CN105564442B - Kong Tie transportation systems and empty iron transportation resources - Google Patents
Kong Tie transportation systems and empty iron transportation resources Download PDFInfo
- Publication number
- CN105564442B CN105564442B CN201610029507.9A CN201610029507A CN105564442B CN 105564442 B CN105564442 B CN 105564442B CN 201610029507 A CN201610029507 A CN 201610029507A CN 105564442 B CN105564442 B CN 105564442B
- Authority
- CN
- China
- Prior art keywords
- start site
- platform
- empty iron
- lift
- station platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title claims abstract description 168
- 229910052742 iron Inorganic materials 0.000 title claims abstract description 84
- 238000000034 method Methods 0.000 claims description 9
- 230000000284 resting effect Effects 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000010276 construction Methods 0.000 claims description 3
- 239000007787 solid Substances 0.000 claims 1
- 230000032258 transport Effects 0.000 description 29
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 7
- 230000005484 gravity Effects 0.000 description 6
- 230000008569 process Effects 0.000 description 5
- 230000000694 effects Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 229910052751 metal Inorganic materials 0.000 description 2
- PMVSDNDAUGGCCE-TYYBGVCCSA-L Ferrous fumarate Chemical compound [Fe+2].[O-]C(=O)\C=C\C([O-])=O PMVSDNDAUGGCCE-TYYBGVCCSA-L 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000000977 initiatory effect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000021715 photosynthesis, light harvesting Effects 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61B—RAILWAY SYSTEMS; EQUIPMENT THEREFOR NOT OTHERWISE PROVIDED FOR
- B61B1/00—General arrangement of stations, platforms, or sidings; Railway networks; Rail vehicle marshalling systems
Abstract
The present invention, which provides Kong Tie transportation systems and empty iron transportation resources, Kong Tie transportation systems, to be included:Empty iron carrier, start site and purpose website.Start site includes start site platform, start site body and the first lift.Start site platform protrudes horizontally up with respect to start site body side.Start site platform is connected with the first lift, and the first lift control start site platform moves up and down in start site body, to adjust the height of the start site platform.Purpose website includes purpose station platform and purpose website body, and purpose station platform is arranged on purpose website body, and purpose station platform is protruded horizontally up for stopping empty iron carrier with respect to purpose website body side;First lift makes start site platform be in same level height with purpose station platform.Above-mentioned Kong Tie transportation systems and empty iron transportation resources have the characteristics that energy expenditure is low, conevying efficiency is high and can alleviate road traffic pressure.
Description
Technical field
The present invention relates to air transport technical field, is transported in particular to a kind of empty iron applied to air transport
System and empty iron transportation resources.
Background technology
Existing traditional means of transportation mainly includes land transportation, water transport and air transport.Land transportation constructs reason (such as because of continental geology:
High mountain, hills and mountain valley etc.) causing land transportation road, air line distance is obviously very short on map, and uses land often than more tortuous
Fortune transport really needs to travel very long stretch way, less efficient, while jam is very universal in land transportation road, can enter one
Step reduces the efficiency of land transportation transport.Water transport applies in general to the flourishing area of water system (such as:Canal or ocean bank city), water
Fortune transport there is also conevying efficiency it is relatively low the problem of.Compared with land transportation and water transport mode, air transport then has larger advantage.So
And in air transport aircraft take off or flight course in because need constantly adjustment flight position height need persistently to overcome gravity
Acting, can cause energy dissipation again.
The content of the invention
In order to overcome above shortcomings in the prior art, the technical problems to be solved by the invention are to provide one kind and disappeared
The transportation system and transportation resources that energy consumption is small and efficiency is higher.
For transportation system, the specific embodiment of the invention provides a kind of Kong Tie transportation systems.The Kong Tie transportation systems
Including:Empty iron carrier, start site and purpose website.The start site includes start site platform, start site body
And first lift.The start site platform and the first lift are fixedly installed on the start site body, the starting
The relatively described start site body side of station platform is protruded horizontally up for stopping the empty iron carrier.Put down the start site
Platform is connected with first lift, and first lift controls the start site platform on the start site body
Move up and down, to adjust the height of the start site platform.The purpose website includes purpose station platform and purpose
Website body.The purpose station platform is arranged on the purpose website body, the relatively described purpose of purpose station platform
Website body side is protruded horizontally up for stopping the empty iron carrier.First lift make the start site platform with
The purpose station platform is in same level height.
Further, purpose website described in above-mentioned Kong Tie transportation systems also includes the second lift.Second lifting
Machine is arranged on the purpose website body and is connected with the purpose station platform, and second lift controls the point of destination
Point platform moves up and down on the purpose website body, to adjust the height of the purpose station platform.Described first
Lift and/or second lift make the start site platform be in same level height with the purpose station platform
Degree.
Further, start site described in above-mentioned Kong Tie transportation systems also includes the first lowering or hoisting gear, described first liter
Falling unit is arranged at the start site body and is used for article in the start site body bottom portion and the start site platform
Between transport.The purpose website also includes the second lowering or hoisting gear, and second lowering or hoisting gear is arranged at the purpose website
Body is used for transport of the article between the purpose website body bottom portion and the purpose station platform.
Further, starting point described in above-mentioned Kong Tie transportation systems also includes the first fixing device, and described first fixes
Device is arranged on the start site platform, and first fixing device is used for resting in described in the start site platform
Empty iron carrier is fixed.The purpose website also includes the second fixing device, and second fixing device is arranged on described
Purpose station platform, second fixing device are used to carry out the empty iron carrier for resting in the purpose station platform
It is fixed.
Further, start site described in above-mentioned Kong Tie transportation systems also includes the first conveying arrangement, first fortune
Defeated device is arranged at the start site platform, and first conveying arrangement is used to article being transported into the empty iron carrier.
The purpose website also includes the second conveying arrangement, and second conveying arrangement is arranged at the purpose station platform, and described
Two conveying arrangements are used to transport article from the empty iron carrier.
Further, the first conveying arrangement described in above-mentioned Kong Tie transportation systems and the second conveying arrangement are transmission crawler belt.
Further, empty iron carrier described in above-mentioned Kong Tie transportation systems includes aerostatics and aircraft.
Further, empty iron carrier is preferably dirigible described in above-mentioned Kong Tie transportation systems.
Further, start site body described in above-mentioned Kong Tie transportation systems or the purpose website body are steelframe knot
Structure.
For transportation resources, another specific embodiment of the present invention provides a kind of empty iron transportation resources, and this method is using upper
The Kong Tie transportation systems stated, this method include:The article of the start site platform is transported into the empty iron carrier;It is logical
Crossing first lift makes the start site platform be in same level height with the purpose station platform;The empty iron
Carrier flies to the purpose station platform by way of moving horizontally from the start site platform;The empty iron carrier
Rest in the purpose station platform;Article is transported to the purpose station platform from the empty iron carrier.
In terms of existing technologies, the invention has the advantages that:Start site and purpose website are established, it is described
Relative level height can be adjusted by being used to stop the start site platform of the empty iron carrier in start site.Needing to carry out
During empty iron transport, the level height of the start site platform is adjusted, the start site platform is put down with the purpose website
Platform is in same level height.The empty iron carrier only need to be moved to the purpose website from the start site plateau levels
Platform, it is not necessary to overcome gravity acting in this process, can reduce energy loss has the effect of energy-saving and emission-reduction, transport
The short efficiency for improving transport in path, while the pressure that can also alleviate traffic above-ground is transported using empty iron.
Brief description of the drawings
, below will be to embodiment or existing for the clearer explanation embodiment of the present invention or technical scheme of the prior art
There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are only this
Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with
Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is a kind of working state schematic representation for the Kong Tie transportation systems that the specific embodiment of the invention provides.
Fig. 2 is another working state schematic representation for the Kong Tie transportation systems that the specific embodiment of the invention provides.
Fig. 3 is the empty iron transportation resources of Kong Tie transportation systems shown in the application drawing 1 of another specific embodiment offer of the present invention
Flow chart.
Wherein, reference is summarized as follows:
Kong Tie transportation systems 100, empty iron carrier 110;Start site 120;Start site platform 121;Start site sheet
Body 122;Chute 1222;First lift 123;First lowering or hoisting gear 124;First fixing device 125;First conveying arrangement 126;
Purpose website 130;Purpose station platform 131;Purpose website body 132;Second lift 133;Second lowering or hoisting gear 134;The
Two fixing devices 135;Second conveying arrangement 136;Article 200.
Embodiment
Existing Traditional Transportation mode how is overcome to consume energy big and low efficiency technical problem, to those skilled in the art
It is the technical problem for being badly in need of solving.
In view of this, the specific embodiment of the invention provides a kind of Kong Tie transportation systems.The Kong Tie transportation systems include:It is empty
Iron carrier, start site and purpose website.The start site includes start site platform, start site body and first liter
Drop machine.The start site platform and the first lift are fixedly installed on the start site body, the start site platform
Relatively described start site body side is protruded horizontally up for stopping the empty iron carrier.The start site platform with it is described
First lift connects, and first lift controls the start site platform to be carried out on the start site body up and down
It is mobile, to adjust the height of the start site platform.The purpose website includes purpose station platform and purpose website body.
The purpose station platform is arranged on the purpose website body, the relatively described purpose website body one of the purpose station platform
Side is protruded horizontally up for stopping the empty iron carrier.First lift makes the start site platform and the point of destination
Point platform is in same level height.Start site and purpose website are established, is used to stop the empty iron in the start site
The start site platform of carrier can adjust relative level height.When needing to carry out empty iron transport, the initiating station is adjusted
The level height of point platform, the start site platform is set to be in same level height with the purpose station platform.The sky
Iron carrier only need to be moved to the purpose station platform from the start site plateau levels, it is not necessary in this process
Overcome gravity acting, can reduce energy loss has an effect of energy-saving and emission-reduction, the short efficiency for improving transport of transportation route, together
Shi Caiyong skies iron transports the pressure that can also alleviate traffic above-ground.
The present invention is described in further detail below by specific embodiment and with reference to accompanying drawing.
Reference picture 1 and Fig. 2, this specific embodiment provide a kind of Kong Tie transportation systems 100, the Kong Tie transportation systems 100
Empty iron carrier 110, start site 120 and purpose website 130 can be included.Wherein, empty iron carrier 110 be used for will be to be transported
Article 200 is transported to the purpose website 130 from the start site 120, and the empty iron carrier 110 is using aerostatics and flies
Row device is realized.Preferably, using dirigible as empty iron carrier 110.The start site 120 can include:Start site
Platform 121, the lift 123 of start site body 122 and first.The start site body 122 can be natural forms (such as:
Massif), the start site body 122 can also be artificial structure (such as:High building, steel tower).The start site platform 121
It is arranged on the start site body 122, the relatively described side water of start site body 122 of the start site platform 121
It is flattened to go out to stop so as to the empty iron carrier 110.First lift 123 is fixedly installed on the start site body
On 122, first lift 123 is connected with the start site platform 121, and first lift 123 can control institute
State the relatively described start site body 122 of start site platform 121 to move up and down, to adjust the start site platform 121
Highly.
The purpose website 130 can include purpose station platform 131 and purpose website body 132.The purpose website
Platform 131 is arranged on the purpose website body 132, the relatively described purpose website body 132 of the purpose station platform 131
Side is protruded horizontally up for stopping the empty iron carrier 110.When to carry out empty iron transport, the start site platform is adjusted
121 height, the start site platform 121 is set to be in same level height with the purpose station platform 131.The empty iron
Carrier 110 is from the translational movement of start site platform 121 to the purpose station platform 131.
Using the above-mentioned Kong Tie transportation systems 100 provided, the empty iron carrier 110 only need to be from the start site platform
121 are moved horizontally to the purpose station platform 131, it is not necessary to overcome gravity acting in this process, can reduce energy
Effect of the amount loss with energy-saving and emission-reduction, the short efficiency for improving transport of transportation route, while can also be alleviated using the transport of empty iron
The pressure of traffic above-ground.
Reference picture 1 and Fig. 2, in this specific embodiment, the start site body 122 with the start site platform
A chute 1222 from top to bottom can be provided with 121 link positions, first lift 123 can be driven by motor
The start site platform 121 relatively described start site body in the chute 1222 is driven to be moved about 122.
The start site platform 121 and the preferred polylith metal structural slab of the purpose station platform 131 are spliced.Stand
Point platform general present position height is higher, be spliced using polylith metal structural slab be easy to station platform assembly and
Follow-up maintenance.
Reference picture 1 and Fig. 2, in this specific embodiment, further, the purpose website 130 can also include second
Lift 133, second lift 133 be arranged on the purpose website body 132 and with the purpose station platform
131 connections.With first lift 123 as the attachment structure of start site body 122, second lift
133 can also control the purpose station platform 131 to be moved up and down on the purpose website body 132, to adjust
State the height of purpose station platform 131.When carrying out empty iron transport, by adjusting the start site platform 121 and/or purpose
The height of station platform 131, you can so that the start site platform 121 is in same water with the purpose station platform 131
Flat height.Specifically, for example the height of the start site platform 121 is 1000 meters (following height refers both to height above sea level),
And the height of the purpose station platform 131 is 900 meters.The first is achieved in that the height of the start site platform 121
Degree drops to 900 meters;It is achieved in that the elevated height of the purpose station platform 131 to 1000 meters for second;The third
Be achieved in that at the same adjust the purpose station platform 131 and the height of start site platform 121 make that its is equal (such as:
950 meters).After the start site platform 121 is consistent with the level height of purpose station platform 131 adjustment, the empty iron fortune
Defeated device 110 moves to the purpose station platform 131 from the start site platform 121, avoids sky iron carrier 110 from transporting
During the energy loss caused by overcoming gravity acting.
Reference picture 1, in above-mentioned Kong Tie transportation systems 100, further, the start site 120 can also include the
One lowering or hoisting gear 124, first lowering or hoisting gear 124 are arranged at the start site body 122, first lowering or hoisting gear
124 are used for the transport of the progress article 200 between the bottom of start site body 122 and the start site platform 121.Institute
The second lowering or hoisting gear 134 can also also be included by stating on purpose website 130, similar with the first lowering or hoisting gear 124, described second liter
Falling unit 134 is used to carry out article 200 between the bottom of purpose website body 132 and the purpose station platform 131
Transport.The first lowering or hoisting gear 124 described in this specific embodiment and the second lowering or hoisting gear 134 can be elevators.
Reference picture 1, in above-mentioned Kong Tie transportation systems 100, further, the start site 120 can also include the
One fixing device 125, first fixing device 125 are arranged on the start site platform 121, first fixing device
125 are used to the empty iron carrier 110 for resting in the start site platform 121 be fixed.Identically with this, it is described
Purpose website 130 can also include the second fixing device 135, and second fixing device 135 is arranged on the purpose website and put down
Platform 131, second fixing device 135 are used to enter the empty iron carrier 110 for resting in the purpose station platform 131
Row is fixed.In the embodiment of the present invention, first fixing device 125 and second fixing device 135 can
To be an electromagnet, one iron block is set in the bottom of empty iron carrier 110.When empty iron carrier 110 needs to stop, make described
Work of electromagnet, the electromagnet firmly adsorbs empty iron carrier 110 fixation under magneticaction.When empty iron carrier 110
When needing to leave, the electromagnet is set to be stopped, empty iron carrier 110 departs from magnetic force constraint can be with free movement.In this hair
In bright another embodiment, first fixing device 125 and second fixing device 135 can also be sucker.
Reference picture 1 and Fig. 2, in above-mentioned Kong Tie transportation systems 100, further, the start site 120 also includes the
One conveying arrangement 126, first conveying arrangement 126 are arranged at the start site platform 121, first conveying arrangement
126 are used to article 200 being transported into the empty iron carrier 110.The purpose website 130 also includes the second conveying arrangement 136,
Second conveying arrangement 136 is arranged at the purpose station platform 131, and second conveying arrangement 136 is used for article 200
Transported from the empty iron carrier 110.Specifically, first conveying arrangement 126 and second conveying arrangement 136 can be with
It is the transmission crawler belt with transmittability.
In this specific embodiment, when the start site body 122 or the purpose website body 132 are culture
During thing, the start site body 122 or the purpose website body 132 can be steel frame construction, convenient using steel frame construction
The foundation of website body and follow-up maintenance work.
A kind of empty iron transportation resources is also provided in the another specific embodiment of the present invention, the sky iron transportation resources is applied to
In Kong Tie transportation systems 100 in a upper specific embodiment.Reference picture 3, this method specifically includes following steps.
Step S101, the article 200 of the start site platform 121 is transported into the empty iron carrier 110.
Step S102, make the start site platform 121 and the purpose website by adjusting first lift 123
Platform 131 is in same level height.
Step S103, the empty iron carrier 110 are moved horizontally to the purpose website from the start site platform 121
Platform 131.
Step S104, the empty iron carrier 110 rest in the purpose station platform 131.
Step S105, article 200 is transported to the purpose station platform 131 from the empty iron carrier 110.
Above-mentioned specific embodiment is described using the Kong Tie transportation systems and empty iron transportation resources transporting to article
Process, it is to be understood that above-mentioned Kong Tie transportation systems and empty iron transportation resources be equally applicable to live body (such as:People) fortune
It is defeated.
In summary, above-mentioned Kong Tie transportation systems and empty iron transportation resources, by establishing start site and purpose website, institute
Relative level height can be adjusted for stopping the start site platform of the empty iron carrier by stating in start site.Need into
When the empty iron of row transports, the level height of the start site platform is adjusted, makes the start site platform and the purpose website
Platform is in same level height.The empty iron carrier only need to be moved to the point of destination from the start site plateau levels
Point platform, it is not necessary to overcome gravity acting in this process, the effect that energy loss plays energy-saving and emission-reduction can be reduced, transport
The short efficiency for improving transport in defeated path, while the pressure that can also alleviate traffic above-ground is transported using empty iron.
It should be noted that each embodiment in this specification is described by the way of progressive, each embodiment weight
Point explanation is all difference with other embodiment, between each embodiment identical similar part mutually referring to.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area
For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies
Change, equivalent substitution, improvement etc., should be included in the scope of the protection.It should be noted that:Similar label and letter exists
Similar terms is represented in following accompanying drawing, therefore, once being defined in a certain Xiang Yi accompanying drawing, is then not required in subsequent accompanying drawing
It is further defined and explained.
In the description of the invention, it is necessary to explanation, term " " center ", " on ", " under ", "left", "right", " vertical ",
The orientation or position relationship of the instruction such as " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship, or should
Invention product using when the orientation usually put or position relationship, be for only for ease of the description present invention and simplify description, without
It is instruction or implies that signified device or element there must be specific orientation, with specific azimuth configuration and operation, therefore not
It is understood that as limitation of the present invention.
In the description of the invention, it is also necessary to explanation, unless otherwise clearly defined and limited, term " setting ",
" installation ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or one
Connect body;Can be mechanical connection or electrical connection;Can be joined directly together, can also be indirect by intermediary
It is connected, can is the connection of two element internals.For the ordinary skill in the art, on being understood with concrete condition
State the concrete meaning of term in the present invention.
Claims (9)
- A kind of 1. Kong Tie transportation systems, it is characterised in that including:Empty iron carrier, start site and purpose website, the starting Website includes start site platform, start site body and the first lift, and the start site platform and the first lift are consolidated Surely the start site body is arranged on, the relatively described start site body side of the start site platform, which protrudes horizontally up, to be used for The empty iron carrier is stopped, the start site platform is connected with first lift, and first lift controls institute State start site platform to move up and down on the start site body, to adjust the height of the start site platform; The purpose website includes purpose station platform and purpose website body, and the purpose station platform is arranged on the purpose website Body, the relatively described purpose website body side of the purpose station platform are protruded horizontally up for stopping the empty iron carrier; First lift makes the start site platform be in same level height with the purpose station platform;The purpose website also includes the second lift, second lift be arranged on the purpose website body and with it is described Purpose station platform connects, and second lift controls the purpose station platform to be carried out on the purpose website body Lower movement, to adjust the height of the purpose station platform;First lift and/or second lift make described rise Beginning station platform is in same level height with the purpose station platform.
- 2. Kong Tie transportation systems as claimed in claim 1, it is characterised in that:The start site also includes the first lifting and filled Put, first lowering or hoisting gear be arranged at the start site body be used for article the start site body bottom portion with it is described Transport between the platform of start site;The purpose website also includes the second lowering or hoisting gear, and second lowering or hoisting gear is arranged at The purpose website body is used for transport of the article between the purpose website body bottom portion and the purpose station platform.
- 3. Kong Tie transportation systems as claimed in claim 1, it is characterised in that:The start site also includes first and fixes dress Put, first fixing device is arranged on the start site platform, and first fixing device is used for resting in described rise The empty iron carrier of beginning station platform is fixed;The purpose website also includes the second fixing device, and described second is solid Determine device and be arranged on the purpose station platform, second fixing device is used for the institute to resting in the purpose station platform Sky iron carrier is stated to be fixed.
- 4. Kong Tie transportation systems as claimed in claim 1, it is characterised in that:The start site also includes the first transport and filled Put, first conveying arrangement is arranged at the start site platform, and first conveying arrangement is described for article to be transported into In empty iron carrier;The purpose website also includes the second conveying arrangement, and second conveying arrangement is arranged at the point of destination Point platform, second conveying arrangement are used to transport article from the empty iron carrier.
- 5. Kong Tie transportation systems as claimed in claim 4, it is characterised in that:First conveying arrangement and the second conveying arrangement To transmit crawler belt.
- 6. Kong Tie transportation systems as claimed in claim 1, it is characterised in that:The empty iron carrier includes aerostatics and flight Device.
- 7. Kong Tie transportation systems as claimed in claim 6, it is characterised in that:The empty iron carrier is dirigible.
- 8. Kong Tie transportation systems as claimed in claim 1, it is characterised in that:The start site body or the purpose website Body is steel frame construction.
- A kind of 9. empty iron transportation resources, applied to the Kong Tie transportation systems described in claim 1, it is characterised in that this method bag Include:The article of the start site platform is transported into the empty iron carrier;The start site platform is set to be in same level height with the purpose station platform by adjusting first lift Degree;The empty iron carrier is moved to the purpose station platform from the start site plateau levels;The empty iron carrier rests in the purpose station platform;Article is transported to the purpose station platform from the empty iron carrier.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610029507.9A CN105564442B (en) | 2016-01-15 | 2016-01-15 | Kong Tie transportation systems and empty iron transportation resources |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610029507.9A CN105564442B (en) | 2016-01-15 | 2016-01-15 | Kong Tie transportation systems and empty iron transportation resources |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105564442A CN105564442A (en) | 2016-05-11 |
CN105564442B true CN105564442B (en) | 2018-03-02 |
Family
ID=55875213
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610029507.9A Expired - Fee Related CN105564442B (en) | 2016-01-15 | 2016-01-15 | Kong Tie transportation systems and empty iron transportation resources |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105564442B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108263396B (en) * | 2018-02-27 | 2024-02-06 | 中唐空铁集团有限公司 | Power assembly for air iron |
CN110497924A (en) * | 2019-08-21 | 2019-11-26 | 中建空列(北京)工程设计研究院有限公司 | A kind of empty rail pipeline transportation system for tunnel |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1849251A (en) * | 2002-10-11 | 2006-10-18 | 布鲁克斯自动技术公司 | Access to one or more levels of material storage shelves by an overhead hoist transport vehicle from a single track position |
CN201710952U (en) * | 2009-08-11 | 2011-01-19 | 渠仁书 | Suspension cable type low-altitude flight system |
CN102001339A (en) * | 2010-11-07 | 2011-04-06 | 陈利明 | Urban cable traffic system |
CN205273457U (en) * | 2016-01-15 | 2016-06-01 | 彭红廷 | Empty indisputable conveyor system |
-
2016
- 2016-01-15 CN CN201610029507.9A patent/CN105564442B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1849251A (en) * | 2002-10-11 | 2006-10-18 | 布鲁克斯自动技术公司 | Access to one or more levels of material storage shelves by an overhead hoist transport vehicle from a single track position |
CN201710952U (en) * | 2009-08-11 | 2011-01-19 | 渠仁书 | Suspension cable type low-altitude flight system |
CN102001339A (en) * | 2010-11-07 | 2011-04-06 | 陈利明 | Urban cable traffic system |
CN205273457U (en) * | 2016-01-15 | 2016-06-01 | 彭红廷 | Empty indisputable conveyor system |
Also Published As
Publication number | Publication date |
---|---|
CN105564442A (en) | 2016-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105564442B (en) | Kong Tie transportation systems and empty iron transportation resources | |
CN206538154U (en) | The lifting drive of shifting carrying platform in stacking machine | |
CN103770790A (en) | Overhead rail transport platform system | |
CN202063137U (en) | Double-carrying-cable circulation-type freight cableway system | |
CN105019364B (en) | A kind of head tower slides vertical transfer method | |
CN206052568U (en) | The long hoist cable of suspension bridge bank slope beam section swings shifting erecting device | |
CN107313356B (en) | A kind of fortune beam method that double-decker bridge is built | |
CN102602398B (en) | Quick-transporting method and quick-transport device for foldable temporary cableways | |
CN104120701A (en) | Construction method and device for hoisting of heavy and large part of vertical ship lift | |
CN205273457U (en) | Empty indisputable conveyor system | |
CN105015365A (en) | Upper and lower two-way logistics rail method and Upper and lower two-way logistics rail device | |
CN102041779A (en) | Erection crane and construction method thereof | |
CN202337945U (en) | Outer side in-place beam body lifting device | |
CN107988909B (en) | Railway is just roof beam rapid transit erects and uses trailer | |
CN102849626A (en) | Indoor non-standard crane installation method | |
CN204982676U (en) | Conveyer is assembled on steel purlin girder segment section ground | |
CN105015555A (en) | Physical distribution vehicle with upper layer and lower layer | |
CN207714055U (en) | A kind of Novel overpass | |
CN208331435U (en) | A kind of plumbing installation | |
CN105200922A (en) | Steel truss section ground splicing and transporting device and transporting method | |
CN201950066U (en) | Roller displacement hoisting-descending device | |
CN204000521U (en) | Electric propeller hanging device | |
CN208516706U (en) | High speed Lift car type elevator | |
CN204264139U (en) | Upper and lower two-way logistic car | |
CN204264140U (en) | Upper and lower two-way logistics track |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180302 |
|