CN105417271A - Electric transmission line iron tower pile pay-off device and construction method thereof - Google Patents

Electric transmission line iron tower pile pay-off device and construction method thereof Download PDF

Info

Publication number
CN105417271A
CN105417271A CN201510774851.6A CN201510774851A CN105417271A CN 105417271 A CN105417271 A CN 105417271A CN 201510774851 A CN201510774851 A CN 201510774851A CN 105417271 A CN105417271 A CN 105417271A
Authority
CN
China
Prior art keywords
connecting rod
transmission line
iron tower
base plate
track adjusting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510774851.6A
Other languages
Chinese (zh)
Other versions
CN105417271B (en
Inventor
高世龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lin Zhan Ping
Yang Jie Ru
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510774851.6A priority Critical patent/CN105417271B/en
Publication of CN105417271A publication Critical patent/CN105417271A/en
Application granted granted Critical
Publication of CN105417271B publication Critical patent/CN105417271B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H49/00Unwinding or paying-out filamentary material; Supporting, storing or transporting packages from which filamentary material is to be withdrawn or paid-out
    • B65H49/18Methods or apparatus in which packages rotate
    • B65H49/20Package-supporting devices
    • B65H49/32Stands or frameworks
    • B65H49/324Constructional details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H75/00Storing webs, tapes, or filamentary material, e.g. on reels
    • B65H75/02Cores, formers, supports, or holders for coiled, wound, or folded material, e.g. reels, spindles, bobbins, cop tubes, cans, mandrels or chucks
    • B65H75/34Cores, formers, supports, or holders for coiled, wound, or folded material, e.g. reels, spindles, bobbins, cop tubes, cans, mandrels or chucks specially adapted or mounted for storing and repeatedly paying-out and re-storing lengths of material provided for particular purposes, e.g. anchored hoses, power cables
    • B65H75/38Cores, formers, supports, or holders for coiled, wound, or folded material, e.g. reels, spindles, bobbins, cop tubes, cans, mandrels or chucks specially adapted or mounted for storing and repeatedly paying-out and re-storing lengths of material provided for particular purposes, e.g. anchored hoses, power cables involving the use of a core or former internal to, and supporting, a stored package of material
    • B65H75/40Cores, formers, supports, or holders for coiled, wound, or folded material, e.g. reels, spindles, bobbins, cop tubes, cans, mandrels or chucks specially adapted or mounted for storing and repeatedly paying-out and re-storing lengths of material provided for particular purposes, e.g. anchored hoses, power cables involving the use of a core or former internal to, and supporting, a stored package of material mobile or transportable
    • B65H75/42Cores, formers, supports, or holders for coiled, wound, or folded material, e.g. reels, spindles, bobbins, cop tubes, cans, mandrels or chucks specially adapted or mounted for storing and repeatedly paying-out and re-storing lengths of material provided for particular purposes, e.g. anchored hoses, power cables involving the use of a core or former internal to, and supporting, a stored package of material mobile or transportable attached to, or forming part of, mobile tools, machines or vehicles
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • H02G1/04Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H2701/00Handled material; Storage means
    • B65H2701/30Handled filamentary material
    • B65H2701/34Handled filamentary material electric cords or electric power cables

Landscapes

  • Types And Forms Of Lifts (AREA)
  • Electric Cable Installation (AREA)

Abstract

The invention discloses an electric transmission line iron tower pile pay-off device and a construction method thereof. The electric transmission line iron tower pay-off device comprises a bottom plate. Dovetail grooves are formed in the bottom plate. Supporting plates are clamped into the dovetail grooves through bottom connecting parts and installed on the bottom plate. The electric transmission line iron tower pay-off device is characterized in that pin clamps are installed on the supporting plates; first connecting rods, second connecting rods and third connecting rods form triangular supports which are installed on the upper portions of the supporting plates; shaft brackets are installed at the joints of the first connecting rods and the second connecting rods; fourth pins arranged at the bottoms of the second connecting rods penetrate into the supporting plates; the first connecting rods are connected with the third connecting rods through second pins; the third connecting rods penetrate into the pin clamps for fixation through adjusting pins. The electric transmission line iron tower pile pay-off device and the construction method thereof have the beneficial effects that the electric transmission line iron tower pile pay-off device is fixed to the upper portion of a transport vehicle and driven by the vehicle to move forward for paying off; meanwhile, a winding reel is convenient to disassemble without large amount of labor; the device is high in wire outgoing speed, and outgoing circuits are free of winding, so that the device is suitable for application and popularization.

Description

Iron tower of power transmission line stake actinobacillus device and construction method thereof
Technical field
The present invention relates to a kind of electric power network constructing device, be specifically related to a kind of iron tower of power transmission line stake actinobacillus device and construction method thereof, belong to technical field of electric power construction.
Background technology
Power engineering (electricpowerengineering), namely relevant with the production of electric energy, conveying, distribution engineering, broadly also comprises the engineering that electricity is applied in multiple fields as power and energy.Its bubbling area is made up of angle steel mutually arranged side by side, and the orientation of angle steel is parallel with liquid flow path direction.The wedge angle limit of steel tower stake angle steel is in bottom, and cross section is in " V " font, and have certain grid seam between adjacent two angle steel, downflow spout is identical with general column plate.The liquid of a upper plate flows into " V " font angle steel by downflow spout, gas then by grid sew on rise time and liquid generation bubbling, carry out mass transport process, the Liquid Flow state on column plate and sieve plate similar.Angle iron tower plate pressure drop is less, and gas phase flux is comparatively large, and plate efficiency is better, and structure is simple, and convenient processing and manufacture, rigidity is better.
The invention discloses a kind of underground laying cable paying-off tackle as Patent publication No CN103618261A discloses, the object of this invention is to provide a kind of underground laying cable paying-off tackle that can reduce labor intensity, prevent pillar from wearing and tearing.Technical scheme of the present invention completes as follows, underground laying cable paying-off tackle, it includes one piece of semi-circular tube frid, the two side, one end of semi-circular tube frid is welded with a piece of outside curved outstanding connecting panel respectively, an anchor shaft is installed between in the middle part of two pieces of connecting panels, anchor shaft is provided with a pulley block with bearing, is respectively equipped with a U-shaped snap ring at the two ends of anchor shaft.As long as the cable of traction carries through having along pulley and unwrapping wire groove by the present invention in use, install, easy to use, effectively prevent the wearing and tearing of pillar, reduce labor intensity.
And for example Patent publication No CN204156413U discloses for a kind of cable drum carriage with shock absorber, it comprises vehicle frame mechanism, payingoff mechanism, the front end trailer coupling being fixed on vehicle frame mechanism and shock absorber, vehicle frame mechanism comprises underframe and is located at the movable castor of underframe both sides, underframe is vertically installed with complex root bracing frame; Payingoff mechanism comprises left cable disc, right cable disc and bobbin between the two, and the central rotational of every two bracing frames arranges a bobbin; Shock absorber is arranged on side, bobbin top, it brake rod comprising fixedly sleeved stationary magazine creel on bobbin and be threaded with stationary magazine creel, one end of brake rod is fixedly installed the sticking part for fitting with bobbin of arc, and the other end is fixedly installed the handle stretched out outside stationary magazine creel.The utility model by increasing shock absorber on wheeled cable drum carriage, when situations such as occurring construction ahead needs to stop unwrapping wire immediately, makes bobbin stop operating, thus realizes the prevention of bobbin, can obtain and prevent cable to break the effect of stock, damage in insulation etc.
At present, the line construction work between iron tower of power transmission line stake is too heavy, because the relative aperture of high tension cord is thicker, weight is large, needing manually to promote spool and advances, also needing manually to tighten up when tightening up in erection process, speed is slow, and workmen's work capacity is large.Simultaneously when outlet, spool due to weight large, winding displacement is also more difficult.
Summary of the invention
Instant invention overcomes prior art Problems existing, propose a kind of iron tower of power transmission line stake actinobacillus device and construction method thereof, this device and construction method thereof are between iron tower of power transmission line stake during line construction, easy to use, save manpower, go out linear velocity fast, be not wound around between the circuit of outlet simultaneously.
Concrete technical scheme of the present invention is as follows: iron tower of power transmission line stake actinobacillus device, comprise base plate, described base plate is provided with dovetail furrow, stay bearing plate is snapped in dovetail furrow by bottom linker and is arranged on base plate, it is characterized in that: described stay bearing plate is provided with pin folder, connecting rod one, connecting rod two and connecting rod three form spider and are arranged on above stay bearing plate, wherein: connecting rod one and connecting rod two junction are provided with shaft tray, be provided with pin four and penetrate in stay bearing plate bottom connecting rod two; Connecting rod one is connected with connecting rod three by pin two, and connecting rod threeway overregulate pin penetrates pin folder internal fixtion;
Described shaft tray is provided with spool, and spool both sides are provided with adapter plate, and shaft tray is provided with sensor, and described base plate is provided with bearing support block, and screw rod is arranged on bearing support block, and described screw rod one end is connected with motor; Signal wire (SW) is connected with between described motor and sensor;
Described screw rod is also provided with track adjusting wheel, and track adjusting wheel permanent seat is mounted on below track adjusting wheel, described track adjusting wheel permanent seat is also provided with and splits track adjusting wheel; Base plate is also provided with lift dog;
Described lift dog comprises height regulating frame, and base plate three is arranged on above height regulating frame, and described base plate three is provided with cable-through hole above, rolls rod and (is arranged in cable-through hole, described cable-through hole is provided with cover plate.Described cover plate is also provided with inserted sheet to insert in base plate three.
Preferentially, described spool both sides are also provided with handle, and connecting rod is connected between handle, connecting rod are provided with track adjusting wheel one, and described handle is also provided with friction lining; Detouchable spring is installed bottom handle.
Preferentially, be also provided with bracing frame bottom described base plate, cardan wheel is arranged on above bracing frame.Described cardan wheel can carry out left and right and fold on bracing frame.
In addition, present invention also offers a kind of automatic payingoff construction method of iron tower of power transmission line stake actinobacillus device, it is characterized in that, comprise the following steps:
1) pack up folding for cardan wheel, single unit system is placed on transport trolley; 2) by manually being disassembled by spring, handle is pressed down automatically; 3) by shaft tray pull-up, with pin four for fulcrum, connecting rod one and connecting rod two position change, and reduce the position of shaft tray; 4) spool is manually fixed on shaft tray to pushing by utilization, makes connecting rod one and connecting rod two reset simultaneously and forms triangle; 5) by the cable pull-up above spool by after track adjusting wheel through split to enter cable-through hole track adjusting wheel roll between rod, electric motor starting drives screw rod to rotate to start outside defeated line, pick up cable enter the steel tower stake construction of line by workmen; 6) when the electric wire in spool is finished, repeat not 1)-5), until line construction completes.
Beneficial effect of the present invention: be fixed on by this device above transport trolley, drives its advance unwrapping wire by vehicle, and spool convenient disassembly, does not need to expend too many manpower simultaneously, and it is fast that device goes out linear velocity, is not wound around, is applicable to promoting the use of between the circuit of outlet simultaneously.
Accompanying drawing explanation
Fig. 1 is the structural representation of iron tower of power transmission line stake actinobacillus device of the present invention;
Fig. 2 be spider of the present invention structural representation;
Fig. 3 is the structural representation of another form of Fig. 2;
Fig. 4 is the structural representation of track adjusting wheel permanent seat of the present invention;
Fig. 5 is the structural representation of lift dog of the present invention;
Fig. 6 is that the present invention constructs schematic diagram.
Detailed description of the invention
As shown in the figure, iron tower of power transmission line stake actinobacillus device, comprise base plate 1, described base plate 1 is provided with dovetail furrow 13, stay bearing plate 28 is snapped in dovetail furrow 13 by bottom linker and is arranged on base plate 1, described stay bearing plate 28 is provided with pin folder 31, pin folder 31 has multiple pin-and-hole above, is met the spool 8 of different-diameter by the height regulating pin 11 to penetrate the adjustable spider of different pin-and-holes.Connecting rod 1, connecting rod 2 20 and connecting rod 3 32 composition spider is arranged on above stay bearing plate 28, and wherein: connecting rod 1 and connecting rod 2 20 junction are provided with shaft tray 19, shaft tray 19 scribbles lubricating oil above.Being provided with pin 4 21 bottom connecting rod 2 20 penetrates in stay bearing plate 28; Connecting rod 1 is connected with connecting rod 3 32 by pin 2 16, and connecting rod 3 32 presss from both sides 31 internal fixtion by regulating pin 11 to penetrate pin.
Shaft tray 19 is provided with spool 8, spool 8 both sides are provided with adapter plate 9, shaft tray 19 are provided with sensor 29, described base plate 1 is provided with bearing support block 2, screw rod 3 is arranged on bearing support block 2, and described screw rod 3 one end is connected with motor 12, and motor 12 is PLC control motor; Be connected with signal wire (SW) between described motor 12 and sensor 29, by the transducing signal of sensor 29, make motor 12 with spool 8 synchronous rotary.
Screw rod 3 is also provided with track adjusting wheel 23, and track adjusting wheel permanent seat 24 is mounted on below track adjusting wheel 23, described track adjusting wheel permanent seat 24 is also provided with and splits track adjusting wheel 25; Base plate 1 is also provided with lift dog 15;
1. described in, lift dog 15 comprises height regulating frame 152, and base plate 3 153 is arranged on above height regulating frame 152, and described base plate 3 154 is provided with cable-through hole 156 above, rolls rod 154 and is arranged in cable-through hole 156, described cable-through hole 156 is provided with cover plate 157.Cover plate 157 being also provided with inserted sheet 151 inserts in base plate 3 153, is going out in line process, rolls rod 154 swing offset and can be blocked restriction displacement range by inserted sheet 151, prevents rolling rod 154 and drops.
Spool 8 both sides are also provided with handle 5, and connecting rod 6 is connected between handle 5, connecting rod 6 is provided with track adjusting wheel 1, and described handle 5 is also provided with friction lining 30; Detouchable spring 10 is installed bottom handle 5.Also be provided with bracing frame 26 bottom base plate 1, cardan wheel 27 is arranged on above bracing frame 26.Described cardan wheel 27 can carry out left and right and fold on bracing frame 26.
In addition, present invention also offers a kind of automatic payingoff construction method of iron tower of power transmission line stake actinobacillus device, it is characterized in that, comprise the following steps:
1) pack up folding for cardan wheel 27, single unit system is placed on transport trolley; 2) by manually being disassembled by spring 10, handle 5 is pressed down automatically; 3) by shaft tray 19 pull-up, with pin 4 21 for fulcrum, connecting rod 1 and connecting rod 2 20 position change, and reduce the position of shaft tray 19; 4) spool 8 is manually fixed on shaft tray 19 to pushing by utilization, makes connecting rod 1 and connecting rod 2 20 reset simultaneously and forms triangle; 5) by the cable pull-up above spool 8 by after track adjusting wheel 23 through split to enter cable-through hole 156 track adjusting wheel 25 roll between rod 154, motor 12 starts drive screw rod 3 and rotates the outside defeated line of beginning, picks up cable enter the steel tower stake construction of line by workmen; 6) when the electric wire in spool 8 is finished, repeat not 1)-5), until line construction completes.
In addition to the implementation, the present invention can also have other embodiments.All employings are equal to the technical scheme of replacement or equivalent transformation formation, all drop on the protection domain of application claims.

Claims (6)

1. iron tower of power transmission line stake actinobacillus device, comprise base plate (1), described base plate (1) is provided with dovetail furrow (13), stay bearing plate (28) is snapped in dovetail furrow (13) by bottom linker and is arranged on base plate (1), it is characterized in that: described stay bearing plate (28) is provided with pin folder (31), connecting rod one (17), connecting rod two (20) and connecting rod three (32) form spider and are arranged on above stay bearing plate (28), wherein: connecting rod one (17) and connecting rod two (20) junction are provided with shaft tray (19), connecting rod two (20) bottom is provided with pin four (21) and penetrates in stay bearing plate (28), connecting rod one (17) is connected with connecting rod three (32) by pin two (16), and connecting rod three (32) penetrates pin folder (31) internal fixtion by regulating pin (11),
Described shaft tray (19) is provided with spool (8), spool (8) both sides are provided with adapter plate (9), shaft tray (19) is provided with sensor (29), described base plate (1) is provided with bearing support block (2), screw rod (3) is arranged on bearing support block (2), and described screw rod (3) one end is connected with motor (12); Signal wire (SW) is connected with between described motor (12) and sensor (29);
Described screw rod (3) is also provided with track adjusting wheel (23), track adjusting wheel permanent seat (24) is mounted on track adjusting wheel (23) below, described track adjusting wheel permanent seat (24) is also provided with and splits track adjusting wheel (25), base plate (1) is also provided with lift dog (15);
Described lift dog (15) comprises height regulating frame (152), base plate three (153) is arranged on above height regulating frame (152), described base plate three (154) is provided with cable-through hole (156) above, rolling rod (154) is arranged in cable-through hole (156), described cable-through hole (156) is provided with cover plate (157).
2. iron tower of power transmission line stake actinobacillus device as claimed in claim 1, it is characterized in that: described spool (8) both sides are also provided with handle (5), connecting rod (6) is connected between handle (5), connecting rod (6) is provided with track adjusting wheel one (7), described handle (5) is also provided with friction lining (30); Handle (5) bottom is provided with detouchable spring (10).
3. iron tower of power transmission line stake actinobacillus device as claimed in claim 1 or 2, is characterized in that: described base plate (1) bottom is also provided with bracing frame (26), and cardan wheel (27) is arranged on above bracing frame (26).
4. iron tower of power transmission line stake actinobacillus device as claimed in claim 3, is characterized in that: described cardan wheel (27) can carry out left and right and fold on bracing frame (26).
5. iron tower of power transmission line stake actinobacillus device as claimed in claim 1, is characterized in that: described cover plate (157) is also provided with inserted sheet (151) and inserts in base plate three (153).
6. the automatic payingoff construction method of iron tower of power transmission line stake actinobacillus device, is characterized in that, comprise the following steps:
Pack up folding for cardan wheel (27), single unit system is placed on transport trolley; 2) by manually being disassembled by spring (10), handle (5) is pressed down automatically; 3) by shaft tray (19) pull-up, with pin four (21) for fulcrum, connecting rod one (17) and connecting rod two (20) position change, and reduce the position of shaft tray (19); 4) spool (8) is manually fixed on shaft tray (19) to pushing by utilization, makes connecting rod one (17) and connecting rod two (20) reset simultaneously and forms triangle; 5) by the cable pull-up above spool (8) by after track adjusting wheel (23) through split to enter cable-through hole (156) track adjusting wheel (25) roll between rod (154), motor (12) starts drive screw rod (3) and rotates the outside defeated line of beginning, picks up cable enter the steel tower stake construction of line by workmen; 6) when the electric wire in spool (8) is finished, repeat not 1)-5), until line construction completes.
CN201510774851.6A 2015-11-13 2015-11-13 Iron tower of power transmission line stake actinobacillus device and its construction method Active CN105417271B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510774851.6A CN105417271B (en) 2015-11-13 2015-11-13 Iron tower of power transmission line stake actinobacillus device and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510774851.6A CN105417271B (en) 2015-11-13 2015-11-13 Iron tower of power transmission line stake actinobacillus device and its construction method

Publications (2)

Publication Number Publication Date
CN105417271A true CN105417271A (en) 2016-03-23
CN105417271B CN105417271B (en) 2019-04-12

Family

ID=55495897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510774851.6A Active CN105417271B (en) 2015-11-13 2015-11-13 Iron tower of power transmission line stake actinobacillus device and its construction method

Country Status (1)

Country Link
CN (1) CN105417271B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111268496A (en) * 2020-03-27 2020-06-12 广东电网有限责任公司 Rope structure releasing assembly
CN111416474A (en) * 2018-12-18 2020-07-14 日本电产三协株式会社 Driving device for drain valve
CN113432635A (en) * 2021-06-18 2021-09-24 浙江中新电力工程建设有限公司 Energy data monitoring and analyzing system and method based on comprehensive energy complementation

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020166917A1 (en) * 2001-05-08 2002-11-14 Eagelman John M. Electronic length control wire pay-off system and method
CN103015136A (en) * 2012-11-29 2013-04-03 偌纬创艺私人有限公司 Outdoor drying rack capable of improving clothes drying and putting away efficiency and being pulled indoors
CN103342264A (en) * 2013-06-18 2013-10-09 国家电网公司 Electric paying-off automobile
CN203398651U (en) * 2013-06-14 2014-01-15 国家电网公司 Cable reel brake device
US20140193235A1 (en) * 2013-01-08 2014-07-10 Cerro Wire Llc Reel handling device and method
CN104192637A (en) * 2014-09-16 2014-12-10 北京航空航天大学 Rope drive device with reciprocating wire arrangement function
CN104332882A (en) * 2014-11-19 2015-02-04 国家电网公司 Adjustable cable paying-off support
CN104863529A (en) * 2015-04-09 2015-08-26 山东科瑞机械制造有限公司 Rapid-traverse type power catwalk
CN204643336U (en) * 2015-03-23 2015-09-16 上海宝钢工业技术服务有限公司 Fix and rotate the frock of control for wire disk
CN204751676U (en) * 2015-07-27 2015-11-11 东莞市精端自动化设备有限公司 Shielded wire paying out machine

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020166917A1 (en) * 2001-05-08 2002-11-14 Eagelman John M. Electronic length control wire pay-off system and method
CN103015136A (en) * 2012-11-29 2013-04-03 偌纬创艺私人有限公司 Outdoor drying rack capable of improving clothes drying and putting away efficiency and being pulled indoors
US20140193235A1 (en) * 2013-01-08 2014-07-10 Cerro Wire Llc Reel handling device and method
CN203398651U (en) * 2013-06-14 2014-01-15 国家电网公司 Cable reel brake device
CN103342264A (en) * 2013-06-18 2013-10-09 国家电网公司 Electric paying-off automobile
CN104192637A (en) * 2014-09-16 2014-12-10 北京航空航天大学 Rope drive device with reciprocating wire arrangement function
CN104332882A (en) * 2014-11-19 2015-02-04 国家电网公司 Adjustable cable paying-off support
CN204643336U (en) * 2015-03-23 2015-09-16 上海宝钢工业技术服务有限公司 Fix and rotate the frock of control for wire disk
CN104863529A (en) * 2015-04-09 2015-08-26 山东科瑞机械制造有限公司 Rapid-traverse type power catwalk
CN204751676U (en) * 2015-07-27 2015-11-11 东莞市精端自动化设备有限公司 Shielded wire paying out machine

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111416474A (en) * 2018-12-18 2020-07-14 日本电产三协株式会社 Driving device for drain valve
CN111268496A (en) * 2020-03-27 2020-06-12 广东电网有限责任公司 Rope structure releasing assembly
CN111268496B (en) * 2020-03-27 2024-04-12 广东电网有限责任公司 Rope body structure release assembly
CN113432635A (en) * 2021-06-18 2021-09-24 浙江中新电力工程建设有限公司 Energy data monitoring and analyzing system and method based on comprehensive energy complementation

Also Published As

Publication number Publication date
CN105417271B (en) 2019-04-12

Similar Documents

Publication Publication Date Title
CN110061451B (en) Cable pay-off is used in electric power construction
CN102815565B (en) Combined multifunctional tape winding and unwinding device
CN203690811U (en) Multifunctional cable laying and paying-off apparatus for cable drum
CN105293162A (en) Power transmission line iron tower pile paying-off device and construction method thereof
CN206135310U (en) Duct cable conveyor
CN105417271A (en) Electric transmission line iron tower pile pay-off device and construction method thereof
CN204897040U (en) Automatic car that receive and releases of optical cable
CN203423593U (en) Core pulling inspection device for large-sized motor
CN204103371U (en) A kind of movable type cable laying apparatu
CN102176613A (en) Portable intelligent cable wire barrow
CN105293163A (en) Paying-off device for iron tower pile of transmission line and construction method of paying-off device
CN202639156U (en) Mineral cable straightener
CN202721428U (en) Power supply multifunctional winding and pay-off barrow
CN202247093U (en) Lifting mechanism for creel
CN210404563U (en) Automatic wire tightening device
CN202704641U (en) Combined-type multifunctional tape coiling and uncoiling device
CN208479044U (en) A kind of tool-type architectural electricity threading uses auxiliary device
CN209383168U (en) A kind of mobile separation receipts creel stand
CN203473886U (en) Scattered coil steering device
CN202373912U (en) Traveling type manual pay-off stand
CN202063603U (en) Wire guide roller used for pay-off machine
CN105151876A (en) Winding system of textile machine
CN218491113U (en) Construction pipe laying pay-off
CN103420222A (en) Friction-type plastic pipe winding machine
CN202296568U (en) Cord laying device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190307

Address after: 518000 2 4C, Zhongli yuan, Nanshan District, Shenzhen, Guangdong.

Applicant after: Yang Jieru

Applicant after: Gao Shuangfeng

Address before: 737200 22 eight, Yu Bao Village, six dam Township, Yongchang County, Jinchang, Gansu

Applicant before: Gao Shilong

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191011

Address after: 518000 Guangdong city of Shenzhen province Nanshan District sea Lai Building 2 4C

Co-patentee after: Lin Zhan Ping

Patentee after: Yang Jie Ru

Address before: 518000 Guangdong city of Shenzhen province Nanshan District sea Lai Building 2 4C

Co-patentee before: Gao Shuang Feng

Patentee before: Yang Jie Ru

TR01 Transfer of patent right
CP02 Change in the address of a patent holder

Address after: Room 107, no.379 Pingshan Avenue, Yufeng District, Liuzhou City, Guangxi Zhuang Autonomous Region

Patentee after: Yang Jieru

Patentee after: Lin Zhanping

Address before: 518000 2 4C, Zhongli yuan, Nanshan District, Shenzhen, Guangdong.

Patentee before: Yang Jieru

Patentee before: Lin Zhanping

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 518000 2 4C, Zhongli yuan, Nanshan District, Shenzhen, Guangdong.

Patentee after: Yang Jieru

Patentee after: Lin Zhanping

Address before: Room 107, no.379 Pingshan Avenue, Yufeng District, Liuzhou City, Guangxi Zhuang Autonomous Region

Patentee before: Yang Jieru

Patentee before: Lin Zhanping

CP02 Change in the address of a patent holder