CN105570532B - 一种顶管位移偏差的纠偏施工方法 - Google Patents
一种顶管位移偏差的纠偏施工方法 Download PDFInfo
- Publication number
- CN105570532B CN105570532B CN201510925635.7A CN201510925635A CN105570532B CN 105570532 B CN105570532 B CN 105570532B CN 201510925635 A CN201510925635 A CN 201510925635A CN 105570532 B CN105570532 B CN 105570532B
- Authority
- CN
- China
- Prior art keywords
- push pipe
- deviation
- framework
- steel reinforcement
- plug
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/06—Accessories therefor, e.g. anchors
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明提供一种顶管位移偏差的纠偏施工方法,属于市政工程技术领域。该方法首先在顶管预制时,在顶管的端头预埋钢筋卡栓,钢筋卡栓均布在顶管四周,在顶管的上部预插入挂勾,采用悬挂垂球来查看顶管的前进的高差及左右方位偏差,随着顶管不断的延伸,每节在顶进到对应位置后,通过垂球的对中来查看顶管的偏位情况,若存在偏位,在前进顶管的端头,安装钢筋外挂架,外挂钢筋架卡在顶管端头,通过左右及上下缓慢撬动外挂架上钢筋骨架,使顶管缓慢移动,纠偏过程完成后卸下钢筋外挂架,继续顶进。本发明方法安装操作简单方便,位移偏差每节均在控制范围内,不会造成较大偏差,控制偏差准确。
Description
技术领域:
本发明属于市政工程技术领域,具体涉及一种顶管位移偏差的纠偏施工方法,尤其涉及通过垂球及顶管外挂调整骨架及卡栓来完成纠偏过程的一种施工方法。
背景技术:
目前在城市道路施工中,随着市政工程的不断增多,对埋设于地下的管网工程在施工中如何减少对道路交通、周边构筑物及周边居民的影响提出了更高的要求。为了最大限度地减少对地面环境的影响,在地下管线的铺设与改造中,非开挖施工技术越来越多受到重视。作为非开挖技术中近几年采用的顶管施工技术广泛用于城市道路管网改造工程中,但混凝土顶管在顶进的过程中由于受力的不均匀及顶进方向的不同,造成顶管的位移偏差,如何控制在顶进过程中位移的偏差,是施工中的控制重点。
发明内容:
本发明针对现有顶管位移偏差处理技术中存在的以上问题,提供一种顶管位移偏差的纠偏施工方法。本发明施工方法具体步骤如下:
(1)在顶管预制时,在顶管3的端头预埋长度为5cm的钢筋卡栓4,所述钢筋卡栓4均布在所述顶管3的四周,所述顶管3的上端设有挂垂球5的挂勾6。
(2)制作外挂钢筋骨架1,所述外挂钢筋骨架1的宽度与所述顶管3的壁厚一致;在外挂钢筋骨架1内圈上焊接钢筋骨架挂勾2。
(3)在顶管3上部上悬挂垂球5。
(4)在顶管3顶进过程中,通过垂球5的左右位移摆动及纵向位移偏差来判断顶管的位移偏差。
(5)在发生左右位移偏差时,在所述顶管3前进的作业面,开挖一定的工作面,安装所述外挂钢筋骨架1及钢筋骨架挂勾2,所述外挂钢筋骨架1挂在所述钢筋卡栓4上,卡栓为相扣设置,通过旋转所述钢筋骨架挂勾2,使钢筋骨架挂勾2与所述钢筋卡栓4紧紧卡住,采用撬杠在左右位置缓慢撬动所述外挂钢筋骨架1的内侧,撬动位置当所述垂球5的方向及左右偏差跟上一节顶管纵平面相同时,停止撬动,在撬动的背面垫入速凝混凝土。
(6)当上下位置存在偏差时,采用在所述外挂钢筋骨架1上下相应位置进行撬动,使位置缓慢纠正过来,实现整个纠偏过程。
本发明方法安装操作简单方便,位移偏差每节均在控制范围内,不会造成较大偏差,控制偏差准确无误。
附图说明:
图1为本发明外挂钢筋骨架纠偏安装纵面图;
图2为本发明外挂钢筋骨架纠偏安装的剖面图;
图3为本发明顶管结构示意图;
图4为本发明外挂钢筋骨架结构示意图;
图5为图4左视结构示意图;
图中:1:外挂钢筋骨架;2:钢筋骨架挂勾;3:顶管;4:钢筋卡栓;5:垂球;6:挂勾。
具体实施方式:
本发明提供一种顶管位移偏差的纠偏施工方法。该方法具体步骤如下:
(1)在顶管3的端头预埋长度为5cm的钢筋卡栓4,钢筋卡栓4均布在顶管3的四周,顶管3的上端设有挂垂球5的挂勾6,在顶管3上部悬挂垂球5。
(2)制作外挂钢筋骨架1,外挂钢筋骨架1的宽度与顶管3的壁厚一致,在外挂钢筋骨架1内圈上焊接钢筋骨架挂勾2,钢筋骨架挂勾2相向设置焊接。
(3)在发生左右位移偏差时,在顶管3前进的作业面,开挖一定的工作面,安装外挂钢筋骨架1及钢筋骨架挂勾2,外挂钢筋骨架1挂在钢筋卡栓4上,通过旋转钢筋骨架挂勾2,使钢筋骨架挂勾2与钢筋卡栓4紧紧卡住,采用撬杠在左右位置缓慢撬动外挂钢筋骨架1的内侧,撬动位置当垂球5的方向及左右偏差跟上一节顶管纵平面相同时,停止撬动,在撬动的背面垫入速凝混凝土。
(4)当上下位置存在偏差时,采用在外挂钢筋骨架1上下相应位置进行撬动,使位置缓慢纠正过来,实现整个纠偏过程。
本发明通过一种装置和调整位移偏差的施工方法来实现,此装置设置于顶管的施工管道前端,在顶管预制的过程中在顶管的上部预插入小勾,采用悬挂垂球来查看顶管的前进的高差及左右方位偏差,随着顶管不断的延伸,每节在顶进到对应位置后,通过前后顶管的垂球的对中来查看顶管的偏位情况,若存在偏位,在前进顶管的端头,安装钢筋外挂架,外挂钢筋架卡在顶管端头,通过左右及上下缓慢撬动外挂架上的撬环,使顶管缓慢移动,纠偏过程完成后卸下钢筋外挂架,继续顶进。
此施工方法简单易操作,在顶管前进操作面小、空间有限的条件下,使顶管的偏差控制在允许的范围内,调整起来方便可行,节省人力物力。运用此施工方法,只须1-2人即可完成纠偏过程,效果显著。
Claims (1)
1.一种顶管位移偏差的纠偏施工方法,其特征在于该施工方法具体步骤如下:
(1)在顶管预制时,在顶管(3)的端头预埋长度为5cm的钢筋卡栓(4),所述钢筋卡栓(4)均布在所述顶管(3)的四周,所述顶管(3)的上端设有挂垂球(5)的挂勾(6);
(2)制作外挂钢筋骨架(1),所述外挂钢筋骨架(1)的宽度与所述顶管(3)的壁厚一致,在所述外挂钢筋骨架(1)内圈上焊接钢筋骨架挂勾(2),所述钢筋骨架挂勾(2)相向设置焊接;
(3)在所述顶管(3)上部悬挂所述垂球(5);
(4)在所述顶管(3)顶进过程中,通过所述垂球(5)的左右位移摆动及纵向位移偏差来判断顶管的位移偏差;
(5)在发生左右位移偏差时,在所述顶管(3)前进的作业面,开挖一定的工作面,安装所述外挂钢筋骨架(1)及钢筋骨架挂勾(2),所述外挂钢筋骨架(1)挂在所述钢筋卡栓(4)上,卡栓为相扣设置,通过旋转所述钢筋骨架挂勾(2),使钢筋骨架挂勾(2)与所述钢筋卡栓(4)紧紧卡住,采用撬杠在左右位置缓慢撬动所述外挂钢筋骨架(1)的内侧,撬动位置当所述垂球(5)的方向及左右偏差跟上一节顶管纵平面相同时,停止撬动,在撬动的背面垫入速凝混凝土;
(6)当上下位置存在偏差时,采用在所述外挂钢筋骨架(1)上下相应位置进行撬动,使位置缓慢纠正过来,实现整个纠偏过程。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510925635.7A CN105570532B (zh) | 2015-12-10 | 2015-12-10 | 一种顶管位移偏差的纠偏施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510925635.7A CN105570532B (zh) | 2015-12-10 | 2015-12-10 | 一种顶管位移偏差的纠偏施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105570532A CN105570532A (zh) | 2016-05-11 |
CN105570532B true CN105570532B (zh) | 2017-07-04 |
Family
ID=55880991
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510925635.7A Active CN105570532B (zh) | 2015-12-10 | 2015-12-10 | 一种顶管位移偏差的纠偏施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105570532B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110726003B (zh) * | 2019-09-27 | 2021-02-26 | 中建七局第二建筑有限公司 | 一种玻璃钢夹砂管安装过程中的纠偏施工方法 |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06129188A (ja) * | 1992-10-20 | 1994-05-10 | Takasago Thermal Eng Co Ltd | 埋設配管施工方法 |
JP2681586B2 (ja) * | 1992-12-17 | 1997-11-26 | 株式会社奥村組 | 管体推進装置 |
JP3978746B2 (ja) * | 2003-03-31 | 2007-09-19 | 堤 郁夫 | 管体設置方法 |
CN1456832A (zh) * | 2003-04-17 | 2003-11-19 | 冯毅 | 水下进出平衡顶管法施工工艺 |
JP4196292B2 (ja) * | 2004-06-14 | 2008-12-17 | 清水建設株式会社 | 既設管撤去方法 |
CN201363486Y (zh) * | 2009-03-30 | 2009-12-16 | 江西省第三建筑有限责任公司 | 带加长管的泥水平衡顶管机机头 |
CN103603997B (zh) * | 2013-11-19 | 2015-12-30 | 厦门水务集团有限公司 | 顶管后退纠偏的施工方法 |
-
2015
- 2015-12-10 CN CN201510925635.7A patent/CN105570532B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN105570532A (zh) | 2016-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9777881B2 (en) | Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines | |
KR20210130725A (ko) | 보강장치 및 다량 수분 함유 자갈 지층 중 심층 피트 국소 냉동 보강 시공 방법 | |
CN109323049B (zh) | 应用于穿越桥梁的套管式输水管道及其安装施工方法 | |
CN103758123B (zh) | 人工挖孔灌注桩护壁衬的施工方法 | |
CN104612698A (zh) | 一种浅埋暗挖隧道上台阶中隔壁施工方法 | |
CN103821520B (zh) | 固定矿山立井井筒装备的方法 | |
CN105256812A (zh) | 基坑预制装配式混凝土支撑结构及其施工方法 | |
CN112727466A (zh) | 一种无支护预制拼装式盾构隧道风井结构施工方法 | |
CN110206071B (zh) | 一种地下连续墙接缝加固方法与装置 | |
CN103807504B (zh) | 钢筋混凝土顶管地下t形对接的施工方法 | |
CN104453915B (zh) | 大断面竖井预注浆加固快速开挖方法 | |
CN102220764B (zh) | 深基坑支护体系的施工方法 | |
CN105570532B (zh) | 一种顶管位移偏差的纠偏施工方法 | |
CN110671132B (zh) | 一种基于套拱的深埋黄土隧道变形控制施工结构及方法 | |
CN104863183A (zh) | 大断面隧道近接建筑物施工隔离减震桩结构及施工方法 | |
JP7178243B2 (ja) | トンネル覆工体の施工方法 | |
CN203891047U (zh) | 搭设钢平台进行陆上桥梁基础施工设备 | |
CN207717504U (zh) | 一种用于超大型岔管群水压试验的支撑结构 | |
CN105484270A (zh) | 一种毗邻深基坑高陡老旧毛石挡土墙加固保护施工方法 | |
CN105863649A (zh) | 一种地表微创地下空间暗挖的构筑技术 | |
CN105274984A (zh) | 一种双重套管全回转施工立柱桩方法 | |
CN104711981A (zh) | 一种基坑土钉支护结构和方法 | |
CN109797635B (zh) | 一种用于公路施工的混凝土浇筑模板自动施工方法及配套装置 | |
CN110552702B (zh) | 一种拼装波纹钢板地下综合管廊的暗挖施工方法 | |
CN203701089U (zh) | 一种钢筋砼排水管护壁人工挖孔接桩用结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |