CN105207110A - Method and device for construction temporary electricity utilization arrangement - Google Patents

Method and device for construction temporary electricity utilization arrangement Download PDF

Info

Publication number
CN105207110A
CN105207110A CN201510339825.0A CN201510339825A CN105207110A CN 105207110 A CN105207110 A CN 105207110A CN 201510339825 A CN201510339825 A CN 201510339825A CN 105207110 A CN105207110 A CN 105207110A
Authority
CN
China
Prior art keywords
construction
steel support
temporary electricity
electric wire
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510339825.0A
Other languages
Chinese (zh)
Inventor
王一培
万泽卿
吴卿鸿
余涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Third Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority to CN201510339825.0A priority Critical patent/CN105207110A/en
Publication of CN105207110A publication Critical patent/CN105207110A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a method and a device for construction temporary electricity utilization arrangement. According to the method disclosed by the invention, a prefabricated T-shaped steel bracket is arranged at the edge of a construction passageway, the T-shaped steel bracket is distributed at the edge of the construction passageway, an electric wire is erected at the upper part of the T-shaped steel bracket, and the electric wire is fixed through a steel stranded wire. According to the invention, a mode similar to electric wire pole overhead electric wire arrangement is adopted, thereby facilitating construction electricity taking, eliminating potential safety hazards existing in temporary electricity utilization electric wire arrangement, and having the characteristics of simple and convenient operation, safety and practicability. The device is convenient in assembling and removing operation, and the labor cost is saved; the device is not easy to damage, can be recycled after being used, and is high in repeated utilization rate; and the appearance is unified, a purpose of safe and civilized construction is achieved, and the device has the advantages of construction site overall image improvement and the like. It is tested and proved by practice that the method and the device disclosed by the invention have the characteristics of safety, simple and convenient operation, easy construction, significant economic benefit and the like.

Description

A kind of method that temporary electricity of constructing is arranged and device
Technical field
The present invention relates to a kind of method and device of temporary electricity layout of constructing, belong to architectural engineering temporary facility application.
Background technology
In construction overall process, the temporary electricity amount of assigning a work is large, and how to ensure that Electrical Safety and electric wire move towards to arrange is a difficult problem always.In general construction, the phenomenon that electric wire is arbitrarily settled along ground is general, and built on stilts layout of electric wire limits by various condition in addition, more difficult realization.This way shortcoming is: the insulating barrier of electric wire of easily grinding away, and causes the harm such as electric leakage, short circuit, and in work progress, power taking is inconvenient, causes workmen's electric shock accidents.In addition, power taking of generally constructing connects electricity needs professional electrician first to pick out plug-in socket.Along with the propelling of construction schedule, temporary electricity scope expands gradually, and electric wire consumption increases gradually, therefore more increases the hidden danger of safety utilization of electric power.Especially, in floor, the haywire between floor and floor is arranged, intricate, hidden danger exists everywhere, does not meet the requirement of engineering civilized construction.
Summary of the invention
The object of the invention is: for the defect of prior art, a kind of method providing temporary electricity of constructing to arrange and device, the inconvenience of built on stilts electric wire arrangement can be solved, electric wire along the problem of ground configuration and how safely and fast power taking electricity consumption, to overcome the deficiency of existing slope retaining technology.
Technical scheme of the present invention
The method that temporary electricity of constructing is arranged, the method arranges prefabricated T steel support at construction channel edge, and this T steel support is distributed in construction channel edge place, and T steel frame upper is installed electricity lines and by steel strand wire securing electric lines.
In the method that aforesaid a kind of temporary electricity of constructing is arranged, described T steel frame bottom is through being bolted to construction channel edge, and T steel frame upper both wings prepared screw-bolt hole hole, hangs electronic box in the middle of T steel support.
In the method that aforesaid a kind of temporary electricity of constructing is arranged, porcelain vase is set at the bolt hole place of T steel frame upper both wings side.
The device that a kind of temporary electricity of constructing is arranged, comprise the prefabricated T steel support being located at construction channel edge, T steel support is bolted on ground, bolt one is provided with in T steel frame upper both wings prepared screw-bolt hole hole on bolt hole, the bolt one of T steel support both wings side is fixed with porcelain vase, be provided with electronic box in T steel mid-stent, electronic box both sides are respectively provided with socket.
In the device that aforesaid a kind of temporary electricity of constructing is arranged, described socket comprises 220V aviation quick socket and 380V aviation quick socket.
In the device that aforesaid a kind of temporary electricity of constructing is arranged, described electronic box is hung on T steel support by the moment reinforcement that back is welded.
Compared with prior art, present invention employs the mode that similar wire column makes somebody a mere figurehead electric wire arrangement, facilitate construction power taking, eliminate temporary electricity electric wire and arrange the potential safety hazard existed, there is simple to operation, safe and practical feature.Install, dismantling operation is convenient, save labour cost; Not fragile, can reclaim after using, recycling rate of waterused is high; Uniform appearance, reaches the object of safety construction, promotes the advantages such as building site overall image.Prove through practice test, the present invention has the features such as safe, easy and simple to handle, easy construction, remarkable in economical benefits.
Accompanying drawing explanation
Accompanying drawing 1 is structural representation of the present invention;
Accompanying drawing 2 is structural representations of T steel support in the present invention.
Embodiment
Below in conjunction with accompanying drawing to the present invention with being described in further detail, but not as any limitation of the invention.
Embodiments of the invention: a kind of method that temporary electricity of constructing is arranged, it is characterized in that: the method arranges prefabricated T steel support at construction channel edge, this T steel support is distributed in construction channel edge place, and T steel frame upper is installed electricity lines and by steel strand wire securing electric lines.
Wherein T steel frame bottom is through being bolted to construction channel edge, T steel frame upper both wings prepared screw-bolt hole hole, hangs electronic box in the middle of T steel support: at the bolt hole place of T steel frame upper both wings side, porcelain vase is set.
The device that a kind of temporary electricity of constructing constructed by said method is arranged, as shown in drawings, comprise the prefabricated T steel support 1T shape steel bracket 1 being located at construction channel edge and be fixed on ground by bolt 5, bolt 1 is provided with in both wings prepared screw-bolt hole hole, T steel support 1 top on bolt hole, the bolt 1 of T steel support 1 both wings side is fixed with porcelain vase 3, electronic box 4 is provided with in the middle part of T steel support 1, this electronic box 4 is hung on T steel support 1 by the moment reinforcement that back is welded, electronic box 4 both sides are respectively provided with socket, this socket comprises 220V aviation quick socket 6 and 380V aviation quick socket 7.
The present embodiment operationally, only need to install by figure, arrange this device at construction channel edge every suitable distance, install electricity lines, and walks around porcelain vase by T steel frame upper, and by steel strand wire securing electric lines.Electronic box is provided with aviation quick socket in addition, and power taking is very convenient.Although the present invention's structure is simple, method is very ingenious, well solves the difficult problem that job site temporary electricity makes somebody a mere figurehead layout.The bolt of another wing of T steel frame upper is for subsequent use, can hang illuminating lamp etc.

Claims (6)

1. the method that temporary electricity of constructing is arranged, is characterized in that: the method arranges prefabricated T steel support at construction channel edge, and this T steel support is distributed in construction channel edge place, and T steel frame upper is installed electricity lines and by steel strand wire securing electric lines.
2. the method for a kind of temporary electricity layout of constructing according to claim 1, is characterized in that: described T steel frame bottom is through being bolted to construction channel edge, and T steel frame upper both wings prepared screw-bolt hole hole, hangs electronic box in the middle of T steel support.
3. the method for a kind of temporary electricity layout of constructing according to claim 2, is characterized in that: arrange porcelain vase at the bolt hole place of T steel frame upper both wings side.
4. the device of temporary electricity layout of constructing, comprise the prefabricated T steel support (1) being located at construction channel edge, it is characterized in that: T steel support (1) is fixed on ground by bolt (5), on bolt hole, bolt one (2) is provided with in both wings prepared screw-bolt hole hole, T steel support (1) top, the bolt one (2) of T steel support (1) both wings side is fixed with porcelain vase (3), be provided with electronic box (4) at T steel support (1) middle part, electronic box (4) both sides are respectively provided with socket.
5. the device of a kind of temporary electricity layout of constructing according to claim 4, is characterized in that: described socket comprises 220V aviation quick socket (6) and 380V aviation quick socket (7).
6. the device of a kind of temporary electricity layout of constructing according to claim 4, is characterized in that: described electronic box (4) is hung on T steel support (1) by the moment reinforcement that back is welded.
CN201510339825.0A 2015-06-18 2015-06-18 Method and device for construction temporary electricity utilization arrangement Pending CN105207110A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510339825.0A CN105207110A (en) 2015-06-18 2015-06-18 Method and device for construction temporary electricity utilization arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510339825.0A CN105207110A (en) 2015-06-18 2015-06-18 Method and device for construction temporary electricity utilization arrangement

Publications (1)

Publication Number Publication Date
CN105207110A true CN105207110A (en) 2015-12-30

Family

ID=54954623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510339825.0A Pending CN105207110A (en) 2015-06-18 2015-06-18 Method and device for construction temporary electricity utilization arrangement

Country Status (1)

Country Link
CN (1) CN105207110A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106410718A (en) * 2016-11-01 2017-02-15 金螳螂精装科技(苏州)有限公司 Construction site temporary power supply erecting system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201199618Y (en) * 2008-04-29 2009-02-25 江苏省电力公司泗阳县供电公司 Line fixing rack
KR100908446B1 (en) * 2008-12-04 2009-07-21 홍봉선 Supporting bar for an over head line
CN201663401U (en) * 2009-08-11 2010-12-01 姚维华 Mobile electric box
CN202423950U (en) * 2011-12-12 2012-09-05 河南省电力公司安阳供电公司 Temporary power line support
CN203504065U (en) * 2013-09-18 2014-03-26 中建六局建设发展有限公司 Simple temporary bracket for raising wire
CN204680987U (en) * 2015-06-18 2015-09-30 中建四局第三建筑工程有限公司 The device that a kind of temporary electricity of constructing is arranged

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201199618Y (en) * 2008-04-29 2009-02-25 江苏省电力公司泗阳县供电公司 Line fixing rack
KR100908446B1 (en) * 2008-12-04 2009-07-21 홍봉선 Supporting bar for an over head line
CN201663401U (en) * 2009-08-11 2010-12-01 姚维华 Mobile electric box
CN202423950U (en) * 2011-12-12 2012-09-05 河南省电力公司安阳供电公司 Temporary power line support
CN203504065U (en) * 2013-09-18 2014-03-26 中建六局建设发展有限公司 Simple temporary bracket for raising wire
CN204680987U (en) * 2015-06-18 2015-09-30 中建四局第三建筑工程有限公司 The device that a kind of temporary electricity of constructing is arranged

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106410718A (en) * 2016-11-01 2017-02-15 金螳螂精装科技(苏州)有限公司 Construction site temporary power supply erecting system

Similar Documents

Publication Publication Date Title
CN103266779A (en) Lifting slippage construction device for crossing horizontal obstacle and method thereof
CN204680987U (en) The device that a kind of temporary electricity of constructing is arranged
CN103532048B (en) A kind of large-scale lattice crossing frame of Rapid Combination
CN202359878U (en) Buried type expandable insulating rail
CN106505484A (en) Piping lane cable laying method
CN203284128U (en) Hoisting tool of main mechanism of switch blade
CN105207110A (en) Method and device for construction temporary electricity utilization arrangement
CN204040556U (en) A telescopic graduation two electronic box protection canopy
CN202373939U (en) Live-working double-conductor lifting device
CN205189502U (en) Rail for electric overhaul equipment
CN204983712U (en) But socket joint round pin stationary height -adjusting protection canopy
CN202081666U (en) Mounting working pergola for cable accessory
CN205188867U (en) Vertical intercepting device in parking area
CN203545559U (en) Electric meter box hoisting tool
CN204343778U (en) A kind of line bar
CN203345999U (en) Special multifunctional lifting frame for busbar bridge
CN102957113B (en) Decoration construction temporary power construction system
CN202906291U (en) Operation rope ladder hanging equipment
CN202153620U (en) Equipotential working insulating platform
CN202268651U (en) Fixing device of transmission wire lifter
CN105305300A (en) Device used for replacing tubular bus support porcelain insulator
CN204992475U (en) A device for job site cable conductor erects
CN204626923U (en) A kind of lifting being applicable to climbing frame base turns to girder steel
CN210105730U (en) Portable crane span structure climbing ladder
CN202268650U (en) Insulation pulling plate of transmission wire lifter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151230