CN105239729A - Construction method for restoration of secondary hole excavation in constructed roof for pipeline penetration - Google Patents

Construction method for restoration of secondary hole excavation in constructed roof for pipeline penetration Download PDF

Info

Publication number
CN105239729A
CN105239729A CN201510631110.2A CN201510631110A CN105239729A CN 105239729 A CN105239729 A CN 105239729A CN 201510631110 A CN201510631110 A CN 201510631110A CN 105239729 A CN105239729 A CN 105239729A
Authority
CN
China
Prior art keywords
roofing
region
constructed
construction method
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510631110.2A
Other languages
Chinese (zh)
Other versions
CN105239729B (en
Inventor
夏志强
于新平
谭建国
余刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201510631110.2A priority Critical patent/CN105239729B/en
Publication of CN105239729A publication Critical patent/CN105239729A/en
Application granted granted Critical
Publication of CN105239729B publication Critical patent/CN105239729B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a construction method for restoration of secondary hole excavation in a constructed roof for pipeline penetration. The constructed roof comprises a waterproof roll layer, an insulation board layer and a concrete layer which are arranged on a structural roof board from bottom to top. The construction method includes: excavating a penetrating pipeline hole in the constructed roof and inserting a pipeline into the pipeline hole; chiseling the constructed roof circumferentially by centering on the pipeline and chiseling till the waterproof roll layer is reached so as to form a chiseling area; brushing waterproof paint on the surface, exposed over the chiseling area, of the pipeline and the surface of the waterproof roll layer in the chiseling area; pouring concrete in the chiseling area and vibrating to allow the concrete to be compact. The construction method has the advantage that reaction sticky waterproof rolls are paved on the pipeline in the secondary hole and the waterproof roll layer in the chiseling area, and the concrete is poured in the chiseling area and vibrated to be compact, so that good waterproof effect can be achieved.

Description

To construct the construction method that poling repairs that to punch after roofing
Technical field
The present invention relates to building engineering field, the construction method that the poling that punches after referring in particular to a kind of roofing of having constructed is repaired.
Background technology
Construction works more of the prior art, due to the reason such as change of design scheme, cause having pipeline through the roofing of having constructed, must again must to punch after roofing, and to punch the process of repairing to its secondary.Because roof waterproof now, insulation and rigid layer have all been constructed, on shaping roofing floor, secondary punches and wears fire main, possesses great leakage hidden trouble.Further, roofing poling does not belong to identical material due to tube wall and concrete, and compatible poor, there is thermal stresses, and be very easy to cracking near the mouth of pipe, be roof waterproof technological difficulties always.
In order to improve the water resistance of roofing, in prior art, normal waterproof roll or the water-repellent paint of adopting carries out waterproofing work to Roof system.When adopting waterproof roll as roof waterproof construction, waterproof roll cannot receive head at this position coiled material, can only receive head by water-repellent paint or construction sealant, is the position easily occurring cracking under thermal stresses and aging action impact.When adopting water-repellent paint as roof waterproof construction; water-repellent paint construction is complete all to be protected by cement mortar, and general thickness of mortar coverage, at 20mm ~ 30mm, closes up at drain gully position mortar and more easily occurs problem of Cracking; even destroy original waterproofing course, cause seepage.
Therefore, in prior art, to and the roofing secondary that completes construction punch carry out poling the mouth of pipe near cracking, seepage and the repair process technical problem that become this area urgently to be resolved hurrily.
Summary of the invention
Because the problems referred to above, the construction method that the poling that punches after the invention provides a kind of roofing of having constructed is repaired, roofing of having constructed comprises the waterproof roll layer be arranged on structure roof panel, insulation flaggy and layer of concrete from bottom to top, and described construction method comprises:
Roofing of constructing excavates the pipe hole run through, in described pipe hole, plugs pipeline;
Circumferentially roofing of constructing is cut centered by described pipeline, and cut to described waterproof roll layer, cut region to be formed;
Cut described in described pipeline exposes region surface and described in cut the surface brushing water-repellent paint respectively of the waterproof roll layer in region;
Cut described in described pipeline exposes region surface and described in cut the waterproof roll layer in region surface lay the sticky waterproof roll of reaction;
Concreting in region is cut and vibration compacting described.
The present invention has constructed the construction method that poling repairs that to punch after roofing, by the waterproof roll layer that exposes after cutting and after the sticky waterproof roll of reaction laid by the pipeline that punches, and cutting concreting in region and vibration compacting, complete the poling repairing construction that punches after roofing of constructing, good waterproof effect can be reached.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, when excavating described pipe hole, and the diameter 50mm larger than the diameter of described pipeline in described pipe hole.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, cuts when constructing roofing, described in cut region radius be not less than 300mm.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, when cutting the external coating water-repellent paint in region described in described pipeline exposes, the constructed finished surface of roofing of brushing aspect ratio exceeds 300mm.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is:
Adopt described water-repellent paint to carry out the cementation of fissures at the described Nodes cutting layer of concrete in region and the described insulation flaggy cut in region to close;
Adopt described water-repellent paint to carry out the cementation of fissures at the described Nodes cutting insulation flaggy in region and the described waterproof roll layer cut in region to close.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, the surface of the described layer of concrete cut in region and described in cut the insulation flaggy in region surface adopt loss circulation material and described water-repellent paint to carry out shutoff.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, described water-repellent paint is polyurethane water-proof paint, and the thickness of described water-repellent paint is 1.5mm.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, described reaction is glued waterproof roll and is overlapped with described waterproof roll layer and exceed 300mm along described pipeline turning over to the finished surface than roofing of constructing, waterproof roll is glued in described reaction and the described concrete interface of building in region that cuts adopts cement paste to seal, and the seam crossing of described pipeline and described waterproof roll layer adopts ointment filleting.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, the described concrete of building in region that cuts adopts C30 expansion pea gravel concreten, mix 8% waterproof agent, described in the concrete of building exceed 20mm than the finished surface of roofing of having constructed.
Constructed to punch after the roofing further improvement of construction method of poling reparation of the present invention is, the part that described concrete of building exceeds the finished surface of roofing of constructing apart within the scope of described pipeline 350mm, carries out putting slope along the center of described pipeline to the outside of described pipeline by the 2cm discrepancy in elevation.
Accompanying drawing explanation
Fig. 1 is that the present invention has constructed the flow chart of construction method that poling repairs of punching after roofing.
Fig. 2 is that the present invention has constructed the structural representation of roofing of constructing of construction method of poling reparation of punching after roofing.
Fig. 3 be in Fig. 1 step S101 complete after structural representation.
Fig. 4 be in Fig. 1 step S102 complete after structural representation.
Fig. 5 is the enlarged diagram of Fig. 4 interior joint A.
Fig. 6 be in Fig. 1 step S104 complete after structural representation.
Fig. 7 be in Fig. 1 step S105 complete after structural representation.
Detailed description of the invention
In order to make object of the present invention, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, be not intended to limit the present invention.
First, coordinate referring to shown in Fig. 2, Fig. 2 is that the present invention has constructed the structural representation of roofing of constructing of construction method of poling reparation of punching after roofing.The present invention has constructed and to have punched after roofing in construction method that poling repairs, and roofing 9 of having constructed comprises the waterproof roll layer 91 be arranged on structure roof panel 90, insulation flaggy 92 and layer of concrete 93 from bottom to top.Wherein, structure roof panel 90 is with smashing with troweling, and surface cleaning is clean; Waterproof roll layer 91 is 1.5mm thick reaction bonded type macromolecule wet paving waterproof roll (one side glues, green black intersection powerful film); Insulation flaggy 92 is the thick extruded polystyrene board of 30mm; Layer of concrete 93 is 40mm thick C20 muscle fine-stone concrete layer, joins φ 6.5I level steel, two-way 150, reinforced mesh colligation, if 4m*4m dividing joint, stitches wide 10mm, sealing compound filleting.Preferably, 1.2 solid cement based penetration crystallization type water proofing paints are also provided with between structure roof panel 90 and waterproof roll layer 91; 10mm thick low-intensity M5 mortar separation layer is also provided with between insulation flaggy 92 and layer of concrete 93.
Coordinate referring to shown in Fig. 1, Fig. 1 is that the present invention has constructed the flow chart of construction method that poling repairs of punching after roofing.The present invention has constructed the construction method that poling repairs that to punch after roofing, comprising:
step S101: shown in composition graphs 3, Fig. 3 be in Fig. 1 step S101 complete after structural representation.In the pipe hole 10 of roofing 9 excavating and running through of constructing, in pipe hole 10, plug pipeline 20.Preferably, during excavation pipe hole 10, the diameter 50mm larger than the diameter of pipeline 20 in pipe hole 10, ensures that pipeline 20 can pass through.
step S102: shown in composition graphs 4, Fig. 4 be in Fig. 1 step S102 complete after structural representation.Circumferentially roofing 9 of constructing is cut centered by pipeline 20, cut the layer of concrete 93 of roofing 9 of constructing and be incubated flaggy 92 to the waterproof roll layer 91 of roofing 9 of constructing, cutting region 30 to be formed.Preferably, cut when constructing roofing 9, the radius cutting region 30 is not less than 300mm, to ensure that rear paving waterproof roll has enough lap length.
step S103: expose the surface cutting region 30 and the surface cutting the waterproof roll layer 91 in region 30 brushing water-repellent paint respectively at pipeline 20.Preferably, when pipeline 20 exposes the external coating water-repellent paint cutting region 30, the constructed finished surface 94 of roofing 9 of brushing aspect ratio exceeds 300mm, to ensure better waterproof effect.
Particularly, consult shown in Fig. 5, Fig. 5 is the enlarged diagram of Fig. 4 interior joint A.Adopt water-repellent paint 40 to carry out the cementation of fissures at the layer of concrete 93 cut in region 30 and the Nodes of the insulation flaggy 92 cut in region 30 to close; Adopt water-repellent paint 40 to carry out the cementation of fissures at the insulation flaggy 92 cut in region 30 and the Nodes of the waterproof roll layer 91 cut in region 30 to close; Loss circulation material and water-repellent paint 40 is adopted to carry out shutoff on the surface of the layer of concrete 93 cut in region 30 and the surface that cuts the insulation flaggy 92 in region 30.Preferably, water-repellent paint 40 is polyurethane water-proof paint, and the thickness of water-repellent paint is 1.5mm, and described loss circulation material is leak stopping spirit.
step S104: shown in composition graphs 6, Fig. 6 be in Fig. 1 step S104 complete after structural representation.The surface cutting region 30 and the sticky waterproof roll 50 of the surface cutting the waterproof roll layer 91 in region 30 laying reaction is exposed at pipeline 20.Preferably, the sticky waterproof roll 50 of reaction overlaps with waterproof roll layer 91 and exceeds 300mm along the finished surface 94 pipeline 20 turned over to than roofing 9 of constructing, and pipeline 20 adopts ointment 110 filleting, to ensure better waterproof effect with the seam crossing of waterproof roll layer 91.
step S105: shown in composition graphs 7, Fig. 7 be in Fig. 1 step S105 complete after structural representation.Cutting in region 30 concreting 60 and vibration compacting.Preferably, cut the concrete 60 of building in region 30 and adopt C30 expansion pea gravel concreten, mix 8% waterproof agent, the concrete 60 of building exceeds 20mm than the finished surface 94 of roofing 9 of constructing.Further, the part 610 that the concrete 60 of building exceeds the finished surface 94 of roofing 9 of constructing at distance pipeline 20, is carried out putting slope along the center of pipeline 20 to the outside of pipeline 20 by the 2cm discrepancy in elevation, is ensured that water can not toward the inside diffluence of pipeline 20 within the scope of 350mm.Further, the sticky waterproof roll 50 of reaction adopts cement paste to seal, to ensure better waterproof effect with the interface cutting the concrete 60 of building in region 30.
The present invention has constructed the construction method that poling repairs that to punch after roofing, by the waterproof roll layer that exposes after cutting and after the sticky waterproof roll of reaction laid by the pipeline that punches, and cutting concreting in region and vibration compacting, complete the poling repairing construction that punches after roofing of constructing, good waterproof effect can be reached.
The above is only preferred embodiment of the present invention, not any pro forma restriction is done to the present invention, although the present invention discloses as above with preferred embodiment, but and be not used to limit the present invention, any those skilled in the art, not departing from the scope of technical solution of the present invention, make a little change when the technology contents of above-mentioned announcement can be utilized or be modified to the Equivalent embodiments of equivalent variations, in every case be the content not departing from technical solution of the present invention, according to any simple modification that technical spirit of the present invention is done above embodiment, equivalent variations and modification, all still belong in the scope of technical solution of the present invention.

Claims (10)

1. constructed the construction method that poling repairs that to punch after roofing, roofing of having constructed comprises the waterproof roll layer be arranged on structure roof panel, insulation flaggy and layer of concrete from bottom to top, and it is characterized in that, described construction method comprises:
Roofing of constructing excavates the pipe hole run through, in described pipe hole, plugs pipeline;
Circumferentially roofing of constructing is cut centered by described pipeline, and cut to described waterproof roll layer, cut region to be formed;
Cut described in described pipeline exposes region surface and described in cut the surface brushing water-repellent paint respectively of the waterproof roll layer in region;
Cut described in described pipeline exposes region surface and described in cut the waterproof roll layer in region surface lay the sticky waterproof roll of reaction;
Concreting in region is cut and vibration compacting described.
2. the construction method that the poling that punches after roofing of having constructed as claimed in claim 1 is repaired, is characterized in that, when excavating described pipe hole, and the diameter 50mm larger than the diameter of described pipeline in described pipe hole.
3. to have constructed as claimed in claim 1 the construction method that poling repairs that to punch after roofing, it is characterized in that, cut when constructing roofing, described in cut region radius be not less than 300mm.
4. to have constructed as claimed in claim 1 the construction method that poling repairs that to punch after roofing, it is characterized in that, when cutting the external coating water-repellent paint in region described in described pipeline exposes, the constructed finished surface of roofing of brushing aspect ratio exceeds 300mm.
5. the construction method that the poling that punches after roofing of having constructed as claimed in claim 1 is repaired, is characterized in that:
Adopt described water-repellent paint to carry out the cementation of fissures at the described Nodes cutting layer of concrete in region and the described insulation flaggy cut in region to close;
Adopt described water-repellent paint to carry out the cementation of fissures at the described Nodes cutting insulation flaggy in region and the described waterproof roll layer cut in region to close.
6. the construction method that the poling that punches after roofing of having constructed as claimed in claim 1 is repaired, it is characterized in that, the surface of the described layer of concrete cut in region and described in cut the insulation flaggy in region surface adopt loss circulation material and described water-repellent paint to carry out shutoff.
7. the construction method that the poling that punches after the roofing of constructing as described in claim 1,4,5 or 6 is repaired, it is characterized in that, described water-repellent paint is polyurethane water-proof paint, and the thickness of described water-repellent paint is 1.5mm.
8. the construction method that the poling that punches after roofing of having constructed as claimed in claim 1 is repaired, it is characterized in that, described reaction is glued waterproof roll and is overlapped with described waterproof roll layer and exceed 300mm along described pipeline turning over to the finished surface than roofing of constructing, waterproof roll is glued in described reaction and the described concrete interface of building in region that cuts adopts cement paste to seal, and the seam crossing of described pipeline and described waterproof roll layer adopts ointment filleting.
9. the construction method that the poling that punches after roofing of having constructed as claimed in claim 1 is repaired, it is characterized in that, the described concrete of building in region of cutting adopts C30 expansion pea gravel concreten, mixes 8% waterproof agent, described in the concrete of building exceed 20mm than the finished surface of roofing of having constructed.
10. the construction method that the poling that punches after roofing of having constructed as claimed in claim 1 is repaired, it is characterized in that, the part that described concrete of building exceeds the finished surface of roofing of constructing apart within the scope of described pipeline 350mm, carries out putting slope along the center of described pipeline to the outside of described pipeline by the 2cm discrepancy in elevation.
CN201510631110.2A 2015-09-29 2015-09-29 It has constructed the construction method of poling reparation of punching after roofing Active CN105239729B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510631110.2A CN105239729B (en) 2015-09-29 2015-09-29 It has constructed the construction method of poling reparation of punching after roofing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510631110.2A CN105239729B (en) 2015-09-29 2015-09-29 It has constructed the construction method of poling reparation of punching after roofing

Publications (2)

Publication Number Publication Date
CN105239729A true CN105239729A (en) 2016-01-13
CN105239729B CN105239729B (en) 2018-07-31

Family

ID=55037527

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510631110.2A Active CN105239729B (en) 2015-09-29 2015-09-29 It has constructed the construction method of poling reparation of punching after roofing

Country Status (1)

Country Link
CN (1) CN105239729B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288274A (en) * 2017-07-03 2017-10-24 中国十七冶集团有限公司 It is a kind of go out roof pipeline composite water-proof processing method
CN108979195A (en) * 2018-08-25 2018-12-11 广州天衣防水补强新技术开发有限公司 Holes reinforced construction method after reinforced concrete floor
CN109184089A (en) * 2018-08-06 2019-01-11 恒城建设科技有限公司 Building element and preparation method thereof and construction method
CN113323428A (en) * 2020-11-17 2021-08-31 广东良实机电工程有限公司 Construction method for additionally building pipeline well by opening hole on existing roof
CN116290874A (en) * 2023-02-07 2023-06-23 中国十七冶集团有限公司 Anti-leakage open pore plugging method for inverted roof waterproof construction

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004190238A (en) * 2002-12-09 2004-07-08 Ohbayashi Corp Method for injecting water stop into steel-pipe joint section
CN102561405A (en) * 2010-12-09 2012-07-11 上海市基础工程有限公司 Opening treatment method for pipe-roofing continuous perforation
CN203258205U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Anti-leakage structure of floor-penetrating pipeline without sleeve
CN204001334U (en) * 2014-07-24 2014-12-10 中国建筑东北设计研究院有限公司 Be applicable to first seal the in-situ reinforced concrete slab punching afterwards

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004190238A (en) * 2002-12-09 2004-07-08 Ohbayashi Corp Method for injecting water stop into steel-pipe joint section
CN102561405A (en) * 2010-12-09 2012-07-11 上海市基础工程有限公司 Opening treatment method for pipe-roofing continuous perforation
CN203258205U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Anti-leakage structure of floor-penetrating pipeline without sleeve
CN204001334U (en) * 2014-07-24 2014-12-10 中国建筑东北设计研究院有限公司 Be applicable to first seal the in-situ reinforced concrete slab punching afterwards

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
庄景山: "《安装工程质量常见问题与防治300例》", 30 June 2015 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288274A (en) * 2017-07-03 2017-10-24 中国十七冶集团有限公司 It is a kind of go out roof pipeline composite water-proof processing method
CN109184089A (en) * 2018-08-06 2019-01-11 恒城建设科技有限公司 Building element and preparation method thereof and construction method
CN108979195A (en) * 2018-08-25 2018-12-11 广州天衣防水补强新技术开发有限公司 Holes reinforced construction method after reinforced concrete floor
CN113323428A (en) * 2020-11-17 2021-08-31 广东良实机电工程有限公司 Construction method for additionally building pipeline well by opening hole on existing roof
CN116290874A (en) * 2023-02-07 2023-06-23 中国十七冶集团有限公司 Anti-leakage open pore plugging method for inverted roof waterproof construction

Also Published As

Publication number Publication date
CN105239729B (en) 2018-07-31

Similar Documents

Publication Publication Date Title
CN106120873B (en) A kind of construction method of pile-raft foundation pre-installed and inverted adhered composite high-molecular waterproof roll
CN105239729A (en) Construction method for restoration of secondary hole excavation in constructed roof for pipeline penetration
CN110747899B (en) Basement waterproof construction method
CN111734457B (en) Construction method of tunnel water-drainage-preventing system
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN206319910U (en) Infiltration disposal system is reinforced in a kind of tunnel-liner
CN106640154A (en) Treatment method and structure for water seepage of tunnel lining circular construction joint crack
CN108842817A (en) A kind of subway station overlays waterproof roll structure and its construction technology
CN102561405A (en) Opening treatment method for pipe-roofing continuous perforation
CN105019919A (en) Tunnel for transmitting fluid and construction method thereof
CN105839677A (en) Advanced water prevention construction process for post-cast strip of side wall of basement
CN106812219A (en) Filling wall top stuff up a crack construction method
CN109440951A (en) New-old concrete works intersection stitches waterproof construction and construction technology
CN202660067U (en) Waterproof sleeve preventing wall body leakage
CN108842816A (en) A kind of waterproofing for subway station structure and its construction technology
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN109667607B (en) Tunnel partition waterproof construction process
CN110541431A (en) waterproof structure of pipe gallery and construction method thereof
CN102425228A (en) Multifunctional environment-friendly movable water tank
CN202401561U (en) Multifunctional environment-friendly movable water channel
CN209397743U (en) New-old concrete works intersection stitches waterproof construction
CN107761783A (en) The method for waterproofing of skyscraper underground pile crown
CN110130667A (en) A kind of method of the pre-buried pipeline finished product protection of flooring
CN109296011A (en) Underground structrue engineering concrete structure seam waterproof construction technology
CN205329900U (en) Prefabricated coincide wallboard underground waterproof construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant