CN105569339B - Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase - Google Patents

Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase Download PDF

Info

Publication number
CN105569339B
CN105569339B CN201511029293.7A CN201511029293A CN105569339B CN 105569339 B CN105569339 B CN 105569339B CN 201511029293 A CN201511029293 A CN 201511029293A CN 105569339 B CN105569339 B CN 105569339B
Authority
CN
China
Prior art keywords
construction
sections
combined
storehouse
order
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201511029293.7A
Other languages
Chinese (zh)
Other versions
CN105569339A (en
Inventor
张同波
叶林
王宇飞
李翠翠
吴伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingjian Group Co Ltd
Original Assignee
Qingjian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingjian Group Co Ltd filed Critical Qingjian Group Co Ltd
Priority to CN201511029293.7A priority Critical patent/CN105569339B/en
Publication of CN105569339A publication Critical patent/CN105569339A/en
Application granted granted Critical
Publication of CN105569339B publication Critical patent/CN105569339B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Abstract

The present invention and technical field of building construction, a kind of order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase are specifically disclosed, the construction method includes order with jumping the construction organization technology that storehouse is combined and the construction organization technology that interval is combined with strengthening phase.The overlong jointless structural construction method being combined " sequentially with jumping storehouse, intermittently with strengthening " of the present invention, it can be widely applied in Overlong Concrete Structure construction, Shrinkage Cracking of Concrete can be efficiently controlled, construction quality is improved, accelerates speed of application, there is higher economic and social benefit.

Description

Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase
Technical field
The present invention relates to technical field of building construction, more particularly to a kind of order with jumping storehouse, intermittently being combined with strengthening phase Overlong jointless structural construction method.
Background technology
Overlong Concrete Structure is constructed, now to use setting post-cast strip method or carry out jump storehouse method construction more, but post-cast strip A series of problems in practice of construction operating process be present, and jumping storehouse method merely has larger limitation.Using setting post-cast strip Method, in practice of construction operating process, often Yin Liu sets post-cast strip and causes many construction quality problems.And jump storehouse fado For mass concrete, and it is mostly 7-10 days to pour interval time, limitation be present.
The content of the invention
In order to solve above-mentioned problems of the prior art, the invention provides a kind of order with jumping storehouse, intermittently with adding The overlong jointless structural construction method being combined by force, this overlong jointless structural being combined " sequentially with jumping storehouse, intermittently with strengthening " Construction technology can be widely applied in Overlong Concrete Structure construction, can efficiently control Shrinkage Cracking of Concrete, improve Construction quality, accelerate speed of application, there is higher economic and social benefit.
The technical proposal of the invention is realized in this way:
Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase, it is characterised in that:The construction Method includes order with jumping the construction organization technology that storehouse is combined and the construction organization technology that interval is combined with strengthening phase;
The order with jump storehouse be combined, is intermittently combined with strengthening phase refer in concrete pouring construction to satisfaction it is most short The adjacent construction section of intermittent time, the construction method being combined using order with jumping storehouse, to being unsatisfactory for the most short intermittent time and not The adjacent construction section for jumping storehouse method can be used, using the construction method of intermittent reinforcing band;
The overlong jointless structural construction refers to must be provided with building as defined in post-cast strip more than specification to length, carried out It is not provided with the method for any control disposable sequence construction of temperature shrinkage post-cast strip;
The most short intermittent time:The concrete temperature drawn by experiment and theory analysis shrinks, in controlled range The most short of adjacent concrete construction section pours interval time;
The operation side for the construction organization technology that the order is combined with jumping storehouse can be divided into I and II great Qu, A/B/ Eight construction sections of C/D/E/F/G/H, the order with jump the construction organization technology that is combined of storehouse include order flowing water sequence of construction, Jump storehouse sequence of construction;
The operation side for the construction organization technology that the interval is combined with strengthening phase is six constructions of A, B, C, D, E and F Section, expansion reinforcing band is set between regional.
Further, the order flowing water sequence of construction is to carry out cross construction, sequence of construction respectively in I and II great Qu I.e. A construction sections proceed to B construction sections, then proceed to C construction sections, finally move to D construction sections;E construction sections proceed to F constructions Section, then proceed to G construction sections, finally move to H construction sections.
Further, the jump storehouse sequence of construction can be that parallel construction or flowing water and parallel combination are constructed, and construction is suitable Sequence first carries out A construction sections to C construction sections, then to E construction sections, finally to G construction sections, then carries out B construction sections to D construction sections, F construction sections are arrived again, finally to H construction sections.
Further, the sequence of construction for the construction organization technology that the interval is combined with strengthening phase is that A construction sections proceed to B Construction section, then proceed to C construction sections;D construction sections proceed to E construction sections, then proceed to F construction sections.
Further, the construction section is poured simultaneously, and the A construction sections and D construction sections, B construction sections and E construction sections, C are applied Expansion reinforcing band is set between workshop section and F construction sections.
The beneficial effects of the invention are as follows:This overlong jointless structural construction being combined " sequentially with jumping storehouse, intermittently with strengthening " Technology can be widely applied in Overlong Concrete Structure construction, can efficiently control Shrinkage Cracking of Concrete, improve engineering Quality, accelerate speed of application, there is higher economic and social benefit.It is directed to the construction of different parts Overlong Concrete Structure Situation, it is proposed that the overlong jointless structural construction method of " be sequentially combined with jumping storehouse, intermittently combined with strengthening phase " of system, both The demand of anti-crack of Overlong Concrete Structure can be met, and be combined with practice of construction hoc scenario, before construction quality is ensured Put, accelerate the speed of construction, reduce the cost of construction.Meet the demand of anti-crack of Overlong Concrete Structure, improve engineering Quality;Pour the most short intermittent time is combined with the sequence construction intermittent time, adapts to engineering practice of construction hoc scenario, accelerates to apply Work speed, is widely used in Practical Project, has dissemination.
Brief description of the drawings
Fig. 1 is order flowing water sequence of construction schematic diagram;
Fig. 2 is jump storehouse method sequence of construction schematic diagram;
Fig. 3 is wall and basement floor slab construction schematic illustration of tissue;
Fig. 4 is intermittent reinforcing band sequence of construction schematic diagram.
Reference:1st, wall;2nd, expansion reinforcing band.
Embodiment
With reference to specific embodiment, the present invention will be further described, but does not limit the present invention.
A kind of order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase, construction method include suitable Sequence is the same as jumping the construction organization technology that storehouse is combined and the construction organization technology that interval is combined with strengthening phase;
Order is combined with jumping storehouse, is intermittently combined and refers in concrete pouring construction to the most short interval of satisfaction with strengthening phase The adjacent construction section of time, the construction method being combined using order with jumping storehouse, can not make again to being unsatisfactory for the most short intermittent time With jump storehouse method adjacent construction section, using the construction method of intermittent reinforcing band;
Overlong jointless structural construction refers to must be provided with building as defined in post-cast strip more than specification to length, not set The method for putting any control disposable sequence construction of temperature shrinkage post-cast strip;
The most short intermittent time is that the concrete temperature drawn by experiment and theory analysis shrinks, adjacent in controlled range The most short of concrete construction section pours interval time.
1st, the construction organization technology being sequentially combined with jumping storehouse
To ensure the jointless construction of Overlong Concrete Structure, jointless construction is kept under different construction requirements, is mainly taken suitable The mobilization that sequence is combined with jumping storehouse.First choose a typical condition of construction to illustrate, face of making even is 160 meters of * 60 meters of operation sides, are divided into Liang Ge great areas:I and II;8 construction sections, numbering A/B/C/D/E/F/G/H.
(1) as shown in Figure 1, when order cross construction can meet the requirement of most short intermittent time, then subregion is organized Order cross construction;The intermittent time can be changed by adjusting the construction organization of critical process (reinforcing bar), it is most short to meet Intermittent time or the requirement of duration.Cross construction is carried out respectively in I, II Liang Ge great areas, and sequence of construction is as illustrated, apply Workshop section A → B → C → D and construction section E → F → G → H.It is tight in the duration and when can meeting most short intermittent time requirement, it can pass through Extend the node of critical process forward, form it into certain parallel construction, to accelerate speed of application, i.e.,:Parallel and flowing water knot Close construction.The colligation of critical process reinforcing bar carries out certain parallel construction, so as to accelerate speed of application.
(2) as shown in Figure 2, it is tight in the duration and when can not meet that the most short intermittent time requires, it can select to jump storehouse construction Method, should be that parallel construction or flowing water be constructed with parallel combination in its construction organization.First construct construction section A, C, E, G Section is constructed construction section B, D, F, H section again.It is mass concrete in main building, its most short intermittent time is long and sequence construction can not expire When foot requires, it can also use to jump storehouse and sequentially combine and construct.
(3) wall 1 and basement floor slab construction tissue.It is first, consistent with bottom plate subregion;Second, it can not meet in wall 1 When intermittent time requires, subregion can be increased to reduce pinch confinement of the bottom plate to wall 1.As shown in Figure 3, wall 1 presses bottom Plate has carried out corresponding subregion.
2nd, the construction organization technology intermittently combined with strengthening phase
As shown in Figure 4, when engineering adjacent area is to meet that construction period need to pour in 1-3 days, it is impossible to meet most short Intermittent time, when can not carry out jumping the construction of storehouse method again, the construction method of selectively-expandable reinforcing strip 2.Here a typical case is selected Engineering Projects, this method is illustrated.
Operation side is six construction sections of A/B/C/D/E/F, and sequence construction is construction section A → B → C and construction section D → E →F;Such as require construction section while pour, you can expansion reinforcing band 2 is set between A-D, B-E, C-F area, reaches synchronous construction Purpose, save the duration.
Upper described is only the preferred embodiment of invention, is not intended to limit the invention, all spirit in the present invention and Within principle, any modification, equivalent substitution and improvements made etc., it should be included in the scope of the protection.

Claims (5)

1. order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase, it is characterised in that:The construction party Method includes order with jumping the construction organization technology that storehouse is combined and the construction organization technology that interval is combined with strengthening phase;
The order is combined with jumping storehouse, is intermittently combined and refers in concrete pouring construction to the most short interval of satisfaction with strengthening phase The adjacent construction section of time, the construction method being combined using order with jumping storehouse, can not make again to being unsatisfactory for the most short intermittent time With jump storehouse method adjacent construction section, using the construction method of intermittent reinforcing band;
The overlong jointless structural construction refers to must be provided with building as defined in post-cast strip more than specification to length, not set The method for putting any control disposable sequence construction of temperature shrinkage post-cast strip;
The most short intermittent time:The concrete temperature drawn by experiment and theory analysis shrinks, adjacent in controlled range The most short of concrete construction section pours interval time;
The operation side for the construction organization technology that the order is combined with jumping storehouse is divided into I and II great Qu, A/B/C/D/E/ Eight construction sections of F/G/H, with jumping, the construction organization technology that storehouse is combined includes order flowing water sequence of construction to the order, jump storehouse is applied Work order;
The operation side for the construction organization technology that the interval is combined with strengthening phase is six construction sections of A, B, C, D, E and F, respectively Expansion reinforcing band is set between individual region.
2. order according to claim 1 and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase, its It is characterised by, the order flowing water sequence of construction is to carry out cross construction respectively in I and II great Qu, and sequence of construction is A constructions Section proceeds to B construction sections, then proceeds to C construction sections, finally moves to D construction sections;E construction sections proceed to F construction sections, then carry out To G construction sections, H construction sections are finally moved to.
3. order according to claim 2 and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase, its It is characterised by, the jump storehouse sequence of construction is that parallel construction or flowing water and parallel combination are constructed, and sequence of construction first carries out A Construction section finally to G construction sections, then carries out B construction sections to D construction sections to C construction sections, then to E construction sections, then to F construction sections, Finally arrive H construction sections.
4. order according to claim 1 and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase, its It is characterised by, the sequence of construction for the construction organization technology that the interval is combined with strengthening phase proceeds to B construction sections for A construction sections, Proceed to C construction sections again;D construction sections proceed to E construction sections, then proceed to F construction sections.
5. order according to claim 4 and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase, its It is characterised by, the construction section pours simultaneously, the A construction sections and D construction sections, B construction sections and E construction sections, C construction sections and F Expansion reinforcing band is set between construction section.
CN201511029293.7A 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase Active CN105569339B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511029293.7A CN105569339B (en) 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511029293.7A CN105569339B (en) 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase

Publications (2)

Publication Number Publication Date
CN105569339A CN105569339A (en) 2016-05-11
CN105569339B true CN105569339B (en) 2017-11-17

Family

ID=55879910

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511029293.7A Active CN105569339B (en) 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase

Country Status (1)

Country Link
CN (1) CN105569339B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638998A (en) * 2016-10-17 2017-05-10 中国建筑第八工程局有限公司 Concrete vertical alternative bay construction method
CN108396899A (en) * 2018-03-23 2018-08-14 中国十七冶集团有限公司 A kind of ground library concrete plate surface jumps block formula pouring structure and its construction method
CN112709261A (en) * 2020-12-22 2021-04-27 碧源建工有限公司 Construction method based on skip method and intermittent expansion reinforcing belt
CN113897909B (en) * 2021-09-07 2022-09-30 中建一局集团建设发展有限公司 Construction method of expansion reinforcing band connecting structure in complex arc-shaped water channel

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06313305A (en) * 1993-04-28 1994-11-08 Kawasaki Steel Corp Jointless multiple span floor slab bridge
NL193327C (en) * 1993-05-21 1999-06-02 Bers F J Van Method for laying a floating floor using an elastic underlay, as well as an elastic underlay with an adhesive layer and a paper layer.
US5760106A (en) * 1995-07-05 1998-06-02 Board Of Trustees Operating Michigan State University Sealant method of epoxy resin-clay composites
CN102251674A (en) * 2011-06-05 2011-11-23 山东宁建建设集团有限公司 Bunker-skipping type seamless construction method of ultra-long concrete structure
CN102677899A (en) * 2012-03-09 2012-09-19 中石油东北炼化工程有限公司吉林设计院 Seamless structural method of overlong reinforced concrete pond

Also Published As

Publication number Publication date
CN105569339A (en) 2016-05-11

Similar Documents

Publication Publication Date Title
CN105569339B (en) Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase
CN104975716A (en) Construction method for employing dismounting-free formwork in casting constructional column and ring beam concrete
CN204343459U (en) The parapet node structure of overlaid plate type concrete shear wall system
CN107605070A (en) The node connection engineering method of overlaid plate type Combined concrete prefabricated components
CN204386018U (en) Autoclaved aerated concrete slabs steel sheet arrangement of reinforcement
CN208586815U (en) Beam form shell and exempt from template reinforced beam
CN106285001B (en) A kind of facet integration segment quickly intersects flowing water construction method
CN103061509B (en) Construction process for implementing post-cast strip casting by post-cast strip stiff steel pipe support system
CN205115941U (en) Building block of concatenation formula concrete road
CN103015597A (en) Construction method of energy-saving ribbed cavity floor
CN105133838B (en) A kind of concreting method for reducing construction module deformation
CN107012973A (en) The masonry structure and its construction method of a kind of new ribs building block
CN207211440U (en) Overlaid plate type Combined concrete prefabricated components
CN103216085B (en) A kind of removable lining self-bearing type reinforcement bar truss mould plate
CN104110131B (en) A kind of wall structure post hollow concrete formwork
CN201627360U (en) Turnover formwork construction device
CN109296116A (en) Centralized transverse prestress binding masonry and its method for applying prestressing force built in one kind
CN106968366A (en) A kind of construction method for pouring constructional column free removal template
CN208934250U (en) A kind of assembled exempts to tear round beam column concrete blinding open
CN206016054U (en) A kind of collar tie beam of aerated blocks or strip and preformed bricks
CN206752755U (en) A kind of constructional column, which pours, exempts from formwork prefabricated components
CN206681260U (en) A kind of multilayer steel-enclosed concrete members composite coupling beams
CN206616776U (en) A kind of Concrete seat pad of fixed floor bar
KR102213088B9 (en) Precast concrete girder for used by continuous construction method
CN203293352U (en) Die for utilizing building waste materials to prefabricate triangular building blocks

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant