CN104631479A - Construction method of soil-changing and stirring waterproof curtain - Google Patents

Construction method of soil-changing and stirring waterproof curtain Download PDF

Info

Publication number
CN104631479A
CN104631479A CN201410813752.XA CN201410813752A CN104631479A CN 104631479 A CN104631479 A CN 104631479A CN 201410813752 A CN201410813752 A CN 201410813752A CN 104631479 A CN104631479 A CN 104631479A
Authority
CN
China
Prior art keywords
hole
pile
construction
stirring
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410813752.XA
Other languages
Chinese (zh)
Other versions
CN104631479B (en
Inventor
张生雨
白汉民
王冬生
邱太刚
温支生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201610103716.3A priority Critical patent/CN105586978B/en
Priority to CN201610102949.1A priority patent/CN105735332B/en
Priority to CN201410813752.XA priority patent/CN104631479B/en
Publication of CN104631479A publication Critical patent/CN104631479A/en
Application granted granted Critical
Publication of CN104631479B publication Critical patent/CN104631479B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a construction method of a waterproof curtain for soil replacement and stirring, which comprises the following steps: the method comprises the steps of releasing guide hole pile positions according to the axis of a cement stirring pile; embedding a steel casing, stabilizing the hole wall by adopting slurry, and taking out the soil to be excavated in the hole by using a rotary excavator in wet operation; thirdly, stabilizing the hole wall by adopting slurry until the operation space of hole guiding and backfilling meets the requirements; fourthly, removing mud in the pile hole by using a gas lift mud discharging machine, and backfilling pile-forming soil; fifthly, excavating a slurry discharge guide channel, wherein the backfill completion distance meets the continuous operation requirement of the cement mixing pile; sixthly, positioning a cement mixer, and constructing a cement mixing pile; and forcibly stirring the left untreated interlayer parts of the pile hole positions of two adjacent guide holes by a stirring machine to finish the construction of the waterproof curtain for soil replacement and stirring. The invention has scientific and reasonable design, simple process and low construction cost when being used for the waterproof curtain of the deep foundation pit, fully utilizes common construction machinery, and has good waterproof effect and safe and reliable construction.

Description

The construction method of the water-stop curtain that soil removal and replacement is stirred
Technical field
The invention belongs to water-stop curtain field, the construction method of the water-stop curtain that especially a kind of soil removal and replacement is stirred.
Background technology
During the underground construction Construction of Deep Excavation Engineering that particularly groundwater table is higher, often need the arranged outside water-stop curtain at soldier pile, water-stop curtain generally adopts continuous print cement mixing method to be formed.When water-stop curtain runs into the geological stratification being difficult to pass through in the depth bounds of design, during as gravel layer, hard skerry and erratic boulder etc., use conventional cement-soil mixing pile machine tool, complete as two axle cement-soil mixing pile machines, triaxial cement mixing pile machine etc. are difficult to construction.
For the skerry being difficult to pass through, single tube high-pressure rotary-spray equipment can be adopted its pointwise to be stirred in advance loose, and then cement mixing method of constructing, but the method still cannot be implemented for deep gravel layer and erratic boulder.
Interlocking pile or ground-connecting-wall can be adopted for deep gravel layer and erratic boulder, play the effect of supporting and sealing simultaneously.But during interlocking pile construction, require high to the quality stability of ultra-retardation concrete, and very easily due to the seepage in the direction generation deflection perpendicular to wall between the A stake of interlocking pile and B stake.Ground-connecting-wall seam crossing is the easily position producing seepage, adopt two-wheel flute milling machine can effectively avoid joint seepage, but this process costs is higher, and the cost of ground-connecting-wall own is higher, is not suitable for all engineerings.
TRD engineering method easily can tackle hardpan, as cobble, viscosity mud, sandstone, oil shale, limestone, granite etc., stir, there is not malocclusion, guarantee body of wall high continuity and high sealing, but TRD engineering method cost is high.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, the construction method of the water-stop curtain providing a kind of soil removal and replacement to stir, the method design science is reasonable, for water seal for deep foundation pit curtain, technique is simple, construction cost is low, make full use of common construction machinery, the water-stop curtain stagnant water effect completed is good, and construction safety is reliable.
The present invention solves its technical problem and is achieved through the following technical solutions:
A construction method for the water-stop curtain that soil removal and replacement is stirred, the step of its method is:
(1), discharge by cement mixing pile axis and draw stake position, hole;
(2), bury steel pile casting underground, adopt mud to stablize hole wall, Spiral digging machine wet work will treat in hole that shoveling matter is taken out;
(3), observe drilling bucket and take out and treat shoveling matter situation, determine to draw hole depth, boring removes rotary drilling rig after reaching and drawing hole depth, continues to adopt mud to stablize hole wall until draw hole and backfilling operation space meets the demands;
(4), adopt gaslift plasma discharge machinery to get rid of mud in stake holes, backfill pile earth material, controls plasma discharge amount corresponding to backfill amount;
(5) backfill distance to meet cement mixing pile and to work continuously requirement, dig plasma discharge guide channel on cement mixing pile axis both sides;
(6) cement mixer is in place, and cement paste stirring system process pump is starched, and starts stake machine and carries out cement mixing pile driving construction;
(7) adjacent two draw stake holes position, hole and remain untreated sandwich portion, by Mixing Machine action of forced stirring, complete the water-stop curtain construction that soil removal and replacement is stirred.
And described stake position, hole of drawing is discharged by three axes agitating pile axis and is drawn stake position, hole φ 1000@1200.
And described steel pile casting height 2m, steel pile casting diameter 20cm larger than design stake footpath, steel pile casting end face exceeds operation platform 30cm.
And described Spiral digging machine wet work is jumped manual labour skill and is drawn stake holes, and drawing stake holes is φ 1000mm.
And described treats that shoveling matter is gravel, cobble or erratic boulder.
And it is the construction of φ 850 1200 three axes agitating pile that described startup stake machine carries out cement mixing pile driving construction.
Advantage of the present invention and beneficial effect are:
1, the water-stop curtain that this soil removal and replacement is stirred takes out the soil property being unfavorable for pile in containing stratum such as dust, cobble, erratic boulders, and backfill is simultaneously beneficial to the material of pile (one-tenth wall), proceeds the construction of agitation pile.This method construction quality is guaranteed, and construction machinery tissue is less by market restriction.
2, the technology maturation of water-stop curtain, the technique that stir of this soil removal and replacement is simple, with low cost, and make full use of common construction machinery, the water-stop curtain stagnant water effect completed is good.
Accompanying drawing explanation
Fig. 1 is that the schematic diagram digging and draw hole is revolved in the present invention;
Fig. 2 is the schematic diagram that the present invention completes construction cement mixing pile.
Wherein 1 is cement mixing pile, 2 for drawing hole, 3 is original ground, 4 is the unfavorable interlayers such as dust, cobble, erratic boulder, 5 is the earth material backfilled, and 6 is groundwater table, and H1 is water-stop curtain support post length, H2 is the unfavorable interlayer geology buried depth such as dust, cobble, erratic boulder in water-stop curtain support post depth bounds, and H3 is unfavorable interlayer geology thickness.
Detailed description of the invention
Below by specific embodiment, the invention will be further described, and following examples are descriptive, is not determinate, can not limit protection scope of the present invention with this.
A construction method for the water-stop curtain that soil removal and replacement is stirred, the step of its method is:
(1), discharge by cement mixing pile axis and draw stake position, hole; Draw stake position, hole to discharge by three axes agitating pile axis and draw stake position, hole φ 1000@1200.
(2), bury steel pile casting underground, adopt mud to stablize hole wall, mud adopts tonerde and water mix form and mix a certain proportion of swell soil, prepares mud.Spiral digging machine wet work will treat in hole that shoveling matter is taken out; Steel pile casting height 2m, steel pile casting diameter 20cm larger than design stake footpath, steel pile casting end face exceeds operation platform 30cm.Spiral digging machine wet work is jumped manual labour skill and is drawn stake holes, and drawing stake holes is φ 1000mm.Treat that shoveling matter is gravel, cobble or erratic boulder.
(3), observe drilling bucket and take out and treat shoveling matter situation, determine to draw hole depth, boring removes rotary drilling rig after reaching and drawing hole depth, continues to adopt mud to stablize hole wall until draw hole and backfilling operation space meets the demands;
(4), adopt gaslift plasma discharge machinery to get rid of mud in stake holes, backfill pile earth material, controls plasma discharge amount corresponding to backfill amount;
(5) backfill distance to meet cement mixing pile and to work continuously requirement, dig plasma discharge guide channel on cement mixing pile axis both sides;
(6) cement mixer is in place, and cement paste stirring system process pump is starched, and starts stake machine and carries out cement mixing pile driving construction; It is the construction of φ 850 1200 three axes agitating pile that startup stake machine carries out cement mixing pile driving construction.
(7) adjacent two draw stake holes position, hole and remain untreated sandwich portion, by Mixing Machine action of forced stirring, complete the water-stop curtain construction that soil removal and replacement is stirred.

Claims (6)

1. a construction method for the water-stop curtain of soil removal and replacement stirring, is characterized in that: steps of the method are:
(1), discharge by cement mixing pile axis and draw stake position, hole;
(2), bury steel pile casting underground, adopt mud to stablize hole wall, Spiral digging machine wet work will treat in hole that shoveling matter is taken out;
(3), observe drilling bucket and take out and treat shoveling matter situation, determine to draw hole depth, boring removes rotary drilling rig after reaching and drawing hole depth, continues to adopt mud to stablize hole wall until draw hole and backfilling operation space meets the demands;
(4), adopt gaslift plasma discharge machinery to get rid of mud in stake holes, backfill pile earth material, controls plasma discharge amount corresponding to backfill amount;
(5) backfill distance to meet cement mixing pile and to work continuously requirement, dig plasma discharge guide channel on cement mixing pile axis both sides;
(6) cement mixer is in place, and cement paste stirring system process pump is starched, and starts stake machine and carries out cement mixing pile driving construction;
(7) adjacent two draw stake holes position, hole and remain untreated sandwich portion, by Mixing Machine action of forced stirring, complete the water-stop curtain construction that soil removal and replacement is stirred.
2. the construction method of water-stop curtain that stirs of soil removal and replacement according to claim 1, is characterized in that: described stake position, hole of drawing is discharged by three axes agitating pile axis and drawn stake position, hole φ 1000@1200.
3. the construction method of the water-stop curtain of soil removal and replacement stirring according to claim 1, is characterized in that: described steel pile casting height 2m, and steel pile casting diameter 20cm larger than design stake footpath, steel pile casting end face exceeds operation platform 30cm.
4. the construction method of the water-stop curtain of soil removal and replacement stirring according to claim 1, is characterized in that: described Spiral digging machine wet work is jumped manual labour skill and drawn stake holes, and drawing stake holes is φ 1000mm.
5. the construction method of the water-stop curtain of soil removal and replacement stirring according to claim 1, is characterized in that: described treats that shoveling matter is gravel, cobble or erratic boulder.
6. the construction method of the water-stop curtain of soil removal and replacement stirring according to claim 1, is characterized in that: it is the construction of φ 850 1200 three axes agitating pile that described startup stake machine carries out cement mixing pile driving construction.
CN201410813752.XA 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain Active CN104631479B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201610103716.3A CN105586978B (en) 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel
CN201610102949.1A CN105735332B (en) 2014-12-23 2014-12-23 A kind of soil removal and replacement stirring water-stop curtain construction method
CN201410813752.XA CN104631479B (en) 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410813752.XA CN104631479B (en) 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain

Related Child Applications (2)

Application Number Title Priority Date Filing Date
CN201610102949.1A Division CN105735332B (en) 2014-12-23 2014-12-23 A kind of soil removal and replacement stirring water-stop curtain construction method
CN201610103716.3A Division CN105586978B (en) 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel

Publications (2)

Publication Number Publication Date
CN104631479A true CN104631479A (en) 2015-05-20
CN104631479B CN104631479B (en) 2016-08-31

Family

ID=53210677

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201410813752.XA Active CN104631479B (en) 2014-12-23 2014-12-23 Construction method of soil-changing and stirring waterproof curtain
CN201610103716.3A Active CN105586978B (en) 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201610103716.3A Active CN105586978B (en) 2014-12-23 2014-12-23 Soil removal and replacement stirring water-stop curtain construction method based on gravel

Country Status (1)

Country Link
CN (2) CN104631479B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631479B (en) * 2014-12-23 2016-08-31 中冶天工集团有限公司 Construction method of soil-changing and stirring waterproof curtain
CN110241836A (en) * 2019-07-04 2019-09-17 嘉盛建设集团有限公司 A kind of construction method of embedding rock water-stop curtain
CN111042061B (en) * 2019-12-30 2020-09-25 中国水电基础局有限公司 Construction method of ultra-deep impervious wall

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19832935C1 (en) * 1997-11-19 1999-12-16 Bauer Spezialtiefbau Method of production high pressure injected building foundation
CN1635223A (en) * 2003-12-26 2005-07-06 上海市基础工程公司 Bridge cofferdam waterstop construction process
CN101255689A (en) * 2008-03-12 2008-09-03 何世鸣 Long helical spraying-rotary stirring soilcement purdah pile as well as construction method thereof
CN102286981A (en) * 2011-07-15 2011-12-21 深圳市鸿荣轩建设工程有限公司 Waterproof curtain and construction method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631479B (en) * 2014-12-23 2016-08-31 中冶天工集团有限公司 Construction method of soil-changing and stirring waterproof curtain

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19832935C1 (en) * 1997-11-19 1999-12-16 Bauer Spezialtiefbau Method of production high pressure injected building foundation
CN1635223A (en) * 2003-12-26 2005-07-06 上海市基础工程公司 Bridge cofferdam waterstop construction process
CN101255689A (en) * 2008-03-12 2008-09-03 何世鸣 Long helical spraying-rotary stirring soilcement purdah pile as well as construction method thereof
CN102286981A (en) * 2011-07-15 2011-12-21 深圳市鸿荣轩建设工程有限公司 Waterproof curtain and construction method thereof

Also Published As

Publication number Publication date
CN104631479B (en) 2016-08-31
CN105586978A (en) 2016-05-18
CN105586978B (en) 2019-01-18

Similar Documents

Publication Publication Date Title
CN106545005B (en) A kind of reinforcing body and reinforcement means of subway tunnel shield end
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN105863648B (en) A kind of tunneling is shallow to cover large-section tunnel construction method
CN102286984A (en) Water-stop curtain and construction method thereof
CN109098175A (en) A kind of tri-axes deep mixing pile construction method
CN111042249A (en) Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN104963346A (en) Support construction method for deep foundation pit in complex geological condition
CN110952528A (en) Construction method of cement-soil underground continuous wall under complex geological conditions
CN201395793Y (en) Long spiral high-pressure spraying mud injecting stirring pile-forming device
CN108265706A (en) A kind of engineering pile and pile-formation process in solution cavity geology
CN107338789A (en) A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake
CN107060800A (en) A kind of shield-tunneling construction huge stone handling construction method
US3839871A (en) Earthen dam repair
CN104631479B (en) Construction method of soil-changing and stirring waterproof curtain
CN110241836A (en) A kind of construction method of embedding rock water-stop curtain
KR20140019861A (en) Foundation method for complex pile
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
CN105019913A (en) Base rock uplift region shielding tool-changing in-situ reinforcement method
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN206800431U (en) A kind of sealing bottom type caisson wall
CN107700508A (en) A kind of shaped steel stirs the construction method of water spray soil curtain support pile
KR20080112453A (en) A ground improvement method of construction
CN104612164A (en) Reinforced composite envelope structure construction method
CN103821140B (en) A kind of construction method of reinforcing soft foundation
KR20140001042A (en) Boring apparatus for complex pile and foundation method using the same

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant