam pilot hole fluting grouting construction method | |
CN203625893U (en) | Rock-embedded cast-in-place pile | |
CN104612179B (en) | Through the construction method of the diaphram wall of super thick silty sand ground | |
CN105714834B (en) | A kind of construction technology of hardpan preexisting hole grouting behind shaft or drift lining H profile steel stake | |
CN106168024A (en) | A drilling construction method is dug in special formation rotation | |
CN108532586A (en) | A kind of construction method of garage parking diaphram wall | |
CN103882858A (en) | Construction method of micro-piles with diameter of 300 mm | |
CN102953372A (en) | Steel pipe pile and construction method thereof | |
CN105256795A (en) | End support type thread core composite pile and construction device and method for end support type thread core composite pile | |
CN104164873B (en) | Prestressed pipe pile and construction method thereof | |
CN105019913A (en) | Base rock uplift region shielding tool-changing in-situ reinforcement method | |
CN107268599B (en) | Substrate buried type large-scale filling karst cave reinforcing structure and reinforcing method | |
CN104612164A (en) | Reinforced composite envelope structure construction method | |
CN105133641A (en) | Thin-wall continuous-wall-type foundation reinforcing structure and method | |
KR20080027481A (en) | Ground boring method using multi-point rock boring | |
CN110241836A (en) | A kind of construction method of embedding rock water-stop curtain | |
CN114482099A (en) | Steel sheet pile cofferdam construction method | |
CN108005065A (en) | The constructing structure and construction method of PHC static pressure pipe piles | |
CN205688454U (en) | Power transmission tower resistance to plucking well foundation | |
CN104631479B (en) | Construction method of soil-changing and stirring waterproof curtain | |
CN203334953U (en) | Long rod type hole leading pile machine | |
CN209760216U (en) | reinforcement system based on soft soil foundation drainage consolidation | |
CN203755332U (en) | Device for treating collapsible loess with lime-soil compaction piles and CFG rigid piles combined | |
CN105839661A (en) | Anti-pulling open caisson foundation for power transmission tower |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150513 |