CN105370038A - 一种钢筋混凝土剪力墙墙体施工缝的接茬方法 - Google Patents
一种钢筋混凝土剪力墙墙体施工缝的接茬方法 Download PDFInfo
- Publication number
- CN105370038A CN105370038A CN201410425442.0A CN201410425442A CN105370038A CN 105370038 A CN105370038 A CN 105370038A CN 201410425442 A CN201410425442 A CN 201410425442A CN 105370038 A CN105370038 A CN 105370038A
- Authority
- CN
- China
- Prior art keywords
- wall
- shear wall
- reinforced concrete
- connects
- stitched
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种钢筋混凝土剪力墙墙体施工缝的接茬方法,该方法的施工流程包括剪力墙外墙钢筋绑扎、剪力墙外墙模板支设、混凝土浇筑、模板拆模以及混凝土养护,其中:所述剪力墙外墙模板支设的施工方法包括了“在模板拼装的施工缝处固定板条、在施工缝的两侧采用水泥支撑加密布置、在施工缝的接茬部位处下延200mm预留对拉螺栓并以外龙骨夹紧固定”等步骤。本发明的优点是:可避免接茬处产生漏浆、蜂窝麻面以及错茬等问题的发生,从而减少混凝土外墙发生渗漏的概率;可保证剪力墙墙体的外观质量和使用功能并避免难度很大的后期维修,从而减少维修费用的支出。
Description
技术领域
本发明涉及一种钢筋混凝土剪力墙的施工方法,更具体地说,本发明涉及一种钢筋混凝土剪力墙墙体施工缝的接茬方法。
背景技术
钢筋混凝土剪力墙墙体接茬在建筑工程施工过程中是一个比较复杂且难度较大的重要节点,尤其是对于民用建筑,其混凝土外墙墙体施工缝的接茬施工状态更是直接影响着其外观质量的好坏。
通常情况下,钢筋混凝土剪力墙墙体的接茬施工,均采用在施工导墙或外墙模板下延200mm的部位预留螺栓并以木方夹紧固定的方法,来避免外墙观感差、层间接茬部位漏浆以及模板浇筑时流泪等缺点。但该方法的实施还是无法保证外墙接茬处的施工质量,以至存在以下缺陷:
(1)接茬处仍然容易漏浆并产生蜂窝麻面、错茬等质量问题;
(2)缺陷(1)的存在,外墙渗水并影响建筑的外观质量和使用功能;
(3)缺陷(1)、(2)的存在,导致后期维修费用较高且维修难度也大。
发明内容
本发明的目的就是克服上述现有技术的缺陷,并为此提供一种施工方便、费用低廉、效果可靠的钢筋混凝土剪力墙墙体施工缝的接茬方法。
本发明的技术方案是:
一种钢筋混凝土剪力墙墙体施工缝的接茬方法,包括剪力墙外墙钢筋绑扎、剪力墙外墙模板支设、混凝土浇筑、模板拆模以及混凝土养护等施工流程,其中:所述剪力墙外墙模板支设的施工方法包括以下步骤:
(1)采用多层板面板预拼装剪力墙外墙模板并以钢筋绑扎固定;
(2)在模板拼装的施工缝处固定板条;
(3)在施工缝的两侧采用水泥支撑加密布置;
(4)用塔吊将完成预拼装的剪力墙外墙模板吊装到安装位置;
(5)用木方以不大于200mm的间距做内龙骨;
(6)用双脚手管以不大于200mm的间距做外龙骨,要求底部一道外龙骨距地面的尺寸不大于200mm;
(7)在外龙骨上弹线定距并以600mm为纵横间距加工对拉螺栓孔;
(8)在所述的对拉螺栓孔内安装第一对拉螺栓;
(9)在施工缝的接茬部位处下延200mm预留第二对拉螺栓并以外龙骨夹紧固定。
在前述步骤(1)中,所述多层板面板的厚度为15mm。
在前述步骤(2)中,所述板条的厚度为25mm。
在前述步骤(3)中,施工缝两侧加密布置水泥支撑范围为30mm-50mm。
在前述步骤(4)中,所述剪力墙外墙模板的安装高度为层高加100mm。
在前述步骤(5)中,所述木方的规格为50x100mm。
在前述步骤(6)中,所述双脚手管的规格为φ48x3.5。
在前述步骤(8)中,所述第一对拉螺栓的直径为φ14。
在前述步骤(8)中,所述第二对拉螺栓的直径为φ16。
本发明采用对拉螺栓和加固板条相结合的施工方式,保证了剪力墙接茬处的施工质量,其有益效果是:
(1)可以避免接茬处产生漏浆、蜂窝麻面以及错茬等问题的发生,从而减少混凝土外墙发生渗漏的概率。
(2)可以保证剪力墙墙体的外观质量和使用功能,并避免难度很大的后期维修,从而减少维修费用的支出。
附图说明
图1是本发明在剪力墙墙体施工中支设模板的剖面示意图。
图2是本发明在剪力墙墙体施工中拆除模板后的剖面示意图。
图中标记:1--剪力墙外墙模板,2--板条,3--接茬部位,4--纵向钢筋,5--横向钢筋,6--内龙骨,7--外龙骨,8--第一对拉螺栓,9--混凝土,10--第二对拉螺栓。
具体实施方式
为了使本发明的技术方案更容易被清楚理解,下面结合附图和民建工程外墙施工的实施例作以详细说明。
图1示出了本发明在剪力墙墙体施工中支设模板的情况。
参照图1,剪力墙外墙模板1采用15mm厚的多层板面板拼装而成,25mm厚的板条2固定在两个多层板面板的施工缝处。
图2是本发明在剪力墙墙体施工中拆除模板后的示意图。
参照图2,完成混凝土9的浇筑并拆除施工缝下部的多层板面板,所述施工缝的接茬部位3呈现外观平整的良好状态。
参照图1、图2,本发明钢筋混凝土剪力墙墙体施工缝的接茬方法,以剪力墙外墙钢筋绑扎、剪力墙外墙模板支设、混凝土浇筑、模板拆模以及混凝土养护为施工流程,其中:剪力墙外墙模板支设的施工方法包括以下步骤:
(1)按照图纸设计尺寸,采用15mm厚的多层板面板预拼装剪力墙外墙模板1,并以纵向钢筋4和横向钢筋5绑扎固定;
(2)在拼装剪力墙外墙模板1的施工缝处固定25mm厚的板条2,以确保两个多层板面板之间不错缝、不跑浆;
(3)在所述施工缝两侧的30mm~50mm范围内采用水泥支撑加密布置;
(4)用塔吊将完成预拼装的剪力墙外墙模板1吊运并安装到需要安装的部位,其安装高度为层高加100mm;
(5)用规格为50x100mm木方做内龙骨6,要求其间距不大于200mm;
(6)用规格为φ48x3.5的双脚手管做外龙骨7要求底部一道外龙骨距地面的尺寸不大于200mm;
(7)按照技术方案的要求,在外龙骨7上弹线定距并进行对拉螺栓孔的钻孔加工,保证所述对拉螺栓孔的纵横间距均为600mm;
(8)在所述的对拉螺栓孔内安装直径为φ14的第一对拉螺栓8,对构成剪力墙的内、外墙面面板进行对拉,以保证模板加固体系承重时受力合理;
(9)在剪力墙外墙模板1施工缝的接茬部位3处下延200mm预留直径为φ16的第二对拉螺栓10,并以双脚手管做外龙骨7对其夹紧固定,以避免外墙观感差、层间接茬部位漏浆、流泪等问题的出现。
在前述步骤(2)中,为了防止板条2的脱落,务必在施工过程中将所述的板条2与施工缝处的多层板面板装钉牢固。
在本发明方法的实施过程中,尤其是剪力墙外墙模板支设方法的每个步骤,均有严格的施工监视,从而保证可靠的施工质量。
实践证明:实施本发明的钢筋混凝土剪力墙墙体施工缝的接茬方法,对防止剪力墙模板浇筑时产生漏浆、蜂窝麻面、错茬等质量问题起到了极其重要的作用,尤其是对拉螺栓和加固板条相结合的施工方式,可以彻底解决现有的施工方法通常存在的外墙观感差、层间接茬部位漏浆以及模板浇筑时流泪等缺点,从而使民建施工效率及其施工质量得到整体提高。
以上参照附图和实施例,对本发明的技术方案进行了示意性描述,该描述没有限制性。本领域的技术人员应能理解,在实际应用中,本发明中各个步骤的实施细节均有可能发生某些变化,而其他人员在其启示下也可能做出相似设计。特别需要指出的是:只要不脱离本发明的设计宗旨,所有显而易见的细节变化或相似设计,均包含在本发明的保护范围之内。
Claims (9)
1.一种钢筋混凝土剪力墙墙体施工缝的接茬方法,包括剪力墙外墙钢筋绑扎、剪力墙外墙模板支设、混凝土浇筑、模板拆模以及混凝土养护等施工流程,其特征是:所述剪力墙外墙模板支设的施工方法包括以下步骤:
(1)采用多层板面板预拼装剪力墙外墙模板并以钢筋绑扎固定;
(2)在模板拼装的施工缝处固定板条;
(3)在施工缝的两侧采用水泥支撑加密布置;
(4)用塔吊将完成预拼装的剪力墙外墙模板吊装到安装位置;
(5)用木方以不大于200mm的间距做内龙骨;
(6)用双脚手管以不大于200mm的间距做外龙骨,要求底部一道外龙骨距地面的尺寸不大于200mm;
(7)在外龙骨上弹线定距并以600mm为纵横间距加工对拉螺栓孔;
(8)在所述的对拉螺栓孔内安装第一对拉螺栓;
(9)在施工缝的接茬部位处下延200mm预留第二对拉螺栓并以外龙骨夹紧固定。
2.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:所述多层板面板的厚度为15mm。
3.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:所述板条的厚度为25mm。
4.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:施工缝两侧加密布置水泥支撑范围为30mm-50mm。
5.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:所述剪力墙外墙模板的安装高度为层高加100mm。
6.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:所述木方的规格为50x100mm。
7.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:所述双脚手管的规格为φ48x3.5。
8.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:所述第一对拉螺栓的直径为φ14。
9.根据权利要求1所述的钢筋混凝土剪力墙墙体施工缝的接茬方法,其特征是:所述第二对拉螺栓的直径为φ16。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410425442.0A CN105370038A (zh) | 2014-08-26 | 2014-08-26 | 一种钢筋混凝土剪力墙墙体施工缝的接茬方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410425442.0A CN105370038A (zh) | 2014-08-26 | 2014-08-26 | 一种钢筋混凝土剪力墙墙体施工缝的接茬方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105370038A true CN105370038A (zh) | 2016-03-02 |
Family
ID=55372613
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410425442.0A Pending CN105370038A (zh) | 2014-08-26 | 2014-08-26 | 一种钢筋混凝土剪力墙墙体施工缝的接茬方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105370038A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106639315A (zh) * | 2016-10-19 | 2017-05-10 | 北京城建北方建设有限责任公司 | 抹灰填充墙与清水混凝土墙交界处抗裂施工方法 |
CN106968352A (zh) * | 2017-06-06 | 2017-07-21 | 中建八局第四建设有限公司 | 墙体施工缝施工方法 |
CN107090918A (zh) * | 2017-06-16 | 2017-08-25 | 中国二十二冶集团有限公司 | 砼施工缝接茬施工方法 |
CN108612316A (zh) * | 2018-05-24 | 2018-10-02 | 中国二十冶集团有限公司 | 一种控制模板安装顺直度的方法 |
CN109025280A (zh) * | 2018-09-01 | 2018-12-18 | 深圳市前海胜德建筑科技有限公司 | 一种免塞缝下脚及施工方法 |
CN111411774A (zh) * | 2020-04-27 | 2020-07-14 | 五冶集团上海有限公司 | 一种防止施工缝错台漏浆的模板结构及施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201065641Y (zh) * | 2007-06-26 | 2008-05-28 | 成都市新湖装饰材料有限公司 | 建筑施工现浇用的塑料模板 |
JP2011127361A (ja) * | 2009-12-18 | 2011-06-30 | Takahashi Kanri:Kk | 隣地空無し仮枠rc‐0(ゼロ) |
CN202073311U (zh) * | 2011-04-21 | 2011-12-14 | 深圳市建工集团股份有限公司 | 一种饰面钢大模板 |
CN102444285A (zh) * | 2010-10-09 | 2012-05-09 | 中国建筑第四工程局有限公司 | 一种地下室钢筋混凝土外墙的制作方法 |
CN202644980U (zh) * | 2012-06-01 | 2013-01-02 | 中建三局建设工程股份有限公司 | 结构边缘构件模板接头加固体系 |
-
2014
- 2014-08-26 CN CN201410425442.0A patent/CN105370038A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201065641Y (zh) * | 2007-06-26 | 2008-05-28 | 成都市新湖装饰材料有限公司 | 建筑施工现浇用的塑料模板 |
JP2011127361A (ja) * | 2009-12-18 | 2011-06-30 | Takahashi Kanri:Kk | 隣地空無し仮枠rc‐0(ゼロ) |
CN102444285A (zh) * | 2010-10-09 | 2012-05-09 | 中国建筑第四工程局有限公司 | 一种地下室钢筋混凝土外墙的制作方法 |
CN202073311U (zh) * | 2011-04-21 | 2011-12-14 | 深圳市建工集团股份有限公司 | 一种饰面钢大模板 |
CN202644980U (zh) * | 2012-06-01 | 2013-01-02 | 中建三局建设工程股份有限公司 | 结构边缘构件模板接头加固体系 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106639315A (zh) * | 2016-10-19 | 2017-05-10 | 北京城建北方建设有限责任公司 | 抹灰填充墙与清水混凝土墙交界处抗裂施工方法 |
CN106968352A (zh) * | 2017-06-06 | 2017-07-21 | 中建八局第四建设有限公司 | 墙体施工缝施工方法 |
CN107090918A (zh) * | 2017-06-16 | 2017-08-25 | 中国二十二冶集团有限公司 | 砼施工缝接茬施工方法 |
CN108612316A (zh) * | 2018-05-24 | 2018-10-02 | 中国二十冶集团有限公司 | 一种控制模板安装顺直度的方法 |
CN109025280A (zh) * | 2018-09-01 | 2018-12-18 | 深圳市前海胜德建筑科技有限公司 | 一种免塞缝下脚及施工方法 |
CN111411774A (zh) * | 2020-04-27 | 2020-07-14 | 五冶集团上海有限公司 | 一种防止施工缝错台漏浆的模板结构及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105370038A (zh) | 一种钢筋混凝土剪力墙墙体施工缝的接茬方法 | |
CN109505609B (zh) | 浅埋暗挖城市地下综合管廊无支架施工方法及综合管廊 | |
CN104153485A (zh) | 一种防止窗户渗水的外墙企口及其施工方法 | |
CN104947684B (zh) | 一种基于装配式可回收工艺土钉墙支护的施工方法 | |
CN204826308U (zh) | 一种预制型钢混凝土剪力墙预拼结构装配式建筑 | |
CN105421810B (zh) | 一种预制墙板加固砌体结构及其施工方法 | |
CN204983662U (zh) | 一种对拉螺杆与钢管排架组合单侧支模装置 | |
CN203429641U (zh) | 建筑施工用单侧支模加固结构体系 | |
CN208965714U (zh) | 一种装配式混凝土预制管廊主体框架结构 | |
CN113719029A (zh) | 一种基于暗牛腿的装配式梁柱连接节点及其施工方法 | |
CN110067321B (zh) | 一种装配式剪力墙柔性连接装置及其施工方法 | |
CN206157913U (zh) | 一种装配式方钢管混凝土柱与钢梁连接节点 | |
CN105401580A (zh) | 地下通廊混凝土浇筑施工方法 | |
CN103790176B (zh) | 一种预埋短肢柱结构的施工方法 | |
CN104314105B (zh) | 地下室外墙板与现浇扶壁柱的连接竖向拼缝结构及施工方法 | |
CN110645022A (zh) | 一种联络通道自锚式模板支架系统及施工方法 | |
CN104712138A (zh) | 混凝土外墙塑料模板与多层木模板结合支模的施工方法 | |
CN208534081U (zh) | 一种老建筑构造柱的改造结构 | |
CN104895221B (zh) | 装配式型钢约束混凝土剪力墙结构 | |
CN212224604U (zh) | 一种用于外墙脚手架与墙体结构连接的连墙组件 | |
CN204151835U (zh) | 地下室外墙板与现浇扶壁柱的连接竖向拼缝结构 | |
CN101886470B (zh) | 清水混凝土密肋梁施工方法 | |
CN203411992U (zh) | 大体积混凝土内深孔预留孔洞模板 | |
CN103850257A (zh) | 用于岩质边坡的开挖坡体结构及其开挖施工方法 | |
CN109137984A (zh) | 装配整体式混合预制综合管廊 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160302 |
|
WD01 | Invention patent application deemed withdrawn after publication |