CN202081666U - Mounting working pergola for cable accessory - Google Patents

Mounting working pergola for cable accessory Download PDF

Info

Publication number
CN202081666U
CN202081666U CN2011201632068U CN201120163206U CN202081666U CN 202081666 U CN202081666 U CN 202081666U CN 2011201632068 U CN2011201632068 U CN 2011201632068U CN 201120163206 U CN201120163206 U CN 201120163206U CN 202081666 U CN202081666 U CN 202081666U
Authority
CN
China
Prior art keywords
fixed
roof panel
installation work
cable accessory
work frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201632068U
Other languages
Chinese (zh)
Inventor
陆浩臻
贺智涛
吴倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority to CN2011201632068U priority Critical patent/CN202081666U/en
Application granted granted Critical
Publication of CN202081666U publication Critical patent/CN202081666U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a mounting working pergola for a cable accessory, which comprises a shed top, a pair of wall bodies arranged oppositely and doors arranged at two ends of the pair of the wall bodies, wherein the shed top comprises a plurality of roof frames and a plurality of roof panels, the plurality of the roof frames are arranged in parallel, and the plurality of the roof panels are erected and fixed on the roof frames; and each wall body comprises a support structure and a wall panel, the wall panels are fixed on the support structures and the roof frames are fixed with the support structures. The mounting working pergola for a cable joint can overcome the defects in the prior art, not only realize aesthetic appearance and convenience in mounting and transportation, but also greatly shorten the mounting time, win time for electrical power emergency repair, be applicable to different terrains and further realize large bearing capacity, high safety and higher practicality.

Description

Cable accessory installation work frame
Technical field
The utility model relates to a kind of work frame, refers in particular to a kind of cable accessory installation work frame.
Background technology
110kV and above Voltage Cable Lines Construction are the important component parts of electrical network main grid structure, and its safe and stable operation is related to the firm of major network reliability.Present most cable is a cross-linked polyethylene insulated cable, cross-linked polyethylene insulated cable is to change the polythene material strand a kind of cables with extruded insulation of three-dimensional-structure (tridimensional network) back as insulation into from linear structure, in a single day this kind cable breaks down, have not recoverability, must take emergency repair measure immediately.High voltage cable generally adopts the form of direct-burried or poling to be laid in the position of about 1.2 meters of below grounds, and the corridor road environment is various and complicated, causes the complicated of first-aid repair construction environment, is difficult to create in the very first time rush to repair environment preferably.And in the installation process of cable accessory,, must take measures such as rainproof, moistureproof, dustproof to the ten/height that requires of working environment, otherwise just might cause serious quality problems, influence the engineering life-span.Therefore, for circuit is sent a telegram in reply as early as possible, shortens power off time as much as possible and is dwindled the influence that has a power failure and bring, simultaneously also for the repairing personnel can safety, working healthily, guarantee construction quality, very be necessary after fault takes place, the very first time is that a good construction environment is created in the installation of cable repairing annex, make repairing work can be smoothly, safety carries out, improve and rush to repair efficient and construction quality.
Prior art mainly adopts following two kinds of cable accessory installation work frames:
1. adopt the steel scaffold, the simple and easy frame that Tie Tong sets up, the top reaches to hide and enclose with colour bar cloth or canvas all around covers, and whole work frame is extremely simple and crude, and is neither windproof, not rainproof again, directly influences the quality that annex is installed.The professional contingent that this kind cable accessory installation work frame need have relevant qualification sets up, and length consuming time generally needs 4 ~ 5 hours, and good looking appearance is poor, is difficult to satisfy the requirement of municipal civilization construction.
2. employing container, this kind mode requires high to landform, can't on the circuit corridor of complexity, use, and need the big machinery vehicle to be responsible for transportation and lifting, can not be according to length, width and the height of random assembly unit of landform and adjustment cable accessory installation work frame.
In addition, two kinds of cable accessory installation work frames of prior art all have operating temperature height in the cable accessory installation work frame, be unfavorable for constructor's operation, crane cable annex inconvenience, simultaneously, do not have deficiencies such as professional electric power system and stressed design, work brings inconvenience to electric power first-aid.
Summary of the invention
The utility model provides a kind of cable connector installation work frame, it has overcome the defective of prior art, good looking appearance not only, installation, convenient transportation have shortened the set-up time, greatly for electric power first-aid has won the time, and can adapt to different landform, load capacity is big, and is safe, has advantages of high practicability.
The utility model is achieved in that
A kind of cable accessory installation work frame, it includes: ceiling, a pair of body of wall that is oppositely arranged and be arranged to described body of wall two ends the door, described ceiling includes a plurality of roof trusses and a plurality of roof panel, a plurality of described roof trusses be arranged in parallel, and a plurality of described roof panel set up and are fixed on the described roof truss; Described body of wall includes supporting structure and shingle nail, and described shingle nail is fixed on the described supporting structure, and described roof truss and described supporting structure are fixed.
Preferably, described roof truss be shaped as triangle, described roof panel be shaped as reverse V-shaped with the form fit of described roof truss, these leg-of-mutton two hypotenuses are respectively applied for fixing described roof panel, each described roof panel is fixed on adjacent two described roof trusses.Reverse V-shaped roof truss not only makes cable accessory installation work frame volume inside bigger, makes things convenient for lifting appliance.
Preferably, for described roof panel can be installed easily and efficiently, the left and right two ends of described ceiling are cornice, and described cornice place is fixed with the roof panel mounting groove, and the two ends of described roof panel are installed on respectively in the described roof panel mounting groove.When described roof panel is installed, the edge of described roof panel is aimed at described roof panel mounting groove, promoted described roof panel, described roof panel moves to the appropriate location along described roof panel mounting groove.
Preferably, described supporting structure includes a plurality of foot rests and at least one fixed mount, and a plurality of described foot rests be arranged in parallel, and described fixed mount and a plurality of described foot rests are vertical to be connected and fixing.
Preferably, for described shingle nail can be installed easily and efficiently, the upper end of described foot rest, lower end are equipped with the shingle nail mounting groove, and the upper/lower terminal of described shingle nail is installed on respectively in the described shingle nail mounting groove.
Preferably, it also includes sealing plate, and described sealing plate is positioned at the top of described door, and be positioned at outmost two described roof trusses and fix.
Preferably, connect by the wingceltis bar between adjacent two roof trusses, strengthened the steadiness of described roof truss further.
Preferably, described supporting structure also includes at least one indoor diagonal brace, and an end and the described foot rest of described indoor diagonal brace are fixed, and the other end and described supporting structure are fixed.Not only further strengthen the steadiness of described cable connector installation work frame, and can be used for hoisting heavy.
Preferably, described roof panel mounting groove and described shingle nail mounting groove are Qian font channel-section steel.
Further preferably, it also includes plug slot, electronic box, lamp, exhaust fan and air-conditioning, and it is installed on respectively on described ceiling, body of wall or the sealing plate.
The utility model compared with prior art has following beneficial effect:
1. appearance looks elegant is generous, meets the municipal civilization construction requirement;
2. roof panel and shingle nail adopt the reflection and heat insulation material, reduce operating temperature;
3. the weight of can slinging in described cable connector installation work frame draws through test, and can sling is not more than 1 ton weight, satisfies the needs that annex is installed.
4. installation personnel does not need the professional, as long as through simple training, use simple tools just can assemble and disassemble to changing cable connector installation work frame, can finish assembling rapidly with interior at two hours, and the material after disassembling can adopt medium transporter just can transport, and has improved operating efficiency greatly.
5. can carry out random assembly unit and adjustment according to landform, satisfy the needs of different length, width, height landform and construction environment.
6. its inside is provided with rational wiring, be provided with common equipments such as electronic box, lamp, exhaust fan, plug slot and air-conditioning, avoided prior art to occur situations such as electric leakage, spread of voltage, load too high easily, guaranteed enough illuminations and stable voltage, for construction provides good environment.
Description of drawings
Fig. 1 does not install the top view of the cable connector installation work frame of roof panel for the utility model;
Fig. 2 is the sectional view of the 1-1 of Fig. 1;
Fig. 3 is the sectional view of the 2-2 of Fig. 1;
Fig. 4 is the enlarged drawing of A2-1 among Fig. 2;
Fig. 5 is the enlarged drawing of A2-2 among Fig. 2;
The stereogram of Fig. 6 the utility model cable connector installation work frame;
Fig. 7 is the structural representation of the ceiling of the utility model cable connector installation work frame;
Fig. 8 is the indoor configuration schematic diagram of the utility model cable connector installation work frame;
Fig. 9 is the outdoor configuration schematic diagram of the utility model cable connector installation work frame.
The specific embodiment
Below in conjunction with accompanying drawing embodiment of the present utility model is elaborated:
As Fig. 1 to Fig. 3, shown in Figure 6, the utility model cable accessory installation work frame (hereinafter to be referred as work frame) include: ceiling, a pair of body of wall that is oppositely arranged and be arranged to described body of wall two ends the door 3(as shown in Figure 6), described ceiling includes a plurality of roof trusses 11 and a plurality of roof panel 12, a plurality of described roof trusses 11 be arranged in parallel, and a plurality of described roof panel 12 set up and are fixed on the described roof truss 11; Described body of wall includes supporting structure and shingle nail 22, and described shingle nail 22 is fixed on the described supporting structure, and described roof truss 11 is fixed with described supporting structure.
As Fig. 2 and shown in Figure 7, described roof truss 11 be shaped as triangle, described roof panel 12 be shaped as cooperate with described roof truss 11 reverse V-shaped, these leg-of-mutton two hypotenuses are respectively applied for fixing described roof panel 12.As shown in Figure 6, a plurality of roof panel 12 are installed on the described roof truss 11 successively, are provided with 15 sealings of stainless steel T section bar between adjacent two described roof panel 12, avoid rainwater to enter.
The left and right two ends of described ceiling are cornice, and described cornice place is fixed with roof panel mounting groove 13(as shown in Figure 4), the two ends of described roof panel 12 are installed on respectively in the described roof panel mounting groove 13.In this preferred embodiment, described roof panel mounting groove 13 is a Qian font channel-section steel, described Qian font channel-section steel is welded on the angle bar, and it is fixing by bolt and described roof truss 11, and the slightly larger in diameter of described Qian font channel-section steel is in the thickness of described roof panel 12, when described roof panel 12 is installed, described roof panel 12 can be promoted along described Qian font channel-section steel, save the set-up time.
In order further to fix described roof panel 12, the ridge of described ceiling is provided with the inverted V-shape steel, and the top of the roof panel 12 of itself and inverted V-shape is close to.
As Fig. 2 or shown in Figure 6, in order further to strengthen the stability of described roof truss 11, connect by wingceltis bar 14 between adjacent two roof trusses 11, described wingceltis bar 14 adopts bolt with described roof truss 11, the material of described wingceltis bar 14 is a band steel, in order to ensure its stability, preferred described wingceltis bar 14 is a mouthful 50*30 band steel.
Continue as shown in Figure 3, described supporting structure includes a plurality of foot rests 23 and at least one fixed mount 24, a plurality of described foot rests 23 be arranged in parallel, and described roof truss 11 adopts bolt with described foot rest 23, and described fixed mount 24 and a plurality of described foot rest 23 be vertical to be connected and to fix.Described fixed mount 24 is fixing successively by bolt and described foot rest 23.In the present embodiment, described foot rest 23 is portable foot rest, and 2 fixed mounts 24 preferably are installed.
Described supporting structure also includes at least one indoor diagonal brace 26, and an end of described indoor diagonal brace 26 and described roof truss 11 are fixing, and the other end and described foot rest 23 are fixing, and its fixed form is bolt.In the present embodiment, the upper end of preferred described indoor diagonal brace 26 and the lower edge of leg-of-mutton described roof truss 11 are fixed, and the lower end of lower end and described foot rest 23 is fixed, and bolt is all adopted in its upper end, lower end, not only can play the effect of stablizing described work frame, and can be used for hoisting heavy.Preferably except that the described roof truss 11 that is positioned at described body of wall two ends (outermost), all the other described roof trusses 11 all are fixed with indoor diagonal brace 26 to present embodiment.Preferred described indoor diagonal brace 26 is a mouthful 50*50 square steel, and it can bear the weight that weight is 500kg.
As shown in Figure 5, in order to finish the installation of described shingle nail 22 easily and efficiently, the upper end of described foot rest 23, lower end all are fixed with shingle nail mounting groove 25, and the upper/lower terminal of described shingle nail 22 is installed on respectively in the described shingle nail mounting groove 25.Similar to described roof panel mounting groove 13, described shingle nail mounting groove 22 also is preferably Qian font channel-section steel, and its mounting means is also similar to described roof panel mounting groove 13.
In this preferred embodiment, the material of described roof panel 12 and described shingle nail 22 is chromatic steel sandwich plate, for increasing the durability of chromatic steel sandwich plate, makes its not cracky, and described chromatic steel sandwich plate adopts the stainless steel bound edge, has increased its aesthetic property simultaneously again.The material of preferred described roof truss 11 and described fixed mount 24 is a mouthful 50*50 square steel.
As shown in Figure 6, in order to strengthen the sealing of described work frame, it also includes sealing plate 4, and described sealing plate 4 is fixed with being positioned at outermost two described roof trusses 11, and is positioned at the top of described door 3.Leave exhaust fan installing hole 41 on the preferred described sealing plate 4, be used to install exhaust fan.
The preferred described door 3 of present embodiment is a rolling-gate, and the upper end of rolling-gate is installed on the lower edge that is positioned at the described roof truss 11 of outermost triangle, and its mounting method has belonged to prior art, and the utility model does not repeat them here.
As Fig. 8 and shown in Figure 9, described work frame also includes plug slot 6, electronic box 8, lamp 9, exhaust fan and air-conditioning 7, and it is installed on respectively on described ceiling, body of wall or the sealing plate 4.Present embodiment preferably is installed on described plug slot 6 and described lamp 9 on the described fixed mount 24, and described electronic box 8 is installed on the described foot rest 23, and described air-conditioning is installed on the described shingle nail 22.
When described work frame is installed, install according to following steps:
At first, position line, determine the installation site of this work frame according to landform and needs on the spot.
Secondly, upright first pair of foot rest 23 fixed with interim diagonal brace and cross bar, and roof truss 11 is installed then, and be with fixed mount 24 that foot rest 23 is fixing after finishing; Upright then second pair of foot rest 23, and foot rest 23 is fixing with fixed mount 24, second roof truss 11 is installed again; Finish the installation of all foot rests 23, fixed mount 24 and roof truss 11 successively according to above-mentioned steps, described work frame is basic forming.
Once more, adorn an indoor diagonal brace 26 in the indoor every side of roof truss 11 lower edges of work frame, the frame of will working is reinforced, and Qian font channel-section steel is installed, and forms described roof panel mounting groove 13 and described shingle nail mounting groove 25 successively.
Then, described roof panel 12 is aimed at described roof panel mounting groove 13, and promote described roof panel 12 to the appropriate location, finish the installation of a described roof panel 12, finish the installation of all described roof panel 12 successively according to above-mentioned steps, and stainless steel T section bar 15 is installed between each described roof panel 12; Described shingle nail 22 is aimed at the described shingle nail mounting groove 25 of being located at described foot rest 23 upper/lower terminals, and promote described shingle nail 22 to the appropriate location, finish the installation of a described shingle nail 22, finish the installation of all described shingle nails 22 according to above-mentioned steps successively.Reverse V-shaped material is installed is again formed ridge.
At last, according to the mounting method of prior art rolling-gate, described door 3 is installed at the two ends of work frame; According to the mounting method of prior art, finish the installation of electric equipments such as described connector assembly 6, air-conditioning 7, electronic box 8, lamp 9 and air distribution fan again.
When disassembling this work frame, un-mate sequence is opposite with erection sequence, and from top to bottom, the electric equipment in the first dismounting work frame is removed structures such as door 3, shingle nail 22, roof panel 12, roof truss 11 and supporting structure more successively.
In the utility model preferred embodiment, preferred described roof truss 11 all adopts bolt quick detachable, that easily fix with described fixed mount 24, described indoor diagonal brace 26 with described roof truss 11 and described foot rest 23 with described wingceltis bar 14, described foot rest 23.
Only be specific embodiment of the utility model below, do not limit protection domain of the present utility model with this; Any replacement and the improvement done on the basis of not violating the utility model design all belong to protection domain of the present utility model.

Claims (10)

1. cable accessory installation work frame, it is characterized in that, it includes: ceiling, a pair of body of wall that is oppositely arranged and be arranged to described body of wall two ends the door, described ceiling includes a plurality of roof trusses and a plurality of roof panel, a plurality of described roof trusses be arranged in parallel, and a plurality of described roof panel set up and are fixed on the described roof truss; Described body of wall includes supporting structure and shingle nail, and described shingle nail is fixed on the described supporting structure, and described roof truss and described supporting structure are fixed.
2. cable accessory installation work frame as claimed in claim 1, it is characterized in that, described roof truss be shaped as triangle, described roof panel be shaped as reverse V-shaped with the form fit of described roof truss, these leg-of-mutton two hypotenuses are respectively applied for fixing described roof panel, and each described roof panel is fixed on adjacent two described roof trusses.
3. cable accessory installation work frame as claimed in claim 1 is characterized in that the left and right two ends of described ceiling are cornice, and described cornice place is fixed with the roof panel mounting groove, and the two ends of described roof panel are installed on respectively in the described roof panel mounting groove.
4. cable accessory installation work frame as claimed in claim 1 is characterized in that described supporting structure includes a plurality of foot rests and at least one fixed mount, and a plurality of described foot rests be arranged in parallel, and described fixed mount and a plurality of described foot rests are vertical to be connected and fixing.
5. cable accessory installation work frame as claimed in claim 4 is characterized in that the upper end of described foot rest, lower end all are fixed with the shingle nail mounting groove, and the upper/lower terminal of described shingle nail lays respectively in the described shingle nail mounting groove.
6. cable accessory installation work frame as claimed in claim 1 is characterized in that it also includes sealing plate, and described sealing plate is positioned at the top of described door, and be positioned at outmost two described roof trusses and fix.
7. cable accessory installation work frame as claimed in claim 1 is characterized in that, connects by the wingceltis bar between adjacent two roof trusses.
8. cable accessory installation work frame as claimed in claim 4 is characterized in that described supporting structure also includes at least one indoor diagonal brace, and an end and the described roof truss of described indoor diagonal brace are fixed, and the other end and described foot rest are fixed.
9. as claim 3 or 5 described cable accessory installation work frames, it is characterized in that described roof panel mounting groove and described shingle nail mounting groove are Qian font channel-section steel.
10. as claim 1 or 6 described cable accessory installation work frames, it is characterized in that it also includes plug slot, electronic box, lamp, exhaust fan and air-conditioning, it is installed on respectively on described ceiling, body of wall or the sealing plate.
CN2011201632068U 2011-05-20 2011-05-20 Mounting working pergola for cable accessory Expired - Lifetime CN202081666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201632068U CN202081666U (en) 2011-05-20 2011-05-20 Mounting working pergola for cable accessory

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201632068U CN202081666U (en) 2011-05-20 2011-05-20 Mounting working pergola for cable accessory

Publications (1)

Publication Number Publication Date
CN202081666U true CN202081666U (en) 2011-12-21

Family

ID=45342302

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201632068U Expired - Lifetime CN202081666U (en) 2011-05-20 2011-05-20 Mounting working pergola for cable accessory

Country Status (1)

Country Link
CN (1) CN202081666U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296842A (en) * 2011-05-20 2011-12-28 广东电网公司广州供电局 Operation shed frame for mounting cable accessory
CN105421828A (en) * 2015-12-15 2016-03-23 上海久隆电力(集团)有限公司 Cable joint workshop for user terminal platform
CN112031171A (en) * 2020-08-25 2020-12-04 广东电网有限责任公司 Movable maintenance working shed

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296842A (en) * 2011-05-20 2011-12-28 广东电网公司广州供电局 Operation shed frame for mounting cable accessory
CN105421828A (en) * 2015-12-15 2016-03-23 上海久隆电力(集团)有限公司 Cable joint workshop for user terminal platform
CN105421828B (en) * 2015-12-15 2018-08-24 上海久隆电力(集团)有限公司 A kind of outdoor terminal platform cable connector workplace
CN112031171A (en) * 2020-08-25 2020-12-04 广东电网有限责任公司 Movable maintenance working shed
CN112031171B (en) * 2020-08-25 2022-04-12 广东电网有限责任公司 Movable maintenance working shed

Similar Documents

Publication Publication Date Title
CN103410670B (en) Truss type wind-driven generator tower frame and there is the wind power generating set of this pylon
CN104405155B (en) A kind of substation
CN202081666U (en) Mounting working pergola for cable accessory
CN103628710B (en) A kind of portable detachable box-type medium-voltage frequency conversion chamber
CN103243874A (en) Photovoltaic roof adapting fixture and photovoltaic roof structure with same
CN201495631U (en) Combined type prefabricated house
CN212078231U (en) Assembled steel construction building
CN102296842A (en) Operation shed frame for mounting cable accessory
CN203813347U (en) Portable mobile operating room for manufacturing and testing cable head
CN206570926U (en) A kind of assembling type steel structure beam slab of convenient dismounting
CN204190233U (en) A kind of low pressure rod-type power distribution cabinet operating platform
CN205479755U (en) A synthesize integrated suspension system of pipe support that is used for motor car application storehouse of inspecting
CN210350562U (en) Box-type substation convenient to installation
CN205071609U (en) Protective shield
CN210319498U (en) Apply to LED lighting device of municipal construction
CN207377206U (en) Transformer room and the windproof hardened system of transformer room
CN205296985U (en) Can dismantle solar energy covering or awning on a car, boat, etc. room
CN205976631U (en) But sled dressization mobility control room
CN204876637U (en) Portable prefabricated house
CN104377578A (en) Low-voltage pole type power distribution cabinet operating platform
CN104821613A (en) Charging system based on novel electric vehicle
CN204343731U (en) A kind of substation
CN219343475U (en) Modular assembled building structure
CN216359541U (en) Assembling and positioning device for prefabricated building enclosure
CN205206036U (en) Machine room

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20111221