CN105839661A - Anti-pulling open caisson foundation for power transmission tower - Google Patents
Anti-pulling open caisson foundation for power transmission tower Download PDFInfo
- Publication number
- CN105839661A CN105839661A CN201610316698.7A CN201610316698A CN105839661A CN 105839661 A CN105839661 A CN 105839661A CN 201610316698 A CN201610316698 A CN 201610316698A CN 105839661 A CN105839661 A CN 105839661A
- Authority
- CN
- China
- Prior art keywords
- open caisson
- basis
- cylinder
- power transmission
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 19
- 239000004567 concrete Substances 0.000 claims description 11
- 239000002689 soil Substances 0.000 claims description 10
- 239000011150 reinforced concrete Substances 0.000 claims description 3
- 230000015271 coagulation Effects 0.000 claims 1
- 238000005345 coagulation Methods 0.000 claims 1
- 238000004519 manufacturing process Methods 0.000 abstract description 6
- 238000007789 sealing Methods 0.000 abstract 2
- 238000010276 construction Methods 0.000 description 6
- 238000005266 casting Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005755 formation reaction Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/18—Foundations formed by making use of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
Abstract
The invention discloses an anti-pulling open caisson foundation for a power transmission tower. The anti-pulling open caisson foundation comprises a cylindrical open caisson (1), a sealing bottom (2) arranged at the lower end of the open caisson (1), and a sealing cover (3) arranged at the upper end of the open caisson (1). A plurality of through holes (11) are formed in the side wall of the open caisson (1). A column (4) is inserted in each through hole (11) in a connected manner, and is perpendicular to the axis of the open caisson (1). The anti-pulling open caisson foundation for the power transmission tower is high in anti-pulling force, low in production cost and convenient to construct.
Description
Technical field
The invention belongs to power transmission tower basis technical field, a kind of withdrawal resistance is strong, production cost is low, easy construction
Power transmission tower resistance to plucking well foundation.
Background technology
Power transmission tower does not only rely on and is placed in the bearing capacity that the basis bottom it provides enough, also needs the resistance to plucking that basis offer is enough
Power.
Current power transmission tower often uses raft foundation or pile foundation.When using raft foundation, owing to foundation's bottom area is big,
As for providing enough withdrawal resistances, then needed to add great burying, cause earthwork evacuation amount big;As for reduce earthwork evacuation amount,
Then buried depth, it is difficult to enough withdrawal resistances are provided.When using pile foundation, then need to use cast-in-situ bored pile can meet power transmission tower
The bearing capacity on basis and resistance to plucking requirement, thus cost is higher.
Therefore, prior art there is the problem that power transmission tower is basic when ensureing enough withdrawal resistance requirements, and cost is high.
Summary of the invention
It is an object of the invention to provide a kind of power transmission tower resistance to plucking well foundation, withdrawal resistance is strong, production cost is low, construction party
Just.
The technical solution realizing the object of the invention is:
A kind of power transmission tower resistance to plucking well foundation, the back cover including cylindric open caisson, being placed in described open caisson lower end, be placed in described
The capping of open caisson upper end, the sidewall of described open caisson is provided with multiple through hole, grafting one cylinder in each through hole, described cylinder
Vertical with open caisson axis.
Compared with prior art, its remarkable advantage is the present invention:
1, withdrawal resistance is strong: and all-in-one-piece multiple cylinder vertical with open caisson axis as root key, based on provide enough
Withdrawal resistance.
2, production cost is low, easy construction: use open caisson mode, greatly reduces excavation of foundation pit amount, withdrawal resistance and holding
Load power relies primarily on subsoil and backfill soil provides, and greatly reduces concrete material and uses, and production cost is low, and construction party
Just.
The present invention is described in further detail with detailed description of the invention below in conjunction with the accompanying drawings.
Accompanying drawing explanation
Fig. 1 is the structural representation of power transmission tower resistance to plucking well foundation of the present invention.
Fig. 2 is the top view of power transmission tower resistance to plucking well foundation of the present invention.
In figure, open caisson 1, back cover 2, capping 3, through hole 11, cylinder 4.
Detailed description of the invention
As it is shown in figure 1, power transmission tower resistance to plucking well foundation of the present invention, including cylindric open caisson 1, it is placed in described open caisson 1 time
The back cover 2 held, the capping 3 being placed in described open caisson 1 upper end, the sidewall of described open caisson 1 is provided with multiple through hole 11, often
Grafting one cylinder 4 in individual through hole 11, described cylinder 4 is vertical with open caisson 1 axis.
Described open caisson 1 is formed by armored concrete is prefabricated.
Described cylinder 4 is formed by armored concrete is prefabricated.
Described back cover 2 is formed by armored concrete cast in situs.
Described capping 3 is formed by armored concrete cast in situs.
Described cylinder 4 and through hole 11 loose fit on open caisson 1 sidewall, cylinder 4 install in place after, at cylinder 4 and through hole
Casting concrete between 11 gaps.
Backfill element soil in described open caisson 1.
Backfilling element soil in described open caisson 1 periphery and roll compacting, compacting factor is not less than 0.92, height after the earthen backfill of described element
Go out ground 350mm.
The power transmission tower resistance to plucking well foundation of each present invention, is placed on an angle bottom power transmission tower tower body.
The construction technology of of the present invention power transmission tower resistance to plucking well foundation is presented herein below.
(1) prefabricated open caisson 1, and open caisson 1 borehole wall reserves through hole 11, as root keyhole, prefabricated reinforced concrete column body 4,
As root key;
(2) excavate slightly larger than the foundation ditch of open caisson 1 outside dimension in basic engineering position, and lay sand-gravel cushion whole at the end, hole
Flat;
(3) open caisson 1 is transferred to foundation ditch;
(4) from open caisson 1 inside, cylinder 4 is inserted the borehole wall to reserve through hole 11, and use pushing tow mode to be pushed up by cylinder 4
In underground layer so that it is insert among the soil layer of open caisson surrounding as root key;
(5) casting concrete between cylinder 4 and through hole 11 gap so that root key is integrally formed with open caisson;
(6) back cover is carried out at open caisson 1 lower end casting concrete;Backfill element soil in described open caisson 1;
(7) bind the circular cushion cap of formation by open caisson top casting concrete, and as the cushion cap on tower body basis;
(8) backfilling plain fill outside open caisson and roll compacting, compacting factor is not less than 0.92, and described plain fill exceeds ground
Face more than 350mm.
From above-mentioned work progress it can also be seen that, withdrawal resistance of the present invention is strong, production cost is low, easy construction.
Claims (8)
1. a power transmission tower resistance to plucking well foundation, it is characterised in that: include cylindric open caisson (1), be placed in described open caisson (1)
The back cover (2) of lower end, being placed in the capping (3) of described open caisson (1) upper end, the sidewall of described open caisson (1) is provided with many
Individual through hole (11), grafting one cylinder (4) in each through hole (11), described cylinder (4) hangs down with open caisson (1) axis
Directly.
Basis the most according to claim 1, it is characterised in that: described open caisson (1) by armored concrete prefabricated and
Become.
Basis the most according to claim 1, it is characterised in that: described cylinder (4) by armored concrete prefabricated and
Become.
Basis the most according to claim 1, it is characterised in that: described back cover (2) is watered by reinforced concrete soil scene
Build and form.
Basis the most according to claim 1, it is characterised in that: described capping (3) is watered by reinforced concrete soil scene
Build and form.
Basis the most according to claim 1, it is characterised in that: on described cylinder (4) and open caisson (1) sidewall
Through hole (11) loose fit, cylinder (4) install in place after, between cylinder (4) and through hole (11) gap, pour coagulation
Soil.
Basis the most according to claim 1, it is characterised in that: backfill element soil in described open caisson (1).
Basis the most according to claim 1, it is characterised in that: backfill element soil in described open caisson (1) periphery and grind
Pressure compacting, compacting factor is not less than 0.92,350mm above ground level after the earthen backfill of described element.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610316698.7A CN105839661A (en) | 2016-05-12 | 2016-05-12 | Anti-pulling open caisson foundation for power transmission tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610316698.7A CN105839661A (en) | 2016-05-12 | 2016-05-12 | Anti-pulling open caisson foundation for power transmission tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105839661A true CN105839661A (en) | 2016-08-10 |
Family
ID=56591214
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610316698.7A Pending CN105839661A (en) | 2016-05-12 | 2016-05-12 | Anti-pulling open caisson foundation for power transmission tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105839661A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0393925A (en) * | 1989-09-06 | 1991-04-18 | Toda Constr Co Ltd | Simultaneous construction method of structure above or under ground |
CN201809779U (en) * | 2010-10-13 | 2011-04-27 | 河南省电力勘测设计院 | Open caisson foundation of power transmission line iron tower |
KR20120132713A (en) * | 2011-05-30 | 2012-12-10 | 삼성파워텍주식회사 | Split concrete foundation structure of transmission tower |
CN204676585U (en) * | 2015-04-20 | 2015-09-30 | 国家电网公司 | A kind of transmission line of electricity open caisson Screw Anchor composite foundation |
CN205688454U (en) * | 2016-05-12 | 2016-11-16 | 扬州大学 | Power transmission tower resistance to plucking well foundation |
-
2016
- 2016-05-12 CN CN201610316698.7A patent/CN105839661A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0393925A (en) * | 1989-09-06 | 1991-04-18 | Toda Constr Co Ltd | Simultaneous construction method of structure above or under ground |
CN201809779U (en) * | 2010-10-13 | 2011-04-27 | 河南省电力勘测设计院 | Open caisson foundation of power transmission line iron tower |
KR20120132713A (en) * | 2011-05-30 | 2012-12-10 | 삼성파워텍주식회사 | Split concrete foundation structure of transmission tower |
CN204676585U (en) * | 2015-04-20 | 2015-09-30 | 国家电网公司 | A kind of transmission line of electricity open caisson Screw Anchor composite foundation |
CN205688454U (en) * | 2016-05-12 | 2016-11-16 | 扬州大学 | Power transmission tower resistance to plucking well foundation |
Non-Patent Citations (1)
Title |
---|
殷永高: "根式基础、锚碇构思即施工工艺探讨", 《中国公路学会桥梁和结构工程分会2006年全国桥梁学术会议论文集 》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101265701A (en) | Soft soil foundation reinforcing means | |
CN205688454U (en) | Power transmission tower resistance to plucking well foundation | |
CN104727308A (en) | Immersed tube compaction pile or cast-in-place concrete pile construction device and method | |
CN108277794B (en) | Vacuum power consolidation composite drainage system for hydraulic filling soft soil foundation | |
CN100373013C (en) | Treatment method for thick collapsed loess foundation | |
CN202559368U (en) | Subsidence-reducing pile structure of capped steel pipe of immersed tunnel | |
CN104975611A (en) | Sinking device and method for well point drawdown pipe of liquid soil layer | |
CN101591906A (en) | The method for processing foundation of intubate, multipass vacuum well-point dewatering dynamic consolidation | |
CN104389305A (en) | Sand-filled bamboo-joint pile and construction method thereof | |
CN203222795U (en) | Manual hole digging pile | |
CN104264653A (en) | Superhigh energy level dynamic compaction and replacement compatible construction process | |
CN102953392B (en) | A kind of pile foundation structure of photovoltaic plant and pile foundation construction technique | |
CN202969370U (en) | Novel steel pipe pile | |
CN204238209U (en) | A kind of back-up sand bamboo joint pile | |
CN110080169A (en) | A kind of construction method reclaimed fields from the sea utilized based on basement | |
CN104141304B (en) | The construction method of a kind of extrusion molding preformed pile stiff-core cement soil Y shape stake | |
CN203939036U (en) | A kind of steel sheet pile cofferdam structure that is applicable to river course | |
CN104988948A (en) | Rib plate type retaining wall and construction method thereof | |
CN108914959A (en) | A kind of foundation structure and its construction method built suitable for mountain area room | |
CN202610808U (en) | Press-anchor-restrict method foundation pit retaining structure | |
CN107700434A (en) | A kind of dome grating formula armored concrete mud-rock flow blocking dam and its construction process | |
CN105839661A (en) | Anti-pulling open caisson foundation for power transmission tower | |
CN205000251U (en) | Complete embedding circular cushion cap construction structures in only pier river course shallow water of single pile | |
CN204780991U (en) | Floor formula retaining wall | |
CN204059343U (en) | The stake of extrusion molding preformed pile stiff-core cement soil Y shape |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160810 |
|
WD01 | Invention patent application deemed withdrawn after publication |