CN102957113B - Decoration construction temporary power construction system - Google Patents

Decoration construction temporary power construction system Download PDF

Info

Publication number
CN102957113B
CN102957113B CN201210446509.XA CN201210446509A CN102957113B CN 102957113 B CN102957113 B CN 102957113B CN 201210446509 A CN201210446509 A CN 201210446509A CN 102957113 B CN102957113 B CN 102957113B
Authority
CN
China
Prior art keywords
construction
suspension bracket
cucurbit
ceramic
temporary power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210446509.XA
Other languages
Chinese (zh)
Other versions
CN102957113A (en
Inventor
唐潇俊
赵会来
粱虓
单昱俊
石琳惠
季林
王郭彬
郑哲
孙艳
丁松飞
张卫斌
程书海
陈伟
朱春林
顾蒋权
王华伟
秦永祥
刘剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Gold Mantis Construction Decoration Co Ltd
Original Assignee
Suzhou Gold Mantis Construction Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Gold Mantis Construction Decoration Co Ltd filed Critical Suzhou Gold Mantis Construction Decoration Co Ltd
Priority to CN201210446509.XA priority Critical patent/CN102957113B/en
Publication of CN102957113A publication Critical patent/CN102957113A/en
Application granted granted Critical
Publication of CN102957113B publication Critical patent/CN102957113B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The invention discloses a kind of decoration construction temporary power construction system, it comprises suspension bracket (1), hang spring (2), ceramic cucurbit (3), cable (4), suspension bracket (1) and floor construction are fixed, suspension bracket (1) is provided with ceramic cucurbit (3), hang spring (2) and floor construction are fixed, and hang spring (2) are provided with ceramic cucurbit (3); Some suspension brackets (1), some hang springs (2) distribute on the electric power system line alignment of planning, and cable (4) is installed on ceramic cucurbit (3) by band (8).Decoration construction temporary power construction system of the present invention, can improve the functional efficiency of temporary power facility, does not need constantly adjustment to face electric decorating position, reduces engineering management cost, cost of labor and material cost, and safer.

Description

Decoration construction temporary power construction system
Technical field
The present invention relates to a kind of decoration construction temporary power construction system.
Background technology
Existing interior decoration job site temporary electricity mostly be establish along wall stand, independent vertical rod erection.Along with the expansion of the scope of operation, this type of sets up mode can not meet on-the-spot omnibearing power supply for construction demand.Especially in construction peak period, between work post, operation, electricity consumption is particularly thorny, has had a strong impact on the continuity that construction is connected, and also easily damages finished product, semi-finished product, and it is very serious that manpower and materials waste situation.
There is following drawback in conventional temporary power measure:
1, a large amount of A-frame is made and vertical rod material requested cost is higher;
2, a large amount of A-frame is made and vertical rod consumes manually more;
3, along with the expansion of the scope of operation, need constantly adjustment to face electric decorating position, impact construction, affects progress, forms potential safety hazard.
Summary of the invention
The object of the invention is: provide a kind of decoration construction temporary power construction system, it can improve the functional efficiency of temporary power facility, do not need constantly adjustment to face electric decorating position, reduce engineering management cost, cost of labor and material cost, and safer.
Technical scheme of the present invention is: a kind of decoration construction temporary power construction system, it comprises suspension bracket, hang spring, ceramic cucurbit, cable.Suspension bracket and floor construction are fixed, and suspension bracket are provided with ceramic cucurbit; Hang spring and floor construction are fixed, and hang spring are provided with ceramic cucurbit; Some suspension brackets, some hang springs distribute on the electric power system line alignment of planning, and cable is installed on ceramic cucurbit by band.
Below technique scheme is further expalined:
Described suspension bracket is arranged at the position, turning of line alignment, and on the craspedodrome direction of line alignment, interval arranges some hang springs.
What the craspedodrome direction of described line alignment is arranged hang spring is spaced apart 5 meters.
Described suspension bracket is the angle bar suspension bracket that angle bar makes, and suspension bracket forms T-shaped structure by two sections of angle bar, and the upper end of T-shaped is fixed by expansion bolt and floor construction.
Described hang spring is fixed by top explosion bolt and floor construction.
Described ceramic cucurbit is connected and fixed by bolt and nut and suspension bracket.
Described ceramic cucurbit is connected and fixed by nut and hang spring.
Described suspension bracket is also provided with the diagonal brace of booster action.
Advantage of the present invention is: decoration construction temporary power construction system of the present invention, and floor as fixing point, is not affected ground, wall construction by it, does not substantially affect end face construction.Therefore there will not be and repeatedly arrange temporary electricity and cause pause of constructing, effectively improve the continuity of safety construction, greatly reduce expending of the human and material resources that repeated work causes.This technology is made rational planning for the erection mode facing electricity, improves the functional efficiency facing electric facility, reduces engineering management cost, saved certain social resources.This erection scheme can be avoided establishing along wall stand, independent vertical rod erection and repeated multiple timesly again set up temporary electricity and the adverse effect brought.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described:
Fig. 1 of the present inventionly moves towards floor map;
Fig. 2 is that schematic diagram is moved towards in space of the present invention;
Structural representation when Fig. 3 is suspension bracket of the present invention work;
Structural representation when Fig. 4 is hang spring of the present invention work;
Wherein: 1 suspension bracket; 2 hang springs; 3 ceramic cucurbits; 4 cables; 5 nuts; 6 expansion bolts; 7 top explosion bolts; 8 bands.
Embodiment
Embodiment: as shown in Figure 1, Figure 2, Figure 3, Figure 4, a kind of decoration construction temporary power construction system, it comprises suspension bracket 1, hang spring 2, ceramic cucurbit 3, cable 4.Suspension bracket 1 and floor construction are fixed, and suspension bracket 1 are provided with ceramic cucurbit 3, and hang spring 2 and floor construction are fixed, and hang spring 2 are provided with ceramic cucurbit 3; Some suspension brackets 1, some hang springs 2 distribute on the electric power system line alignment of planning, and cable 4 is installed on ceramic cucurbit 3 by band 8.
Suspension bracket 1 is arranged at the position, turning of line alignment, the craspedodrome place interval of line alignment some hang springs 2 are set.What the craspedodrome direction of line alignment is arranged hang spring is spaced apart 5 meters.
The angle bar suspension bracket that suspension bracket 1 makes for angle bar, suspension bracket 1 forms T-shaped structure by two sections of angle bar, and the upper end of T-shaped is fixed by expansion bolt 6 and floor construction.
Hang spring 2 is fixed with floor construction by top explosion bolt 7.
Cucurbit 3 is connected and fixed by bolt and nut and suspension bracket 1 pottery.
Cucurbit 3 is connected and fixed by nut 5 and hang spring 2 pottery.
Suspension bracket 1 is also provided with the diagonal brace of booster action.
When the present embodiment is implemented, according to actual design needs, determine the size of angle bar suspension bracket 1, hang spring 2, adopt expansion bolt 6 to fix suspension bracket 1 along line alignment at floor slab bottoms turning, adopt top explosion bolt 7 to install hang spring 2 at interval of about 5 meters, bottom is lower than the minimum absolute altitude 50cm of furred ceiling.With due regard to can increase diagonal brace for hanging longer angle bar suspension bracket 1 because meeting furred ceiling absolute altitude, avoiding suspension bracket 1 to produce large distortion because of lateral stressed.Pottery cucurbit 3 uses bolt and nut to fix up and down, up and down distance 20cm ~ 30cm.The level correction post-tensioning realizing tie point establishes cable 4, cable 4 is adopted band 8 is stable to be placed on ceramic cucurbit 3.
It should be pointed out that for the present invention through absolutely proving, also can have the embodiment of multiple conversion and remodeling, be not limited to the specific embodiment of above-mentioned execution mode.Above-described embodiment is as just explanation of the present invention, instead of restriction.In a word, protection scope of the present invention should comprise those apparent conversion or alternative and remodeling to those skilled in the art.

Claims (6)

1. a decoration construction temporary power construction system, it is characterized in that: it comprises suspension bracket (1), hang spring (2), ceramic cucurbit (3), cable (4), suspension bracket (1) and floor construction are fixed, suspension bracket (1) is provided with ceramic cucurbit (3), hang spring (2) and floor construction are fixed, and hang spring (2) are provided with ceramic cucurbit (3); Some suspension brackets (1), some hang springs (2) distribute on the electric power system line alignment of planning, and cable (4) is installed on ceramic cucurbit (3) by band (8);
Described suspension bracket (1) is arranged at the position, turning of line alignment, and on the craspedodrome direction of line alignment, interval arranges some hang springs (2);
The angle bar suspension bracket that described suspension bracket (1) makes for angle bar, suspension bracket (1) forms T-shaped structure by two sections of angle bar, and the upper end of T-shaped is fixed by expansion bolt (6) and floor construction.
2. decoration construction temporary power construction system according to claim 1, is characterized in that: what the craspedodrome direction of described line alignment is arranged hang spring (2) is spaced apart 5 meters.
3. decoration construction temporary power construction system according to claim 1, is characterized in that: described hang spring (2) is fixed by top explosion bolt (7) and floor construction.
4. decoration construction temporary power construction system according to claim 1, is characterized in that: described ceramic cucurbit (3) is connected and fixed by bolt and nut and suspension bracket (1).
5. decoration construction temporary power construction system according to claim 1, is characterized in that: described ceramic cucurbit (3) is connected and fixed by nut (5) and hang spring (2).
6. decoration construction temporary power construction system according to claim 1, is characterized in that: the diagonal brace described suspension bracket (1) being also provided with booster action.
CN201210446509.XA 2012-11-09 2012-11-09 Decoration construction temporary power construction system Active CN102957113B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210446509.XA CN102957113B (en) 2012-11-09 2012-11-09 Decoration construction temporary power construction system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210446509.XA CN102957113B (en) 2012-11-09 2012-11-09 Decoration construction temporary power construction system

Publications (2)

Publication Number Publication Date
CN102957113A CN102957113A (en) 2013-03-06
CN102957113B true CN102957113B (en) 2016-01-20

Family

ID=47765539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210446509.XA Active CN102957113B (en) 2012-11-09 2012-11-09 Decoration construction temporary power construction system

Country Status (1)

Country Link
CN (1) CN102957113B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106410718A (en) * 2016-11-01 2017-02-15 金螳螂精装科技(苏州)有限公司 Construction site temporary power supply erecting system
CN110620348A (en) * 2019-08-30 2019-12-27 北京首钢建设集团有限公司 Temporary power frame construction method utilizing indoor assembled temporary power hanger rod

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3664010A (en) * 1970-03-19 1972-05-23 Preformed Line Products Co Line tie
CN2808640Y (en) * 2005-06-16 2006-08-23 上海市安装工程有限公司 Hanger frame for subway engineering
CN202906328U (en) * 2012-11-09 2013-04-24 苏州金螳螂建筑装饰股份有限公司 A temporary power supply erecting system used in decoration construction

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2694773C (en) * 2009-02-27 2017-10-10 Reginald David Gilbert Stackable cable hanger

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3664010A (en) * 1970-03-19 1972-05-23 Preformed Line Products Co Line tie
CN2808640Y (en) * 2005-06-16 2006-08-23 上海市安装工程有限公司 Hanger frame for subway engineering
CN202906328U (en) * 2012-11-09 2013-04-24 苏州金螳螂建筑装饰股份有限公司 A temporary power supply erecting system used in decoration construction

Also Published As

Publication number Publication date
CN102957113A (en) 2013-03-06

Similar Documents

Publication Publication Date Title
CN203430059U (en) Temporary fixing device used for installing large-span steel structure roof primary truss
CN204326698U (en) A kind of protective fence of dimension adjustable
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN104895193A (en) Precast outer wallboard connecting box and connecting joint
CN203809870U (en) Supporting and fixing tool for level pump pipe on concrete floor
CN202787926U (en) Overhanging scaffold simple and convenient to disassemble and assemble
CN102957113B (en) Decoration construction temporary power construction system
CN204538469U (en) Diagonal-bracing type line lever switch support
CN202906328U (en) A temporary power supply erecting system used in decoration construction
CN202745353U (en) Tool-type overhanging scaffold
CN102352690A (en) Construction method of anti-floating locating system of cast-in-place concrete hollow floorslab steel tube
CN202157581U (en) Foundation-pit limb shaping protection device
CN205296927U (en) Steel bar machining shed
CN203531482U (en) Protective cover of distribution box
CN203145040U (en) Prefabricated slab iron tower foundation convenient to disassemble and transport
CN203430009U (en) Construction hanging basket
CN108086523B (en) Light steel concrete block composite wall and construction method thereof
CN202139543U (en) Support structure for continuous box girder construction
CN204960324U (en) Suspension type floor formwork support device
CN205296985U (en) Can dismantle solar energy covering or awning on a car, boat, etc. room
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN204680987U (en) The device that a kind of temporary electricity of constructing is arranged
CN204212302U (en) A kind of hollowcore slab light pipe float Structure
CN203603490U (en) Supporting structure used for erecting formwork truss on prefabricated beam
CN203684709U (en) Adjusting device for assembly inclination angle of truss of steel structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model