CN105586969A - 钻孔灌注桩桩头分层凿除法 - Google Patents

钻孔灌注桩桩头分层凿除法 Download PDF

Info

Publication number
CN105586969A
CN105586969A CN201410641511.1A CN201410641511A CN105586969A CN 105586969 A CN105586969 A CN 105586969A CN 201410641511 A CN201410641511 A CN 201410641511A CN 105586969 A CN105586969 A CN 105586969A
Authority
CN
China
Prior art keywords
pile crown
pile
excavation
cuts
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410641511.1A
Other languages
English (en)
Inventor
赖文平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410641511.1A priority Critical patent/CN105586969A/zh
Publication of CN105586969A publication Critical patent/CN105586969A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本发明公开了一种钻孔灌注桩桩头凿除的方法及步骤,本发明适用于各类高度的桩头凿除,对基坑开挖进行分层开挖,对桩头进行分层凿除,特别是针对一些高大桩头,本发明具有更广泛的适用性,故命名为:钻孔灌注桩高大桩头分层凿除法。其步骤包括:(1)基坑初探式开挖:确定开挖基坑内超灌高度最大的桩头,以此作为基坑分层开挖及桩头分层凿除的分层标准;(2)桩头高程测量:确定基坑内超灌高度最大的桩头后,用测量仪器测量超灌桩头顶面高程,并与设计桩顶高程对比,确定超灌高度;(3)桩头分层凿除法层数的确定:选取最有利凿桩高度,确定分层凿除法的层数;(4)根据(3)所分的层数,逐层开挖基坑,逐层凿除桩头。

Description

钻孔灌注桩桩头分层凿除法
技术领域:
本发明涉及一种土木工程施工中钻孔灌注桩桩头的凿除方法,尤其是针对钻孔灌注桩混凝土高大桩头的凿除方法。
背景技术:
现有的钻孔灌注桩桩头的凿除方法是在桩头超灌高度合理的情况才适用的,在目前的工程建设中,当超灌高度合理的钻孔灌注桩桩头采用风镐结合人工修凿时,普遍采用的桩头凿除方法可以归结为以下步骤:
(1)基坑开挖:确定开挖尺寸后将基坑一次性开挖至垫层底以上30cm左右,留下的部分采用人工挖除、修整。
(2)桩头测量:基坑开挖完成后,进行桩头高程放样,考虑预留桩头嵌入结构物的高度后,做好标线。
(3)桩头凿除:凿桩作业人员进入基坑内根据做好的标线将桩头凿除,再用合适吨位的吊车将凿除的桩头吊运出基坑,弃置于指定位置。
当施工过程中遇到高大桩头时,这一凿除方法存在许多涉及施工安全、施工质量及施工进度的缺陷:
(1)施工安全:桩头凿除高度一般控制在0.5~1.5m,当桩头高度超过作业人员身高2倍时,凿桩过程中桩头容易倾倒压伤施工作业人员。
(2)施工质量:高大桩头倾倒后容易挤压碰撞临近桩基,影响桩身质量。
(3)施工进度:当发现高大桩头无法用现有吨位的吊车吊运桩头,则必须调用其它合适机械,造成不必要的二次施工和机械的二次调用,影响施工进度。
发明内容:
本发明所要解决的施工技术问题是提高一种适用于各种高度的桩头凿除方法。
本发明解决上述施工技术问题所采用的技术方案及施工步骤如下:
(1)基坑初探式开挖:确定开挖基坑内超灌高度最大的桩头,以此桩头作为基坑分层开挖及桩头分层凿除的分层标准。
根据勘探地质和基坑深度情况,并综合考虑施工作业空间,确定开挖尺寸和开挖方式,做好边坡防护及坑顶安全防护,必要时采取基坑降水措施。在满足基坑开挖条件后,挖掘机进行初探式开挖,开挖深度以桩头顶面漏出10cm为宜,依次确定基坑内所有桩头顶面所在位置。
(2)桩头高程测量:确定基坑内超灌高度最大的桩头后,用水准仪测量超灌桩头顶面高程h,并与设计桩顶高程H对比,确定超灌高度Δh=H-h。
根据基坑初探式开挖确定的桩头顶面位置,选取桩头顶面高程最大的桩头,用水准仪测量其顶面高程值,并与设计桩顶高程对比,确定超灌高度,本文以桩头超灌高度为4m做为计算实例。
(3)桩头分层凿除法层数的确定:以1.5m的最有利凿桩高度为准,确定分层凿除法的层数n=Δh/1.5,最有利凿桩高度可根据实际情况进行选取,一般取0.5~2m为宜。
根据超灌高度,确定桩头宜分几层进行凿除,以桩头超灌4m为例,则n=4/1.5=3,宜分3层进行凿除。
(4)第一层桩头凿除:将基坑开挖至距离超灌桩头顶面1.5m处,凿桩作业人员进入基坑内将第一层桩头凿除,用合适吨位的吊车将凿除的桩头吊运出基坑,弃置于指定位置。
(5)第二层桩头凿除:将基坑开挖至距离超灌桩头顶面3.0m处,凿桩作业人员进入基坑内将第二层桩头凿除,用合适吨位的吊车将凿除的桩头吊运出基坑,弃置于指定位置。
(6)第三层桩头凿除:将基坑开挖至垫层底以上30cm左右,留下部分采用人工挖清,凿桩作业人员进入基坑内将第三层桩头凿除(注意预留桩头嵌入结构物的高度),用合适吨位的吊车将凿除的桩头吊运出基坑,弃置于指定位置,桩头凿除完毕。
与目前现有的桩头凿除方法相比,本发明的优点在于适用于各个高度的桩头凿除,可以根据实际需要进行分层,适用情况更为广泛。

Claims (4)

1.一种土木工程施工中钻孔灌注桩桩头的凿除方法,尤其是针对钻孔灌注桩混凝土高大桩头的凿除方法,其特征是:基坑开挖不一次性开挖到位,桩头不一次性凿除完毕。
2.根据权利要求1所述的桩头凿除方法,其特征是:在施工过程中遇到高大桩头时,这一凿除方法避免了许多涉及施工安全、施工质量及施工进度的缺陷。
3.根据权利要求1所述的桩头凿除方法,其步骤包括:(1)基坑初探式开挖:确定开挖基坑内超灌高度最大的桩头,以此桩头作为基坑分层开挖及桩头分层凿除的分层标准;(2)桩头高程测量:确定基坑内超灌高度最大的桩头后,用水准仪测量超灌桩头顶面高程h,并与设计桩顶高程H对比,确定超灌高度Δh=H-h:(3)桩头分层凿除法层数的确定:以1.5m的最有利凿桩高度为准,确定分层凿除法的层数n=Δh/1.5,最有利凿桩高度可根据实际情况进行选取,一般取0.5~2m为宜;(4)根据(3)所分的层数,逐层开挖基坑,逐层凿除桩头。
4.根据权利要求1所述的桩头凿除方法,其特征是:可以根据工程实际需要,适用于各个高度的桩头凿除对桩头凿除高度进行分层,使施工过程更为安全,施工质量更有保证,提高施工进度。
CN201410641511.1A 2014-11-14 2014-11-14 钻孔灌注桩桩头分层凿除法 Pending CN105586969A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410641511.1A CN105586969A (zh) 2014-11-14 2014-11-14 钻孔灌注桩桩头分层凿除法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410641511.1A CN105586969A (zh) 2014-11-14 2014-11-14 钻孔灌注桩桩头分层凿除法

Publications (1)

Publication Number Publication Date
CN105586969A true CN105586969A (zh) 2016-05-18

Family

ID=55926854

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410641511.1A Pending CN105586969A (zh) 2014-11-14 2014-11-14 钻孔灌注桩桩头分层凿除法

Country Status (1)

Country Link
CN (1) CN105586969A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970961A (zh) * 2016-05-20 2016-09-28 中国电建集团华东勘测设计研究院有限公司 一种灌注桩围护基坑安全截桩方法
CN115182346A (zh) * 2022-06-22 2022-10-14 中交广州航道局有限公司 一种环保型海底dcm桩头清除施工工艺

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970961A (zh) * 2016-05-20 2016-09-28 中国电建集团华东勘测设计研究院有限公司 一种灌注桩围护基坑安全截桩方法
CN105970961B (zh) * 2016-05-20 2018-08-07 中国电建集团华东勘测设计研究院有限公司 一种灌注桩围护基坑安全截桩方法
CN115182346A (zh) * 2022-06-22 2022-10-14 中交广州航道局有限公司 一种环保型海底dcm桩头清除施工工艺

Similar Documents

Publication Publication Date Title
CN106120702B (zh) 高填方人工地基分层回填分层强夯组合加固方法
CN104846829A (zh) 预留盾构穿越复合式基坑围护墙及其施工方法
CN106812531A (zh) 盾构机的盾构始发施工方法
CN102635113A (zh) 一种液压振动沉管灌注桩施工方法
CN204199335U (zh) 一种减小phc管桩施工挤土效应的泄压井
CN106567379A (zh) 人工排降水、垫层、低能量置换强夯浅层地基加固方法
CN112030956A (zh) 一种岩溶地层钻孔灌注桩施工方法
CN104632244A (zh) 确定地面沉降对地铁隧道沉降影响及保护隧道结构的方法
CN112227296A (zh) 水下深基槽破岩施工方法
CN110259467A (zh) 泥水平衡盾构下穿江河施工方法
CN205576888U (zh) 一种增压式真空预压法加固软土地基结构
CN107503344A (zh) 周转式分节钢护筒护壁人工挖孔灌注桩的施工方法
CN105586969A (zh) 钻孔灌注桩桩头分层凿除法
CN111648353A (zh) 一种基于bim三维地质模型的岩溶地区旋挖灌注桩施工方法
CN112281894A (zh) 一种桩基础施工方法
CN113846618A (zh) 一种地基处理强夯置换加固方法
CN108425359A (zh) 一种采用地下水回灌控制降水对环境影响的方法
CN113502817B (zh) 一种自动化施工预应力桩的方法
CN110984132A (zh) 复杂地质条件下地下连续墙成槽的施工方法
CN105200994A (zh) 预留盾构穿越复合式基坑围护装置的施工工法
CN110424486A (zh) 一种非标准地下连续墙的施工方法
CN112962586A (zh) 一种适用于岩层地区的钻孔灌注桩施工工艺
CN212052725U (zh) 溶洞区桩施工结构
CN103806444A (zh) 一种软土层旋挖桩施工方法
CN111335912A (zh) 湿陷性黄土地区软土地基大管径机械顶管施工工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Lai Wenping

Document name: Notification of before Expiration of Request of Examination as to Substance

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160518