CN105544603A - 一种用于地下管线加固的施工方法 - Google Patents

一种用于地下管线加固的施工方法 Download PDF

Info

Publication number
CN105544603A
CN105544603A CN201510905328.2A CN201510905328A CN105544603A CN 105544603 A CN105544603 A CN 105544603A CN 201510905328 A CN201510905328 A CN 201510905328A CN 105544603 A CN105544603 A CN 105544603A
Authority
CN
China
Prior art keywords
truss
pipeline
original
original pipeline
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510905328.2A
Other languages
English (en)
Inventor
赵国良
庞海清
席斯日古冷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN201510905328.2A priority Critical patent/CN105544603A/zh
Publication of CN105544603A publication Critical patent/CN105544603A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种用于地下管线加固的施工方法,其特征是:在新增地下管线或构筑物与原有管线交汇处至原有管线顶标高,在挖开土方所形成的基槽上设置桁架加固体系,用横截面为半圆形的管段,用连接在桁架加固体系上的手动葫芦对管段进行调节固定,在管段的下部设置钢筋混凝土支撑墩,对原有管线的支撑加固。其优点是:与其他方法比较,在不拆除原有地下管线、不影响原有管线正常使用的情况下,施工地下管线或构筑物,有效的解决了拆除原有管线带来的协调工作困难、工期延误、经济损失等问题;该方法具有施工简便、工具可周转、施工费用低、工期短等优点。

Description

一种用于地下管线加固的施工方法
技术领域
本发明涉及一种用于地下管线加固的施工方法,属于市政管廊及新增地下管线施工领域。
背景技术
在市政工程施工项目中,有钢筋混凝土管线、电缆等地下管线,横穿新建地下建、构筑物时,原管线无法拆除,给市政地下工程施工安装带来了诸多不便和困扰。
例如:某城市中心区综合管廊工程一期一标段,综合管廊K-0-486.3至K-0-586.867施工段,桩位号为K-0-555.657处,原有装备园区污水主管线,管顶标高为-3.0m,直径为Φ600mm钢筋混凝土管线,需要在其下方横穿综合管廊,因装备园区污水管线污水流量极大,无法拆除污水管线,给施工带来了困扰。
发明内容
本发明的目的是为了解决原有地下钢筋混凝土管线、电缆等管线,横穿新建地下建、构筑物,原有管线无法拆除,且需正常使用,给市政地下工程施工安装带来了诸多不便和困扰,提供一种操作简单安全的用于原有管线加固的施工方法。
本发明的方法采用如下步骤:
1.在新增地下管线或构筑物与原有管线交汇处至原有管线顶标高,在挖开土方所形成的基槽两侧平整土方进行桁架混凝土基础施工;
2.待桁架混凝土基础达到强度后进行桁架安装,在基槽两侧桁架混凝土基础上分别固定桁架立柱,在两个桁架立柱底部之间连接桁架横梁;
3.在原有管线下方衬托与原有管线直径形匹配、横截面为半圆形的管段,并用手动葫芦对管段进行调节固定,手动葫芦的上部与桁架横梁连接,在固定连接点用钢丝绳与桁架横梁、桁架立柱、桁架混凝土基础间进行连接加固,形成悬索桥结构,构成桁架加固体系,完成对原有管线承托加固;
4.对原有管线加承托固完成后,将基槽内原有管线下方土层下挖10-20cm,进行沉降观测,确认原有管线加固安全无误后,开始新增地下管线或构筑物基槽的土方开挖;
5.新增地下管线或构筑物施工完毕后,在原有管线的加固管段的下部设置钢筋混凝土支撑墩,钢筋混凝土支撑墩建在新增地下管线基槽的底部地基上(将新增地下管线包住)或构筑物的顶部,完成对原有管线的支撑加固;
6.回填土回填至原有管线顶标高时,拆除桁架加固体系,拆除过程全程跟踪测量观测,拆除完毕后再观测1-2天后,确保原有管线不再下沉后,在进行上部土方回填,完成施工。
本发明的优点是:与其他方法比较,在不拆除原有地下管线、不影响原有管线正常使用的情况下,施工地下管线或构筑物,有效的解决了拆除原有管线带来的协调工作困难、工期延误、经济损失等问题;该方法具有施工简便、工具可周转、施工费用低、工期短等优点。
附图说明
图1是本发明方法的施工示意图;
图2是图1的A--A剖面图。
图中:1、桁架横梁,2、桁架立柱,3、原有污水管线,4、钢丝绳,5、手动葫芦,6、花篮螺丝,7、轴承,8、地锚,9、管段,10、埋件,11、钢筋混凝土支撑墩。
具体实施方式
实施例
某城市中心区综合管廊工程一期一标段,综合管廊K-0-486.3至K-0-586.867施工段,桩位号为K-0-555.657处,原有装备园区污水主管线,管顶标高为-3.0m,直径为Φ600mm钢筋混凝土管线,需要在其下方横穿综合管廊。
参照附图,施工步骤如下:
1.在新增构筑物与原有污水管线3交汇处至原有污水管线顶标高,在挖开土方所形成的基槽两侧平整土方进行桁架混凝土基础施工;
2.待桁架混凝土基础达到强度后进行桁架安装,在基槽两侧桁架混凝土基础上分别用埋件10桁架固定立柱2,在两个桁架立柱底部之间连接桁架横梁1,在每个桁架立柱顶部设置轴承7;
3.在原有污水管线下方衬托与原有管线直径形匹配、横截面为半圆形的管段9,如果原有污水管线有接口,管段衬托在接口处,管段9是由圆管从管端中心立剖制成的;用手动葫芦5对管段进行调节固定,手动葫芦的上部与桁架横梁连接,在固定连接点用钢丝绳4与桁架横梁、桁架立柱顶部轴承、安装在桁架混凝土基础上的地锚间进行连接加固,形成悬索桥结构,构成桁架加固体系,完成对原有污水管线承托加固;
4.对原有污水管线加承托固完成后,将基槽内原有污水管线下方土层下挖10-20cm,进行沉降观测,确认原有污水管线加固安全无误后,开始新增地下构筑物基槽的土方开挖;
5.新增地下构筑物施工完毕后,在原有污水管线的加固管段的下部设置钢筋混凝土支撑墩11,钢筋混凝土支撑墩建在地下构筑物的顶部,完成对原有污水管线的支撑加固;
6.回填土回填至原有污水管线顶标高时,拆除桁架加固体系,拆除过程全程跟踪测量观测,拆除完毕后再观测1-2天后,确保原有污水管线不再下沉后,在进行上部土方回填,完成施工。
实践证明,该方法在不拆除地下原有管线,不影响原有管线正常使用的情况下,正常施工新增构筑物,有效解决了拆除原有管线带来的协调工作困难、工期延误、经济损失等问题。具有施工简便、工具可周转、施工费用低、工期短等优点,取得了良好的效果。

Claims (1)

1.一种用于地下管线加固的施工方法,其特征是:采用如下步骤:
1)在新增地下管线或构筑物与原有管线交汇处至原有管线顶标高,在挖开土方所形成的基槽两侧平整土方进行桁架混凝土基础施工;
2)待桁架混凝土基础达到强度后进行桁架安装,在基槽两侧桁架混凝土基础上分别固定桁架立柱,在两个桁架立柱底部之间连接桁架横梁;
3)在原有管线下方衬托与原有管线直径形匹配、横截面为半圆形的管段,并用手动葫芦对管段进行调节固定,手动葫芦的上部与桁架横梁连接,在固定连接点用钢丝绳与桁架横梁、桁架立柱、桁架混凝土基础间进行连接加固,形成悬索桥结构,构成桁架加固体系,完成对原有管线承托加固;
4)对原有管线加承托固完成后,将基槽内原有管线下方土层下挖10-20cm,进行沉降观测,确认原有管线加固安全无误后,开始新增地下管线或构筑物基槽的土方开挖;
5)新增地下管线或构筑物施工完毕后,在原有管线的加固管段的下部设置钢筋混凝土支撑墩,钢筋混凝土支撑墩建在新增地下管线基槽的底部地基上或构筑物的顶部,完成对原有管线的支撑加固;
6)回填土回填至原有管线顶标高时,拆除桁架加固体系,拆除过程全程跟踪测量观测,拆除完毕后再观测1-2天后,确保原有管线不再下沉后,在进行上部土方回填,完成施工。
CN201510905328.2A 2015-12-10 2015-12-10 一种用于地下管线加固的施工方法 Pending CN105544603A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510905328.2A CN105544603A (zh) 2015-12-10 2015-12-10 一种用于地下管线加固的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510905328.2A CN105544603A (zh) 2015-12-10 2015-12-10 一种用于地下管线加固的施工方法

Publications (1)

Publication Number Publication Date
CN105544603A true CN105544603A (zh) 2016-05-04

Family

ID=55824123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510905328.2A Pending CN105544603A (zh) 2015-12-10 2015-12-10 一种用于地下管线加固的施工方法

Country Status (1)

Country Link
CN (1) CN105544603A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106087701A (zh) * 2016-08-10 2016-11-09 上海市城市建设设计研究总院 高架桥梁和地下综合管廊合建结构
CN106838465A (zh) * 2017-02-24 2017-06-13 中冶建工集团有限公司 地下综合管廊既有管道开挖保护施工方法
CN110230730A (zh) * 2019-05-20 2019-09-13 中国二冶集团有限公司 用于管线加固的施工方法
CN110924435A (zh) * 2019-12-16 2020-03-27 山东顺河路桥工程有限公司 一种横穿构筑物下方的横穿管线固定装置及其施工方法
CN111509649A (zh) * 2019-01-30 2020-08-07 大唐东营发电有限公司 一种临时调试电源配置方案
CN111503373A (zh) * 2020-04-17 2020-08-07 中国十七冶集团有限公司 一种地下管线保护结构及其施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0363306A (ja) * 1989-07-31 1991-03-19 Kawasaki Steel Corp 吊橋型式管橋
JPH09316900A (ja) * 1996-05-31 1997-12-09 Hazama Gumi Ltd 逆打ち工法
CN201902703U (zh) * 2010-12-09 2011-07-20 西安建筑科技大学 一种地下管线悬吊保护装置
CN102877539A (zh) * 2012-09-26 2013-01-16 中国建筑第二工程局有限公司 型钢悬挂式污水管改线结构及其施工方法
CN103321245A (zh) * 2013-06-18 2013-09-25 中铁十六局集团地铁工程有限公司 一种盾构掘进时地下管线的保护装置及施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0363306A (ja) * 1989-07-31 1991-03-19 Kawasaki Steel Corp 吊橋型式管橋
JPH09316900A (ja) * 1996-05-31 1997-12-09 Hazama Gumi Ltd 逆打ち工法
CN201902703U (zh) * 2010-12-09 2011-07-20 西安建筑科技大学 一种地下管线悬吊保护装置
CN102877539A (zh) * 2012-09-26 2013-01-16 中国建筑第二工程局有限公司 型钢悬挂式污水管改线结构及其施工方法
CN103321245A (zh) * 2013-06-18 2013-09-25 中铁十六局集团地铁工程有限公司 一种盾构掘进时地下管线的保护装置及施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宋炜炜: "城市桥梁邻近重要管线施工保护技术", 《浙江建筑》 *
赵雅洁等: "贝雷桁架在管线保护中的应用", 《科技传播》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106087701A (zh) * 2016-08-10 2016-11-09 上海市城市建设设计研究总院 高架桥梁和地下综合管廊合建结构
CN106087701B (zh) * 2016-08-10 2017-09-12 上海市城市建设设计研究总院(集团)有限公司 高架桥梁和地下综合管廊合建结构
CN106838465A (zh) * 2017-02-24 2017-06-13 中冶建工集团有限公司 地下综合管廊既有管道开挖保护施工方法
CN106838465B (zh) * 2017-02-24 2018-09-04 中冶建工集团有限公司 地下综合管廊既有管道开挖保护施工方法
CN111509649A (zh) * 2019-01-30 2020-08-07 大唐东营发电有限公司 一种临时调试电源配置方案
CN110230730A (zh) * 2019-05-20 2019-09-13 中国二冶集团有限公司 用于管线加固的施工方法
CN110924435A (zh) * 2019-12-16 2020-03-27 山东顺河路桥工程有限公司 一种横穿构筑物下方的横穿管线固定装置及其施工方法
CN111503373A (zh) * 2020-04-17 2020-08-07 中国十七冶集团有限公司 一种地下管线保护结构及其施工方法

Similar Documents

Publication Publication Date Title
CN105544603A (zh) 一种用于地下管线加固的施工方法
CN103981898B (zh) 一种整体明挖节点逆作的地下工程施工方法
CN106437798B (zh) 一种穿过盾构掘进断面的锚索群的预处理方法
CN102434717B (zh) 工字钢顶管工作坑的施工方法
CN205711788U (zh) 一种地下管道保护涵
CN103485790A (zh) 一种管幕-支护结构组合体系浅埋暗挖法
CN104110038A (zh) 深厚淤泥质软土地区大面积基坑围护结构的施工方法
CN202689031U (zh) 深基坑支护挡墙
CN100510281C (zh) 超大直径、超埋深度调蓄池的半逆作施工方法
CN102635119A (zh) 一种用于旋流井施工的支护方法
CN111734425A (zh) 一种下穿机场航站楼的暗挖隧道的施工方法
CN108457289A (zh) 一种复杂条件下的沉井施工方法
CN103215958A (zh) 膨胀土地区深基坑降水与支护施工方法
CN104895079A (zh) 钢板桩打设的逆做施工方法
CN109594574A (zh) 基于有限空间的大型顶管沉井逆作施工方法
CN108755719A (zh) 跨海海底市政隧道围堰明挖施工方法
CN102493810B (zh) 管道斜井工程灌浆施工工艺
CN108978709B (zh) 一种空间受限环境下城市综合管廊分支施工方法
CN110512594A (zh) 旋挖钻机遇空洞成孔成桩的简易方法
Parashar et al. Performance monitoring of deep shafts at Changi WRP project, Singapore
CN107023012B (zh) 多道环形砼支撑深基坑土方外运施工方法
CN109119943A (zh) 电缆在顶管两端的敷设方式优化方法
CN103510525A (zh) 一种重力式水泥土墙结合单排桩的基坑梯级支护方法
CN205134332U (zh) 市政排水管线坑槽支护结构
CN110485465B (zh) 一种富水地层预设顶管门洞的圆形工作井及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160504

WD01 Invention patent application deemed withdrawn after publication